MONTHYEARIR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21327A1702021-06-16016 June 2021 ES-401-6 ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A0922021-06-16016 June 2021 ES-301-6 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1202021-06-16016 June 2021 ES-201-2 ML21327A3362021-06-16016 June 2021 Handouts to Applicants (Summary) ML21327A3262021-06-16016 June 2021 Administered Written Exam with Answer Key ML21328A1382021-06-16016 June 2021 Proposed Admin JPMs ML21327A3212021-06-16016 June 2021 Administered Scenarios ML21328A1622021-06-16016 June 2021 Proposed Control Room and In-Plant JPMs ML21328A1642021-06-16016 June 2021 Proposed Scenarios ML21328A1662021-06-16016 June 2021 Proposed Written Exam with Answer Key ML21327A3082021-06-16016 June 2021 Administered Admin JPMs ML21327A3422021-06-16016 June 2021 Modified Question Source Information ML21327A3142021-06-16016 June 2021 Administered Control Room and In-Plant JPMs ML21120A0202021-05-0303 May 2021 Operator Licensing Examination Approval IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 ML22158A1462021-02-0505 February 2021 Fer 2020 Ile ES-301-7 Operating Test Review Worksheet-Final ML22158A1302021-02-0505 February 2021 Fer 2020 ES-201-1 Rev 11 ML22158A1332021-02-0505 February 2021 Fer 2020 Ile Final Es 201-3 ML22158A1382021-02-0505 February 2021 Fer 2020 Ile Es 403-1 RO-SRO Written Exam Grading Quality Checklist ML22158A1582021-02-0505 February 2021 Fer 2020 Ile NRC ES-401-4 Record of Rejected KAs Rev 11 2023-08-16
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21327A1702021-06-16016 June 2021 ES-401-6 ML21326A1202021-06-16016 June 2021 ES-201-2 ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21327A0922021-06-16016 June 2021 ES-301-6 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A3362021-06-16016 June 2021 Handouts to Applicants (Summary) ML21327A3262021-06-16016 June 2021 Administered Written Exam with Answer Key ML21327A3212021-06-16016 June 2021 Administered Scenarios ML21327A3142021-06-16016 June 2021 Administered Control Room and In-Plant JPMs ML21327A3082021-06-16016 June 2021 Administered Admin JPMs ML21328A1662021-06-16016 June 2021 Proposed Written Exam with Answer Key ML21328A1642021-06-16016 June 2021 Proposed Scenarios ML21328A1622021-06-16016 June 2021 Proposed Control Room and In-Plant JPMs ML21327A3422021-06-16016 June 2021 Modified Question Source Information ML21328A1382021-06-16016 June 2021 Proposed Admin JPMs ML21120A0202021-05-0303 May 2021 Operator Licensing Examination Approval IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 ML22158A1582021-02-0505 February 2021 Fer 2020 Ile NRC ES-401-4 Record of Rejected KAs Rev 11 ML22158A1382021-02-0505 February 2021 Fer 2020 Ile Es 403-1 RO-SRO Written Exam Grading Quality Checklist ML22158A1332021-02-0505 February 2021 Fer 2020 Ile Final Es 201-3 ML22158A1302021-02-0505 February 2021 Fer 2020 ES-201-1 Rev 11 ML22158A1642021-02-0505 February 2021 Ile Outline Review Comments 2023-08-16
[Table view] |
Text
OPERATING TEST COMMENTS JPM COMMENTS
- 1. JPM No. 2010-301-AT-01R - Unable to setup simulator to support performance of MODE 5 Shiftly/Daily Surveillance
- a. Changed from a MODE 5 to MODE 4 surveillance
- b. Changed K/A from 2.1.44 to 2.1.18
- c. Changed task elements due to changes in MODE to include:
- i. Recording of Torus Water Level ii. Recording of RPV Flange Temperature iii. Identification abnormal indication for annunciator 3D57 iv. Identification of abnormal RHR configuration
- v. Identification of abnormal SRM indication
- 2. JPM No. 2010-301-AT-01S
- a. Changed K/A from 2.1.44 to 2.1.40 to reflect SRO nature of JPM
- b. Changed SRM verification step
- i. From 1 SRM below 3 cps to 2 SRMs below 3 cps ii. Included completed SRM signal to noise verification packages to be evaluated
- c. Included Secondary Containment Differential Pressure Correction Tables as required material
- 3. JPM No. 2010-301-AT-02
- a. Revised to allow use of IPCS including addition of appropriate cues
- b. Revised to include data tables (information to be provided when requested);
allows performance in classroom setting rather than in Simulator
- 4. JPM No. 2010-301-AT-03S
- a. Changed task from Assess Shutdown Risk to Evaluate a Temporary Change Notice since procedure guidance for assessing risk was too generic to support a JPM.
- b. Replacement JPM from bank
- 5. JPM No. 2010-301-AT-04R
- a. Changed to RO only
- b. Revised required materials to include Mock Up RWP and Survey Map
- 6. JPM No. 2010-301-AT-04S
- a. Added new SRO only JPM to Review and approve Discharge Permit
- b. Replacement JPM from bank
- 7. JPM No. 2010-301-AT-05S
- a. Updated to reflect changes in procedure.
- 8. JPM No. 2010-301-CR-04
- a. Included a recommended IC for setup
- b. Added clarifying information to evaluator prompt and note
- 9. JPM No. 2010-301-CR-05
- a. Added step to setup to ensure that injection path is isolated
- b. Added step to un-isolate injection path
- c. Included preferred level band in evaluator notes.
- 10. JPM No. 2010-301-CR-07
- a. Added guidance for simulator operator to act as RO responsible for maintaining reactor period and ranging of IRMs
- 11. JPM No. 2010-301-IP-02
- a. Changed valve number and fuse location to simplify access to panel
- 12. JPM No. 2010-301-IP-03
- a. Added clarifying information for evaluator
- b. Added missed step SCENARIO COMMENTS
- 1. Scenario 1
- a. Eliminated reactivity manipulation to shorten scenario run time
- b. Increased delay time for sticking IRM to provide a more noticeable indication of failure.
- c. Included additional role play messages for communicator
- d. Added clarification that applicants may isolate RCIC before auto isolation signal is actuated
- e. Added clarifying note for CRD Flow transmitter failure
- f. Added clarifying not related to exiting ATWS EOP power leg to SCRAM AOP
- g. Changed mechanical vacuum pump failure from a credited component failure to simply an observation of failure
- 2. Scenario 2
- a. Changed RR Pump trip event type from Reactivity Manipulation to Component malfunction due to insufficient time between initiation of malfunction and automatic trip of pump.
- b. Added Role-Play communications
- c. Revised Bypass Valve Test expected actions to include both procedurally allowed methods for reclosing valve.
- d. Revised expected TS actions for failed accumulator to provide more detail
- e. Added expectation for insertion of CRAM array in response to RR Pump Trip
- f. Revised response actions for Feed Pump suction strainer clogging to include possibility that applicants may trip pump rather than perform a controlled shutdown of pump (power already low enough to support single pump operation due to RR pump trip response)
- 3. Scenario 3
- a. Changed CW system rupture event type from Major to Component failure.
- b. Revised severity of SBFW Injection valve failure to permit some injection to ensure that response to small break LOCA is driven by containment parameters and not RPV parameters
- c. Eliminated RCIC malfunction and changed HPCI failure from a credited malfunction to recognition of failure.
- d. Added Role-Play communications
- e. Changed stator water cooling malfunction from TCV failure to HX fouling
- f. Added clarifying information where needed.