MONTHYEARIR 05000295/20240012024-09-0404 September 2024 NRC Inspection Report No. 07201037/2024001; 05000295/2024001; and 05000304/2024001 - Zion Nuclear Power Station ML24192A1752024-07-10010 July 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07201037/2024401 ML24136A2392024-06-11011 June 2024 ISFSI - Exemption from Select Requirements of Title 10 of the Code of Federal Regulations Part 73 (EPID L-2023-LLE-0089 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RS-24-052, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report RS-24-047, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. ML23356A0072023-12-22022 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-122, Amendment No. 15 to Indemnity Agreement No. B-592023-11-29029 November 2023 Amendment No. 15 to Indemnity Agreement No. B-59 ML23291A0802023-11-16016 November 2023 Issuance of Conforming Amendments Regarding Direct Transfer of DPR-39 and DPR-48 Facility Operating Licenses from Zionsolutions, LLC to Constellation Energy Generation LLC ML23286A3132023-11-14014 November 2023 EPA Phase 2 Closure Letter 10-13-23 ML23310A3132023-11-0808 November 2023 Cover Letter, S.Anderson, NRC to J.Sauger, Energysolutions, Remaining Final Status Surveys RS-23-116, Supplemental Information in Response to Order Consenting to License Transfers and Approval of Conforming License Amendments2023-11-0808 November 2023 Supplemental Information in Response to Order Consenting to License Transfers and Approval of Conforming License Amendments ML23286A3092023-11-0808 November 2023 Partial Site Release, Zion Nuclear Power Station, Units 1 and 2 ML23310A1082023-11-0303 November 2023 Confirmatory Survey Report 2023 IR 05000295/20230012023-11-0202 November 2023 NRC Inspection Report No. 05000295/2023001(DRSS); 05000304/2023001 (Drss) - Zion Nuclear Power Station ML23251A0712023-09-0808 September 2023 Confirmatory Survey Extent of Condition Review ML23237B4132023-08-25025 August 2023 Response to Summary of May 4, 2023, Clarification Meeting Regarding the Partial Site Release Request ML23186A1902023-07-0606 July 2023 Review of Zion Solutions Responses to Requests for Additional Information Related to Zion Nuclear Power Station, Units 1 and 2 Decommissioning and Estimated Partial Site Release Review Schedule ZS-2023-0012, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-12012 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report ML23117A3692023-04-26026 April 2023 Annual Radioactive Effluent Release Report ML23116A2012023-04-24024 April 2023 Occupational Radiation Exposure Annual Report for 2022 ML23094A1292023-03-30030 March 2023 Annual Property Insurance Status Report ML23094A1322023-03-29029 March 2023 Decommissioning Funding Status Report for Shutdown Reactor ML23068A0122023-03-0303 March 2023 Withdrawal of Zion License Amendment Request for the License Termination Plan ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000295/20220012023-01-27027 January 2023 NRC Inspection Report 05000295/2022001 (Drss); 05000304/2022001 (Drss) ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring ML22308A1762022-11-17017 November 2022 J. Sauger Letter Regarding Zion License Transfer Order Fourth Extension ML22313A0562022-11-17017 November 2022 Audit Report - Letter to J Sauger ML22306A1342022-11-0909 November 2022 Receipt of Information and License Amendment Request for the Zion Nuclear Power Station, Units 1 and 2, Docket Nos. 50-295 and 50-304 RS-22-113, Updated ISFSI Decommissioning Funding Plan for Zion Nuclear Power Station2022-10-26026 October 2022 Updated ISFSI Decommissioning Funding Plan for Zion Nuclear Power Station ML22294A1622022-10-19019 October 2022 Request for Extension of Order Approving Transfer of the License for Zion Nuclear Power Station, Units 1 and 2, from Zionsolutions, LLC to Constellation Energy Company, LLC ML22293A4332022-10-17017 October 2022 Response to NRC Staff Questions Raised During the Regulatory Audit of RAI Responses Conducted July 19-20, 2022, and August 24-25, 2022 ML22273A1452022-10-0404 October 2022 U.S. NRC Analysis of Zion Solutions, LLC Decommissioning Funding Status Report for the Zion Nuclear Power Station Units 1 and 2 ML22279A9932022-09-30030 September 2022 Revised Final Status Survey Release Records, Final Reports, and Discrete Radioactive Particle Survey Report Technical Support Document ML22237A0952022-08-23023 August 2022 Revised Final Status Survey Release Records ML22200A0112022-07-19019 July 2022 Letter to J. Sauger, Zionsolutions, from K. Conway, NRC, - Regulatory Audit Plan Re Zionsolutions' Response to RAI Related to Partial Site Release and Recent Site Survey Activities ML22111A1872022-04-0606 April 2022 Technical Support Document 2022-001, Discrete Radioactive Particle Survey Report, Revision 1 NMP1L3458, Constellation Energy Generation, LLC, Annual Property Insurance Status Report2022-04-0101 April 2022 Constellation Energy Generation, LLC, Annual Property Insurance Status Report ML22089A0982022-03-28028 March 2022 Revised Response to Request for Additional Information Related to Partial Site Release and Recent Site Survey Activities ZS-2022-0008, Report on Status of Decommissioning Funding for Shutdown Reactors2022-03-28028 March 2022 Report on Status of Decommissioning Funding for Shutdown Reactors ML22089A0262022-03-28028 March 2022 Technical Support Document 2022-001, Discrete Radioactive Particle Survey Report, Revision 0 ML22087A0052022-03-24024 March 2022 Annual Property Insurance Status Report ZS-2022-0001, License Amendment Request for the License Termination Plan2022-03-23023 March 2022 License Amendment Request for the License Termination Plan ML22068A0462022-03-14014 March 2022 Independent Spent Fuel Storage Installation Security Inspection Report 07201037/2022401 ML22069A3292022-03-0808 March 2022 Response to Request for Additional Information Related to Partial Site Release and Recent Site Survey Activities, and Notification of Foundation Pad Discovery RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement IR 05000295/20210012022-02-22022 February 2022 NRC Inspection Report No. 05000295/2021001(DNMS); 05000304/2021001(DNMS) 2024-09-04
[Table view] |
Text
November 15, 2017
Mr. John Sauger Executive VP & Chief Nuclear Officer Zion Nuclear Power Station ZionSolutions, LLC 101 Shiloh Boulevard Zion, IL 60099 SUBJECT: ZION NUCLEAR POWER STATION (DECOMMISSIONING)INDEPENDENT SPENT FUEL STORAGE INSTALLATIONNRC SECURITY INSPECTION REPORT 05000295/2017401(DRS), 05000304/2017401(DRS), 07201037/2017401(DRS)
Dear Mr. Sauger:
On October 19, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the Physical Security Program for the Zion Nuclear Power Station, Independent Spent Fuel Storage Installation located near Zion, Illinois. In addition, the inspector evaluated the implementation of the Material Control and Accounting Program in accordance with Title 10 of the Code of Federal Regulations (CFR), Part 72.72(b). At the conclusion of the inspection on October 19, 2017, the inspector discussed the results of the inspection with you and other members of your staff. The inspection results are documented in the enclosed report. The NRC inspector did not identify any finding or violation of more-than-minor significance. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire -Related InformationWithhold from public disclosure under 10 CFR in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii). Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,/RA/ Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket No. 050-00295, 050-00304, 072-01037 License No. DPR-39, DPR-48, General License (ISFSI)
Enclosure:
IR 05000295/2017401(DRS); 05000304/2017401(DRS) 07201037/2017401(DRS) cc w/encl: J. Houff, ISFSI Plant Manager cc w/o encl: ZionSolutions Service List