Letter Sequence RAI |
---|
|
|
MONTHYEARML1005704142010-02-24024 February 2010 Technical Specifications Change - Main Control Room Chiller Completion Time Extension Project stage: Request ML1006801422010-04-0101 April 2010 Acceptance Review Regarding the Proposed Allowed Outage Time One-Time Extension for the Chiller Upgrade Project (Tac No. ME3429) Project stage: Acceptance Review ML1026500432010-09-20020 September 2010 Technical Specifications Change - Main Control Room Chiller Completion Time Extension - Supplemental Information Project stage: Request ML1028000312010-10-0808 October 2010 Request for Additional Information Regarding the Proposed Allowed Outage Time One- Time Extension for the Chiller Upgrade Project Project stage: RAI ML1031204552010-11-0505 November 2010 Response to Request for Additional Information Concerning - Technical Specifications Change WBN-TS-09-16 - Main Control Room Chiller Completion Time Extension Project stage: Response to RAI ML1101902802011-02-0808 February 2011 License Amendment, Issuance of Amendment Revising TS 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) Project stage: Approval 2010-02-24
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21102A1312021-04-19019 April 2021 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 ML21095A0422021-04-0202 April 2021 NRR E-mail Capture - Added Clarification to RAI 2 for Thot LAR ML21095A0402021-04-0202 April 2021 NRR E-mail Capture - Request for Additional Information Re Generic Letter 95-05 90-Day Report and LAR to Adjust Growth Rate for Thot (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0412021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0442021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21091A0772021-04-0101 April 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Technical Specification 5.7.2.19, Containment Leakage Rate Testing Program ML21095A0462021-03-22022 March 2021 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Generic Letter 95-05 90-Day Report for Watts Bar Unit 2 ML21039A6402021-02-0808 February 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 1 Technical Specifications Related to Steam Generator Tube Inspection Frequency ML21012A2032021-01-11011 January 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar UFSAR to Use Alternate Probability of Detection ML20350B5592020-12-15015 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Adopt Traveler TSTF-490 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20322A4412020-11-17017 November 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20322A4392020-11-0505 November 2020 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20308A3512020-11-0202 November 2020 Request for Additional Information on WBN Request for Exemption from 10 CFR Part 73, Appendix B, Section VI for the Conduct of an Annual Force-on-Force Exercise (EPID L-2020-LLE-0165 (COVID-19)) ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information ML20196L8622020-07-14014 July 2020 NRR E-mail Capture - Watts Bar Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Implement the Full Spectrum LOCA Methodology ML20086G4802020-03-26026 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) - Part 2 ML20085G3572020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20084M1942020-03-24024 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20083J3952020-03-12012 March 2020 NRR E-mail Capture - Draft Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML19340A6842019-12-0505 December 2019 NRR E-mail Capture - Request for Additional Information for WBN2 Request for One-Time Extension of Completion Time for TS 3.7.8 (L-2019-LLA-0020) ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19186A4352019-07-0505 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Correction to Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19169A3592019-06-18018 June 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19106A0462019-04-15015 April 2019 NRR E-mail Capture - Watts BAR, Units 1 and 2 Request for Additional Informatin (RAI) Regarding Changes to Technical Specifications Sections 3.8.1, 3.8.7, 3.8.8, and 3.8.9 ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program ML18313A2202018-11-0707 November 2018 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML18282A6372018-10-0909 October 2018 NRR E-mail Capture - RAIs (Final) - LAR to Revise the Steam Generator Technical Specifications for Watts Bar Nuclear Plant, Unit 2 ML18270A2362018-09-26026 September 2018 NRR E-mail Capture - Watts Bar Units 1 and 2 RAIs - Modify TS 3.8.9 Completion Time for Inoperable 120V AC Vital Buses (L-2018-LLA-0050) ML18240A0702018-08-27027 August 2018 NRR E-mail Capture - RAI for Watts Bar Unit 2 Tpbars LAR and Watts Bar Units 1 and 2 LAR Related to Fuel Storage ML18199A1822018-07-17017 July 2018 NRR E-mail Capture - Request for Additional Information Regarding Watts Bar Unit 1 Extension of Surveillance Requirement Intervals ML18123A3942018-05-0303 May 2018 NRR E-mail Capture - Request for Additional Information Unit 2 Cycle 1 Steam Generator Tube Inspection Report ML18057A6372018-02-23023 February 2018 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet Topical Report TVA-NPG-AWA16 - EPIC: L-2016-TOP-0011) ML18031A6592018-02-0606 February 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Revise Technical Specification 4.2.1 and Technical Specifications Related to Fuel Storage ML18016A0112018-01-12012 January 2018 Draft Request for Additional Information Exigent Amendment Request for Inoperable Reactor Coolant Temperature Indication ML17226A0032017-08-11011 August 2017 NRR E-mail Capture - Watts Bar, Unit 1 - Final Request for Additional Information Concerning Request to Amend Turbine Trip Low Fluid Oil Pressure Reactor Protection System Trip Setpoint 2023-06-15
[Table view] Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 October 8, 2010 Mr. R. M. Krich Vice President, Nuclear Licensing Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 WATTS BAR NUCLEAR PLANT, UNIT 1 -REQUEST FOR ADDITIONAL INFORMATION REGARDING THE PROPOSED ALLOWED OUTAGE TIME ONE-TIME EXTENSION FOR THE CHILLER UPGRADE PROJECT (TAC NO. ME3429)
Dear Mr. Krich:
By letter dated February 24, 2010 (Agencywide Document and Access Management System Accession No. ML 100570414), as supplemented September 20,2010 (ML 102650043), Tennessee Valley Authority (TVA) submitted a license amendment request for Watts Bar Nuclear Plant, Unit 1. The proposed amendment request would revise Technical Specification (TS) 3.7.11 "Control Room Emergency Air Temperature Control System (CREATCS)." The proposed change would only be applicable during plant modifications to upgrade the CREATCS chillers.
This "one-time" TS change would be implemented during WBN Unit 1 Cycles 10 and 11 beginning December 1,2010, and ending January 29,2012. TVA has requested the U.S. Nuclear Regulatory Commission (NRC) staff complete its review by December 1, 2010. In order to complete its review, the NRC staff requires additional information.
Enclosed is the NRC staff's request for additional information (RAI) concerning the proposed allowed outage time one-time extension for the chiller upgrade project. Based on discussions with your staff on October 5, 2010, we understand that you plan to respond to the enclosed RAI by October 29, 2010.
-2 If you have any questions regarding this issue, please feel free to contact me at (301) 415-3100.
G. Lamb, Senior Project Manager Wi s Bar Special Projects Branch D ision of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-390
Enclosure:
RAI cc: Distribution via Listserv REQUEST FOR ADDITIONAL INFORMATION REGARDING THE PROPOSED ALLOWED OUTAGE TIME ONE-TIME EXTENSION FOR THE CHILLER UPGRADE WATTS BAR NUCLEAR PLANT, UNIT 1 TENNESSEE VALLEY AUTHORITY DOCKET NO. 50-390 By letter dated February 24, 2010 (Agencywide Document and Access Management System Accession No. ML 100570414), as supplemented September 20, 2010 (ML 102650043), Tennessee Valley Authority (TVA) submitted a license amendment request for Watts Bar Nuclear Plant (WBN), Unit 1. The proposed amendment request would revise Technical Specification (TS) 3.7.11 "Control Room Emergency Air Temperature Control System (CREATCS)." The proposed change would only be applicable during plant modifications to upgrade the CREATCS chillers.
This "one-time" TS change would be implemented during WBN Unit 1 Cycles 10 and 11 beginning December 1,2010, and ending January 29,2012. TVA has requested the U.S. Nuclear Regulatory Commission (NRC) staff complete its review by December 1, 2010. In order to complete its review, the NRC staff requires additional information.
Below is the NRC staff's request for additional information (RAI) concerning the proposed allowed outage time one-time extension for the chiller upgrade project. In your application dated February 24,2010, the Note associated with TS 3.7.11 could potentially allow one CREA TCS train to be taken out of service multiple times. Do you intend to remove one CREATCS train from service multiple times? If not, please revise the Note to limit each train to be out of service one time only. Section 1.0 (4 th paragraph) indicates that one main control room (MCR) chiller train can maintain the ambient temperature in the MCR and its associated spaces below their design limit (less than 104 OF). Section 2.1.2 (1 st paragraph) indicates that the temporary chilled water package will also maintain the personnel comfort temperature less than or equal to 90 of. Section 3.2 (1 st paragraph) makes a reference to WBN Calculation MDQ00003120090157 and states that "The calculation concluded that with the initial ambient temperature at 75 of, it would take at least 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> upon the loss of cooling before the maximum environmental temperature of 104 OF would be exceeded in the MCR." From this statement, it appears that the MCR cooling system normally maintains the MCR at 75 of. Since the nominal rating of the temporary chiller is considerably larger than the loss-of-coolant accident (LOCA) heat load (as indicated in Section 3.1.4, Table 4), it also appears that the temporary chilled water system can also maintain the control room below all the temperature criteria discussed above. But, Table 1 also references a calculated room temperature of less than 85 OF with the temporary equipment.
Please provide a perspective of all the different temperatures
-2 noted above and clarify if the temporary chilled water system is capable of fulfilling all the cooling functions of the permanent system. Please explain if the temporary chilled water system for the MCR has any impact on the control room habitability.
Include in your response, a discussion of the control room envelope boundary, control room emergency filtration system and postaccident radiological protection, fire and flood, and how they might be impacted.
Also, include a discussion on the precautions taken to protect other equipment in the plant from fire, physical damage, movement of portable equipment, etc. during construction activities. There is a statement in the second paragraph of Section 3.1.3, "Compensatory Measures" that reads "Qualified personnel will be provided with informal training on these instructions." Explain the difference between "informal training" and any other types of training at WBN Unit 1 and provide your justification why "informal training" is deemed to be adequate, keeping in context that the temporary cooling equipment performs important safety-related function if it is called upon to operate during postaccident conditions. The statement in Requirement 2 under Section 3.1.3 indicates that qualified personnel will be stationed in the area whenever the valves are in the "Open" position and the temporary cooling system is in service. Confirm that qualified personnel will be stationed throughout the 60-day period, even when the temporary system is not operating during this period. Also, provide details about the additional areas where qualified personnel will be stationed and the purpose of their presence during this period. The statement in Requirement 4 under Section 3.1.3 states that no planned maintenance activity, except for Surveillance Requirements (SRs) 3.8.1.2, 3.8.1.3, and 3.8.1.7, that could impact the operability of the diesel generators (DGs) that provide emergency power to the operable MCR chiller train will be performed.
Based on TS 3.7.11, Condition A, if the only qualified MCR cooling system available during the 60-day period becomes inoperable, WBN Unit 1 will enter limiting condition of operation (LCO) 3.0.3 immediately.
If the DG SRs result in immediate maintenance to the DGs, explain the impact on the operability of the MCR cooling system in TS 3.7.11. Include in your response, any other systems that support the MCR cooling system and how their maintenance or surveillance could also impact TS 3.7.11. The shutdown board room (SDBR) cooling system is not a TS support system. However, in Section 4.1, "Applicable Regulatory Requirements/Criteria," there is a reference made to 6.9 KiloVolts (kV) SDBR TSs. Further, in Section 2.1.3 "Phase 3 SDBR Chiller A and MCR Chiller A Replacement," it is stated that "If train -B SDBR chiller were to fail during installation of the new train -A SDBR chiller package, the plant will evaluate the impact and enter the appropriate TS action if required." Please explain how the 6.9 kV SDBR or any other TSs is impacted by the SDBR cooling system failures.
Include in your response, a discussion of the processes in place that would lead you from the time the failures are discovered to when the determination is made that TSs are impacted. The temporary chillers will be located outside in the yard. The License Amendment Request did not provide any discussion on how the plant deals with adverse weather
-3 conditions such as thunderstorms, tornado watches or tornado warnings, hurricanes, high winds, etc. Provide a discussion of how the temporary equipment could be affected under these conditions, and the processes in place at WBN Unit 1 to address these conditions, and how the temporary equipment is protected and downtime minimized.
-2 If you have any questions regarding this issue, please feel free to contact me at (301) 415-3100.
Sincerely, IRAI John G. Lamb, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-390
Enclosure:
RAI cc: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDorlDpr Resource LPWB Reading RidsOpaMail Resource RidsNrrDorlLp-Wb Resource RidsOgcRp Resource RidsAcrsAcnw_MailCTR Resource RidsRgn2MailCenler Resource RidsNrrDssScvb Resource RidsNrrPMWattsBar1 Resource RidsNrrDirsllsb Resource VCusumano, NRR/DIRS/ITSB RidsNrrLABClaylon Resource NKaripineni, NRR/DSS/SCVB Accession No'.. ML 102800031 OFFICE DORLIWBSP/PM DORLIWBSP/LA DORLIWBSP/BC NAME JLamb BClaylon SCamp bell DATE 10108/10 10107 110 10108/10 OFFICIAL RECORD COPY