MONTHYEARNRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-21-0055, Guarantee of Payment of Deferred Premiums2021-12-0202 December 2021 Guarantee of Payment of Deferred Premiums NRC-19-0078, Guarantee of Payment of Deferred Premiums2019-12-0202 December 2019 Guarantee of Payment of Deferred Premiums NRC-12-0057, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report Period Ending June 30, 20122012-08-27027 August 2012 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report Period Ending June 30, 2012 ML0816504352008-07-21021 July 2008 Allegation Program Annual Trends Report Cy 2007 NRC-07-0019, 2006 Annual Reports for Fermi 22007-04-24024 April 2007 2006 Annual Reports for Fermi 2 NRC-06-0035, Annual Financial Report2006-04-24024 April 2006 Annual Financial Report NRC-06-0016, Annual Reports2006-03-16016 March 2006 Annual Reports NRC-05-0058, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report Year Ending June 30, 20052005-08-26026 August 2005 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report Year Ending June 30, 2005 NRC-05-0040, Annual Financial Report2005-04-27027 April 2005 Annual Financial Report NRC-04-0027, 2003 Annual Financial Report for the DTE Energy Company2004-04-19019 April 2004 2003 Annual Financial Report for the DTE Energy Company NRC-03-0043, Annual Radioactive Effluent Release and Radiological Environmental Operating Reports2003-04-29029 April 2003 Annual Radioactive Effluent Release and Radiological Environmental Operating Reports NRC-03-0030, Annual Financial Report2003-03-24024 March 2003 Annual Financial Report 2023-11-29
[Table view] Category:Letter
MONTHYEARIR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 ML23216A1872023-08-0404 August 2023 Submittal of Relief Request RR-A25 for Extended License Period ML23206A1272023-07-26026 July 2023 NOED for Fermi Power Plant, Unit Two Technical Specification 3.7.2, Emergency Equipment Cooling Water Emergency Equipment Service Water System and Ultimate Heat Sink ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23122A2332023-06-26026 June 2023 Issuance of Amendment No. 223 Regarding Revision of Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23158A1332023-06-0808 June 2023 Notice of Enforcement Discretion (NOED) for Fermi Power Plant, Unit Two (EPID L-2023-LLD-0000) Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/ Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink ML23130A1032023-05-17017 May 2023 Regulatory Audit Summary Regarding License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency IR 05000341/20234022023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23118A3612023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23114A1172023-05-0101 May 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23115A4152023-04-25025 April 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML23124A2032023-04-10010 April 2023 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22325A2992023-02-24024 February 2023 Audit Plan in Support of Review of License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML23200A2162023-01-20020 January 2023 Outline Submittal Letter 2024-02-05
[Table view] |
Text
Fermi 2 6400 North Dixie Hwy., Newport, Al 48166 Detroit Edison March 16,2006 NRC-06-0016 U. S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington D C 20555
Reference:
Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
Subject:
2005 Annual Reports for Fermi 2 The Fermi 2 Technical Specifications (TS) contains a requirement for submitting a report for safety relief Valve challenges (Technical Specification 5.6.6). Enclosure A is provided in accordance with Technical Specification 5.6.6 to meet this requirement.
Enclosure B is attached and contains a report on service life of the main steam bypass lines. This satisfies the commitment stated in Detroit Edison letter to the NRC dated November 7, 1986 (VP-86-0154).
Enclosure C is attached in accordance with 10 CFR 50.46(a)(3)(ii) and contains a report of Emergency Core Cooling System (ECCS) cooling performance-evaluation model changes or errors.Should you have any questions or require additional information, please contact me at (734) 586-5197.Sincerely, Ronald W. Gaston Manager, Nuclear Licensing* iDC)A DTE Energy Company USNRC NRC-06-00 16 March 16, 2006 Page 2 Enclosure A: Safety Relief Valve Challenge Report Enclosure B: Service Life of Main Steam Bypass Lines Enclosure C: ECCS Cooling Performance Evaluation Model Changes or Errors cc: w/Enclosures D. H. Jaffe T. J. Kozak NRC Resident Office Regional Administrator, Region III Supervisor, Electric Operators, Michigan Public Service Commission
-4 Enclosure A to NRC-06-0016 March I16, 2006 Page 1 of 2 ENCLOSURE A FERMI 2 SAFETY RELIEF VALVE CHALLENGE REPORT JANUARY 1 -DECEMBER 31,2005 DETROIT EDISON COMPANY NRC DOCKET NO. 50-341 FACILITY OPERATING LICENSE NO. NPF-43 Enclosuire A to NRC-06-001 6 March 16, 2006 Page 2 of 2 Safety Relief Valve Challenges There were no instances in 2005 where reactor pressure was high enough to require Safety Relief Valve (SRV) actuation.
There were no instances in 2005 where an SRV actuation was demanded by an automatic logic system or the valves were cycled for surveillance testing.
a Enclosure B to NRC-06-0016 March 16, 2006 Page 1 of 2 ENCLOSURE B FERMI 2 SERVICE LIFE OF MAIN STEAM BYPASS LINES JANUARY 1 -DECEMBER 31,2005 DETROIT EDISON COMPANY NRC DOCKET NO. 50-341 FACILITY OPERATING LICENSE NO. NPF-43 I Enclosure B to NRC-06-0016 March 16,2006 Page 2 of 2 Service Life of Main Steam Bypass Lines In accordance with Detroit Edison letter to the NRC dated November 7, 1986 (VP-86-0154), the cumulative time the main steam bypass lines are operated with the bypass valves between 30 percent and 45 percent open will be reported annually.
A cumulative value of 100 days is riot to be exceeded without prior NRC notification.
Evaluations performed by Stone and Webster and by Hopper and Associates concluded that the bypass lines are acceptable for safe operation when operated within the 100 day constraint.
Based on these evaluations, the new main steam bypass piping that was installed in 1985 :has a service life that will allow it to function for the life of the plant under anticipated operating conditions.
The main steam bypass lines cumulative usage was 40.66 days as of December 31, 2005.
Enclosure C to NRC-06-0016 March 16, 2006 Page 1 of 2 ENCLOSURE C FERMI 2 ECC'S COOLING PERFORMANCE EVALUATION MODEL CHANGES OR ERRORS JANUARY I -DECEMBER 31,2005 DETROIT EDISON COMPANY NRC DOCKET NO. 50-341 FACILITY OPERATING LICENSE NO. NPF-43 Enclosure C to NRC-06-0016 March 16, 2006 Page 2 of 2 ECCS Cooling Performance Evaluation Model Changes or Errors There have been no errors identified since last year's annual report.The current license basis Peak Clad Temperature (PCT) for Fermi 2 is 1650 degrees Fahrenheit.
This is a change from the previous reporting period. Fermi 2 re-analyzed the Loss of CoDlant Accident (LOCA) for all fuel currently in the Reactor Pressure Vessel. Two LOCA analyses were performed for General Electric (GE) 11 and GE 14 fuel which also incorporated all error reports. No new error reports have been issued against Fermi 2 since completing the LOCA analysis.
There is a 550 degrees Fahrenheit margin to the 2200 degrees Fahrenheit PCT limit given in 10 CFR 50.46.