Finding | |
---|---|
Title | Failure to Ensure Personnel Meet Minimum Educational Requirements |
Description | The inspectors identified a noncited violation of Technical Specification 5.3.1, Facility Staff Qualifications, for failure to ensure electrical group supervisors met the minimum qualification requirements specified in American National Standards Institute N18.1-1971, American National Standard Selection and Training of Nuclear Power Plant Personnel. Fort Calhoun Station entered this performance deficiency into their corrective action program as CR 2012-04543. The failure to ensure that electrical supervisors met minimum standards required by technical specifications for activities affecting quality is a performance deficiency. It is more than minor and is therefore a finding because it adversely affects the human performance attribute of the Mitigating Systems Cornerstone and affects the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. In accordance with Inspection Manual Chapter 0609, Attachment 4, Phase 1 Initial Screening and Characterization of Findings, a Phase 1 screening was performed and it was determined that this example was of very low safety significance (Green) because: (1) is not a design or qualification issue confirmed not to result in a loss of operability or functionality; (2) did not represent an actual loss of safety function of the system or train; (3) did not result in the loss of one or more trains of nontechnical specification equipment; and (4) did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. This finding has a cross-cutting aspect in the area of work practices because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2012003 Section 4OA2 |
Date counted | Jun 30, 2012 (2012Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | R Deese J Kirkland P Elkmann J Clark |
CCA | H.2, Field Presence |
INPO aspect | LA.2 |
' | |
Finding - Fort Calhoun - IR 05000285/2012003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Fort Calhoun) @ 2012Q2