MONTHYEARML0531902132005-11-0707 November 2005 Application for Amendment to Facility Operating License Revising Technical Specification, Section 3.9.3. to Allow Refueling Operations with the Containment Equipment Hatch Open Project stage: Request ML0608102112006-03-23023 March 2006 R. E. Ginna Nuclear Power Plant - Request for Additional Information Movement of Fuel with Eqiupment Hatch Open Project stage: RAI ML0613204802006-05-0505 May 2006 R. E. Ginna Nuclear Power Plant, Response to Request for Information Application for Amendment to Facility Operating License Revising Technical Specification Section 3.9.3 to Allow Refueling Operations with the Containment Equipment Hatch O Project stage: Response to RAI ML0616002232006-07-26026 July 2006 R. E. Ginna, License Amendment 98 Regarding Refueling Operations with Equipment Hatch Open Project stage: Approval ML0620903672006-07-26026 July 2006 Technical Specifications, Revises TS 3.9.3, Containment Penetrations, to Allow an Emergency Egress Door, Access Door, or Roll Up Door, as Associated with the Equipment Hatch Penetration, to Be Open, But Capable of Being Closed Project stage: Other 2006-03-23
[Table View] |
Similar Documents at Ginna |
---|
Category:Letter
MONTHYEARIR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 ML24286A0022024-10-11011 October 2024 Core Operating Limits Report Cycle 45, Revision 0 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing RS-24-092, Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-09-25025 September 2024 Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) ML24234A0922024-08-21021 August 2024 Requalification Program Inspection IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24170A3852024-07-16016 July 2024 R. E. Ginna Nuclear Power Plant - Alternative Associated with Inservice Testing of B Auxiliary Feedwater Pump - PR-03 ML24197A0302024-07-15015 July 2024 LLC - Operator Licensing Examination Approval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions IR 05000244/20244022024-06-20020 June 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000244/2024402 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24143A0752024-05-22022 May 2024 Re. Ginna Nuclear Power Plant and Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License ISFSI Casks ML24136A1692024-05-14014 May 2024 And Independent Spent Fuel Storage Installation (ISFSI) - 2023 Annual Radioactive Effluent Release Report and 2023 Annual Radiological Environmental Operating Report ML24134A0042024-05-13013 May 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2024010 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000244/20240012024-04-24024 April 2024 LLC - Integrated Inspection Report 05000244/2024001 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24101A0432024-04-10010 April 2024 2024 10 CFR 50.46 Annual Report IR 05000244/20240112024-04-10010 April 2024 LLC - Fire Protection Team Inspection Report 05000244/2024011 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24088A2042024-03-28028 March 2024 R. E. Ginna Nuclear Power Plant - Response to NRC Request for Additional Information Regarding Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump ML24110A0122024-03-28028 March 2024 2023 Report of Individual Monitoring for R.E. Ginna Nuclear Power Plant LLC, License DPR-18 ML24067A2532024-03-0707 March 2024 Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam IR 05000244/20230062024-02-28028 February 2024 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC, (Report 05000244/2023006) IR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report 2024-09-25
[Table view] |
Text
e - -- , ;
Dave A. Holm R.E. Ginna Nuclear Power Plant, LLC Plant General Manager 1503 Lake Road Ontario, New York 14519-9364 585.771.3635 585.771.3900 Fax Dave.A.Holm @costellation.com Constellation Energy-I Generation Group May 5, 2006 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Control Desk
SUBJECT:
R.E. Ginna Nuclear Power Plant Docket No. 50-244 Response to Request for Information Re: Application for Amendment to Facility Operating License Revising Technical Specification. Section 3.9.3. to Allow Refueling Operations With the Containment Equipment Hatch Open.
Reference 1: Letter to USNRC Document Control Desk from Mary G. Korsnick (Ginna), subject:
Application for Amendment to Facility Operating License Revising Technical Specification, Section 3.9.3, to Allow Refueling Operations with the Containment Equipment Hatch Open, dated November 7, 2005.
Reference 2: Letter to Mary G. Korsnick (Ginna) from Patrick Milano (NRC), subject: R.E. Ginna Nuclear Power Plant - Request for Additional Information Regarding Movement of Fuel with Equipment Hatch Open (TAC No. MC89 10), dated March 23, 2006.
On November 7, 2005 R.E. Ginna Nuclear Power Plant, LLC (Ginna) submitted Reference 1 for NRC review. On March 23, 2006 the NRC requested additional information in Reference 2. Also, on April 13, 2006, Ginna and NRC Staff held a conference call to discuss details of the containment hatch configuration and clarify the information requested in Reference 2. Enclosure (1) to this letter contains the requested information based on the above correspondence and subsequent conversation.
Should you have questions regarding the information in this submittal, please contact Mr. Robert Randall at (585) 771-3734 or Robert.Randall @constellation.com.
Dave A. Holm A-CO f
/ OOA6S/
Document Control Desk May 5, 2006 Page 2 STATE OF NEW YORK
- TO WIT:
COUNTY OF WAYNE I, Dave A. Holm, begin duly sworn, state that I am Plant General Manager, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC), and that I am duly authorized to execute and file this request on behalf of Ginna LLC. To the best of my knowledge and belief, the statements contained in this document are true and correct. To the extent that these statements are not based on my personal knowledge, they are based upon information provided by other Ginna LLC employees and/or consultants. Such information has been reviewed in accordance with company practice and I believe it to be reliable.
(7/4 Subpcribed and sworn before me, a Notary Public in and of te,"P- .this _day
_ of Z4 f -, 2006(
- I JI WITNESS my Hand and Notarial Seal:
My Commission Expires:
DH/MR RICHARD A.JOHNSON NOTARY PUBLIC, STATE OF EWYORK
Enclosures:
- 1. Response to Request for Additional Information No. 01JO6082344 QUALIFIED INWAYNE COUNTY MY COMMISSION EXPIRES OCT. 21, 20_G cc: S. J. Collins, NRC P.D. Milano, NRC - i-'
Resident Inspector, NRC (Ginna)
P.D. Eddy, NYSDPS
_ f_
Enclosure 1 Response to Request for Additional Information R.E. Ginna Nuclear Power Plant, LLC May 5, 2006
Response to Request for Additional Information Question:
In Enclosure I to the November 7, 2005, application, the licensee states that the proposed amendment would permit either both equipment hatch doors, the closure plate access door, or the roll-up door associatedwith the enclosure building to be open during refueling. The control room atmospheric dispersionfactor (X/Q value) used in the dose assessment to support this amendment request assumes that the equipment hatch is the limiting case because it is the largestpenetrationand has the shortest distance to the control room intake. However, the equipment hatch to control room X/Q values were generatedassuming a diffuse (area) release, which could result in lower X/Q values than for a point source release slightly furtherfrom the control room intake.
Confirm that the control room X/Q values associatedwith a postulated releasefrom the equipment hatch are more limiting than the postulated releasesfrom the closure plate access dooror the roll-up door associated with the enclosure building.
Response
The enclosure building encloses the entire hatch assembly, including the barrel and associated airlock.
The front of the enclosure building is isolated from the environment by the roll-up door referenced in the submittal. Reference 1 includes three methods of containment closure.
- 1. Typical operation during refueling is to remove the hatch barrel and air-lock assembly by withdrawing them through the roll-up door to a remote location using a rail track system.
Containment closure is then obtained by closing the roll-up door. Should a refueling accident occur in this configuration, the activity would disperse into the containment atmosphere and diffuse through the 14 foot diameter opening in the containment wall into the enclosure building, and then exit to the environment through the rollup door at the opposite end of the enclosure building. These assumptions are valid for the analysis presented in Reference 1. The rollup door diffuse area source, whether the door is open or closed, are assumed to be equivalent based on the guidance in Regulatory Guide 1.194, section 3.2.4.
- 2. Should the rollup door become inoperable, closure could be obtained by reinstalling the hatch barrel/airlock assembly. The end of the hatch barrel is approximately 4 feet inside the rollup door in this configuration. Because the end of the hatch barrel is close to the rollup door opening, it could be conservatively assumed that no dispersion would occur in the enclosure building before entering the environment. The area source is represented by the airlock door with dimensions of approximately 3'7" by 6'9".
- 3. If the rollup door and hatch barrel/airlock assembly are unavailable, closure could be obtained by covering the 14 foot diameter opening in the containment wall with the closure plate, which contains a personnel access door with dimensions of approximately 4' by 8'. Any release would be through the open personnel access door in the closure plate, into the enclosure building and then out the open rollup door on the opposite end of the enclosure building.
Of the above configurations option 2 was evaluated because, although slightly further from the control room intake than the rollup door, the dimensions of the opening are smaller. Also, because of the proximity of the hatch barrel personnel door to the rollup door, no credit for dispersion in the enclosure building is considered. With the new dimensions and distances calculated as a defuse area source, the R.E. Ginna Nuclear Power Plant, LLC May 5,2006
I I X/Q increases from 5.58E-03 to 5.76E-3, which is a change of approximately 3 % from the value reported in Reference 1. Applying the new X/Q, the post EPU calculated control room dose would increase by 0.05 Rem to 1.45 Rem TEDE. Therefore, all hatch configuration options presented in Reference 1 are acceptable from a dose perspective.
R.E. Ginna Nuclear Power Plant, LLC May 5,2006