Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam System JPM A PAGE 1 OF 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam EVALUATION SHEET Task: Respond to an inadvertent dilution while shutdown per AP/1/A/5500/013 (Boron Dilution), Case II (Boron Dilution While Shutdown)

Alternate Path: Yes Facility JPM #: New Safety Function: 1

Title:

Chemical and Volume Control System K/A 004 A2.06 Ability to (a) predict the impacts of the following malfunctions or operations on the CVCS: and based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Inadvertent boration/dilution Rating(s): 4.2 / 4.3 CFR: 41.5 / 43/5 / 45/3 / 45/5 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

AP/1/A/5500/013 (Boron Dilution) rev. 24 Task Standard: Starts the 1A NI (Safety Injection) pump.

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #168.
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event RACK LOA-NI004 (RACKOUT NI PMP 1B)

OUT RACK LOA-NV067 (RACKOUT NV PMP 1B)

OUT RACK LOA-NV066 (RACKOUT NV PMP 1A) 2 OUT Ensure EVENT 2 = x10i167c (NV-353 & 364 MIXED BED DEMIN 1A ISOL CLOSE

pushbutton)

PAGE 3 OF 14

PAGE 4 0F 14 Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 5 Unit 1 RMWST is aligned for VCT makeup.

INITIATING CUES:

A boron dilution event is in progress, you have been instructed to perform AP/1/A/5500013 (Boron Dilution), Case II (Boron Dilution While Shutdown).

EXAMINER NOTE: After reading cue, provide the applicant with a copy of AP/1/A/5500/013 PAGE 4 OF 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 1. Verify boron dilution event - IN PROGRESS.

___ SAT STANDARD:

___ UNSAT Applicant determines a boron dilution event is in progress per the initiating cue.

COMMENTS:

STEP 2 Verify Reactor Trip: ___ SAT All rod bottom lights - LIT ___UNSAT All reactor trip and bypass breakers - OPEN.

STANDARD:

Applicant verifies the reactor is tripped by verifying all rod bottom lights are lit on the DRPI monitors and that the green OPEN lights are lit for RX TRIP BKR 1A and RX TRIP BKR 1B on 1MC-1.

COMMENTS:

PAGE 5 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 3 3. Verify core alterations - IN PROGRESS.

___ SAT STANDARD:

___ UNSAT Applicant verifies that core alterations are NOT because the unit is in MODE 5 and proceeds to the RNO.

COMMENTS:

STEP 4 3. RNO GO TO Step 5. ___ SAT STANDARD: ___ UNSAT Applicant proceeds to step 5 COMMENTS:

STEP 5 5. Evacuate personnel from reactor building using the CRITICAL following: STEP Containment evacuation alarm ___ SAT Plant page.

___ UNSAT STANDARD:

Applicant depresses the red ON pushbutton for the UNIT 1 CONT EVAC ALARM on 1MC-1 and makes a plant page.

This step is critical to perform either action to protect the health and safety of the people working inside containment.

COMMENTS:

PAGE 6 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 6 6. Stop any dilutions in progress as follows:

___ SAT

a. Place "NC MAKEUP CONTROL" switch to "STOP".

___ UNSAT STANDARD:

Applicant places the NC MAKEUP CONTROL to the STOP position 1MC-10.

COMMENTS:

STEP 7 6. b. Verify Unit 1 RMWST aligned for VCT makeup.

___ SAT STANDARD:

___ UNSAT Applicant verifies the Unit 1 RMWST is aligned per the initial conditions.

COMMENTS:

STEP 8 6. c. Place both reactor makeup water pumps to "OFF".

___ SAT STANDARD:

___ UNSAT Applicant places RX M/U WTR PUMP 1A and RX M/U WTR PUMP 1B to the OFF position on 1MC-10.

COMMENTS:

PAGE 7 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 9 6. d. Isolate the NV demineralizers as follows: CRITICAL STEP

1) Place 1NV-153A (Letdn Hx Otlt 3-Way Valve) in the "VCT" position. ___ SAT STANDARD: ___ UNSAT Applicant places 1NV-153A in the VCT position on 1MC-10.

This step is critical to prevent un-saturating the Mixed Bed Demineralizers.

COMMENTS:

STEP 10 6. d. 2) Ensure the following valves - CLOSED:

___ SAT 1NV-353 & 364 (Mixed Bed Demin 1A Isol) 1NV-368 & 379 (Mixed Bed Demin 1B Isol). ___ UNSAT STANDARD:

Applicant depresses the green CLOSE pushbutton for NV-353 & 364 MIXED BED DEMIN 1A ISOL and verifies the green CLSD light is lit for NV-368 & 379 MIXED BED DEMIN 1A ISOL on 1MC-10.

COMMENTS:

PAGE 8 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE Unit shutdown alignments may have established alternate boration flowpaths.

___ SAT STEP 11 7. Ensure proper BDMS operation as follows:

___ UNSAT

a. Verify at least one of the following alarm(s) - LIT:

1AD-2, E/2 "TRAIN A SHUTDOWN MARGIN ALARM" OR 1AD-2, F/2 "TRAIN B SHUTDOWN MARGIN ALARM".

STANDARD:

Applicant verifies at least one of the alarms is lit.

COMMENTS:

STEP 12 7. b. Ensure the following valves - OPEN:

___ SAT 1NV-252A (NV Pumps Suct From FWST) 1NV-253B (NV Pumps Suct From FWST). ___ UNSAT STANDARD:

Applicant verifies the red OPEN lights are lit for 1NV-252A and 1NV-253B on 1MC-10.

COMMENTS:

PAGE 9 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 13 7. c. Ensure the following valves - CLOSED:

___ SAT 1NV-188A (VCT Otlt Isol) 1NV-189B (VCT Otlt Isol). ___ UNSAT STANDARD:

Applicant verifies that the green CLSD lights are lit for 1NV-188A and 1NV-189B on 1MC-10.

COMMENTS:

STEP 14 7. d. Verify NV pump - ON.

___ SAT STANDARD:

___ UNSAT Applicant determines that no NV pumps are on and proceeds to the RNO.

COMMENTS:

STEP 15 7. d. RNO d. Perform the following:

___ SAT

1) IF NV pump 1A AND 1B boration flowpath NOT available, THEN GO TO Enclosure 1 (NI ___ UNSAT or ND Pump Boron Injection Alignment).

STANDARD:

Applicant proceeds to Enclosure 1.

COMMENTS:

PAGE 10 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT Enclosure 1 STEP 16 1. Align NC system boration flowpath as follows: ___ SAT

a. IF establishing NC system boration, THEN GO TO Step 2. ___ UNSAT STANDARD:

Applicant proceeds to step 2.

COMMENTS:

STEP 17 2. Initiate NC system boration flow as required using at least one of the following boration flowpaths. ___ SAT IF NI Pump 1A aligned to provide boron injection ___ UNSAT flowpath, THEN perform the following to establish NI Pump 1A injection flow:

a. Ensure 1NI-118A (NI Pump 1A C-Leg Inj Isol) - OPEN.

STANDARD:

Applicant verifies that the red OPEN light is lit for 1NI-118A on 1MC-11 COMMENTS:

PAGE 11 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 18 b. START NI Pump 1A. CRITICAL STEP STANDARD:

___ SAT Applicant depresses the red ON pushbutton for NI PMP 1A.

___ UNSAT This step is critical to initiate NC system boration flow.

NOTE TO EXAMINER: No other flow paths will be aligned.

COMMENTS:

STEP 19 3. WHEN NC system boration no longer required, THEN perform Step 5. ___ SAT STANDARD: ___ UNSAT Applicant acknowledges step.

COMMENTS:

STEP 20 4. GO TO Case II (Boron Dilution While Shutdown), Step 9.

___ SAT STANDARD:

___ UNSAT Applicant proceeds to Case II, Step 9.

COMMENTS:

PAGE 12 0F 14

Catawba Nuclear Station JPM A May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE A time delay of up to 3-5 minutes can be expected before indication of negative reactivity insertion is obtained on excore instrumentation. ___ SAT STEP 21 9. Verify neutron flux level - STABLE OR DECREASING. ___ UNSAT STANDARD:

Applicant reads the step.

Examiner Cue: Another operator will complete the procedure.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 13 0F 14

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM A READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 5 Unit 1 RMWST is aligned for VCT makeup.

INITIATING CUES:

A boron dilution event is in progress, you have been instructed to perform AP/1/A/5500013 (Boron Dilution), Case II (Boron Dilution While Shutdown).

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam JPM B PAGE 1 OF 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam EVALUATION SHEET Task: Transfer the Emergency Core Coolant System to the Cold Leg Recirculation Alternate Path: Yes Facility JPM #: NI-088 Safety Function: 2

Title:

Emergency Core Cooling System (ECCS)

K/A 006 A4.07 Ability to manually operate and/or monitor in the control room: ECCS pumps and valves.

Rating(s): 4.4 / 4.4 CFR: 41.7 / 45.5 to 45.8 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

EP/1/A/5000/ES-1.3 (Transfer to Cold Leg Recirculation)

Task Standard: EP/1/A/5000/ES-1.3 Transfer to Cold Leg Recirculation) step 6 is performed and the 1A and 1B NV (Chemical Volume and Control System) and NI (Safety Injection System) pumps are secured.

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #169
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event VLV-NI037F (NI184B CNMT SUMP LINE 1B 0

ISOL (STEM) FAIL TO POSITION)

MAL-NC013A (NC COLD LEG A LEAK) 27.5 VLV-ND005F (ND28A ND HX A OUTLET TO 0

CHARG AB FAIL TO POSITION.

PAGE 3 OF 15

PAGE 4 0F 15 Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A LOCA has occurred on Unit 1.

INITIATING CUES:

1AD-9, E/8 FWST LO-LO LEVEL annunciator is lit and the Control Room Supervisor instructs you, as the BOP, to transfer to Cold Leg Recirculation using EP/1/A/5000/ES-1.3 (Transfer to Cold Leg Recirculation) step 6.

EXAMINER NOTE: After reading the cue, provide the applicant with a copy of EP/1/A/5000/ES-1.3 (Transfer to Cold Leg Recirculation) complete through step 8 with step 6 flagged.

PAGE 4 OF 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 6. WHEN FWST level decreases to 5% (1AD-9, E/8 "FWST LO-LO LEVEL"), THEN align NV and NI Systems for recirc ___ SAT as follows:

___ UNSAT

a. Ensure Enclosure 1 (Foldout Page) is monitored.

STANDARD:

Applicant reads the step.

Examiner Cue: The OATC will monitor Enclosure 1 COMMENTS:

NOTE CSF should not be implemented until directed by this procedure.

STEP 2 b. Verify at least one of the following annunciators - LIT: ___ SAT 1AD-20, B/2 "CONT. SUMP LEVEL >2.5 ft" ___UNSAT OR 1AD-21, B/2 "CONT. SUMP LEVEL >2.5 ft".

STANDARD:

Applicant determines that one or both annunciators are lit.

COMMENTS:

PAGE 5 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 3 c. Verify both ND pumps - ON.

___ SAT STANDARD:

___ UNSAT Applicant determines that only 1 ND pump is running and transitions to the RNO COMMENTS:

STEP 4 6.c. RNO c. Perform the following: ___ SAT

1) IF 1NI-185A (ND Pump 1A Cont Sump Suct) is ___ UNSAT open, THEN start ND pump 1A.

STANDARD:

Applicant determines that ND PUMP 1A is on by verifying the red ON light is lit on 1MC-11.

COMMENTS:

STEP 5 2) IF 1NI-184B (ND Pump 1B Cont Sump Suct) is open, THEN start ND pump 1B. ___ SAT STANDARD: ___ UNSAT Applicant determines that 1NI-184B is not open by verifying the green CLSD light is lit on 1MC-11 and determines that the step is not applicable.

COMMENTS:

PAGE 6 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 6 3) IF any ND pump running with suction aligned to sump, THEN GO TO Step 6.d. ___ SAT STANDARD: ___ UNSAT Applicant determines that ND Pump 1A is running with suction aligned to the sump and proceeds to step 6.d.

COMMENTS:

STEP 7 6. d. Ensure the following valves - CLOSED: CRITICAL STEP 1ND-32A (ND Train 1A Hot Leg Inj Isol) 1ND-65B (ND Train 1B Hot Leg Inj Isol). ___ SAT STANDARD: ___ UNSAT Applicant depresses the green CLOSE pushbuttons for 1ND-32A and 1ND-65B on 1MC-11.

This step is critical to prevent pump run out should only one ND pump be running.

Examiner NOTE: Only one of the valves need to be closed to satisfy the critical step since the valves are in series.

COMMENTS:

PAGE 7 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 8 6. e. Isolate NI Pump Miniflow as follows:

___ SAT

1) Verify NC pressure - LESS THAN 1620 PSIG.

___ UNSAT STANDARD:

Applicant determines that NC (Reactor Coolant System) pressure is less than 1620 psig.

COMMENTS:

STEP 9 2) Ensure the following valves - CLOSED:

___ SAT 1NI-115A (NI Pump 1A Miniflow Isol) 1NI-144A (NI Pump 1B Miniflow Isol). ___ UNSAT STANDARD:

Applicant determines that the green CLSD lights are lit for 1NI-115A and 1NI-144A on 1MC-11.

COMMENTS:

STEP 10 3) Ensure "PWR DISCON FOR 1NI-147B" switch in "ENABLE". ___ SAT STANDARD: ___ UNSAT Applicant determines that the PWR DISCON FOR 1NI-147B is in ENABLE on 1MC-11.

COMMENTS:

PAGE 8 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 11 4) Ensure 1NI-147B (NI Miniflow Hdr To FWST Isol) -

CLOSED. ___ SAT STANDARD: ___ UNSAT Applicant determines that the green CLSD light is lit for 1NI-147B on 1MC-11.

COMMENTS:

STEP 12 6. f. Verify at least one of the following NV pumps miniflow valves - CLOSED: ___ SAT 1NV-203A (NV Pumps A&B Recirc Isol) ___ UNSAT OR 1NV-202B (NV Pmps A&B Recirc Isol).

STANDARD:

Applicant determines that the green CLSD lights is lit for 1NV-203A or 1NV-202B on 1MC-10.

COMMENTS:

STEP 13 g. Ensure 1NI-334B (NI Pump Suct X-Over From ND) - OPEN.

___ SAT STANDARD:

___ UNSAT Applicant determines the red OPEN light is lit for 1NI-334B on 1MC-11.

COMMENTS:

PAGE 9 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 14 h. OPEN the following valves:

___ SAT 1NI-332A (NI Pump Suct X-Over From ND) 1NI-333B (NI Pump Suct From ND). ___ UNSAT STANDARD:

Applicant depresses the red OPEN pushbuttons for 1NI-332A and 1NI-333B on 1MC-11.

COMMENTS:

STEP 15 i. Align ND discharge to suction of NI and NV pumps as follows: ___ SAT

1) OPEN 1ND-28A (ND Supply To NV & 1A NI Pmps). ___ UNSAT STANDARD:

Applicant depresses the red OPEN pushbutton for 1ND-28A on 1MC-11 and determines that the valve will not open and continues.

COMMENTS:

PAGE 10 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 16 2) OPEN 1NI-136B (ND Supply To NI Pump 1B).

___ SAT STANDARD:

___ UNSAT Applicant depresses the red OPEN pushbutton for 1NI-136B on 1MC-11, determines that the valve will not open and proceeds to the next step.

Examiner NOTE: 1NI-136B will not open due to an interlock with 1NI-184B COMMENTS:

STEP 17 j. Verify at least one ND train aligned to provide suction to NV and NI as follows: ___ SAT A Train: ___ UNSAT 1A ND pump running 1ND-28A (ND Supply To NV & 1A NI Pmps) -

OPEN.

STANDARD:

Applicant determines no train can be aligned to provide suction to NV and NI and proceeds to the RNO.

COMMENTS:

PAGE 11 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 18 6.j. RNO j. Perform the following:

___ SAT

1) IF either valve is in intermediate position, THEN allow 20 seconds for valve to open. ___ UNSAT STANDARD:

Applicant determines that this step does not apply.

COMMENTS:

STEP 19 2) IF either valve is open AND its associated ND pump on, THEN GO TO Step 6.k. ___ SAT STANDARD: ___ UNSAT Applicant determines that this step does not apply.

COMMENTS:

PAGE 12 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 20 3) IF both A train and B train unavailable, THEN CRITICAL trip all NV and NI pumps. STEP STANDARD: ___ SAT Applicant determines both A train and B train are unavailable and ___ UNSAT depresses the green OFF pushbuttons for NV PMP 1A, NV PUMP 1B, NI PMP 1A and NI PUMP 1A.

This step is critical to protect the NV and NI pumps from damage from loss of suction and allow them to be available later when the FWST has been refilled.

COMMENTS:

STEP 21 k. Isolate FWST from NV and NI pumps as follows:

___ SAT

1) Place "PWR DISCON FOR 1NI-100B" switch in "ENABLE". ___ UNSAT STANDARD:

Applicant places the switch for PWR DISCON FOR 1NI-100B in the ENABLE position.

COMMENTS:

PAGE 13 0F 15

Catawba Nuclear Station JPM B May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 22 2) CLOSE 1NI-100B (NI Pmps Suct From FWST).

___ SAT STANDARD:

___ UNSAT Applicant depresses the green CLOSE pushbutton for 1NI-100B on 1MC-11.

COMMENTS:

STEP 23 3) CLOSE the following valves:

___ SAT 1NV-252A (NV Pumps Suct From FWST) 1NV-253B (NV Pumps Suct From FWST). ___ UNSAT STANDARD:

Applicant depresses the green CLOSE pushbuttons for 1NV-252A and 1NV-253B on 1MC-10.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 14 0F 15

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK)

May 2014 NRC Initial License Exam JPM B READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A LOCA has occurred on Unit 1.

INITIATING CUES:

1AD-9, E/8 FWST LO-LO LEVEL annunciator is lit and the Control Room Supervisor instructs you, as the BOP, to transfer to Cold Leg Recirculation using EP/1/A/5000/ES-1.3 (Transfer to Cold Leg Recirculation) step 6.

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam System JPM C PAGE 1 OF 9

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam EVALUATION SHEET Task: Perform PT/1/A/4200/023B (NC PORV and Air Supply Stroke Test), Enclosure 13.4 (NC PORV Cycle)

Alternate Path: No Facility JPM #: New Safety Function: 3

Title:

Pressurizer Pressure Control K/A 010 A4.03 Ability to manually operate and/or monitor in the control room: PORV and block valves Rating(s): 4.0 / 3.8 CFR: 41.5 / 43.5 / 45.3 / 45.13 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

PT/1/A/4200/023B (NC PORV and Air Supply Stroke Test), Enclosure 13.4 (NC PORV Cycle) rev. 017 Task Standard: Enclosure 13.4 successfully completed for 1NC-32B (PZR PORV) and the associated valves are returned to the as found position.

Validation Time: 7 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 9

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #170
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event

PAGE 3 OF 9

PAGE 4 0F 9 Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 3.

INITIATING CUES:

The Control Room Supervisor instructs you to perform PT/1/A/4200/023B, Enclosure 13.4 for 1NC-32B.

EXAMINER NOTE: After reading cue, provide the applicant with a copy of PT/1/A/4200/023B, Enclosure 13.4.

PAGE 4 OF 9

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 1.1 IF testing 1NC-32B (Pzr PORV), perform the following:

___ SAT 1.1.1 Record the as found position of 1NC-31B (Pzr PORV Isol) below: ___ UNSAT STANDARD:

Applicant records OPEN as the as found position.

COMMENTS:

CRITICAL STEP 2 1.1.2 Ensure 1NC-31B (Pzr PORV Isol) is closed. STEP STANDARD: ___ SAT Applicant places the switch for 1NC-31B to the CLOSE or OVERRIDE ___UNSAT position.

This step is critical to prevent a pressure transient when 1NC-32B is opened.

COMMENTS:

PAGE 5 0F 9

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 3 1.1.3 Record the as found position of 1NC-32B (Pzr PORV) below: ___ SAT

___ UNSAT STANDARD:

Applicant records CLOSED as the as found position for 1NC-32B COMMENTS:

STEP 4 1.1.4 Circle below the as found switch position of 1NC-32B ___ SAT (Pzr PORV).

___ UNSAT Close Open Auto STANDARD:

Applicant circles Auto as the as found switch position of 1NC-32B.

COMMENTS:

STEP 5 1.1.5 Ensure 1NC-32B (Pzr PORV) is closed.

___ SAT STANDARD:

___ UNSAT Applicant determines that 1NC-32B is closed.

COMMENTS:

PAGE 6 0F 9

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 6 1.1.6 Cycle 1NC-32B (Pzr PORV) from closed to open to CRITICAL closed from the control room. STEP STANDARD: ___ SAT Applicant places the switch for 1NC-32B to the OPEN position and then ___ UNSAT to the AUTO or CLOSE position.

This step is critical to cycle 1NC-32B.

COMMENTS:

STEP 7 1.1.7 Return 1NC-32B (Pzr PORV) to the as found position, as recorded in Step 1.1.3 of this enclosure. ___ SAT STANDARD: ___ UNSAT Applicant determines that 1NC-32B is in the as found position as recorded in step 1.1.3.

COMMENTS:

STEP 8 1.1.8 Return switch for 1NC-32B (Pzr PORV) to the as found CRITICAL position, as recorded in Step 1.1.4 of this enclosure. STEP STANDARD: ___ SAT Applicant places the switch for 1NC-32B to the AUTO position. ___ UNSAT This step is critical to return the switch for 1NC-32B to the as found position.

COMMENTS:

PAGE 7 0F 9

Catawba Nuclear Station JPM C May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 9 1.1.9 Return 1NC-31B (Pzr PORV Isol) to the as found CRITICAL position, as recorded in Step 1.1.1 of this enclosure. STEP STANDARD: ___ SAT Applicant places the switch for 1NC-31B to the OPEN position. ___ UNSAT This step is critical to return 1NC-31B to the as found position and make 1NC-32B available for pressure relief.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 8 0F 9

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM C READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 3.

INITIATING CUES:

The Control Room Supervisor instructs you to perform PT/1/A/4200/023B, Enclosure 13.4 for 1NC-32B.

Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam System JPM D PAGE 1 OF 8

Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam EVALUATION SHEET Task: Start Reactor Coolant Pump 1B Alternate Path: Yes Facility JPM #: NCP081 (modified)

Safety Function: 4P

Title:

Reactor Coolant Pump System K/A 003 A1.01 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the RCPS control including: RCP vibration.

Rating(s): 2.9 / 2.9 CFR: 41.5 / 45.5 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

OP/1/A/6150/002A (Reactor Coolant Pump) rev. 068 Task Standard: 1B Reactor Coolant Pump is tripped when vibration is noted to be greater than NC pump trip criteria.

Validation Time: 20 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 8

Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam

1. Reset to any 100% power IC set.
2. Manually trip the reactor at 1MC-1.
3. Trip all (4) four NCP breakers at 1MC-10.
4. Place CF pump in service for auto S/G level control and secure CA.
5. Insert MAL-NCP005FXB (NCP VIB B MOUNT HORIZ FAILURE) Initial =0 Ramp =240 Value=10, EVENT =1, Delay = 5
6. Insert MAL-NCP005FYB (NCP VIB B MOUNT VERT FAILURE) Initial =0 Ramp =240 Value=10, EVENT =1, Delay = 5
7. Insert MAL-NCP005SXB (NCP VIB B MOUNT HORIZ FAILURE) Initial =0 Ramp =120 Value=30, EVENT =1, Delay = 5
8. Insert MAL-NCP005SYB (NCP VIB B MOUNT VERT FAILURE) Initial =0Ramp =120 Value=30, EVENT =1, Delay = 5
9. Insert EVENT 1 = x10d185M >400 (NCP B AMPS>400)
10. Freeze simulator and write to a snap.

IC SELECTED:

SIMULATOR OPERATOR INSTRUCTIONS:

ENSURE BENTLEY NEVADA VIBRATION MONITORS ON BACK BOARD ARE RESET AND THAT ALARMS 1AD-6 A/5 AND B/5 ARE CLEARED BETWEEN STUDENTS.

PAGE 3 OF 8

Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #171
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event MAL-NCP005FXB (NCP VIB 1B MOUNT 4 10 5 1 HORZ FAILURE) MIN MAL-NCP005FYB (NCP VIB 1B MOUNT VERT 4 10 5 1 FAILURE) MIN MAL-NCP005SXB (NCP VIB 1B SHAFT HORZ 2 30 5 1 FAILURE) MIN MAL-NCP005SYB (NCP VIB 1B SHAFT VERT 2 30 5 1 FAILURE) MIN Ensure EVENT 1 = x10d185m>400 (NCP B AMPS > 400)

PAGE 4 OF 8

PAGE 5 0F 8 Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

EP/1/A/5000/ES-0.2, Natural Circulation Cooldown has been implemented following a Reactor Trip caused by a lightning strike in the switchyard. Normal power has been restored.

INITIATING CUES:

Start NC Pump 1B by completing OP/1/A/6150/002A, NC Pump Operation Enclosure 4.1 beginning at Step 3.14.

EXAMINER NOTE: After reading cue, provide the applicant with a copy of OP/1/A/6150/002A (Reactor Coolant Pump Operation), Enclosure 4.1 (Startup and Operation of the NC Pumps) signed off up to Step 3.14.

PAGE 5 OF 8

Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1 3.14 Two minutes prior to starting NC pump, start one oil lift CRITICAL pump for NCP to be started by pressing the "ON" STEP pushbutton for:

___ SAT "NC PUMP OIL LIFT PUMP B1" "NC PUMP OIL LIFT PUMP B2" ___ UNSAT STANDARD:

Applicant depresses the red ON pushbutton for NC PMP OIL LIFT PMP B1 or B2 approximately two minutes prior to starting the 1B NC Pump.

This step is critical to lift and lubricate the pump so that it can be started.

COMMENTS:

PAGE 6 0F 8

Catawba Nuclear Station JPM D May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: 1. If NC pump is NOT started, the oil lift pump shall be secured to minimize stress on oil nozzles. CRITICAL STEP

2. The Degraded Bus Voltage Relays (27N) may actuate on the essential bus being supplied by the 6.9KV Switchgear ___ SAT associated with the NC Pump to be started in the following step.

The alarm condition is expected to clear within 36 seconds.{PIP ___ UNSAT 95-0287}

STEP 2 3.15 Start desired NC pump by pressing the "ON" pushbutton for: (R.M.)

"NC PUMP 1B" STANDARD:

Applicant depresses the red ON pushbutton for NC PMP 1B. Once Hi Hi vibration is verified, the pump should be tripped.

This step is critical to start the 1B NC Pump and then trip the pump upon verification of Hi Hi Vibration to protect the pump from further damage.

NOTE TO EXAMINER: Approximately 5 seconds after the NCP is started, the Hi Hi Vibration alarm will come in.

The shaft vibration will reach 20 mils prior to reaching 5 on the mount. Per the annunciator response, the pump should be tripped at >20 mils in Modes 1 and 2, but not until >30 mils in Mode 3 (current condition). At 5 mils on the mount, the pump is tripped regardless of mode. 5 mils on the mount will occur before 30 mils on the shaft.

EXAMINER CUE: AFTER the pump is tripped: The CRS has pulled AP/1/A/5500/004 (Loss of Reactor Coolant Pump) and is ready to proceed.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 7 0F 8

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM D READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

EP/1/A/5000/ES-0.2, Natural Circulation Cooldown has been implemented following a Reactor Trip caused by a lightning strike in the switchyard. Normal power has been restored.

INITIATING CUES:

Start NC Pump 1B by completing OP/1/A/6150/002A, NC Pump Operation Enclosure 4.1 beginning at Step 3.14.

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam System JPM E PAGE 1 OF 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam EVALUATION SHEET Task: Synchronize the Generator to the Grid Alternate Path: Yes Facility JPM #: NEW Safety Function: 4S

Title:

Main and Reheat Steam System (MRSS)

K/A 045 A4.02 Ability to manually operate and/or monitor in the control room: T/G controls, including breakers Rating(s): 2.7 / 2.6 CFR: 41.7 / 45.5 to 45.8 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

OP/1/B/6300/001 (Turbine Generator) rev. 099 Task Standard: Synchronizes the generator to the grid and pick up load.

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #172
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event OVR-EP006B (GEN BKR 1B TRIP ENABLE ON 2 PB)

OVR-EP006C (GEN BKR 1B TRIP PB) ON 2 OVR-EP007B (GEN BKR 1A TRIP ENABLE ON 4 PB)

OVR-EP007C (GEN BKR 1A TRIP PB) ON 4 Ensure EVENT 2 = x01i120a & !x01i148e Ensure EVENT 4 = x01i120b & !x01i147e

PAGE 3 OF 11

PAGE 4 0F 11 Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 1 at 14% power.

Turbine Generator startup is in progress per OP/1/B/6300/001 (Turbine Generator)

Enclosure 4.1 (Turbine Generator Startup).

INITIATING CUES:

The CRS has instructed you synchronize the generator to the grid in auto and pick up load starting at Step 3.62. Peer Checks have been waived.

EXAMINER NOTE: After reading cue, provide the applicant with a copy of OP/1/B/6300/001 (Turbine Generator) Enclosure 4.1 (Turbine Generator Startup).

PAGE 4 OF 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 3.62 Synchronize the Generator to the grid as follows:

___ SAT 3.62.1 Prior to placing the turbine generator on line, ensure Rx power is between 13% and 15% power. ___ UNSAT STANDARD:

Applicant determines Rx power is approximately 14%.

COMMENTS:

STEP 2 3.62.2 Announce the following over the plant page: ___ SAT "Placing Unit 1 Main Turbine on line, please clear ___UNSAT the Transformer Yard".

STANDARD:

Applicant makes an announcement using the beige phone on 1MC-1 COMMENTS:

PAGE 5 0F 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: If "MAN/AUTO REG" (1MC1) indicates "MAN", Manual sync of Generator is required.

___ SAT STEP 3 3.62.3 IF Auto sync of the Generator is desired, perform the following: ___ UNSAT 3.62.3.1 Verify "MAN/AUTO REG" in "AUTO" (1MC1).

STANDARD:

Applicant determines auto sync of the generator is desired per the initiating cue and determines that the AUTO light for MAN/AUTO REG is LIT COMMENTS:

PAGE 6 0F 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: 1. When "GEN SYNC SELECT" switch is turned to "AUTO 1A" or "AUTO 1B", the AVR Auto Sync Relay automatically adjusts Terminal voltage and Turbine speed and closes the selected ___ SAT breaker.

___ UNSAT

2. The following will occur when the Generator Breaker closes:

6-7 MWe is picked up.

A Target of 60 MWe is automatically input.

A Load Rate of 12 MW/MIN is automatically input.

The MW feedback loop is placed in service.

The turbine is placed in "HOLD".

STEP 4 3.62.3.2 Turn "GEN SYNC SELECT" switch (1MC1) to "AUTO 1A" or "AUTO 1B" position.

STANDARD:

Applicant places the GEN SYNC SELECT switch to either the AUTO 1A or AUTO 1B position.

EXAMINER NOTE: The first breaker selected will fail to close.

COMMENTS:

STEP 5 3.62.3.3 IF the selected Generator Breaker did NOT close, perform the following: ___ SAT A. Depress "Auto Sync Enable" on Turbine ___ UNSAT Control panel.

STANDARD:

Applicant depresses the Auto Sync Enable button on the Turbine Control Panel.

COMMENTS:

PAGE 7 0F 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 6 B. IF selected Generator Breaker fails to close within 5 minutes, perform Steps ___ SAT 3.62.3.2 - 3.62.3.3 for opposite breaker.

___ UNSAT STANDARD:

Applicant determines that the generator breaker failed to close and returns to step 3.62.3.2 for the opposite breaker.

COMMENTS:

STEP 7 3.62.3.2 Turn "GEN SYNC SELECT" switch (1MC1) CRITICAL to "AUTO 1A" or "AUTO 1B" position. STEP

___ SAT STANDARD:

___ UNSAT Applicant places the GEN SYNC SELECT switch to the opposite position than was selected the first time.

This step is critical to close a generator breaker and synchronize the generator grid.

COMMENTS:

STEP 8 3.62.3.3 IF the selected Generator Breaker did NOT close, perform the following: ___ SAT STANDARD: ___ UNSAT Applicant determines the step does not apply this time.

COMMENTS:

PAGE 8 0F 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 9 3.62.3.4 Return "GEN SYNC SELECT" switch to the "MAN" position. ___ SAT STANDARD: ___ UNSAT Applicant places the GEN SYNC SELECT switch to the MAN position.

COMMENTS:

STEP 10 3.62.4 IF Manual sync of Generator is desired, perform the following: ___ SAT STANDARD: ___ UNSAT Applicant determines that this step does not apply.

COMMENTS:

STEP 11 3.62.5 After Generator Breaker 1A (or 1B) has closed, verify the following: ___ SAT 3.62.5.1 A Target of 60 MWe. ___ UNSAT 3.62.5.2 A Load Rate of 12 MW/Min.

STANDARD:

Applicant verifies a target of 60 MWe and a Load Rate of 12MW/Min is present on the Turbine Control Panel or the Turbine Graphic.

COMMENTS:

PAGE 9 0F 11

Catawba Nuclear Station JPM E May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 12 3.62.6 Select "GO" to pick up load. CRITICAL STEP STANDARD:

___ SAT Applicant depresses the GO button on the Turbine Control Panel.

___ UNSAT This step is critical allow the turbine generator control system to throttle open the control valves to pick up load.

COMMENTS:

STEP 13 3.62.7 WHILE continuing with the power increase, but before 50% power, place other Generator Breaker ___ SAT in service as follows:

___ UNSAT STANDARD:

Applicant reads the step.

EXAMINER CUE: Another operator will place the other breaker in service.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 10 0F 11

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM E READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 1 at 14% power.

Turbine Generator startup is in progress per OP/1/B/6300/001 (Turbine Generator)

Enclosure 4.1 (Turbine Generator Startup).

INITIATING CUES:

The CRS has instructed you synchronize the generator to the grid in auto and pick up load starting at Step 3.62. Peer Checks have been waived.

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam System JPM F PAGE 1 OF 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam EVALUATION SHEET Task: Restoration of Offsite Power Alternate Path: No Facility JPM #: New Safety Function: 6

Title:

A.C. Electrical Distribution K/A 062 A4.01 Ability to manually operate and/or monitor in the control room: All breakers (including available switchyard.

Rating(s): 3.3 / 3.1 CFR: 41.7 / 45.5 to 45.8 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

AP/1/A/5500/007 (Loss of Normal Power), Enclosure 4 (Restoration of Offsite Power) rev. 071 Task Standard: All 6.9 KV busses energized.

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #173
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event OVR-CM024A (HW PMP 1A SEL SW OFF LT) ON 1 OVR-CM024B (HW PMP 1A SEL SW ON LT) OFF 1 20 OVR-CM025A (HW PMP 1B SEL SW OFF LT) ON 1 SEC 20 OVR-CM025B (HW PMP 1B SEL SW ON LT) OFF 1 SEC 1

OVR-CM026A (HW PMP 1C SEL SW OFF LT) ON 1 MIN 1

OVR-CM026B (HW PMP 1C SEL SW ON LT) OFF 1 MIN OVR-EP023B (PCB 15 TRIP TRIP PB) ON OVR-CM024A (HW PMP 1A SEL SW OFF LT) ON 1 SEC 4 OVR-CM024B (HW PMP 1A SEL SW ON LT) OFF 1SEC 4 OVR-CM025A (HW PMP 1B SEL SW OFF LT) ON 1SEC 6 OVR-CM025B (HW PMP 1B SEL SW ON LT) OFF 1SEC 6 OVR-CM026A (HW PMP 1C SEL SW OFF LT) ON 1SEC 8 OVR-CM026B (HW PMP 1C SEL SW ON LT) OFF 1SEC 8 Ensure EVENT 4 = x11o063r (7KV 1TA FDR FRM 1T2A CLSD Light)

Ensure EVENT 6 = x11o147r (7KV 1TB FDR FRM 1T2A CLSD Light)

Ensure EVENT 8 = x11o345r (7KV 1TD FDR FRM 1T1A CLSD Light)

PAGE 3 OF 14

PAGE 4 0F 14 Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is recovering from a Loss of Offsite Power Event.

The TCC has informed the Control Room that the electrical grid has remained energized and adequate switchyard voltage and grid reliability is available to re-energize 6.9 KV busses with motor breakers open.

The status of all 6.9 KV bus lockout relays has been determined.

Power restoration has been approved by station management.

INITIATING CUES:

The SRO instructs you restore offsite power to the 6.9 KV busses per AP/1/A/5500/007 (Loss of Normal Power), Enclosure 4 (Restoration of Offsite Power).

EXAMINER NOTE: After reading cue, provide the applicant with a copy of AP/1/A/5500/007 (Loss of Normal Power), Enclosure 4 (Restoration of Offsite Power).

PAGE 4 OF 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 1. Verify both turbine generator breakers - OPEN.

STANDARD: ___ SAT Applicant determines that the green OPEN lights are lit for GEN BKR ___ UNSAT 1B and GEN BKR 1A on 1MC-11, 1MC-1, or via the OAC.

COMMENTS:

NOTE If loss of grid has occurred, then it may take 6-8 hours to restore power to CNS switchyard.

___ SAT STEP 2 2. Verify with TCC - ELECTRICAL GRID HAS REMAINED ENERGIZED. ___UNSAT STANDARD:

Applicant determines that the electrical grid has remained energized per the initiating cue.

BOOTH OPERATOR CUE: IF TCC is contacted, The electrical grid has remained energized.

COMMENTS:

PAGE 5 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 3 3. Verify switchyard - ENERGIZED.

___ SAT STANDARD:

___ UNSAT Applicant determines that the switchyard is energized via the OAC.

COMMENTS:

STEP 4 4. Ensure both main transformer's MODs - CLOSED.

___ SAT STANDARD:

___ UNSAT Applicant determines that red CLSD lights are lit for MOD 1A and MOD 1B on 1MC-11, or that the MODs are closed via the OAC COMMENTS:

STEP 5 5. Verify with TCC that adequate switchyard voltage and grid reliability available to re-energize affected 6.9 KV busses ___ SAT with motor breakers open.

___ UNSAT STANDARD:

Applicant determines that switchyard voltage and grid reliability is available per the initiating cue.

BOOTH OPERATOR CUE: IF TCC is contacted, Adequate switchyard voltage and grid reliability is available.

COMMENTS:

PAGE 6 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 6 6. Place switches for the following pumps in "OFF" CRITICAL position: STEP All de-energized KR pumps ___ SAT All de-energized hotwell pumps All de-energized condensate booster pumps. ___ UNSAT STANDARD:

Applicant places the switches for HTWL PUMP 1A, 1B, 1C, and CM BSTR PUMP 1A, 1B, and 1C to the OFF position. Applicant also depresses the green OFF pushbutton for KR PUMP A and KR PUMP B.

This step is critical to NOT depress the green OFF pushbutton for KR PUMP B, which is powered from Unit 2, allowing KR Pump B to supply cooling water to Unit 2 loads.

NOTE TO EXAMINER: KR is the Recirculated Cooling Water System.

COMMENTS:

STEP 7 7. Dispatch operator to ensure breakers for all motor loads on all de-energized 6.9 KV busses open. REFER TO ___ SAT Enclosure 22 (Local Load Shed of 6.9 KV Busses).

___ UNSAT STANDARD:

Applicant dispatches an operator by calling the simulator booth operator.

NOTE TO BOOTH OPERATOR: WHEN notified to dispatch operator, REPEAT back the information and THEN INSERT EVENT 1.

COMMENTS:

PAGE 7 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 8 8. Do not continue in this procedure until the following are satisfied: ___ SAT Status of 6.9 KV bus lockout relays are determined ___ UNSAT Station management has approved power restoration.

Enclosure 22 (Local Load Shed of 6.9 KV Busses) is complete.

STANDARD:

Applicant determines that lockout relay status is determined and that station management has approved power restoration per the initial conditions, however, does not continue until contacted by the Booth Operator that Enclosure 22 is complete.

NOTE TO BOOTH OPERATOR: AFTER items triggered from EVENT 1 have timed out, CALL the Control Room and INFORM the applicant that Enclosure 22 is complete COMMENTS:

STEP 9 9. Notify TCC prior to re-energizing affected 6.9 KV busses.

___ SAT STANDARD:

___ UNSAT Applicant calls the Booth Operator to notify the TCC.

NOTE TO BOOTH OPERATOR: WHEN notified about re-energizing the 6.9 KV busses, REPEAT back the information.

COMMENTS:

PAGE 8 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE Zone A or B lockout will occur if at least one main transformer cooling circuit is not restored within 15 minutes of re-energizing main transformer. ___ SAT STEP 10 10. Energize 6.9 KV busses as follows: ___ UNSAT

a. Announce "Energizing Unit 1 main power. All personnel stand clear."

STANDARD:

Applicant makes a plant page via the grey phone on 1MC-1.

COMMENTS:

STEP 11 b. Close at least one of the following PCBs: CRITICAL STEP PCB 15 PCB 18. ___ SAT STANDARD: ___ UNSAT Applicant depresses the red CLOSE pushbuttons for PCB 15 CLOSE and PCB 18 CLOSE on 1 MC-11.

NOTE TO EVALUATOR: PCB 15 will not close.

This step is critical to align power the 1A Main Transformer from offsite.

COMMENTS:

PAGE 9 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 12 c. IF "TRANSF 1A" energized, THEN perform the CRITICAL following for each affected 6.9 KV bus: STEP 1TD: ___ SAT

1) Place "7KV BUS 1TD MODE SEL" switch in "MAN ___ UNSAT A & TIE".
2) Close "7KV 1TD FDR FRM 1T1A".

STANDARD:

Applicant places the switch for 7KV BUS 1TD MODE SEL in the MAN A

& TIE position as depresses the red CLOSE pushbutton for 7KV 1TD FDR FRM 1T1A.

This step is critical to energize 1TD.

COMMENTS:

STEP 13 CRITICAL 1TC: STEP

1) Place "7KV BUS 1TC MODE SEL" switch in "MAN ___ SAT A & TIE".

___ UNSAT

2) Close "7KV 1TC FDR FRM 1T1A".

STANDARD:

Applicant places the switch for 7KV BUS 1TC MODE SEL in the MAN A

& TIE position as depresses the red CLOSE pushbutton for 7KV 1TC FDR FRM 1T1A.

This step is critical to energize 1TC.

COMMENTS:

PAGE 10 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 14 CRITICAL 1TB: STEP

1) Place "7KV BUS 1TB MODE SEL" switch in "MAN ___ SAT A & TIE".

___ UNSAT

2) Close "7KV 1TB FDR FRM 1T2A".

STANDARD:

Applicant places the switch for 7KV BUS 1TB MODE SEL in the MAN A

& TIE position as depresses the red CLOSE pushbutton for 7KV 1TB FDR FRM 1T2A.

This step is critical to energize 1TB.

COMMENTS:

STEP 15 CRITICAL 1TA: STEP

1) Place "7KV BUS 1TA MODE SEL" switch in "MAN ___ SAT A & TIE".

___ UNSAT

2) Close "7KV 1TA FDR FRM 1T2A".

STANDARD:

Applicant places the switch for 7KV BUS 1TA MODE SEL in the MAN A

& TIE position as depresses the red CLOSE pushbutton for 7KV 1TA FDR FRM 1T2A.

This step is critical to energize 1TA.

COMMENTS:

PAGE 11 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 16 d. IF "TRANSF 1B" energized, THEN perform the following for each affected 6.9 KV bus: ___ SAT STANDARD: ___ UNSAT Applicant determines that this step does not apply.

COMMENTS:

STEP 17 e. IF "TRANSF 1A" AND "TRANSF 1B" are energized, THEN place mode select switch for all 6.9KV busses ___ SAT in auto position.

___ UNSAT STANDARD:

Applicant determines that this step does not apply.

COMMENTS:

STEP 18 f. Verify all 6.9 KV switchgear - ENERGIZED.

___ SAT STANDARD:

___ UNSAT Applicant determines that all 6.9 KV switchgear is energized via voltage gauges on 1MC-11 or via the OAC electrical graphic.

COMMENTS:

PAGE 12 0F 14

Catawba Nuclear Station JPM F May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 19 11. RETURN TO step in effect.

___ SAT STANDARD:

___ UNSAT Applicant reads the step.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 13 0F 14

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM F READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is recovering from a Loss of Offsite Power Event.

The TCC has informed the Control Room that the electrical grid has remained energized and adequate switchyard voltage and grid reliability is available to re-energize 6.9 KV busses with motor breakers open.

The status of all 6.9 KV bus lockout relays has been determined.

INITIATING CUES:

The SRO instructs you restore offsite power to the 6.9 KV busses per AP/1/A/5500/007 (Loss of Normal Power), Enclosure 4 (Restoration of Offsite Power).

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam System JPM G PAGE 1 OF 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam EVALUATION SHEET Task: Shift Lower Containment Vent Units Alternate Path: No Facility JPM #: New Safety Function: 5

Title:

Containment Cooling System K/A 022 A4.01 Ability to manually operate and/or monitor in the control room: CCS Fans Rating(s): 3.6 / 3.6 CFR: 41.7 / 45.5 to 45.8 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X Control Room Perform Simulate X

References:

OP/1/A/6450/001 (Containment Ventilation (VV) Systems rev.040 Task Standard: 1B LCVU running and 1A LCVU off.

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC 175
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event

PAGE 3 OF 10

PAGE 4 0F 10 Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 1.

INITIATING CUES:

The Control Room Supervisor has instructed you to shift Lower Containment Vent Units by stopping the 1A LCVU and starting the 1B LCVU.

Steps 3.1 and 3.3 were marked N/A during the pre-job brief.

Peer check has been waived.

EXAMINER NOTE: After reading cue, provide the applicant with a copy of OP/1/A/6450/001 Containment Ventilation (VV) Systems, Enclosure 4.13.

PAGE 4 OF 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 3.2 IF three LCVUs are operating AND it is desired, shift the CRITICAL operating units as follows: STEP 3.2.1 IF the LCVUs are operating in "LOW" speed, perform ___ SAT the following:

___ UNSAT 3.2.1.1 Stop the LCVU to be removed from service by placing its control switch in the "OFF" position:

"VV LCVU 1A" STANDARD:

Applicant places the switch for VV LCVU 1A to the OFF position.

This step is critical to shut down the desired Lower Containment Vent Unit COMMENTS:

NOTE: The procedure may continue up to and including Step 3.2.1.8 before completing the following step.

___ SAT STEP 2 3.2.1.2 Verify the green indicating light illuminates for the LCVU stopped. ___UNSAT STANDARD:

Applicant determines the green indicating light is LIT for VV LCVU 1A.

COMMENTS:

PAGE 5 0F 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 3 3.2.1.3 Verify the red "MAX" indicating light extinguishes for the LCVU stopped. ___ SAT STANDARD:

___ UNSAT Applicant determines the red MAX indicating light for VV LCVU 1A MAX is DARK.

COMMENTS:

STEP 4 3.2.1.4 Verify the green "CLOSED" indicating light illuminates for the LCVU damper associated ___ SAT with the LCVU stopped.

___ UNSAT STANDARD:

Applicant determines the green CLOSED indicating light for 1LCVU-D-1 LWR CONT VENT DAMPER is LIT.

COMMENTS:

PAGE 6 0F 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: If Unit 1 is in Mode 1 and LCVU 1C or 1D is the idle unit that is being placed in service, a delay of approximately 15 to 30 minutes CRITICAL may be needed before starting LCVU 1C or 1D to allow lower STEP containment air temperature to increase. This will prevent exceeding the Tech Spec low limit for air temperature. {PIP 00- ___ SAT 0763, PIP 05-3785}

___ UNSAT STEP 5 3.2.1.5 Start the idle LCVU by placing its control switch in the "LOW" position:

"VV LCVU 1B" STANDARD:

Applicant places the switch for VV LCVU 1B in the LOW position.

This step is critical to start the desired LCVU.

COMMENTS:

STEP 6 3.2.1.6 Verify the red indicating light illuminates for the LCVU placed in service. ___ SAT STANDARD: ___ UNSAT Applicant determines the red (middle) indicating light for VV LCVU 1B is LIT.

COMMENTS:

PAGE 7 0F 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 7 3.2.1.7 Verify the red "OPEN" indicating light illuminates for the LCVU damper associated ___ SAT with the LCVU started.

___ UNSAT STANDARD:

Applicant determines the red OPEN indicating light for 1LCVU-D-2 LWR CONT VENT DAMPER.

COMMENTS:

STEP 8 3.2.1.8 Verify the red "MAX" indicating light illuminates for the LCVU placed in service. ___ SAT STANDARD: ___ UNSAT Applicant determines the red light for VV LCVU 1B MAX is LIT COMMENTS:

STEP 9 3.2.2 IF the LCVUs are operating in "HIGH" speed, perform the following: ___ SAT STANDARD:

___ UNSAT Applicant determines that this step does not apply.

COMMENTS:

PAGE 8 0F 10

Catawba Nuclear Station JPM G May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 10 3.4 Indicate below the operating Pipe Tunnel Booster Fan:

___ SAT "PIPE TUNNEL BSTR FAN 1A" "PIPE TUNNEL BSTR FAN 1B" ___ UNSAT STANDARD:

Applicant marks the box for the operating Pipe Tunnel Booster Fan.

COMMENTS:

STEP 11 3.5 Indicate below the operating LCVUs:

___ SAT "VV LCVU 2A" "VV LCVU 2B" ___ UNSAT "VV LCVU 2C" "VV LCVU 2D STANDARD:

Applicant marks the blocks for the 1B, 1C and 1D LCVUs.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 9 0F 10

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM G READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is in MODE 1.

INITIATING CUES:

The Control Room Supervisor has instructed you to shift Lower Containment Vent Units by stopping the 1A LCVU and starting the 1B LCVU.

Steps 3.1 and 3.3 were marked N/A during the pre-job brief.

Peer check has been waived.

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam System JPM H PAGE 1 OF 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam EVALUATION SHEET Task: Place Standby Component Cooling Train in Service Alternate Path: No Facility JPM #: KC-082 (Modified)

Safety Function: 8

Title:

Component Cooling Water System K/A 008 A4.01 Ability to manually operate and/or monitor in the control room: CCW indications and controls Rating(s): 3.3 / 3.1 CFR: 41.7 / 45.5 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator X In-Plant Perform X Simulate

References:

OP/1/A/6400/005 (Component Cooling System) rev. 116 Task Standard: 1B1 Component Cooling Pump running and B KC HX outlet valve in KC TEMP position. 1A2 KC Pump stopped and A KC HX Outlet Valve aligned for miniflow.

Validation Time: 20 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #175
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event

PAGE 3 OF 14

PAGE 4 0F 14 Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is operating at 100% with 1A2 KC Pump in operation.

KC Pump 1A2 needs to be removed from service to permit preventive maintenance on the pump and motor.

INITIATING CUES:

The Control Room SRO instructs you to shift trains of KC with 1B1 KC Pump in service and take KC Pump 1A2 out of service beginning at step 3.1.2 in enclosure 4.3 of OP/1/A/6400/005.

Concurrent verification and peer checks have been waived and the B train KC pumps have been checked out satisfactorily by a NLO.

EXAMINER NOTE: After reading cue, provide the applicant with a copy of OP/1/A/6400/005 (Component Cooling System), Enclosure 4.3 (Shifting Trains).

PAGE 4 OF 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 3.1.2 Ensure 1RN-347B (KC Hx 1B Inlet Isol) is open.

___ SAT STANDARD:

___ UNSAT Applicant determines that 1RN-347B is open by verifying the red OPEN light is LIT or via the OAC.

COMMENTS:

CRITICAL STEP 2 3.1.3 Ensure "KC HX 1B OTLT MODE" is in "KC TEMP". STEP STANDARD: ___ SAT Applicant places the switch for KC HX 1B OTLT MODE in the KC ___UNSAT TEMP position on 1MC-11.

This step is critical to ensure that the outlet of the KC Heat exchanger is controlled at the proper temperature.

COMMENTS:

PAGE 5 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 3 3.1.4 IF letdown is in service per OP/1/A/6200/001 (Chemical and Volume Control System) perform the following: (R.M.) ___ SAT 3.1.4.1 Verify the Cation Bed Demineralizer is NOT in ___ UNSAT service per OP/1/A/6200/001 (Chemical and Volume Control System).

STANDARD:

Applicant determines that letdown is in service and that the Cation Bed Demineralizers are not in service.

EXAMINER CUE: IF ASKED, The Cation Bed Demineralizers are not in service.

COMMENTS:

STEP 4 3.1.4.2 Record position of 1NV-153A (Letdn Hx Otlt 3-Way ___ SAT Vlv).

Recorded valve position________________ ___ UNSAT STANDARD:

Applicant determines that the position of 1NV-153A is in the DEMIN position.

COMMENTS:

PAGE 6 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 5 3.1.4.3 IF letdown flow is through the demineralizers, notify Primary Chemistry that the demineralizers will be ___ SAT bypassed while shifting KC Trains.

Person notified ____________________________ ___ UNSAT STANDARD:

Applicant determines that letdown flow is through the demineralizers and notifies Primary Chemistry that the demineralizers will be bypassed while shifting KC Trains.

EXAMINER CUE: This is Stephanie Jackson from Primary Chemistry, I understand the demineralizers will be bypassed while shifting KC Trains.

COMMENTS:

STEP 6 3.1.4.4 IF letdown flow is through the demineralizers, notify Radiation Protection that the demineralizers will be ___ SAT bypassed while shifting KC Trains.

Person notified ____________________________ ___ UNSAT STANDARD:

Applicant notifies Radiation Protection that the demineralizers will be bypassed while shifting KC Trains.

EXAMINER CUE: This is Christina Frey from Radiation Protection, I understand that the demineralizers will be bypassed while shifting KC Trains.

COMMENTS:

PAGE 7 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 7 3.1.4.5 Place 1NV-153A (Letdn Hx Otlt 3-Way Vlv) in the CRITICAL "VCT" position. STEP STANDARD: ___ SAT Applicant places the switch for 1NV-153A to the VCT position. ___ UNSAT This step is critical to bypass the demineralizer to prevent a change in reactivity due to the changing boron affinity of the demineralizers caused by letdown temperature changes due to component cooling temperature changes when the trains are shifted.

COMMENTS:

CAUTION: 5700 gpm discharge header flow per each operating KC pump shall NOT be exceeded. CRITICAL STEP STEP 8 3.1.5 Start either KC Train 1B pump:

___ SAT "KC PUMP B1"

___ UNSAT STANDARD:

Applicant depresses the red ON pushbutton for KC PUMP 1B on 1MC-11 This step is critical to start the desired pump.

COMMENTS:

PAGE 8 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 9 3.1.6 Adjust the following flow controllers on 1MC11 to zero gpm flow: ___ SAT 1KC-149 (KF Hx 1A Cool Wtr Otlt) ___ UNSAT STANDARD:

Applicant adjusts the controller for 1KC-149 to zero gpm.

COMMENTS:

STEP 10 3.1.7 Stop all KC Train 1A pumps: CRITICAL STEP "KC PUMP A2"

___ SAT STANDARD:

___ UNSAT Applicant depresses the green OFF pushbutton for KC PUMP A2 on 1MC-11 This step is critical to secured the desired pump.

COMMENTS:

STEP 11 3.1.8 Place "KC HX 1A OTLT MODE" in "MINIFLOW" position.

___ SAT STANDARD:

___ UNSAT Applicant places the switch for KC HX 1A OTLT MODE in the MINIFLOW position on 1MC-11 COMMENTS:

PAGE 9 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 12 3.1.9 IF AT ANY TIME KC Train flow approaches 5700 gpm while performing the next step, ensure 1KC-C40B (Train ___ SAT B Miniflow Isol) is closed.

___ UNSAT STANDARD:

Applicant ensures that 1KC-40B is closed on 1MC-11.

COMMENTS:

STEP 13 3.1.10 Perform the following for the KF cooling loops that are in service: ___ SAT Adjust 1KC-149 (KF Hx 1A Cool Wtr Otlt) flow ___ UNSAT controller on 1MC11 to 3000 gpm or as necessary to maintain Spent Fuel Pool temperature < 125°F.

STANDARD:

Applicant adjusts 1KC-149 flow controller to less than or < 3000 gpm.

EXAMINER NOTE: Since Spent Fuel Pool temperature is only ~ 115°F, the applicant may decide to adjust 1KC-149 at this time.

COMMENTS:

PAGE 10 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: One pump running is preferred as long as flow is < 5700 gpm.

STEP 14 3.1.11 IF KC flow requirement is > 5700 gpm, perform the ___ SAT following:

___ UNSAT STANDARD:

Applicant determines that this step does not apply.

COMMENTS:

STEP 15 3.1.12 IF letdown is in service per OP/1/A/6200/001 (Chemical and Volume Control System), WHEN KC flow and ___ SAT temperature have stabilized perform the following:

(R.M.) ___ UNSAT 3.1.12.1 IF 1NV-153A (Letdn Hx Otlt 3-Way Vlv) position was recorded as "DEMIN" in Step 3.1.4.2 AND no other reason exists for it to remain in the "VCT" position, return it to "AUTO" as follows:

A. Place 1NV-153A in the "DEMIN" position.

(R.M.)

B. Verify 1NV-153A returns to "AUTO".

STANDARD:

Applicant places the control switch for 1NV-153A to the DEMIN position and returns it to AUTO on 1MC-10.

COMMENTS:

PAGE 11 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 16 3.1.12.2 IF letdown flow is through the demineralizers, notify Primary Chemistry that the ___ SAT demineralizers have been restored to service.

Person notified _________________________ ___ UNSAT STANDARD:

Applicant notifies Primary Chemistry that the demineralizers have been restored to service.

EXAMINER CUE: This is Stephanie Jackson from Primary Chemistry, I understand the demineralizers have been restored to service.

COMMENTS:

STEP 17 3.1.12.3 IF letdown flow is through the demineralizers, notify Radiation Protection that the ___ SAT demineralizers have been restored to service.

Person notified _________________________ ___ UNSAT STANDARD:

Applicant notifies Radiation Protection that the demineralizers have been restored to service.

EXAMINER CUE: This is Christina Frey from Radiation Protection, I understand the demineralizers have been restored to service.

COMMENTS:

PAGE 12 0F 14

Catawba Nuclear Station JPM H May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 18 3.1.13 IF RN miniflow was established per Step 3.1.1.2, secure unneeded flow paths. ___ SAT STANDARD: ___ UNSAT Applicant determines that this step does not apply.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 13 0F 14

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM H READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is operating at 100% with 1A2 KC Pump in operation.

KC Pump 1A2 needs to be removed from service to permit preventive maintenance on the pump and motor.

INITIATING CUES:

The Control Room SRO instructs you to shift trains of KC with 1B1 KC Pump in service and take KC Pump 1A2 out of service beginning at step 3.1.2 in enclosure 4.3 of OP/1/A/6400/005.

Concurrent verification and peer checks have been waived and the B train KC pumps have been checked out satisfactorily by a NLO.

Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam System JPM I In-Plant PAGE 1 OF 8

Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam EVALUATION SHEET Task: Break Condenser Vacuum Locally Alternate Path: None Facility JPM #: CA-084 Safety Function: 4S

Title:

Main Turbine Generator (MT/G) System K/A 045 A1.06 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the MT/G system controls including: Expected response of secondary plant parameters following T/G trip Rating(s): 3.3 / 3.7 CFR: 41.5 / 45.5 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant X Perform Simulate X

References:

AP/2/A/5500/006 (Loss of S/G Feedwater) Enclosure 3 Task Standard: Enclosure 3 has been completed with the first vacuum breaker opened within 10 minutes.

Validation Time: 8 minutes Time Critical: Yes X No

===============================================================

Applicant: Time Start: ________

NAME __ ___ Docket # _________ Time Finish: ________

Performance Rating: SAT ____ UNSAT ____ Performance Time ___

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 8

Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event

PAGE 3 OF 8

PAGE 4 0F 8 Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 2 is in Mode 3 following a reactor trip.

INITIATING CUES:

The Control Room Supervisor instructs you to perform AP/2/A/5500/006 (Loss of S/G Feedwater) Enclosure 3 (Local Actions to Break Condenser Vacuum).

This JPM is TIME CRITICAL; time begins when you acknowledge the task.

EXAMINER NOTE: Provide applicant with a copy of the procedure.

PAGE 4 OF 8

Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME _______

Examiner NOTE: CRITICAL STEP Critical Time Start: Record Time that applicant acknowledges the task

_________. ___ SAT CAUTION High air flow rates will exist when vacuum breakers are ___ UNSAT first opened. Stay clear of pipe end.

STEP 1: 1. Break condenser vacuum by opening the following valves:

2CM-368 (2A Main Cond Shell Vacuum Bkr) (TB2-600,2F-2G, 26) (Ladder needed) 2CM-369 (2B Main Cond Shell Vacuum Bkr) (TB2-600, 2F, 24-25) (Ladder needed) 2CM-370 (2C Main Cond Shell Vacuum Bkr) (TB2-609, 2F-

22) (Ladder needed).

STANDARD:

Applicant will describe opening the valves: 2CM-368, 2CM-369, 2CM-370 This step is critical in order to open correct valves for breaking vacuum.

Examiner Note: The critical end time is when the applicant describes opening the first valve. Due to the height of the valves, no fall protection will be required.

Examiner Cue: When applicant describes engaging lever and rotating handwheel counter clockwise to open the following valve then: A large volume of airflow is heard.

Critical end time________

COMMENTS:

PAGE 5 0F 8

Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 2 2. Secure steam to CSAEs as follows: CRITICAL STEP

a. Close the following valves:

___ SAT 2SA-22 (Main Steam To CSAE) (TB2-614, 2M-32) 2SA-27 (Aux Steam To CSAE) (TB-614, 2L-2M, 27). ___UNSAT STANDARD:

Applicant will describe closing 2SA-22 and 2SA-27 This step is critical, because if it is not performed, the CSAEs will continue to pull vacuum.

Examiner Cue: As applicant properly describes closing the valves give cue as appropriate, Valve turns until resistance is felt.

COMMENTS:

STEP 3 b. WHEN time and manpower permit, THEN complete the shutdown of the CSAEs. REFER TO OP/2/B/6300/006 (Main Vacuum). ___ SAT STANDARD:

___ UNSAT Applicant will read the step Examiner Cue: The Control Room Supervisor has instructed another operator to complete the shutdown of the CSAEs.

COMMENTS:

PAGE 6 0F 8

Catawba Nuclear Station JPM I May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 4 3. WHEN requested by Control Room Supervisor, THEN verify condenser vacuum broken as follows:

___ SAT

a. Inspect each vacuum breaker for absence of air flow into condenser. ___ UNSAT
b. Notify Control Room Supervisor of results.

STANDARD:

Applicant will inspect each vacuum breaker for the absence of air flow into the condenser and will report to the Control Room Supervisor.

Examiner Cue: After each inspection, No air flow into condenser.

COMMENTS:

STOP TIME ________

PAGE 7 0F 8

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JKM I DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 2 is in Mode 3 following a reactor trip.

INITIATING CUES:

The Control Room Supervisor instructs you to perform AP/2/A/5500/006 (Loss of S/G Feedwater) Enclosure 3 (Local Actions to Break Condenser Vacuum).

This JPM is TIME CRITICAL; time begins when you acknowledge the task.

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam System JPM J In-Plant PAGE 1 OF 9

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam EVALUATION SHEET Task: Shifting Main Transformer Auxiliaries Alternate Path: No Facility JPM #: EP-016 Safety Function: 6

Title:

Electrical K/A 062 A2.01 Ability to (a) predict the impacts of the following malfunctions or operations on the ac distribution system; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Types of loads that, if de-energized, would degrade or hinder plant operation.

Rating(s): 3.4 / 3.9 CFR: 41.5 / 43.5 / 45.3 / 45.13 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant X Perform Simulate X

References:

OP/1/A/6350/005 (Alternate AC Power Sources) rev. 076, Enclosure 4.24 Task Standard: The 1A Main Transformer Auxiliaries are transferred to an energized source.

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 9

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event

PAGE 3 OF 9

PAGE 4 0F 9 Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is at 100% power.

The incoming feeder breaker to 1LXC tripped due to a load center fault.

As a result, one-half of the 1A Main Transformer Auxiliaries have been de-energized.

INITIATING CUES:

The Unit Supervisor directs you to shift the 1A Main Transformer Auxiliaries to the 1LXD Feeder per Enclosures 4.24 (Shifting Main Transformer 1A Auxiliaries) of OP/1/A/6350/005 (Alternate AC Power Sources).

EXAMINER NOTE: After reading cue, provide the applicant with a copy of OP/1/A/6350/005, Enclosure 4.24.

PAGE 4 OF 9

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

NOTE: 1. Shifting of power supplies shall be performed without delay.

2. All breakers and alarm lights are located inside the cabinet at ___ SAT the Main Transformer.

___ UNSAT

3. During normal operation, loss of a power supply (from LXC or LXD) will be indicated by the associated "NO VOLTAGE BANK A (B)" alarm light at the transformer.
4. Electrical PPE (high voltage gloves, FR clothing, face shield) is required for shifting power supplies.

Examiner Note: Applicant should state that they would acquire the required PPE.

STEP 1: 3.1 IF shifting Bank A power supplies, perform the following:

3.1.1 Verify voltage indicated on 1LXD per one of the following:

Transformer 1TXD Supply Voltage meter with 1LXD-4B closed OR Transformer 1TXS Supply Voltage meter with 1LXD-8B closed STANDARD:

Applicant verifies voltage indicated on transformer 1TXD with 1LXD-4B closed or 1TXS with 1LXD-8B closed.

Examiner Cue: 600 volts is indicated.

COMMENTS:

PAGE 5 0F 9

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 2 3.1.2 IF this is an unexpected loss of power, verify the following at Transformer 1A: ___ SAT "NO VOLTAGE BANK A" alarm light illuminated. ___UNSAT "NO VOLTAGE BANK B" alarm light dark.

STANDARD:

Applicant verifies NO VOLTAGE BANK A alarm light is illuminated and the NO VOLTAGE BANK B alarm light is dark.

Examiner Cue: NO VOLTAGE BANK A is LIT and NO VOLTAGE BANK B is DARK.

COMMENTS:

STEP 3 3.1.3 Open "NORMAL FEEDER 1LXC" breaker. CRITICAL STEP STANDARD:

___ SAT Applicant describes opening the NORMAL FEEDER 1LXC breaker by placing it in the OFF (down) position. ___ UNSAT Examiner Cue: NORMAL FEEDER 1LXC is in the OFF position.

This step is critical to allow the lockout bar to be slid in the following step.

COMMENTS:

PAGE 6 0F 9

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 4 3.1.4 Slide lockout bar to the left. CRITICAL STEP STANDARD:

___ SAT Applicant describes sliding the lockout bar to the left.

___ UNSAT Examiner Cue: Lockout bar is to the left.

This step is critical to allow closing of the EMERG FEEDER 1LXD breaker in the following step.

COMMENTS:

STEP 5 3.1.5 Close "EMERG FEEDER 1LXD" breaker. CRITICAL STEP STANDARD:

___ SAT Applicant describes closing the EMERG FEEDER 1LXD breaker by placing the breaker to the ON (up) position. ___ UNSAT Examiner Cue: EMERG FEEDER 1LXD breaker is in the ON position.

This step is critical to energize the transformer auxiliaries for the 1A Main Transformer COMMENTS:

PAGE 7 0F 9

Catawba Nuclear Station JPM J May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 6 3.1.6 Acknowledge any alarms present.

___ SAT STANDARD:

___ UNSAT Applicant describes acknowledging any alarms.

Examiner Cue: Alarms have been acknowledged.

COMMENTS:

STEP 7 3.1.7 Complete and file Enclosure 4.29 (Unit 1 Main Transformers Cooler Groups Status) to record status. ___ SAT STANDARD: ___ UNSAT Applicant reads the step.

Examiner Cue: Another operator will complete and file enclosure 4.29 NOTE: At this point, Bank A is supplied from 1LXD. Subsequent steps are to return Bank A to 1LXC.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 8 0F 9

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM J DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Unit 1 is at 100% power.

The incoming feeder breaker to 1LXC tripped due to a load center fault.

As a result, one-half of the 1A Main Transformer Auxiliaries have been de-energized.

INITIATING CUES:

The Unit Supervisor directs you to shift the 1A Main Transformer Auxiliaries to the 1LXD Feeder per Enclosures 4.24 (Shifting Main Transformer 1A Auxiliaries) of OP/1/A/6350/005 (Alternate AC Power Sources).

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam System JPM K In-Plant PAGE 1 OF 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam EVALUATION SHEET Task: Place the 2A Hydrogen Analyzer in Service Alternate Path: No Facility JPM #: VX-024 Safety Function: 5

Title:

Hydrogen Recombiner and Purge Control System (HRPS)

K/A 028 A1.01 Ability to predict and/or monitor changes in parameter (to prevent exceeding design limits) associated with operating the HRPS controls including): Hydrogen concentration Rating(s): 3.4 / 3.8 CFR: 41.5 / 45.5 Preferred Evaluation Location: Preferred Evaluation Method:

Simulator In-Plant X Perform Simulate X

References:

EP/2/A/5000/E-1 (Loss of Reactor or Secondary Coolant), rev. 025 OP/2/A/6450/010 (Containment Hydrogen Control Systems Enclosure 4.9), rev. 026 Task Standard: Hydrogen Analyzer Train 2A in Service monitoring upper containment via selection of Position "1".

Validation Time: 15 minutes Time Critical: Yes No X

===============================================================

Applicant: Time Start: __________

NAME___________________________ Docket #_______________ Time Finish: __________

Performance Rating: Performance Time _____

SAT ____ UNSAT ____

Examiner: _____________________________ _____________________________/________

NAME SIGNATURE DATE

===============================================================

COMMENTS PAGE 2 OF 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam SIMULATOR OPERATOR INSTRUCTIONS:

1. ENSURE NRC Examination Security has been established.
2. Reset to IC #168
3. Enter the password.
4. Select Yes on the INITIAL CONDITION RESET pop-up window.
5. Ensure simulator setup per table below.
6. Place simulator in RUN and acknowledge any alarms.
7. ENSURE Extra Operator is present in the simulator.
8. Place simulator in FREEZE until Examiner cue is given.

Instructor Action Final Delay Ramp Delete In Event

PAGE 3 OF 10

PAGE 4 0F 10 Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A large break LOCA has occurred on Unit 2.

The procedure currently in use is EP/2/A/5000/E-1 (Loss of Reactor or Secondary Coolant).

Containment Hydrogen Analyzer 2B is tagged for maintenance.

INITIATING CUES:

The Control Room Supervisor directs you to place Containment Hydrogen Analyzer 2A in service to Position 1 for sampling Upper Containment per OP/2/A/6450/010 (Containment Hydrogen Control Systems) Enclosure 4.9, step 3.1. All initial conditions are complete. Peer check has been waived.

EXAMINER NOTE: After reading cue, provide examinee with a copy of OP/2/6450/010, Enclosure 4.9 with the Initial Conditions signed off.

PAGE 4 OF 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT START TIME: _______

STEP 1: 3.1 Place Hydrogen Analyzer Train A OR Train B in service.

___ SAT 3.1.1 IF aligning Hydrogen Analyzer Train A, proceed as follows: ___ UNSAT 3.1.1.1 Obtain Hydrogen Analyzer Control Panel Train A (2ELCP0251) key (Key #225) from WCC.

STANDARD:

Applicant determines from the initiating cue that A train needs to be aligned and obtains the key #225 EXAMINER NOTE: Key not required to be obtained to complete this JPM task. Once key is identified give cue.

EXAMINER CUE: Key 225 has been obtained.

COMMENTS:

PAGE 5 0F 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: Steps 3.1.1.2 - 3.1.1.5 will be performed at Hydrogen Analyzer Control Panel Train 2A HACP-2A (2ELCP0251) (AB-579, DD-61). CRITICAL STEP STEP 2 3.1.1.2 Select the desired sample location by positioning the "HYDROGEN ANALYZER ___ SAT SAMPLE VALVES PORTS" switch:

___UNSAT Position "1" (for sampling Upper Containment)

Position "2" (for sampling operating level)

Position "3" (for sampling Steam Generator 1B cavity)

Position "ALL" for sampling ALL 3 locations)

STANDARD:

Applicant describes placing the HYDROGEN ANALYZER SAMPLE VALVES PORTS switch in position 1.

EXAMINER CUE: Switch is in position 1.

This step is critical to sample Upper Containment.

COMMENTS:

STEP 3 3.1.1.3 Verify the "POS 1: H2 ANALYZER POS 2:

POST ACCIDENT SAMPLE PANEL" switch is ___ SAT in "POS. 1".

STANDARD: ___ UNSAT Applicant describes verifying the switch is in POS 1 EXAMINER CUE: Switch is in position 1.

COMMENTS:

PAGE 6 0F 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT CRITICAL STEP 4 3.1.1.4 Insert key in "HYDROGEN ANALYZER CONT STEP ISOLATION VALVES" key switch and turn to "OPEN" position. ___ SAT STANDARD:

___ UNSAT Applicant describes inserting the key and turning the key to the OPEN position.

This step is critical to open the containment isolation valves in order to be able to sample upper containment.

EXAMINER CUE: Key is in the OPEN position.

COMMENTS:

STEP 5 3.1.1.5 Verify the following indicating lights are lit:

___ SAT "H2 SAMPLE CONT. ISOLATION VALVES OPEN" ___ UNSAT Sample location(s) selected in Step 3.1.1.2.

STANDARD:

Applicant describes verifying the red OPEN light LIT for H2 Sample Containment Isolation Valves.

EXAMINER CUE: Red OPEN light is lit.

COMMENTS:

PAGE 7 0F 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT NOTE: Steps 3.1.1.6 - 3.1.1.7 will be performed inside A Train Hydrogen Analyzer Control Unit (PAMS) 2MIMT5320A (AB-579, DD-61).

___ SAT STEP 6 3.1.1.6 Verify the "STANDBY/OFF" switch is in the "STANDBY" position. ___ UNSAT STANDARD:

Applicant describes verifying the STANDBY/OFF switch is in the STANDBY position.

EXAMINER CUE: Switch is in the STANDBY position.

COMMENTS:

STEP 7 3.1.1.7 Place the "ON/OFF" switch in the "ON" CRITICAL position. STEP STANDARD: ___ SAT Applicant describes moving the ON/OFF switch up to the ON position. ___ UNSAT This step is critical to turn the analyzer on.

EXAMINER CUE: Switch is in the ON position and the green ON light is lit.

COMMENTS:

PAGE 8 0F 10

Catawba Nuclear Station JPM K May 2014 NRC Initial License Exam STEP/STANDARD SAT/UNSAT STEP 8 3.1.1.8 Monitor H2 concentration at either of the following locations: ___ SAT "Hydrogen Analyzer Control Unit ___ UNSAT "2MIMT5320A" (AB-579, DD-61)

"CONTAINMENT TRN A H2 ANAL" meter (2MIP5320) located on 2MC7.

STANDARD:

Applicant describes calling the control room to inform them that the hydrogen analyzers are in service and can be read on the local unit or on 2MC-7.

EXAMINER CUE: Hydrogen concentration will be monitored on 2MC-7.

COMMENTS:

END OF TASK STOP TIME ________

PAGE 9 0F 10

APPLICANT CUE SHEET (RETURN TO EXAMINER UPON COMPLETION OF TASK) 2014 NRC Initial License Exam JPM K READ TO APPLICANT DIRECTION TO APPLICANT:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A large break LOCA has occurred on Unit 2.

The procedure currently in use is EP/2/A/5000/E-1 (Loss of Reactor or Secondary Coolant).

Containment Hydrogen Analyzer 2B is tagged for maintenance.

INITIATING CUES:

The Control Room Supervisor directs you to place Containment Hydrogen Analyzer 2A in service to Position 1 for sampling Upper Containment per OP/2/A/6450/010 (Containment Hydrogen Control Systems) Enclosure 4.9, step 3.1. All initial conditions are complete. Peer check has been waived.