MONTHYEARML23079A0902023-03-20020 March 2023 1B- Post Exam Comments IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 ML22217A0792022-08-0303 August 2022 301, Corporate Notification Letter (210-day Ltr) ML22199A2552022-07-0606 July 2022 Ds Catawba 2022 RQ Inspection Notification Letter ML21321A0882021-11-17017 November 2021 301 File 2B Exam Draft Items ML21320A3282021-11-16016 November 2021 301 File 2A2 Exam Draft Items (1).pdf ML21320A3312021-11-16016 November 2021 301 File 2A3 Exam Draft Items ML21286A5252021-10-13013 October 2021 1A Final SRO Exam, Answer Key, References ML21286A3632021-10-13013 October 2021 1A Final RO Exam, Answer Key, References ML21258A3892021-09-15015 September 2021 Operating Licensing Examination Approval 05000413/2021301 and 05000414/2021301 ML21055A6072021-02-23023 February 2021 301 Exam Corporate Notification Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 RA-20-0075, Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19308A2502019-11-0404 November 2019 301 ADAMS 2D Page 1 Exam Admin Items Normal Release ML19281E0172019-10-0808 October 2019 301 Exam Report Items Delayed Release RO as Given ML19281E0202019-10-0808 October 2019 301 Post Exam Comments IR 05000413/20193012019-09-0303 September 2019 Operator Licensing Written Examination Approval 05000413/2019301 and 05000414/2019301 ML19058A6322019-07-0101 July 2019 Issuance of Amendments to Revise Emergency Action Level Schemes to Incorporate Clarifications Provided by Emergency Preparedness FAQs RA-19-0237, Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations2019-05-15015 May 2019 Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 ML18086B0442018-02-16016 February 2018 Facility Cover Letter - Rii - March 2018 - GFE ML17241A2282017-08-29029 August 2017 301 ADAMS2D Page 1 Exam Admin Items Immediate Release ML17241A2162017-08-29029 August 2017 301 ADAMS2B Final Exam Items Delay Release ML17241A2232017-08-29029 August 2017 301 ADAMS 2C Exam Admin Items Delay Release IR 05000413/20173012017-08-15015 August 2017 NRC Operator License Examination Report 05000413/2017301 and 05000414/2017301 ML17215A7792017-08-0303 August 2017 301 Post Exam Comments ML17215A7942017-08-0303 August 2017 301 Exam Report Items RO as Given - Delay Release ML17215A8012017-08-0303 August 2017 301 Exam Report Items SRO as Given - Delay Release ML17192A1792017-07-11011 July 2017 301 Exam Final Items 2B - Delay Release 2 Yrs ML17192A1812017-07-11011 July 2017 301 Exam Administrative Items 2C - Delay Release 2 Yrs ML17178A2942017-06-21021 June 2017 Operator Licensing Written Examination Approval 05000413, 414/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 IR 05000413/20163012016-07-13013 July 2016 NRC Operator License Examination Report 05000413/2016301 and 05000414/2016301, May 16 19, 2016 and May 26, 2016 ML16166A1022016-06-13013 June 2016 301 as Given SRO Written Exam with References and Answer Key ML16166A0992016-06-13013 June 2016 301 as Given RO Written Exam with References and Answer Key ML16166A1062016-06-13013 June 2016 301 Facility Post Exam Comments ML16104A4262016-04-0808 April 2016 March 2016 - Catawba NRC Generic Fundamentals Examination Results ML15356A8282015-12-22022 December 2015 Notification of Licensed Operator Initial Examination 05000413/2016301 and 05000414/2016301 ML15245A2942015-08-31031 August 2015 Initial Exam 2015-301 Draft RO Written Exam ML15245A3162015-08-31031 August 2015 Initial Exam 2015-301 General Correspondence ML15245A3112015-08-31031 August 2015 Initial Exam 2015-301 Post Exam Comments ML15245A3092015-08-31031 August 2015 Initial Exam 2015-301 Final Administrative JPMs ML15245A3072015-08-31031 August 2015 Initial Exam 2015-301 Final Sim In-Plant JPMs ML15245A3052015-08-31031 August 2015 Initial Exam 2015-301 Final Simulator Scenarios ML15245A3032015-08-31031 August 2015 Initial Exam 2015-301 Final Administrative Documents ML15245A2962015-08-31031 August 2015 Initial Exam 2015-301 Draft SRO Written Exam ML15245A3022015-08-31031 August 2015 Initial Exam 2015-301 Draft Administrative JPMs ML15245A3012015-08-31031 August 2015 Initial Exam 2015-301 Draft Sim In-plant JPMs ML15245A2992015-08-31031 August 2015 Initial Exam 2015-301 Draft Simulator Scenarios 2023-03-20
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23079A0902023-03-20020 March 2023 1B- Post Exam Comments IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 ML22217A0792022-08-0303 August 2022 301, Corporate Notification Letter (210-day Ltr) ML21321A0882021-11-17017 November 2021 301 File 2B Exam Draft Items ML21320A3282021-11-16016 November 2021 301 File 2A2 Exam Draft Items (1).pdf ML21320A3312021-11-16016 November 2021 301 File 2A3 Exam Draft Items ML21286A5252021-10-13013 October 2021 1A Final SRO Exam, Answer Key, References ML21286A3632021-10-13013 October 2021 1A Final RO Exam, Answer Key, References ML21258A3892021-09-15015 September 2021 Operating Licensing Examination Approval 05000413/2021301 and 05000414/2021301 ML21055A6072021-02-23023 February 2021 301 Exam Corporate Notification Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 RA-20-0075, Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML19308A2502019-11-0404 November 2019 301 ADAMS 2D Page 1 Exam Admin Items Normal Release ML19281E0172019-10-0808 October 2019 301 Exam Report Items Delayed Release RO as Given ML19281E0202019-10-0808 October 2019 301 Post Exam Comments IR 05000413/20193012019-09-0303 September 2019 Operator Licensing Written Examination Approval 05000413/2019301 and 05000414/2019301 RA-19-0237, Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations2019-05-15015 May 2019 Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations ML17241A2282017-08-29029 August 2017 301 ADAMS2D Page 1 Exam Admin Items Immediate Release ML17241A2162017-08-29029 August 2017 301 ADAMS2B Final Exam Items Delay Release ML17241A2232017-08-29029 August 2017 301 ADAMS 2C Exam Admin Items Delay Release IR 05000413/20173012017-08-15015 August 2017 NRC Operator License Examination Report 05000413/2017301 and 05000414/2017301 ML17215A7792017-08-0303 August 2017 301 Post Exam Comments ML17215A7942017-08-0303 August 2017 301 Exam Report Items RO as Given - Delay Release ML17215A8012017-08-0303 August 2017 301 Exam Report Items SRO as Given - Delay Release ML17192A1792017-07-11011 July 2017 301 Exam Final Items 2B - Delay Release 2 Yrs ML17192A1812017-07-11011 July 2017 301 Exam Administrative Items 2C - Delay Release 2 Yrs ML17178A2942017-06-21021 June 2017 Operator Licensing Written Examination Approval 05000413, 414/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16166A1022016-06-13013 June 2016 301 as Given SRO Written Exam with References and Answer Key ML16166A0992016-06-13013 June 2016 301 as Given RO Written Exam with References and Answer Key ML16166A1062016-06-13013 June 2016 301 Facility Post Exam Comments ML16104A4262016-04-0808 April 2016 March 2016 - Catawba NRC Generic Fundamentals Examination Results ML15356A8282015-12-22022 December 2015 Notification of Licensed Operator Initial Examination 05000413/2016301 and 05000414/2016301 ML15245A2942015-08-31031 August 2015 Initial Exam 2015-301 Draft RO Written Exam ML15245A3052015-08-31031 August 2015 Initial Exam 2015-301 Final Simulator Scenarios ML15245A3032015-08-31031 August 2015 Initial Exam 2015-301 Final Administrative Documents ML15245A3072015-08-31031 August 2015 Initial Exam 2015-301 Final Sim In-Plant JPMs ML15245A3112015-08-31031 August 2015 Initial Exam 2015-301 Post Exam Comments ML15245A3162015-08-31031 August 2015 Initial Exam 2015-301 General Correspondence ML15245A2992015-08-31031 August 2015 Initial Exam 2015-301 Draft Simulator Scenarios ML15245A3022015-08-31031 August 2015 Initial Exam 2015-301 Draft Administrative JPMs ML15245A3012015-08-31031 August 2015 Initial Exam 2015-301 Draft Sim In-plant JPMs ML15245A2932015-08-31031 August 2015 Initial Exam 2015-301 Draft Administrative Documents ML15181A2292015-06-30030 June 2015 Initial Exam 2015-301 Final RO Written Exam ML15181A2322015-06-30030 June 2015 Initial Exam 2015-301 Final SRO Written Exam ML14240A6712014-10-27027 October 2014 301 Initial Exam Draft Simulator Scenarios ML14240A6662014-10-27027 October 2014 301 Draft SRO Written Examination ML14290A3322014-10-27027 October 2014 301 Post Exam Comments ML14290A3302014-10-27027 October 2014 301 Final Administrative Jpms ML14290A3262014-10-27027 October 2014 301 Final Sim in Plant JPMs 2023-03-20
[Table view] |
Text
PkDuke C PowerD.M. JAMIL Vice President December 21, 2005 Duke Power Catawba Nuclear Station 4800 Concord Road / CNOI VP York, SC 29745-9635 W. D. Travers, Regional Administrator U. S. Nuclear Regulatory Commission, Region 11 Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 803 831 4251 803 831 3221 fax
SUBJECT:
Duke Energy Corporation Catawba Nuclear Station, Unit I and 2 Docket Nos. 50-413 and 50-414 50-413/2005-301 and 50-414/2005-301 Post-Examination Documentation The enclosed post-examination documentation is provided in accordance with NUREG- 1021, Section 402 E.6. This post-examination documentation is associated with the Catawba Nuclear Station initial written licensing examinations administered the week of December 5, 2005.If you have any questions or need additional information, please contact John Suptela at 803.831.5123.
Sincerely, by U)ro-Dhiaa M. Jamil KEN/s xc: with attachments J. H. Moorman 111, Chief Operating Licensing Branch U. S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center 61 Forsythe Street, S.W., Suite 23T85 Atlanta, GA 30303-8931 without attachments U. S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001 a CaRawba Nudear Statton20th AnnIr mnna 1985- 2005 E. F. Guthrie Senior NRC Resident -Catawba CNOINC www dukepower corn Question 78 BACKGROUND This question was designed to test two knowledge elements: I .The students' ability to recognize the basis for Tech Spec 3.9.4 LCO.2. Determine the correct actions to be taken per Tech Specs in I hour or less given the conditions provided in the stem.The question psychometrics were such that the first parts of A and C were correct, and the second parts of A and B were correct. Therefore, the correct answer based on the key and intended by the exam development team was A.The stem does not address the status of I B train of ND. The validators did not ask questions related to the status of IB train of ND during question validation.
Without knowing the status of the I B train of ND, either A or C could be correct. If I B train of ND is assumed to be inoperable, then A is the correct answer. If I B train of ND is assumed to be operable, then C is the correct answer. Based on other information related to plant conditions in the stem, the operability of I B train cannot be determined since in this plant configuration, one train of equipment may not be operable; although it may be"available" (i.e. both offsite power and emergency D/G may not be aligned to the available essential bus).CONCLUSION By not addressing the condition of I B train of ND, two possible answers could be correct depending on the status assumed for lB train of ND. The stem provides enough information to narrow the correct answer to A or C, but does not provide enough information to select one over the other.The facility recommends that answer A or C be accepted as correct for this question.ATTACHED REFERENCES Question 78 from the 2005 Catawba NRC initial license exam Question:
05-78 1 Pt(s) Given the following conditions:
- Unit 1 in Mode 6* Refueling cavity is filled to 23 feet.* Core reload is in progress* NC temperature is 145 0 F* 1A residual heat removal (ND) train is in operation A leak has been reported on the IA ND pump motor cooler. To repair the leak, cooling flow to the motor cooler must be isolated.
Maintenance estimates it will take 40 minutes to complete repairs.What is the basis for having one ND loop in operation in this condition and how does this affect the ability to continue core reload?A. Provides an indication of reactor coolant temperature.
Core reload must be stopped.B. Ensures that a core Keff of less than or equal to 0.95 is maintained during fuel handling operations.
Core reload must be stopped.C. Provide an indication of reactor coolant temperature.
Core reload may continue provided no operations are permitted that would dilute the refueling cavity boron concentration.
D. Ensures that a core Keff of less than or equal to 0.95 is maintained during fuel handling operations.
Core reload may continue provided no operations are permitted that would dilute the refueling cavity boron concentration.
Ouestion 87 BACKGROUND This question was designed to test two knowledge elements: I. The action required per AP/1/A/5500/028 (Secondary Steam Leak) to address an atmospheric steam dump that is found open 2. The Tech Spec basis for the minimum temperature for criticality.
The question psychometrics were such that the first parts of A and C were correct, and the second parts of B, C, and D were correct. Therefore, the correct answer based on the key and intended by the exam development team was C.The first portion of the stem of the question asks what action is taken per the AP to attempt to close the atmospheric dump. AP step 9.e reads as follows: 9. (Continued)
ACTION/EXPECTED RESPONSE RESPONSE NOT OBTAINED e. Verify atmospheric dump valves -e. Perform the following:
CLOSED.1) Select "OFF RESET" on the following switches: o "STEAM DUMP INTLK BYP TRN A" o "STEAM DUMP INTLK BYP TRN B".2) IF valve will not close, THEN close affected atmospheric dump valve isolation valve.3) IF isolation valve will not close, THEN dispatch operator to fail air to affected atmospheric dump valve.Because the stem did not specify "first" action or similar wording, any action taken per the RNO column in step 9.e above is equally correct. Additionally, the words "attempt to close" imply that initial action may (or may not) be successful which strengthens the fact that any of the actions are correct.It is evident that the students understood the intent of the procedure related to an open atmospheric dump valve at power (to isolate that steam flowpath).
Based on post examination interviews with students, they believed that the first half of all four answers were correct. They interpreted the first part of answers B and D to mean that the steam dump valve was required to be isolated locally.
Their reasons for this determination were: I .Interpretation of the first part of answers B and D to be equivalent to the wording and intent of 9.e.2) RNO since the step does not specifically address where this could be accomplished (control room versus locally).2. Interpretation of the first part of answers B and D to be equivalent to the intent of 9.e.3) RNO since by closing the air supply the atmospheric dump, it should close.This is the only method by which this valve can be closed locally.Either of these reasons alone was sufficient to confirm their belief Given this, they then answered the question based on what they considered the "strongest" answer related to the basis for minimum temperature for criticality.
All students picked either B or D.CONCLUSION The wording of the stem and the psychometrics of the question coupled with the student thought process (without procedural reference) would lead to answers B, C, and D being correct. Based on NUREG- 1021 guidance, a question with no correct answer or more than 2 correct answers should be removed from the examination.
The facility recommends removal of this question from the examination.
ATTACHED REFERENCES AP/I/A/5000/028 (Secondary Steam Leak) Revision 4, page 8 Question 87 from the 2005 Catawba NRC initial license exam ACTION/EXPECTED RESPONSE IRESPONSE NOT nRTATNFnl II ---9. (Continued)
-e. Verify atmospheric dump valves -CLOSED e. Perform the following:
- 1) Select -OFF RESET" on the following switches_ .STEAM DUMP INTLK BYP TRN A"_ "STEAM DUMP INTLK BYP TRN B"._ 2) IF valve will not close, THEN close affected atmospheric dump valve isolation valve.-3) IF isolation valve will not close, THEN dispatch operator to fail air to affected atmospheric dump valve._ I. Venty CA PMP #1 -OFF.f. IF operation of CA PMP #1 is causing uncontrolled cooldown AND flow from CA PMP #1 not required, THEN stop CA PMP #1.
Question:
05-87 1 Pt(s) Initial conditions:
- Unit 1 is operating at 10-8 amps taking critical data* One atmospheric steam dump opens* Crew is performing AP/1/A/5500/028, Secondary Steam Leak What action is taken per AP/1/A/5500/028 to attempt to close the dump valve, and what design bases consideration (per Tech Spec 3.4.2, RCS Minimum Temperature for Criticality) is assured if this action is successful?
A. Take "A" and "B" "STEAM DUMP INTLK BYP" switches to "OFF/RESET" Steam generators are above their nil ductility reference temperature.
B. Dispatch operator to close the atmospheric dump valve isolation locally.MTC will be in the range of slightly positive to negative.C. Take "A" and "B" "STEAM DUMP INTLK BYP" switches to "OFF/RESET" The pressurizer is within its normal startup and operating range.D. Dispatch operator to close the atmospheric dump valve isolation locally.Proper indication and response of the excore detectors when the reactor is critical.