ML072880413

From kanterella
Revision as of 16:24, 19 March 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Request for Technical Assistance, Resolution of the Impact of Air Handler Unavailability on Technical Specification Equipment Based on Interpretation of GL 80-30 Dated April 10, 1980 and NRC Letter to Perry, Dated April 05, 2002
ML072880413
Person / Time
Site: Perry, Harris  Duke Energy icon.png
Issue date: 10/04/2007
From: Corlett D H
Progress Energy Carolinas
To: Vaaler M G
Plant Licensing Branch III-2
References
GL-80-030, HNP-07-138
Download: ML072880413 (8)


Text

Progress Energy OCT 0 4 2007 Serial: HNP-07-138 10 CFR 50.36 Ms. M. G. Vaaler, HNP Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400/LICENSE NO. NPF-63 REQUEST FOR TECHNICAL ASSISTANCE

-RESOLUTION OF THE IMPACT OF AIR HANDLER UNAVAILABILITY ON TECHNICAL SPECIFICATION EQUIPMENT BASED ON INTERPRETATION OF GL 80-30 DATED APRIL 10, 1980 AND NRC LETTER TO PERRY NUCLEAR STATION DATED APRIL 5, 2002 (ML020950074)

Dear Ms. Vaaler:

Recent discussions between the Harris Nuclear Plant staff and the NRC Resident Inspectors at HNP have identified the need for clarification of issues concerning the impact of ventilation system air handler unavailability on Technical Specification (TS)equipment operability based on guidance found in GL 80-30 and an NRC Letter to Perry Nuclear Station. GL 80-30 is dated April 10, 1980, and is entitled "Clarification of the Term 'Operable' as it Applies to Single Failure Criterion for Safety Systems Required by Technical Specifications." The referenced NRC Letter from the NRC to Perry Nuclear Station (ML020950074) was dated April 5, 2002, and had a subject line stating "Application of Generic Letter 80-30 Guidance to an Inoperable Non-Technical Specification Support Subsystem." Background In its letter to Perry Nuclear station, the NRC finds that "the TS definition of operability does not require a TS subsystem's necessary support function to meet the single-failure design criterion.

Thus no TS limits the duration of the non-TS support subsystem outage, even though the single-failure design requirement of the supported TS system is not met. However, by assessing and managing risk in accordance with [10 CFR 50.65] (a)(4), the licensee can determine an appropriate duration for the maintenance activity." The letter goes on to point out that should a risk assessment support a period of unavailability for longer than 90 days for the support subsystem then a 10 CFR 50.59 evaluation would be required.

The letter also clarifies that "This allowance would be permitted regardless of whether the maintenance is corrective or preventive." Progress Energy Carolinas, Inc. A 0 0 (Harris Nuclear Planw P. 0 Box 165 New Hill NC 27562 4 HNP-07-138 Page 2 HNP acknowledges the need to demonstrate that any allowed period of unavailability of a support subsystem function which supports TS required systems is acceptable in accordance with 10 CFR 50.65(a)(4) and that the requirements of 10 CFR 50.59 still apply if a system were to be out of service for more than 90 days.However, HNP does not find any information in the NRC letter to Perry to indicate that its clarification of GL 80-30 is based on specific design or probabilitic risk assessment results related to the Perry Nuclear Station.Requested Action Please provide clarification concerning the generic applicability of the NRC position as presented in the NRC letter to Perry Nuclear Station, "Application of GL 80-30 Guidance to an Inoperable Non-Technical Specification Support Subsytem," dated April 5, 2002.Coordination This request was discussed between HNP representatives, Mr. Phillip O'Bryan -HNP Senior Resident Inspector, and yourself.

It was agreed that HNP should request clarification through its project manager. It is requested that the NRC review and respond to this Request for Technical Information.

Please refer any question regarding this submittal to Mr. Dave Corlett at (919) 362-3137.Sincerely, David H. Corlett Supervisor

-Licensing/Regulatory Programs Harris Nuclear Plant DHC/khv

Attachment:

1. NRC Letter to Mr. Guy Campbell, Perry Nuclear Station dated April 5, 2002 (ML020950074)

C: Mr. P. B. O'Bryan, NRC Sr. Resident Inspector Dr. W. D. Travers, NRC Regional Administrator Document Control Desk, NRC Attachment 1 to SERIAL: HNP-07-138 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400/LICENSE NO, NPF-63 REQUEST FOR TECHNICAL ASSISTANCE

-RESOLUTION OF THE IMPACT OF AIR HANDLER UNAVAILABILITY ON TS EQUIPMENT BASED ON INTERPRETATION OF GL 80-30 DATED APRIL 10, 1980 AND NRC LETTER TO PERRY NUCLEAR STATION DATED APRIL 5, 2002 (ML020950074)

NRC Letter to Mr. Guy Campbell, Perry Nuclear Station dated April 5, 2002 (ML020950074)

Page Al-1 of 6 April 5, 2002 Mr. Guy G. Campbell Vice President

-Nuclear, Perry FirstEnergy Nuclear Operating Company P.O. Box 97, A200 Perry, OH 44081

SUBJECT:

APPLICATION OF GENERIC LETTER 80-30 GUIDANCE TO AN INOPERABLE NON-TECHNICAL SPECIFICATION SUPPORT SUBSYSTEM

Dear Mr. Campbell:

Recent discussions with your staff have focused on the performance of on-line maintenance on systems that provide a support function (i.e., a support system). Specifically, your staff has questioned how to address the single-failure design criterion for support systems that are not included in the technical specifications (TSs) that provide a support function for systems that are included in the TSs.The staff has reviewed the guidance of Generic Letter 80-30, "Clarification of the Term'Operable' as it Applies to Single Failure Criterion for Safety Systems Required by Technical Specifications," that allows a plant to temporarily depart from the single-failure design criterion when the plant is operating within a TS action requirement.

In the enclosure, the staff has clarified the application of this guidance to non-TS support systems, and in particular to those that have two 100 percent capacity subsystems, such as Perry's ventilation system, with each subsystem capable of fully supporting both trains of TS equipment.

The need for this clarification was highlighted by concerns about the conduct of on-line maintenance on Perry's ventilation system. This clarification of the existing generic guidance was developed by the TS Section of the Office of Nuclear Reactor Regulation's Operating Reactor Improvement Program.Please feel free to contact me at (301) 415-1364 if you have any questions.

Sincerely, IRA!Douglas V. Pickett, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosure:

As stated cc w/encl: See next page April 5, 2002 Mr. Guy G. Campbell Vice President

-Nuclear, Perry FirstEnergy Nuclear Operating Company P.O. Box 97, A200 Perry, OH 44081

SUBJECT:

APPLICATION OF GENERIC LETTER 80-30 GUIDANCE TO AN INOPERABLE NON-TECHNICAL SPECIFICATION SUPPORT SUBSYSTEM

Dear Mr. Campbell:

Recent discussions with your staff have focused on the performance of on-line maintenance on systems that provide a support function (i.e., a support system). Specifically, your staff has questioned how to address the single-failure design criterion for support systems that are not included in the technical specifications (TSs) that provide a support function for systems that are included in the TSs.The staff has reviewed the guidance of Generic Letter 80-30, "Clarification of the Term'Operable' as it Applies to Single Failure Criterion for Safety Systems Required by Technical Specifications," that allows a plant to temporarily depart from the single-failure design criterion when the plant is operating within a TS action requirement.

In the enclosure, the staff has clarified the application of this guidance to non-TS support systems, and in particular to those that have two 100 percent capacity subsystems, such as Perry's ventilation system, with each subsystem capable of fully supporting both trains of TS equipment.

The need for this clarification was highlighted by concerns about the conduct of on-line maintenance on Perry's ventilation system. This clarification of the existing generic guidance was developed by the TS Section of the Office of Nuclear Reactor Regulation's Operating Reactor Improvement Program.Please feel free to contact me at (301) 415-1364 if you have any questions.

Sincerely, IRA/Douglas V. Pickett, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosure:

As stated cc w/encl: See next page Distribution:

PUBLIC PD 3-2 r/f OGC EMcKenna WBeckner ACRS GGrant, Rill CHarbuck RDennig CLipa, Rill AMendiola DPickett THarris ADAMS ACCESSION NUMBER:ML020950074 OFFICE PM:LPD3 LA:LPD3 Bt NAME DPickett THarris W\DATE 04/05/02 04/05/02 0,*See 4/2/02 memo from WBeckner to SBajwa C:RORP/Beckner*4/02/02 SC:LPD3 AMendiola 04/05/02 OFFICIAL RECORD COPY Guy G. Campbell FirstEnergy Nuclear Operating Company cc: Mary E. O'Reilly FirstEnergy Corporation 76 South Main St.Akron, OH 44308 Resident Inspector's Office U.S. Nuclear Regulatory Commission P.O. Box 331 Perry, OH 44081-0331 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4531 Sue Hiatt OCRE Interim Representative 8275 Munson Mentor, OH 44060 Gregory A. Dunn Manager -Regulatory Affairs FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, A210 Perry, OH 44081 William R. Kanda, Plant Manager FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, SB306 Perry, OH 44081 Mayor, Village of North Perry North Perry Village Hall 4778 Lockwood Road North Perry Village, OH 44081 Donna Owens, Director Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations

& Maintenance 6606 Tussing Road P. O. Box 4009 Reynoldsburg, OH 43068-9009 Perry Nuclear Power Plant, Unit 1 Carol O'Claire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-7150 Mayor, Village of Perry P.O. Box 100 Perry, OH 44081-0100 Dennis Clum Radiological Assistance Section Supervisor Bureau of Radiation Protection Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Zack. A. Clayton DERR Ohio Environmental Protection Agency ATTN: Mr. Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Chairman Perry Township Board of Trustees 3750 Center Road, Box 65 Perry, OH 44081 Daniel Z. Fisher Transportation Department Public Utilities Commission 180 East Broad Street Columbus, OH 43215-3793 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO APPLICATION OF GENERIC LETTER 80-30 GUIDANCE TO AN INOPERABLE 100 PERCENT CAPACITY NON-TECHNICAL SPECIFICATION SUPPORT SUBSYSTEM FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT, UNIT 1 DOCKET NO. 50-440 Technical Specifications (TSs) play an important part in the risk management of maintenance activities by limiting the duration of safety equipment outages. Because a failure to meet a system's TS limiting condition for operation usually involves a loss of redundancy, the affected system cannot withstand a single-failure and still perform its intended safety function.

TSs provide a time by which the design-basis must be restored (see Generic Letter (GL) 80-30). This staff position is acceptable because, by limiting the duration of plant operation with inoperable safety equipment, the TSs manage the associated increase in risk to an acceptable level.For plant operation with only one or two TS-required components inoperable, probabilistic risk assessment has indicated that the TS strategy for managing risk is usually conservative.

But for operation with multiple TS-required components inoperable, TSs may actually allow operation that is non-conservative compared to the established risk guidelines.

One reason for this is that the Nuclear Regulatory Commission never intended TSs to fully address inoperable components in several systems at the same time. Therefore, in addition to observing the limitations of TSs, licensees must also assess and manage risk associated with maintenance activities in accordance with paragraph (a)(4) of 10 CFR 50.65, the "maintenance rule," which states, Before performing maintenance activities (including but not limited to surveillance, post-maintenance testing, and corrective and preventive maintenance), the licensee shall assess and manage the increase in risk that may result from the proposed maintenance activities.

The scope of the assessment may be limited to structures, systems, and components that a risk-informed evaluation process has shown to be significant to public health and safety.The operability requirements for non-TS support systems are linked to the TS operability requirements of the systems they support, by the TS definition of operability:

A system, subsystem, train, component, or device shall be OPERABLE or have OPERABILITY when it is capable of performing its specified safety function(s) and when all necessary attendant instrumentation, controls, normal or ENCLOSURE emergency electrical power, cooling and seal water, lubrication, and other auxiliary equipment that are required for the system, subsystem, train, component, or device to perform its specified safety function(s) are also capable of performing their related support function(s).

Thus, TSs also play a role in managing the risk associated with maintenance on non-TS support systems.In most designs, the non-TS support system has two subsystems, each supporting just one TS train of safety equipment.

The duration of the maintenance activity is limited by the Required Action Completion Times of the supported TS system(s).

In this case, because the outage time of the non-TS support system is limited by the supported system TSs, the plant is temporarily allowed to depart from the single-failure design criterion, but the licensee may not rely solely on the TS limitations.

As noted above, the licensee must still assess and manage risk in accordance with (a)(4).In some designs, the non-TS support system has two redundant 100 percent capacity subsystems, each capable of supporting both TS trains. Loss of one support subsystem does not result in a loss of support for either train of TS equipment.

Both TS trains remain operable, despite a loss of support function redundancy, because the TS definition of operability does not require a TS subsystem's necessary support function to meet the single-failure design criterion.

Thus, no TS limits the duration of the non-TS support subsystem outage, even though the single-failure design requirement of the supported TS systems is not met. However, by assessing and managing risk in accordance with (a)(4), the licensee can determine an appropriate duration for the maintenance activity.

Use of administrative controls to implement such a risk-informed limitation is an acceptable basis for also allowing a temporary departure from the design-basis configuration during such maintenance.

Although not expected, were a licensee to determine that its risk assessment would permit the support subsystem to be inoperable for more than 90 days, then the licensee would have to evaluate the maintenance configuration as a change to the facility under 10 CFR 50.59, including consideration of the single-failure design criterion.

For the unusual non-TS support system design configuration described, the preceding is a clarification of the previous staff position (GL 80-30) regarding when a temporary departure from the single-failure design criterion is allowed. This allowance would be permitted regardless of whether the maintenance is corrective or preventive.

Regarding the situation in which the non-TS support subsystem is discovered to be in a degraded or non-conforming condition, the licensee must make a prompt determination of operability, as discussed in GL 91-18. If the non-TS support subsystem is determined to be inoperable, then the licensee must determine whether the subsystem's support function is actually needed to support operability of the supported TS systems. In some situations, the licensee may be able to establish other means to temporarily provide the required support function.

If the support function is required, then the risk-management strategies of the TSs and (a)(4), as described above for planned maintenance, will determine the appropriate actions and time limits to return the non-TS support subsystem to operable status, or to shut down the plant.Principal Contributor:

C Harbuck, RORP, NRR Date: