NRR E-mail Capture - Request for Additional Information Unit 2 Cycle 1 Steam Generator Tube Inspection Report
ML18123A394
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 05/03/2018
From: Farideh Saba
Plant Licensing Branch II
To: Wells R
Tennessee Valley Authority
References
L-2018-LRO-0010
Download: ML18123A394 (3)


Text

1 NRR-DMPSPEm Resource From:

Saba, Farideh Sent:

Thursday, May 3, 2018 8:50 AM To:

Wells, Russell Douglas Cc:

Schaaf, Robert; Johnson, Andrew; Tindell, Brian; Schrull, Edward Dustin; Jordan, Natreon

Subject:

Request for Additional Information Re: Unit 2 Cycle 1 Steam Generator Tube Inspection Report (EPID L-2018-LRO-0010)

Importance:

High Tracking Tracking:

Recipient Wells, Russell Douglas Schaaf, Robert Johnson, Andrew Tindell, Brian Schrull, Edward Dustin Jordan, Natreon

Russel, By letter dated February 16, 2018 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML18047A370), the Tennessee Valley Authority (TVA) submitted the results of the steam generator inspections performed at Watts Bar Nuclear Plant, Unit 2. These inspections were performed during the first refueling outage.

The U.S. Nuclear Regulatory Commission (NRC) staff has determined that additional information, as described in the below request for additional information (RAI), is required for the staff to complete its review of the steam generator inspection report.

Draft RAI was sent to you on April 27, 2018, to confirm your understanding of the information that the NRC staff needs to complete the review. On May 2, 2018, a clarification call was held between the TVA and NRC staff to discuss the draft RAIs. As we agreed during this call, please submit TVAs responses to the NRC RAI by June 4, 2018.

Thanks, Farideh Farideh E. Saba, P.E.

Senior Project Manager NRC/ADRO/NRR/DORL 301-415-1447 Mail Stop O-8B01A Farideh.Saba@NRC.GOV

2 REQUEST FOR ADDITIONAL INFORMATION FALL 2017 STEAM GENERATOR TUBE INSPECTION REPORT TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT, UNIT 2 DOCKET NO. 50-391 By letter dated February 16, 2018 (Agencywide Documents Access and Management System Accession No. ML18047A370), Tennessee Valley Authority, (the licensee) submitted the results of the steam generator (SG) inspections performed at Watts Bar Nuclear Plant, Unit 2. These inspections were performed during the first refueling outage (RFO 1).

In order to complete its review, the U.S. Nuclear Regulatory Commission staff requests the following additional information:

1. The technical specifications require that a condition monitoring assessment be performed, during each outage during which the SG tubes are inspected or plugged, to confirm that the performance criteria are being met. The technical specifications also require the reporting of location, orientation (if linear), and measured sizes (if available) of service-induced indications. Please clarify the information provided in the report from RFO 1 regarding the following:
a. Section 2.0, 180 Day Steam Generator Tube Inspection Report, sub-section e., Number of Tubes Plugged During the Inspection Outage for Each Degradation Mechanism, discusses a permeability variation found in a tube in SG 3. Please discuss how signal injection and engineering assessment were used to develop the basis for concluding that condition monitoring was confirmed.
b. Please describe the anomaly in tube support plate H01 of SG 3 (identified during inspection) and how it affected the eddy current inspection scope performed in the tubes near Row 47, Column 48.
c. Please confirm that all service-induced indications that were identified during the fall 2017 outage were included in the February 16, 2018, report.

Hearing Identifier:

NRR_DMPS Email Number:

343 Mail Envelope Properties (DM5PR0901MB2437741D1C38F4022702D6CC9F870)

Subject:

Request for Additional Information Re: Unit 2 Cycle 1 Steam Generator Tube Inspection Report (EPID L-2018-LRO-0010)

Sent Date:

5/3/2018 8:49:37 AM Received Date:

5/3/2018 8:49:00 AM From:

Saba, Farideh Created By:

Farideh.Saba@nrc.gov Recipients:

"Schaaf, Robert" <Robert.Schaaf@nrc.gov>

Tracking Status: None "Johnson, Andrew" <Andrew.Johnson@nrc.gov>

Tracking Status: None "Tindell, Brian" <Brian.Tindell@nrc.gov>

Tracking Status: None "Schrull, Edward Dustin" <edschrull@tva.gov>

Tracking Status: None "Jordan, Natreon" <Natreon.Jordan@nrc.gov>

Tracking Status: None "Wells, Russell Douglas" <rdwells0@tva.gov>

Tracking Status: None Post Office:

DM5PR0901MB2437.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2983 5/3/2018 8:49:00 AM Options Priority:

High Return Notification:

No Reply Requested:

Yes Sensitivity:

Normal Expiration Date:

Recipients Received: