Letter Sequence Draft RAI |
---|
TAC:ME2609, Control Room Habitability, Deletion of E BAR Definition and Revision to RCS Specific Activity Tech Spec (Approved, Closed) TAC:ME2610, Control Room Habitability, Deletion of E BAR Definition and Revision to RCS Specific Activity Tech Spec (Approved, Closed) |
Results
Other: L-PI-10-076, Calculation No. GEN-PI-083, Revision 1, Locked Rotor Accident (LRA) Analysis Using AST, Attachment 5, L-PI-11-060, Response to Requests for Additional Lnformation (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology, L-PI-11-079, Response to Requests for Additional Lnformation (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology, L-PI-13-111, Notification of Alternative Source Term (AST) Implementation and Unit 2 Steam Generator Replacement, ML102300296, ML102300297, ML102300298, ML111822669
|
MONTHYEARL-PI-09-114, License Amendment Request to Adopt the Alternative Source Term Methodology2009-10-27027 October 2009 License Amendment Request to Adopt the Alternative Source Term Methodology Project stage: Request ML0935704512009-12-23023 December 2009 Acceptance Review of LAR to Adopt Alternative Source Term Methodology (TAC Nos. ME2609 & ME2610) Project stage: Acceptance Review L-PI-10-041, Response to Requests for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology2010-04-29029 April 2010 Response to Requests for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology Project stage: Response to RAI L-PI-10-046, Response to Requests for Additional Lnformation License Amendment Request to Adopt the Alternative Source Term Methodology2010-05-25025 May 2010 Response to Requests for Additional Lnformation License Amendment Request to Adopt the Alternative Source Term Methodology Project stage: Request L-PI-10-054, Response to Requests for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology2010-06-23023 June 2010 Response to Requests for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology Project stage: Response to RAI L-PI-10-076, Calculation No. GEN-PI-083, Revision 1, Locked Rotor Accident (LRA) Analysis Using AST, Attachment 52010-07-23023 July 2010 Calculation No. GEN-PI-083, Revision 1, Locked Rotor Accident (LRA) Analysis Using AST, Attachment 5 Project stage: Other ML1023002982010-07-23023 July 2010 Calculation No. GEN-PI-082, Revision 1, Control Rod Ejection Accident - AST, Attachment 4 Project stage: Other ML1023002972010-07-23023 July 2010 Calculation No. GEN-PI-081, Revision 1, Eab, LPZ, and CR Doses Due to Steam Generator Tube Rupture Accident - AST, Attachment 3 Project stage: Other ML1023002962010-07-23023 July 2010 Calculation No. GEN-PI-078, Revision 1, Main Steam Line Break (MSLB) Accident Analysis Using AST, Attachment 2 Project stage: Other ML1022200872010-08-10010 August 2010 Forthcoming Meeting with Northern States Power Company - Minnesota (Nspm), to Discuss the Prairie Island Nuclear Generating Plant Steam Generator Margin-to-Overfill Analysis as It Relates to Pingp'S License Amendment Request to Adopt... Project stage: Meeting ML1023002952010-08-12012 August 2010 Response to Requests for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology Project stage: Response to RAI ML1023805712010-08-25025 August 2010 Meeting Presentation Alternative Source Term Steam Generator Tube Rupture Margin to Overfill Evaluation - Prairie Island Nuclear Generating Plant Project stage: Request ML1025903972010-09-23023 September 2010 Prairie Island, Summary of Meeting with Northern States Power Company to Discuss the Alternative Source Term License Amendment Request Project stage: Meeting ML1032205572010-11-15015 November 2010 Draft RAI Concerning AST SGTR Mto Analysis Project stage: Draft RAI ML1032205552010-11-15015 November 2010 Draft RAI Concerning AST SGTR Mto Analysis Project stage: Draft RAI L-PI-10-112, Prairie Lsland Nuclear Generating Plant Units 1 and 2, Response to Request for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology (TAC Nos. ME2609 and ME26102)2010-12-17017 December 2010 Prairie Lsland Nuclear Generating Plant Units 1 and 2, Response to Request for Additional Information License Amendment Request to Adopt the Alternative Source Term Methodology (TAC Nos. ME2609 and ME26102) Project stage: Response to RAI ML1110400212011-04-0404 April 2011 NRR E-mail Capture - Prairie Island - Revised Alternative Source Term LAR Draft RAI 4-4-2011 Project stage: Draft RAI ML1035404332011-05-12012 May 2011 Requests for Additional Information (RAI) Associated with Adoption of the Alternative Source Term Project stage: RAI L-PI-11-060, Response to Requests for Additional Lnformation (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology2011-06-22022 June 2011 Response to Requests for Additional Lnformation (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology Project stage: Other ML1118226692011-06-29029 June 2011 PINGP - AST Methodology - ME2609 and ME2610 Project stage: Other L-PI-11-068, Response to Requests for Additional Information (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology2011-07-11011 July 2011 Response to Requests for Additional Information (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology Project stage: Response to RAI ML1120819672011-07-20020 July 2011 E-mail Prairie Island - Request for Clarification of June 22, 2011 Request for Additional Information (RAI) Response Project stage: RAI L-PI-11-079, Response to Requests for Additional Lnformation (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology2011-08-0909 August 2011 Response to Requests for Additional Lnformation (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology Project stage: Other ML1125503562011-09-0101 September 2011 Ngp - Draft RAI Concerning SGTR Instrumentation for Alternative Source Term LAR Project stage: Draft RAI ML1125503572011-09-0101 September 2011 PINGP Draft RAI - AST Instrumentation Project stage: Draft RAI ML1131100842011-11-0202 November 2011 Alternative Source Term Draft Request for Additional Information Project stage: Draft RAI ML1131100942011-11-0202 November 2011 RAI Prairie PINGP, Units 1 and 2 Project stage: RAI L-PI-11-099, Response to Requests for Additional Information Regarding Regulatory Guide 1.97 Instrumentation Associated with Adoption of the Alternative Source Term (AST) Methodology2011-12-0808 December 2011 Response to Requests for Additional Information Regarding Regulatory Guide 1.97 Instrumentation Associated with Adoption of the Alternative Source Term (AST) Methodology Project stage: Response to RAI L-PI-12-010, Response to Requests for Additional Information Associated with Adoption of the Alternative Source Term Methodology2012-02-13013 February 2012 Response to Requests for Additional Information Associated with Adoption of the Alternative Source Term Methodology Project stage: Response to RAI L-PI-12-013, Response to Requests for Additional Information Associated with Adoption of the Alternative Source Term (AST) Methodology2012-02-24024 February 2012 Response to Requests for Additional Information Associated with Adoption of the Alternative Source Term (AST) Methodology Project stage: Response to RAI L-PI-12-082, Response to Requests for Additional Information (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology2012-09-13013 September 2012 Response to Requests for Additional Information (RAI) Associated with Adoption of the Alternative Source Term (AST) Methodology Project stage: Response to RAI ML1125212892013-01-22022 January 2013 Issuance of Amendments Adoption of Alternative Source Term Methodology Project stage: Approval L-PI-13-111, Notification of Alternative Source Term (AST) Implementation and Unit 2 Steam Generator Replacement2014-01-13013 January 2014 Notification of Alternative Source Term (AST) Implementation and Unit 2 Steam Generator Replacement Project stage: Other 2011-12-08
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24116A2532024-04-25025 April 2024 Final Request for Additional Information for LAR to Revise SR 3.8.1.2 Note 3 (EPID: L- 2023-LLA-0135) ML24045A0862024-02-12012 February 2024 Final RAI for Alternative RR-09 ML23335A1152023-12-0101 December 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Request for Additional Information LAR to Revise TS 3.7.8 Required Actions ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23096A3082023-04-0707 April 2023 Notification of Inspection an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 ML23053A1432023-02-22022 February 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant ML22166A4112022-06-15015 June 2022 NRR E-mail Capture - Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-08, PIV Leakage ML22160A6022022-06-0909 June 2022 NRR E-mail Capture - Draft Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, 24-Month Operating Cycle Amendment ML22145A4152022-05-25025 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000282/2022402 05000306/2022402 ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22130A5792022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21321A0452021-11-10010 November 2021 Request for Additional Information: Prairie Island 24-Month Cycle Amendment Request ML21305A0102021-10-29029 October 2021 NRR E-mail Capture - Request for Additional Information Prairie Island Cooling Water Amendment ML21252A0122021-08-30030 August 2021 NRR E-mail Capture - Request for Additional Information Amendment Request to Adopt TSTF-471 and 517-T for Prairie Island ML21147A5232021-06-0303 June 2021 Prarie Island Nuclear Generating Plant, Units 1 and 2 - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21131A0752021-05-10010 May 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2021004; 05000306/2021004 ML21099A0972021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000282/2021012 and 05000306/2021012 ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant ML21033A6112021-02-0101 February 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000282/2021010 and 05000306/2021010 ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20192A1442020-07-0707 July 2020 NRR E-mail Capture - Request for Additional Information Prairie Island License Amendment Request to Adopt TSTF-505 ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 ML20133K0692020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20077K6242020-04-13013 April 2020 License Amendment Request - Request for Additional Information ML20052F4102020-02-21021 February 2020 Notification of Nrc Design Bases Assurance Inspection (Programs) (05000282/202010; 05000306/202010) and Initial Request for Information ML20035F1552020-02-0404 February 2020 NRR E-mail Capture - Request for Additional Information Monticello and Prairie Island Alternative Requests to Adopt Code Cases N-786-3 and N-789-3 (Epids: L-2019-LLR-0078 and L-2019-LLR-0079) ML19233A0032019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Prairie Island Relief Requests 1-RR-10 and 2-RR-10 ML19057A1652019-02-26026 February 2019 NRR E-mail Capture - Request for Additional Information Prairie Island 50.69 Amendment Request ML18313A0832018-11-0707 November 2018 NRR E-mail Capture - Request for Additional Information Prairie Island NFPA-805 License Condition Modification Amendment Request ML18264A1912018-09-19019 September 2018 NRC Information Request (9/19/2018); Part B Items (Onsite) IP 71111.08 - E-Mailed 09/19/18 (DRS-M.Holmberg) ML18235A2982018-08-23023 August 2018 NRR E-mail Capture - Request for Additional Information Prairie Island TSTF-425 License Amendment Request ML18169A4202018-06-25025 June 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Modify Renewed Facility Operating License Paragraph 2.C(4)(c) ML18025C0152018-01-24024 January 2018 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000282/2018011; 05000306/2018011 (DRS-A.Dunlop) ML17277B3332017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information Prairie Island Special Heavy Lifting Devices LAR ML17249A9232017-09-0606 September 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2017004; 05000306/2017004 (Exf) ML17235A9982017-08-23023 August 2017 NRR E-mail Capture - Request for Additional Information Prairie Island EAL Scheme Change ML17221A3892017-08-0909 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17219A0762017-08-0707 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17038A5132017-02-0707 February 2017 NRR E-mail Capture - Prairie Island NFPA 805 LAR, PRA RAI 21.01 ML17018A4272017-01-18018 January 2017 NRR E-mail Capture - Request for Additional Information: Prairie Island License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action ML16326A3532016-11-18018 November 2016 NRR E-mail Capture - Draft Request for Information Related to Prairie Island NFPA-805 License Amendment ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) ML16189A2052016-07-0707 July 2016 Notification of NRC Inspection and Request for Information ML16113A1612016-04-21021 April 2016 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant, Units 1 and 2 2024-07-15
[Table view] |
Text
DRAFT REQUEST FOR ADDITIONAL INFORMATION PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 DOCKET NOS. 50-282 AND 50-306
In reviewing the Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submittal dated October 29, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML093160583), which requested adoption of the Alternative Source Term Methodology (AST), in addition to technical specification changes supported by the AST design basis accident radiological consequences analysis for Prairie Island Nuclear Generating Plant (PINGP), Units 1 and 2, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed to complete its review:
Background
The PINGP licensee voluntarily requested to adopt the alternative source term (AST) method for license amendments, as allowed by Title 10 of the Code of Federal Regulations, Section 50.67 (10 CFR 50.67), "Accident source term". In support of its AST application, the licensee performed the required radiological releases analysis for the applicable design-basis-events to demonstrate that the dose limits specified in 10 CFR 50.67(b)(2) are not exceeded.
In the radiological releases analysis for an steam generator tube rupture (SGTR) event, the licensee made a key assumption that the steam generator (SG) overfill will not occur and the affected SG can be isolated during an SGTR event, and thus, only steam releases carrying radioactive material are considered for the radiological releases analysis. Water releases have a significantly greater concentration of radioactive material when compared with that of steam releases and will result in worse radiological releases. If the SG overfill occurs, the assumption of the steam releases cannot be validated. As a result, the radiological releases analysis for the SGTR event becomes invalid and is unacceptable for the AST application
. The margin-to-overfill (MTO) analysis is a method that can be used to validate the assumption that the SG will not overfill and only steam releases will occur during an SGTR event. Without an acceptable MTO analysis, the NRC staff cannot determine the validity of the key assumption, and thus, can accept neither the calculated steam mass releases used as inputs to the radiological releases analysis, nor the associated SGTR radiological releases analysis for
supporting the AST application. Therefore, the NRC staff determines that the conclusion drawn on the results of the MTO analysis is an essential consideration in the NRC staff's determination of acceptability of the SGTR radiological releases analysis, which is used to support the AST application.
Applicable Regulations and Regulatory Guidance
10 CFR 50.67 stipulates that the NRC may issue an AST amendment only if an applicant's analysis demonstrates with reasonable assurance that the dose limits specified in 10 CFR 50.67(b)(2) would be met.
Regulatory Position 1.3.2, specified in Regulatory Guide 1.183, "Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors," states that an analysis is considered to be affected if the proposed modification changes one or more assumptions or inputs used in that analysis such that the results, or the conclusions drawn on those results, are no longer valid.
Section 5.1.3 in Regulatory Guide 1.183 states that the numeric values that are chosen as inputs to the analyses should be selected with the objective of determining a conservative postulated dose.Technical Issues
The NRC staff reviewed the SGTR analysis in the license amendment request (LAR) dated October 27, 2009, and the associated response in the licensee's letter dated May 25, 2010, to the staff's request for additional information (RAI). As stated in its submittals, the licensee used its plant simulator to perform the steam generator (SG) MTO analysis during a SGTR event for the AST application. Specifically, the simulator was used in combination with Emergency Operating Procedures (EOP) E-0, "Reactor Trip or Safety Injection," and E-3, "Steam Generator Tube Rupture," to determine the response time for the break flow termination. Based on the response times (including the operator action times and the reactor coolant system (RCS) response times), the flow rates for the break flow into the ruptured SG, and the volume available in the ruptured SG, the SG MTO was determined.
As a result of its review, the NRC staff observes that the assumptions used in the analysis for various initial plant conditions (such as the pressure difference between the RCS primary side and secondary side in the ruptured SG) are conservative with respect to calculating the break flow rates into the ruptured SG. The NRC staff al so notes that the operator action and the RCS response times affect the overall conservatism of the SGTR MTO analysis, as they are used to determine the total amount of the break flow into the ruptured SG. Therefore, the use of a method acceptable to the NRC for determining the response times is equally as important as the assumptions that maximize break flow rates into the ruptured SG in assuring the adequacy of the SGTR MTO analysis.
During the review, the NRC staff noted that the licensee used its simulator in determining the response times in the MTO analysis. The computer codes and RCS thermal-hydraulic models used in the simulator at PINGP were not previously submitted to the NRC to review and approve for use in the analysis of transients and accidents (including the SGTR event) in support of licensing applications. The NRC staff notes that the simulator was built as a tool for the purpose of training operators, and was not designed for performing analysis in support of the licensing applications. Its physical models are relatively simple compared to those used in the licensing codes. The results of the MTO analysis (in the May 25, 2010 supplement) based on the longest response time from the licensee's simulator exercises show no MTO. In addition, the NRC staff compared the results from the simulator exercises to the results from the NRC-approved MTO method for two other Westinghouse 2-loop plants (PINGP is a Westinghouse 2-loop plant). The comparison revealed that the total response time to terminate the break flow from the primary-to-secondary RCS using the simulator at PINGP was significantly shorter (approximately 30 minutes vs. 50 minutes) than the response times of the other plants. The response time is used to determine the total amount of the break flow to the SG secondary side, which determines the SG MTO. A shorter response time is, therefore, not conservative with respect to the SG overfill analysis.
Request for Additional Information (RAI)
In order for the NRC staff to continue its review, the following additional information is needed:
A. RAI Related to the MTO Analysis
- 1. If the licensee chooses to continue to use its simulator for the MTO analysis, it should provide additional information related to the computer codes and RCS physical models in
the simulator for the NRC staff to review and approve. The additional information provided should include: a discussion of the methodology; computation device manuals; user's manuals and guidelines; scaling reports; assessment reports and uncertainty assessment reports as described in the applicable sections of Regulatory Guide 1.203, "Transient and Accident Analysis Methods."
The information should show that: the constituent equations representing the RCS thermal-hydraulics are correct and complete; the correlations for the heat transfer and flow rate determination are adequately supported by the applicable test data; the nodal scheme appropriately models the RCS; the mathematical methods provide stable solutions; the time step used for the mathematical solution does not result in divergent conditions; the system responses of the RCS for both with and without a loss of AC power are validated by comparing with the applicable integrated and separated effects test data; and the MTO analyses show that the assumptions and the plant conditions used result in a maximum
response time for the AST application.
- 2. Alternatively, the licensee may perform an SGTR MTO analysis for PINGP at current licensed thermal power (CLTP) conditions. The analysis should align as closely as possible to an NRC-approved methodology described in a Westinghouse topical report, WCAP-10698-P-A. However, since the licensee has stated that a limiting single failure is not in the PINGP licensing basis, this exception to the WCAP-10698-P-A methodology will be acceptable. The requested analytical results should include sequences of the event with specification of operator actions and the associated times credited in the analysis, and the response of key plant parameters versus time.
In addition to providing the analytical results, please address the following:
- a. Address compliance with the conditions and restrictions specified in the NRC safety evaluation reports approving the WCAP-10698-P-A methodology.
- b. List in a table the nominal values with the associated uncertainties, and corresponding values used in the MTO analysis for the major input initial conditions described in WCAP-10698-P-A. Discuss the bases used to select the numerical values of the input parameters and show that the numerical values used are conservative, resulting in a minimum SG MTO during an SGTR event.
- c. Ensure that the limiting liquid release pathway and scenario are identified. Include consideration of the steam line equipment water-release failures discussed in WCAP-11002-P (Note that the NRC staff discussed WCAP-11002-P in its evaluation of WCAP-10698-P-A, but did not find that it provided an acceptable method for performing a licensing basis safety analysis). If a liquid release is predicted, provide analyses of the static and dynamic structural effects in the main steam system and of the consequences of passing water through the steam pressure relief valves.
- d. Under the assumed LOOP conditions, address the functionality of each atmospheric dump valve (ADV). Discuss what, if any, mitigating function the ADV provides, and its capability to perform that function under the assumed LOOP conditions. If the valve's actuation must be manual, provide information to demonstrate that the operator is capable of actuating the valve within the analytically assumed time.
- e. For the CLTP case, provide recent trending data for full-power steam generator water level to demonstrate that a conservative initial steam generator water level (with consideration of the uncertainties and fluctuation around the nominal valves) has been selected.
- f. Identify operator actions and associated action times credited in the analysis. Where an operator action is credited, confirm that such action is consistent with station procedures and action times are conservative, resulting in a minimum SG MTO.
- g. Update the licensing basis radiological consequence analyses for the AST conditions to reflect radiological consequences of the above-identified limiting release, should they be more severe than the current, proposed, radiological analysis. Since the NRC staff is allowing the single failure exception to the WCAP-10698-P-A methodology, the above requested analysis represents an event that has a significantly higher likelihood of occurrence. Please also provide the following additional information:
- h. Identify how procedures address the steam generator overfill condition. What parameters do operators monitor to help ensure that overfill does not occur?
- i. For any revised radiological consequence analyses, provide the basis for the assumed flashing fraction, if it is less than 100 percent.
B. RAI Related to the SGTR Mass Release Analysis
- 1. Information on page 116 of the October 27, 2009 LAR indicates that the results of a recent Westinghouse SGTR analysis were used to determine: (1) primary coolant releases to the ruptured SG; (2) steam mass releases from ruptured SG to the environment; and (3) steam mass releases from intact SG to the environment.
Provide a discussion of the Westinghouse SGTR analysis for mass releases determination and verify that the methods used in the analysis are NRC- approved methods, and address compliance with restrictions and conditions specified in the NRC safety evaluation report approving the methods and computer codes. The requested information should also include the plant parameters considered in the analysis, identify the major input initial conditions and the worst single failure used in the analysis, discuss the bases used to select the numerical parameters and demonstrate that the numerical values with consideration of the uncertainties and fluctuations around the nominal values are conservative, resulting in maximum mass releases during an SGTR event. The results to be provided should include sequences of the event with specification of operator actions, associated times credited in the analysis and their bases for acceptance, and the response of key parameters versus
time.
Also, address the acceptability of the analysis performed at the extended power uprate (EPU) power level to the AST application, which is based on the current power level.
- 2. Page 116 of the LAR indicates that, based on the current PINGP licensing basis, the "termination of release from ruptured SG" was completed within 30 minutes from initiation of the SGTR event.
Discuss the "current licensing basis" for the event termination time of 30 minutes, its effect on and acceptability of the radiological release analysis, and its relationship with the break flow termination time of 30 minutes assumed in the MTO analysis.
C. RAI Related to Update of Updated Safety Analysis Report Discuss PINGP's plans to reflect the information provided in response to above items A and B in an update of the Updated Safety Analysis Report (USAR), pursuant to the requirements of 10 CFR 50.71, "Maintenance of records, making of reports."