MONTHYEARML24137A2702024-05-16016 May 2024 NRR E-mail Capture - Entergy Fleet - Acceptance Review of License Amendment Request to Remove Obsolete License Conditions from Operating Licenses for GGNS, RBS, and WF3 (L-2024-LLA-0062) ML24108A1142024-04-17017 April 2024 June 2024 Emergency Preparedness Program Inspection - Request for Information ML24088A0092024-03-27027 March 2024 NRR E-mail Capture - Entergy Fleet - Final Request for Confirmation of Information (RCI) Re Alternative Request EN-RR-22-001 Concerning ASME Code Case N-752 (L-2022-LLR-0054) ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23335A0652023-12-0101 December 2023 NRR E-mail Capture - GGNS - Audit Questions for LARs Associated with TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Init. 4b and 50.69, Risk-Informed Cat. and Treatment of SSCs for Nuclear Pwr Rx (L-2023-LLA-0081/0080) ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23191A8662023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review of LAR Adopting 10 CFR 50.69, Risk-Informed Categorization and Treatment of SSCs for Nuclear Power Reactors ML23191A2802023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review for LAR Adopting TSTF-505, Rev. 2, Provide Risk-Informed Completion Times - RITSTF Initiative 4b ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23009B6912023-01-0909 January 2023 NRR E-mail Capture - Grand Gulf, Unit 1 and River, Unit 1 - Acceptance of Requested Licensing Action Request to Update ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines ML22353A6122022-12-19019 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22206A0152022-07-21021 July 2022 NRR E-mail Capture - Entergy (Grand Gulf, River Bend, and Waterford-3) - Acceptance Review of the RR EN-RR-22-001, Case N-752, Risk-informed Cat & Treatment for Repair/Replacement Activities in Class 2 & 3 Systems ML22173A0372022-06-21021 June 2022 NRR E-mail Capture - Entergy (Grand Gulf and River Bend) - Acceptance Review of the License Amendment Request to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 ML22075A3692022-03-0303 March 2022 Email Grand Gulf 2022 PI&R Request for Information ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21165A1352021-06-14014 June 2021 NRR E-mail Capture - Grand Gulf - Acceptance Review for Inserice Testing Program Relief Request VRR-GGNS-2021-1, Pressure Isolation Valve Testing Frequency ML21119A2152021-04-28028 April 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSE Unit 1 - Acceptance of Relief Request Proposed Alternative to Use ASME OM Code Case OMN-27 ML21109A2142021-04-19019 April 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Rev. Est Hours for Review of Relief Request (RR) - ASME Code RR Safety Eval with NRC-Approved Rev of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21109A2132021-03-23023 March 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Relief Request (RR) Associated with ASME Code RR Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21068A4092021-03-0909 March 2021 NRR E-mail Capture - Entergy Fleet (GGNS and RBS) -Approval of TSTF-501 LAR, Relocate Sored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21015A3452021-01-14014 January 2021 NRR E-mail Capture - Grand Gulf and River Bend - Revised Estimated Hours for Relief Request Associated with ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20363A1462020-12-22022 December 2020 Request for Information: Grand Gulf EP Exercise Inspection - March 2021 ML20352A1192020-12-10010 December 2020 Email from Thomas Saporito 12-10-20 ML20329A1442020-11-20020 November 2020 Terrapower QAPD Preliminary Questions Email ML20323A4162020-11-18018 November 2020 Response to Choice Letter (EA-20-094) ML20337A2712020-11-0909 November 2020 Email - Grand Gulf Nuclear Station 050-00416, Requested Regulatory Conference ML20289A3542020-10-14014 October 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of TSTF-563 LAR, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20258A0202020-09-0909 September 2020 EP Program Inspection RFI, Request for Information to Support and Prepare for Emergency Preparedness (EP) Program Inspection Scheduled to Occur the Week of November 16, 2020 ML20260H4422020-09-0808 September 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Official RAIs for RR Associated with Updating ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20176A4832020-06-22022 June 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of Relief Request Associated with ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20150A6012020-05-29029 May 2020 NRR E-mail Capture - Grand Gulf - Official RAI for LAR Associated with Containment ILRT Interval Change from 10 Years to 15 Years ML20097B8032020-04-0303 April 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the Exigent LAR Associated with One-Time Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies from 11.5 Years to 13.5 Years ML20093C3072020-04-0101 April 2020 NRR E-mail Capture - (External_Sender) Entergy Fleet - Performance-Based Cyber Security Testing Plan Fee Waiver Response Letter (EPID P-2020-PRF-0000; CAC No. 001648) ML20079D9302020-03-19019 March 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with Adopting TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volumes to Licensee Control ML20076B6322020-03-16016 March 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the LAR Associated with Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies ML20057G1752020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-566, Revise Actions for Inoperable RHR-Shutdown Cooling Subsystems ML20057G1592020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML19242C0122019-08-29029 August 2019 2.206 Petitioner (No Public Meeting Required) ML19339H4362019-08-26026 August 2019 Request for Information IR 05000416/2019-004 ML19115A3512019-04-25025 April 2019 LTR-19-0177 Tom Gurdziel, E-mail a Matter of Fairness Entergy Grand Gulf Seems to Be Running Rather Steadily at 100 Percent ML19151A3312019-04-0303 April 2019 (OEDO-19-00053)10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station ML19095B7622019-04-0303 April 2019 Acceptance Review Results for License Amendment Request to Adopt TSTF-564, Revision 2, Safety Limit MCPR (Minimum Critical Power Ratio), for Grand Gulf Nuclear Station, Unit 1 and River Bend Station, Unit 1 (EPID L-22019-LLA-0051) ML19078A3772019-03-19019 March 2019 NRR E-mail Capture - Grand Gulf - Official Rais for Relief Request GG-ISI-023, Inservice Inspection Impracticality, Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML19059A0292019-02-27027 February 2019 NRR E-mail Capture - Acceptance Review Results for License Amendment Request to Adopt TSTF-529, Revision 4, Clarify Use and Application Rules, for Entergy Fleet 2024-05-16
[Table view] |
Text
1NRR-PMDAPEm ResourceFrom:Wang, AlanSent:Sunday, January 11, 2015 6:46 PMTo:'SCARBROUGH, RICHARD A (RSCARBR@entergy.com)'Cc:Burkhardt, Janet; Blechman, PaulaSubject: Grand Gulf Nuclear Station Request for Additional Information Regarding License Amendment Request For Changing Five Technical Specification Allowabe Values (TAC No. MF4693)Richard, By Letter dated August 1, 2014 (Agencywide Documents Access and Management System Accession No. ML14216A383), Entergy Operations, Inc. (Entergy, the licensee), submitted a license amendment request (LAR) for the Grand Gulf Nuclear Station, Unit 1 (GGNS). The LAR proposes to modify the Technical Specification (TS) Surveillance Requirements (SRs) to support correction of five non-conservative technical specification allowable values. The revision to the calculations did not result in setpoint changes, only the allowable values are required to be changed. The US Nuclear Regulatory Commission (NRC) staff has reviewed the August 1, 2014, LAR and determined that the following additional information is required to complete its review of the amendment request.
1) The LAR requests correction of five non-conservative TS allowable values. However, the LAR does not explain how the licensee determined the current allowable values to be non-conservative. Please explain how the current allowable values in the TS are not conservative and therefore, resulted in the need for correcting these values. 2) Section 2.1 in the LAR lists the proposed changes for the five TS allowable values, in addition to information regarding the current Allowable Value (AV) identified in the TSs. The NRC staff noted the Current AV for Sys A & B Containment Spray Timers is listed in this section as 10.25 min. However, the TSs in Attachments 2 and 3 (TS pages) list the Current AV as 10.26 min. Please explain the inconsistency with the value reported for Sys A & B Containment Spray Timers. 3) In Attachment 4 of the LAR, the licensee provided its calculation JC-Q1B21-K114, "Instrument Uncertainty and Setpoint Determination for the System IB21-ADS, Initiation Timer Setpoint Validation." The staff has the following questions regarding this calculation: a. Section 2.0, "Design Requirements," (Sheet 7 of 62) identifies the current Technical Specification AV as 117 seconds. If the LAR is approved and the changes to the TS are implemented, this value in the Design Requirements section of the calculation will no longer be consistent. What is the plan to revise the Design Requirements to reflect the correct TS allowable value? b. Section 4.4, "1B21CK005A,B, ADS Timer Vendor Data," (Sheet 11 of 62) provides detailed information taken from the vendor data sheets, including accuracy, repeatability, and environmental capabilities. However, this calculation does not provide the vendor data sheets for the automatic depressurization system (ADS) Timers impacted by this calculation included with the LAR. Please identify the specific model of ADS Timer that is being used and provide a copy of the vendor data sheets for this model so staff can verify the specifications used in the calculation are accurate.
24) In Attachment 5 of the LAR, the licensee provided its calculation JC-Q1E12-K093, "Instrument Uncertainty and Setpoint Determination for System E12 Containment Spray Actuation Timer."
The staff has the following questions regarding this calculation: a. Section 2.0, "Design Requirements" (Sheet 6 of 47), identifies the current TS AV as 10.26 min and 11.44 min, which are the current AVs before this LAR is approved. If the LAR is approved and the changes to the TS are implemented, these values in the Design Requirements section of the calculation will no longer be consistent. What is the plan to revise the Design Requirements to reflect the correct TS allowable value? b. Sections 7.12, licensee event report (LER) Avoidance System A Loop, and Section 7.13, LER Avoidance System B Loop, (Sheet 20 of 47) calculate the Z value for the LER avoidance for the System A Loop and System B Loop, respectively. The General Electric setpoint methodology identifies a minimum acceptable value for the Z value. However, this section shows the values for System A and System B are below the minimum acceptable Z value for 90% LER avoidance. Please explain the reason for accepting the Z value values for System A and System B. c. Section 4.3, 1E12K093A, B Vendor Data, and Section 4.4, 1E12AK116 Vendor Data, (Sheet 9 and 10 of 47) provides detailed information taken from the vendor data sheets including accuracy, repeatability, and environmental capabilities. There are no copies of the vendor data sheets for the ETR model timers that are impacted by this calculation included with the LAR. Please provide a copy of the vendor data sheets for this model so that staff can verify the information from the vendor data sheets that is used within the calculation is accurate. 5) In Attachment 6 of the LAR, the licensee submitted its calculation JC-Q1R21-90024-1, "Division 1 & 2 Degraded 4.16 KV Bus Voltage Setpoint Validation. Section 3.2.4, Uncertainty Effects - Time Delay Relay," (Sheet 9 of 23) provides detail information taken from the vendor data sheets including accuracy and environmental capabilities. However, this calculation does not provide the vendor data sheets for the bistable logic cards and time delay one shot cards that are impacted by this calculation. Please provide a copy of the vendor data sheets for the bistable and time delay cards so that the NRC staff can verify the information from the vendor data sheets that is used within the calculation is accurate. These Requests for Additional Information were discussed with Mr. Richard Scarbrough on January 5, 2015, and it was agreed that a response would be provided within 60 days of receipt of this email. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1445 or via e-mail at Alan.Wang@nrc.gov.
Alan Wang Project Manager (Grand Gulf Nuclear Station)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222 Hearing Identifier: NRR_PMDA Email Number: 1811 Mail Envelope Properties (C0A338EE37A11447B136119705BF9A3F024B853D1AE9)
Subject: Grand Gulf Nuclear Station Request for Additional Information Regarding License Amendment Request For Changing Five Technical Specification Allowabe Values (TAC No. MF4693)
Sent Date: 1/11/2015 6:45:53 PM Received Date: 1/11/2015 6:45:00 PM From: Wang, Alan Created By: Alan.Wang@nrc.gov Recipients: "Burkhardt, Janet" <Janet.Burkhardt@nrc.gov> Tracking Status: None "Blechman, Paula" <Paula.Blechman@nrc.gov> Tracking Status: None
"'SCARBROUGH, RICHARD A (RSCARBR@entergy.com)'" <RSCARBR@entergy.com> Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 6066 1/11/2015 6:45:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: