ML102520435

From kanterella
Revision as of 05:12, 11 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Denial of Notice of Violation,05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers
ML102520435
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 09/07/2010
From: Bajestani M
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IR-10-603
Download: ML102520435 (10)


See also: IR 05000391/2010603

Text

Tennessee

Valley Authority, Post Office Box 2000, Spring City, Tennessee

37381-2000

September

7, 2010 U. S. Nuclear Regulatory

Commission

ATTN: Document Control Desk Washington, D.C. 20555-0001

Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 Subject: Reference:

Watts Bar Nuclear Plant (WBN) Unit 2 -Denial of Notice of Violation (NOV)05000391/2010603-08, Failure to Adequately

Evaluate and Qualify Molded Case Circuit Breakers 1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction

-NRC Integrated

Inspection

Report 05000391/2010603

and Notice of Violation," dated August 5, 2010 By letter dated August 5, 2010 (Reference

1), the U.S. Nuclear Regulatory

Commission (NRC) issued Inspection

Report Number 05000391/2010603

concerning

the April 6-30, 2010, inspection

conducted

at Tennessee

Valley Authority's (TVA) WBN Unit 2.The inspection

report identified

one Severity Level IV violation

involving

the suitability

of molded case circuit breakers.

The enclosure

to this letter provides TVA's response denying the NOV.There are no new commitments

associated

with this submittal.

If you have any questions, please contact William Crouch at (423) 365-2004.7I\r c-' C

U.S. Nuclear Regulatory

Commission

Page 2 September

7, 2010 I declare under penalty of perjury that the foregoing

is true and correct. Executed on the 7th day of September

2010.Respectfully, Masou ajest ni Watts r Unit 2 Vice President Enclosure:

1. WBN Unit 2 Reply to NOV 05000391/2010603-08

cc (w/enclosure):

Director, Office of Enforcement

U.S. Nuclear Regulatory

Commission

Washington, DC 20555-0001

U. S. Nuclear Regulatory

Commission

Region II Marquis One Tower 245 Peachtree

Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

NRC Resident Inspector

Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee

37381

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

Description

of NOV 05000391/2010603-08

10 CFR 50, Appendix B, Criterion

III, "Design Control,"states

that measures shall be established

for the review for suitability

of application

of materials, parts, and equipment

that are essential

to the safety-related

functions

of the structures, systems, and components (SSCs). The design control measures shall provide for verifying

or checking the adequacy of design, such as by the performance

of design reviews, by the use of alternate

or simplified

calculational

methods, or by the performance

of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying

or checking processes, it shall include suitable qualifications

testing of a prototype

unit under the most adverse design conditions.

Contrary to the above, measures used to review the suitability

of application

of materials, parts, and equipment

essential

to the safety-related

functions

of molded case circuit breakers and measures to provide for the verification

of checking the adequacy of design, such as, calculational

methods, performing

a suitable test program, including

qualifications

testing of a prototype

unit under the most adverse design conditions, were not adequate in that: 1. On October 5, 2009, the applicant

installed

molded case circuit breakers into the 120VAC vital instrument

power boards; however, the test program used to seismically

qualify a prototype

circuit breaker failed to use a suitable mounting method that reflected

the most adverse mounting condition.

2. On September

3, 2009, the applicant

failed to perform an adequate review for suitability

of application

parts and material used to modify dimensional

critical characteristics

in molded case circuit breakers;

further, the applicant

failed to verify the adequacy of design for the modification

and the effects on essential safety related functions

of the circuit breakers.This is identified

as violation (VIO) 005000391/2010603-08, Failure to Adequately

Evaluate and Qualify Molded Case Circuit Breakers.TVA Response TVA denies the violation.

Basis for Denial of the Violation This issue involves the 120 VAC Vital Instrument

Power Board and its internally

mounted Heinemann

Model CF2-Z51 -1 molded case circuit breakers.

This assembly was seismically

tested in 1974 and supplied as a unit by Westinghouse.

Subsequent

to the testing in 1974, the breaker was procured as a replacement

from a third party, and the breaker (not the assembly)

was seismically

tested in 1992 as part of the commercial

grade dedication

process.E-1

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

The notice of violation (NOV) cited two examples of failure to adequately

evaluate and qualify molded case circuit breakers currently

in use.Example 1 stated: "On October 5, 2009, the applicant

installed

molded case circuit breakers into the 120VAC vital instrument

power boards; however, the test program used to seismically

qualify a prototype

circuit breaker failed to use a suitable mounting method that reflected

the most adverse mounting condition." TVA disagrees

that the 1992 qualification

device test did not use a suitable mounting configuration.

The seismic qualification

of the replacement

circuit breakers is described

below.In 1974, Westinghouse

seismically

qualified

the 120 VAC Vital Instrument

Power Board (Westinghouse

Seismic Test Report CO-33419-MKE, TVA Contract No. 74C4-85216, RIMS No. B07890914035)

by testing a complete board assembly with Heinemann

Model CF2-Z51 -1 circuit breakers mounted in the board. The actual mounting of the breakers is shown on Westinghouse

Drawing CO-33419-MKE-M3

in Section C-C. The tested board assembly duplicated

the actual configuration.

The mounting of the breakers consisted

of a 36" front panel with two horizontal

angle iron supports in the rear. The breakers were held in place solely by the clamping pressure applied by the front cover pushing the twelve breakers against the rear angle supports.

There were no additional

screws to secure the breaker to the frame. This configuration

duplicated

the actual configuration

in the plant.o The 1974 Westinghouse

qualification

testing subjected

the assembly to the required seismic motion. The test demonstrated

the response of the assembly and the individual

breakers.

The test procedure included instrumentation

to collect acceleration

data at the locations of the individual

breakers.o The Westinghouse

qualification

testing determined

the natural frequencies

of the test specimen simulating

the boards at WBN.Sine beat tests were then performed

at the natural frequencies

of the panel as determined

by the resonance

search and at 1/2 octave intervals

over the range from 1 to 33 Hertz. The tests were a conservative

simulation

of the actual earthquake

motion at upper building elevations

at WBN. The ten-cycle

sine beat test accelerations

measured at the breaker locations

are conservative

in-cabinet inputs (seismic demand) for testing the breakers as devices.The highest measured acceleration

at the device locations

in the board test was 2.72g.E-2

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

  • IEEE-344-1975, Section 6.4 Device Testing, states, "Devices shall be tested simulating

operating

conditions

to either the levels dictated by expected service requirements

or to their ultimate capability.....

If a device is intended to be mounted on a panel, the panel should be included in the test mounting, or the response at the device mounting location should be monitored

in the assembly test (see Section 6.5), in which case the device may be mounted directly to the shake table if the in-service

excitation

can be simulated."" In 1992, TVA WBN purchased

Heinemann

Model CF2-Z51 -1 circuit breakers from Southern Testing Services as replacement

items for the original Model CF2-Z51-1

circuit breakers in the Westinghouse

120VAC Vital Instrument

Power Boards. The 1992 test was performed

by Southern Testing Services as part of the commercial

grade dedication

for the breakers, not the overall assembly.

The testing was performed, and the breaker configuration

was the same as was tested in 1974. Southern Testing Services chose to perform a test of the breaker (since that was the part they were supplying)

and did not intend the test to address the entire assembly.

The assembly qualification

from 1974 was deemed by TVA to remain valid. In the 1992 test, an individual

breaker was attached directly to the vibratory

source with bolting. A 3g input motion (which exceeded the 2.72g highest measured acceleration

[seismic demand] in the 1974 test) was applied. This 1992 test simulated

the in-service

excitation

as required by IEEE-344-1975

because the 3g input motion exceeded the highest measured acceleration

in the 1974 test. Therefore, the 1992 test confirmed

that the breaker was seismically

qualified.

  • The mounting configuration

used in the 1992 test was appropriate

for device testing of replacement

breakers.

The retention

of breakers in the board assembly was by a clamping arrangement

provided by two rear retaining

angle iron members and the front cover panel. The calculated

natural frequencies

of the front cover panel in the three directions

were also in excess of 33 Hz and rigid. Therefore, the rigid clamping arrangement

of rear retaining

angles and front cover panel did not introduce

any additional

localized

flexibility

that would require replication

in device testing of replacement

breakers.

Since there is no additional

flexibility, the measured maximum in-cabinet

acceleration

of 2.72g was confirmed

to be the minimum seismic input for testing of replacement

breakers (the actual test used 3g). This also confirms that the appropriate

configuration

for testing of replacement

breakers is by rigid mounting to a test fixture. This rigid mounting is provided in the 1992 testing by bolting the breakers to a rigid test fixture.* Rigid attachment

of the breaker was done in the 1992 test by bolting the breaker to the test fixture using the rear tab slotted holes, which resulted in the entire weight of the breaker cantilevered

from the test fixture. Device testing in this manner maximizes

the input of test motion into the test specimen.Thus, TVA believes that the 1974 and 1992 tests meet the provisions

of IEEE-344-1975 and demonstrates

that the original board and the breakers remain seismically

E-3

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

qualified.

The 1992 test used to qualify a replacement

breaker used a suitable mounting method for single breaker testing, i.e., a rigid mounting arrangement

that reflects the rigidity of the clamping arrangement

in the board assembly.

The seismic qualification

of the overall assembly is demonstrated

by the 1974 test.Example 2 stated: "On September

3, 2009, the applicant

failed to perform an adequate review for suitability

of application

parts and material used to modify dimensional

critical characteristics

in molded case circuit breakers;

further, the applicant

failed to verify the adequacy of design for the modification

and the effects on essential

safety related functions

of the circuit breakers." TVA disagrees

that that the impact of the modification

to the method of retaining

the auxiliary

contact switch was not accounted

for in the seismic qualification

of the circuit breakers and overall assembly.The original Heinemann

Circuit Breaker, CF2-Z51 -1, was altered by the manufacturer

by changing the auxiliary

contact switch retainer that attaches to the main body of the breaker. This change was a result of new tooling that removed the thick retaining

plate for the Auxiliary

Contact Assembly mounted on the rear of the breaker. It was replaced by a small molded retainer bracket which secures the auxiliary

contact switch in the same position without adding to the entire depth of the pole containing

it. This alleviated

the difference

in the depth of one pole that contained

the retainer plate versus the depth of the other pole on the two pole breaker. Thus, the back of the new breaker is flat.* In order to accommodate

the shorter depth of the case, a Micarta plate is secured to the back face of the breaker. The thickness

of the Micarta plate is chosen such that the total depth of the breaker and the Micarta plate is identical to the depth of the original breaker and thus the clamping configuration

of the frame remains unchanged.

The Micarta plate is placed over the entire back surface of the breaker, thus creating a larger contact surface between the breaker and the rear angle irons which makes it more stable when secured by the front cover.* The Micarta plate is rigidly secured to the breaker using four screws and thus becomes an integral part of the breaker. The change in weight due to deletion of the previously

used retainer plate and substitution

of the Micarta plate adds approximately

1.5 oz. to the weight of the breaker. The mounting of the breaker with the Micarta plate provides an equivalent

fit to that shown on Westinghouse

Drawing No. CO-3341 9-MKE-M3 in Section C-C and exposes the bus bar to minimum additional

loading.* The functionality

of the breaker has not changed and the basic components (molded case frame, operating

mechanism, contacts and arc extinguisher, trip E-4

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

elements, Auxiliary

contact switch, and thermal connectors)

have not changed.Note that the auxiliary

contact switch does not provide a safety function.

The change in the method of retaining

the auxiliary

contact switch on the Heinemann

breaker and the addition of the Micarta plate spacer for installation

in the board does not impact the seismic qualification

of the reconfigured

breakers.

Therefore, even with the failure of the non-safety-related

auxiliary contact switch to function, the safety-related

function of the circuit breaker would not be affected.Some confusion

during the NRC's inspection

was created by information

contained

in the 1992 qualification

report. The 1992 qualification

report indicated

a Z dimension

of 3.75" and the manufacturer's

catalog now indicates

2.609" for the critical characteristic.

There is an explanation

for the difference.

  • Vendor schematics

show the Z dimension

of 3.75" given in the 1992 qualification

report includes the depth of the main body of the breaker of 2.609" plus the dimension

from the rear body of the breaker to the end of the auxiliary contacts (0.510") plus the dimension

from the front body of the breaker to the end of the lever (0.656") (reference

Attachment

1 and 2 in this Enclosure).

The total dimension

is 3.775" at the maximum arc of the breaker arm and is less than 3.775" in the closed or open position.

The clamping depth of the breaker as installed

in the power board is 2.8509" (2.609" + 0.25"). The depth (2.609")of the main body of the breaker is the same for the original and the reconfigured

breaker. Therefore, the purpose of the 0.25" thick Micarta plate is to maintain the required clamping depth for the reconfigured

breaker." In calculation

WCG-ACQ-1004

the change in mounting depth of the breaker was recognized

and the change with the addition of the Micarta plate was evaluated.

NRC stated that the breaker was modified by attaching

a Micarta plate to the rear of the breaker using 4 nuts and bolts to fit them in the power boards, as described

in Example 1, without updating the qualification

package. However, the qualification

package includes calculation

WCG-ACQ-1

004, which addresses

the qualification

of the circuit breakers with the Micarta plate and concludes

that the component (i.e., circuit breaker) remains seismically

qualified

under like for like conditions

per the 1992 seismic qualification

device test. Since breaker clamping configuration

was improved by creating a larger contact surface between the breaker and the rear angle irons which makes it more stable when secured by the front cover and the change in breaker weight was minor, the seismic qualification

of the overall board was not affected.Calculation

WCG-ACQ-1004

analyzed the effects that were introduced

by the modification, demonstrated

an adequate review for suitability

of application, and analyzed the impact on other components.

Calculation

WCG-ACQ-1004

was prepared to qualify the new Heinemann breakers that will replace existing breakers located in the 120 VAC Vital E-5

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

Instrument

Power Boards. The methodology

of the calculation

was to address maintaining

the seismic qualification

of host equipment

with the replacement

of existing components.

Specifically, calculation

WCG-ACQ-1004

addressed

the following:

o Qualification

of the breaker by identifying

the changes to the breaker as minor changes to the physical shape and the breaker was seismically

qualified

under like for like conditions.

o Attachment

of the breakers to the panel by stating that the breaker attaching

to the panel contains many similar parts with similar weights, all of which have qualified

connections.

The breaker will attach in the same fashion as the existing breakers and is thus qualified

under like for like conditions.

o Panel remains qualified

by recognizing

that the impact of the small change in weight has a negligible

impact on shifting the frequency response of the panel.o Qualification

of the anchorage

of the panel remains unchanged

due to the small change in design weight.The discussion

above demonstrates

that the design control process was followed to ensure that replacement

breakers, including

the reconfigured

breakers, as well as the board assembly, are seismically

qualified

to appropriate

design criteria.

Thus, the replacement

breakers are seismically

qualified

as like for like replacements

using the 1974 and 1992 tests as baseline qualification

tests. Calculation

WCG-ACQ-1004, as explained

above, provides the engineering

analysis that supports the conclusion

that the breakers are qualified.

Conclusion

Testing performed

to qualify both the 120VAC Vital Instrument

Power Boards as an assembly and the replacement

circuit breakers as individual

components

met the requirements

of IEEE-344-1975

and was suitable for seismic qualification.

TVA evaluated

the modification

to the molded case circuit breakers for safety-related

120VAC power applications

and confirmed

that the reconfigured

circuit breakers are qualified

for application

in the 120VAC Vital Instrument

Power Boards. Accordingly, TVA denies the violation.

E-6

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08 CCD 00 o=I To CD -: "C NJ so -D 0 T G) N)+ T ;t ,6)"FU'I!!-i : , , .,7 " i : C: 003"1 Ir N) ~.-j ,K 0A C n I E-7

Enclosure Watts Bar Nuclear Plant Unit 2 Reply to Notice of Violation (NOV)NOV 05000391/2010603-08

00 IOD 0 v)\ C. 11 0 0 r" " " 0 (~1N) tQ C-D 0 (-- 00 X -X Co)0 00 c 0, i O E-8