RA16-021, Cycle 17 Startup Test Report Summary
From kanterella
Revision as of 21:27, 14 April 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
ML16133A269 | |
Person / Time | |
---|---|
Site: | LaSalle ![]() |
Issue date: | 05/12/2016 |
From: | Trafton W J Exelon Generation Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
RA16-021 | |
Download: ML16133A269 (11) | |
Similar Documents at LaSalle | |
---|---|
Category:Inservice/Preservice Inspection and Test Report
MONTHYEARRA23-018, Post-Outage Inservice Inspection (ISI) Summary Report2023-06-27027 June 2023
[Table view]Post-Outage Inservice Inspection (ISI) Summary Report RA22-051, Submittal of the Snubber Program Plan for the Fourth 10-Year Interval2022-11-16016 November 2022 Submittal of the Snubber Program Plan for the Fourth 10-Year Interval RA22-021, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2022-06-0808 June 2022 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report ML21196A5022021-07-15015 July 2021 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA21-017, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2021-04-0909 April 2021 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report NMP2L2711, Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-8792019-10-16016 October 2019 Byron Station; Calvert Cliffs; Clinton Power Station; LaSalle County Station; Limerick Generating Station; and Nine Mile Point Nuclear Station - Proposed Alternative to Utilize Code Case N-879 RA19-034, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2019-06-0707 June 2019 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report NMP2L2700, Co. - Submittal of Proposed Alternative to Utilize Code Case N-879 for Plants2019-04-30030 April 2019 Co. - Submittal of Proposed Alternative to Utilize Code Case N-879 for Plants ML18200A0802018-07-18018 July 2018 Submittal of Fourth 10-Year Interval Inservice Testing (IST) Program Plan RA18-059, Inservice Testing Program Plan, Technical Position TP-052018-07-18018 July 2018 Inservice Testing Program Plan, Technical Position TP-05 ML17314A0082017-11-10010 November 2017 Submittal of Program Plan Associated with the Fourth Lnservice Inspection (ISI) Interval and the Third Containment Lnservice Inspection (Cisi) Interval RA17-055, Post-Outage 90-Day Lnservice Inspection (ISI) Summary Report2017-06-0707 June 2017 Post-Outage 90-Day Lnservice Inspection (ISI) Summary Report RA16-020, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2016-06-0808 June 2016 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA16-021, Cycle 17 Startup Test Report Summary2016-05-12012 May 2016 Cycle 17 Startup Test Report Summary RA15-028, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2015-06-26026 June 2015 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA15-035, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2015-05-28028 May 2015 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RS-15-011, Proposed Alternative to the Examination Requirements for Nozzle-to-Vessel Welds and Inner Radii Sections in Accordance with 10 CFR 50.55a(z)(1)2015-01-29029 January 2015 Proposed Alternative to the Examination Requirements for Nozzle-to-Vessel Welds and Inner Radii Sections in Accordance with 10 CFR 50.55a(z)(1) RA14-018, Post-Outage 90-Day Inservice (ISI) Summary Report2014-05-29029 May 2014 Post-Outage 90-Day Inservice (ISI) Summary Report ML14149A2732014-05-29029 May 2014 LaSalle County Station, Unit 1 - Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA13-023, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2013-05-31031 May 2013 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA12-052, Amended Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2012-10-26026 October 2012 Amended Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA12-018, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2012-06-0505 June 2012 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA11-024, Unit 2 - Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2011-06-0303 June 2011 Unit 2 - Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA10-023, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2010-06-0404 June 2010 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA09-041, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2009-05-0808 May 2009 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA08-070, Submittal of Third 10-Year Inservice Testing (IST) Interval Program Plan2008-12-17017 December 2008 Submittal of Third 10-Year Inservice Testing (IST) Interval Program Plan RA07-045, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2007-06-0101 June 2007 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA07-036, Submittal of Relief Requests Associated with the Third Inservice Inspection (ISI) Interval and the Second Containment Inservice Inspection (Cisi) Interval2007-04-30030 April 2007 Submittal of Relief Requests Associated with the Third Inservice Inspection (ISI) Interval and the Second Containment Inservice Inspection (Cisi) Interval RS-07-058, Amergen/Exelon Nuclear - Request for Relief - Use of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements2007-04-19019 April 2007 Amergen/Exelon Nuclear - Request for Relief - Use of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) Guidelines in Lieu of Specific ASME Code Requirements RA06-063, Proposed Third Ten-Year Interval Inservice Testing Program2006-10-16016 October 2006 Proposed Third Ten-Year Interval Inservice Testing Program ML0629704302006-09-29029 September 2006 Proposed Third Ten-Year Interval Inservice Testing Relief Request RA06-038, Post-Outage 90-Day Inservice Inspection Summary Report2006-06-16016 June 2006 Post-Outage 90-Day Inservice Inspection Summary Report ML0518004412005-06-10010 June 2005 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report ML0429405252004-10-15015 October 2004 Amended 90-Day Post Outage ISI Summary Reports ML0414201292004-05-0707 May 2004 Post-Outage 90-Day Inservice Inspection Summary Report ML0314900182003-05-21021 May 2003 Post-Outage 90-Day Inservice Inspection Summary Report ML0213307432002-05-0606 May 2002 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report 2023-06-27 Category:Letter type:RA MONTHYEARRA23-072, Regulatory Commitment Change Summary Report2023-12-15015 December 2023
[Table view]Regulatory Commitment Change Summary Report RA23-057, Registration of Use of Cask to Store Spent Fuel2023-08-11011 August 2023 Registration of Use of Cask to Store Spent Fuel RA23-055, Registration of Use of Cask to Store Spent Fuel2023-08-11011 August 2023 Registration of Use of Cask to Store Spent Fuel RA23-052, Registration of Use of Cask to Store Spent Fuel2023-08-0404 August 2023 Registration of Use of Cask to Store Spent Fuel RA23-051, Registration of Use of Cask to Store Spent Fuel2023-07-21021 July 2023 Registration of Use of Cask to Store Spent Fuel RA23-048, Registration of Use of Cask to Store Spent Fuel2023-07-14014 July 2023 Registration of Use of Cask to Store Spent Fuel RA23-045, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2023-06-30030 June 2023 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation RA23-047, Registration of Use of Cask to Store Spent Fuel2023-06-30030 June 2023 Registration of Use of Cask to Store Spent Fuel RA23-018, Post-Outage Inservice Inspection (ISI) Summary Report2023-06-27027 June 2023 Post-Outage Inservice Inspection (ISI) Summary Report RA23-046, Registration of Use of Cask to Store Spent Fuel2023-06-23023 June 2023 Registration of Use of Cask to Store Spent Fuel RA23-042, Registration of Use of Cask to Store Spent Fuel2023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel RA23-029, 2022 Annual Radiological Environmental Operating Report2023-05-12012 May 2023 2022 Annual Radiological Environmental Operating Report RA23-028, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report RA23-027, Annual Dose Report for 20222023-04-21021 April 2023 Annual Dose Report for 2022 RA23-025, Post Accident Monitoring Report2023-04-0707 April 2023 Post Accident Monitoring Report RA23-013, Submittal of Triennial Chlorine Survey Report2023-03-30030 March 2023 Submittal of Triennial Chlorine Survey Report RA23-019, Cycle 20 Core Operating Limits Reports2023-03-21021 March 2023 Cycle 20 Core Operating Limits Reports RA22-066, 150 Day Submittal Cover Letter2022-12-0202 December 2022 150 Day Submittal Cover Letter RA22-060, Regulatory Commitment Change Summary Report2022-11-30030 November 2022 Regulatory Commitment Change Summary Report RA22-051, Submittal of the Snubber Program Plan for the Fourth 10-Year Interval2022-11-16016 November 2022 Submittal of the Snubber Program Plan for the Fourth 10-Year Interval RA22-041, Unit 2 Cycle 19 Core Operating Limits Report Revision2022-10-0505 October 2022 Unit 2 Cycle 19 Core Operating Limits Report Revision RA22-029, Cycle 20 Startup Test Report Summary2022-06-10010 June 2022 Cycle 20 Startup Test Report Summary RA22-021, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2022-06-0808 June 2022 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA22-020, Annual Radiological Environmental Operating Report2022-05-13013 May 2022 Annual Radiological Environmental Operating Report RA22-018, Annual Dose Report for 20212022-04-22022 April 2022 Annual Dose Report for 2021 RA22-010, Cycle 20 Core Operating Limits Reports2022-03-21021 March 2022 Cycle 20 Core Operating Limits Reports RA21-059, Regulatory Commitment Change Summary Report2021-11-30030 November 2021 Regulatory Commitment Change Summary Report RA21-050, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2021-11-0909 November 2021 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation RA21-051, County Station Physical Security Plan (Revision 18)2021-09-29029 September 2021 County Station Physical Security Plan (Revision 18) RA21-052, Registration of Use of Cask Store Spent Fuel2021-09-17017 September 2021 Registration of Use of Cask Store Spent Fuel RA21-046, Registration of Use of Cask to Store Spent Fuel2021-08-0505 August 2021 Registration of Use of Cask to Store Spent Fuel RA21-043, Cycle 19 Startup Test Report Summary2021-07-15015 July 2021 Cycle 19 Startup Test Report Summary RA21-031, 2020 Annual Radiological Environmental Operating Report2021-05-13013 May 2021 2020 Annual Radiological Environmental Operating Report RA21-029, Unit 2 - 2020 Annual Radioactive Effluent Release Report2021-04-29029 April 2021 Unit 2 - 2020 Annual Radioactive Effluent Release Report RA21-026, Annual Dose Report for 20202021-04-22022 April 2021 Annual Dose Report for 2020 RA21-016, Netco Rack Insert 10-year Surveillance Report2021-04-15015 April 2021 Netco Rack Insert 10-year Surveillance Report RA21-017, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2021-04-0909 April 2021 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report RA21-019, Unit 2 Cycle 19 Core Operating Limits Reports2021-04-0707 April 2021 Unit 2 Cycle 19 Core Operating Limits Reports RA20-058, Licensee Post Exam Submittal Letter2020-12-0202 December 2020 Licensee Post Exam Submittal Letter RA20-044, Unit 2 - Unit 1 Cycle 19 Core Operating Limits Report2020-09-10010 September 2020 Unit 2 - Unit 1 Cycle 19 Core Operating Limits Report RA20-026, 2019 Annual Radiological Environmental Operating Report2020-05-13013 May 2020 2019 Annual Radiological Environmental Operating Report RA20-023, Annual Dose Report for 20192020-04-28028 April 2020 Annual Dose Report for 2019 RA20-016, Corrected Drawing for One-Line Electrical Power Supply for Containment Vent System Final Integrated Plan2020-03-24024 March 2020 Corrected Drawing for One-Line Electrical Power Supply for Containment Vent System Final Integrated Plan RA20-015, Triennial Chlorine Survey Report2020-03-20020 March 2020 Triennial Chlorine Survey Report RA20-014, Cycle 19 and Cycle 18 Core Operating Limits Reports2020-03-12012 March 2020 Cycle 19 and Cycle 18 Core Operating Limits Reports RA19-048, Registration of Use of Cask to Store Spent Fuel2019-09-0606 September 2019 Registration of Use of Cask to Store Spent Fuel RA19-045, Registration of Use of Cask to Store Spent Fuel2019-08-0909 August 2019 Registration of Use of Cask to Store Spent Fuel RA19-041, Registration of Use of Cask to Store Spent Fuel2019-07-0303 July 2019 Registration of Use of Cask to Store Spent Fuel RA19-039, Registration of Use of Cask to Store Spent Fuel2019-06-25025 June 2019 Registration of Use of Cask to Store Spent Fuel RA19-034, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report2019-06-0707 June 2019 Post-Outage 90-Day Inservice Inspection (ISI) Summary Report 2023-08-04 |