{{#Wiki_filter:April 28, 2016 | {{#Wiki_filter:April 28, 2016 | ||
Mr. Shane M. Marik, Vice President | |||
Mr. Shane M. Marik, Vice President | |||
and Chief Nuclear Officer Omaha Public Power District | |||
Fort Calhoun Station | Fort Calhoun Station | ||
P.O. Box 550 | P.O. Box 550 | ||
Fort Calhoun, NE 68023-0550 SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS | |||
INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION Dear Mr. Marik: | Fort Calhoun, NE 68023-0550 | ||
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS | |||
INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION | |||
Dear Mr. Marik: | |||
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) | The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) | ||
staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant modifications at your Fort Calhoun Station from July 25 through July 29 and August 8 through August 12, 2016. The inspection will consist of three reactor inspectors from the NRC's Region IV office for two weeks. The inspection will be conducted in accordance with NRC Inspection Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications." | staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant modifications at your Fort Calhoun Station from July 25 through July 29 and August 8 through August 12, 2016. The inspection will consist of three reactor inspectors from the NRC's Region IV office for two weeks. The inspection will be conducted in accordance with NRC Inspection | ||
Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications." | |||
Experience has shown that this | |||
inspection is resource intens | |||
ive for both the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. | |||
Please note that the documents are requested to | |||
be provided by July 18, 2016. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It | |||
is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. | |||
We have discussed the schedule for these inspection activities with your staff and understand | We have discussed the schedule for these inspection activities with your staff and understand | ||
that our regulatory contact for this inspection will be Corey Cameron of your licensing | that our regulatory contact for this inspection will be Corey Cameron of your licensing | ||
organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Robert Latta, by telephone at 817-200-1532 or by e-mail at Robert.Latta@nrc.gov. | organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Robert Latta, by telephone at 817-200-1532 or by e-mail at | ||
Robert.Latta@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject to | This letter does not contain new or amended information collection requirements subject to | ||
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information | the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information | ||
collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the | collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the | ||
requesting document displays a currently valid Office of Management and Budget control number. | requesting document displays a currently valid Office of Management and Budget control | ||
S. Marik - 2 - In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | number. | ||
S. Marik - 2 - | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1 | |||
Division of Reactor Safety | |||
Docket No. 50-285 License No. DPR-40 | Docket No. 50-285 License No. DPR-40 | ||
Enclosure: | Enclosure: | ||
Request for Information | Request for Information | ||
cc: Electronic Distribution | cc: Electronic Distribution | ||
S. Marik - 2 - | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1 | |||
Division of Reactor Safety | |||
Docket No. 50-285 License No. DPR-40 | |||
Enclosure: | |||
Request for Information | |||
Letter to Shane M. Marik from Thomas R. Farnholtz, dated April 28, 2016 SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS | |||
INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION | cc: Electronic Distribution | ||
Electronic distribution by RIV: Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Kriss.Kennedy@nrc.gov) DRP Director (Troy.Pruett@nrc.gov) | |||
Distribution | |||
: See next page | |||
ADAMS ACCESSION NUMB | |||
ER: ML16119A486 SUNSI Review By: RLatta | |||
ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword: NRC-002 OFFICE R4:SRI/EB1 R4:C/EB1 NAME RLatta TFarnholtz SIGNATURE /RA/ /RA/ DATE 4/27/16 4/28/16 OFFICIAL RECORD COPY | |||
Letter to Shane M. Marik from Thomas R. Farnholtz, dated April 28, 2016 | |||
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS | |||
INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION | |||
Electronic distribution by RIV: | |||
Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Kriss.Kennedy@nrc.gov) DRP Director (Troy.Pruett@nrc.gov) | |||
DRP Deputy Director (Ryan.Lantz@nrc.gov) | DRP Deputy Director (Ryan.Lantz@nrc.gov) | ||
DRS Director (Anton.Vegel@nrc.gov) | DRS Director (Anton.Vegel@nrc.gov) | ||
Line 56: | Line 113: | ||
Project Engineer, DRP/D (Jan.Tice@nrc.gov) Project Engineer, DRP/D (Jim.Melfi@nrc.gov) RIV Public Affairs Officer (Victor.Dricks@nrc.gov) | Project Engineer, DRP/D (Jan.Tice@nrc.gov) Project Engineer, DRP/D (Jim.Melfi@nrc.gov) RIV Public Affairs Officer (Victor.Dricks@nrc.gov) | ||
NRR Project Manager (Fred.Lyon@nrc.gov) | NRR Project Manager (Fred.Lyon@nrc.gov) | ||
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov) | Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov) | ||
RITS Coordinator (Marisa.Herrera@nrc.gov) | RITS Coordinator (Marisa.Herrera@nrc.gov) | ||
Line 61: | Line 119: | ||
OEWEB Resource@nrc.gov | OEWEB Resource@nrc.gov | ||
OEWEB Resource (Sue.Bogle@nrc.gov) | OEWEB Resource (Sue.Bogle@nrc.gov) | ||
Technical Support Assistant (Loretta.Williams@nrc.gov) RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov) RIV RSLO (Bill.Maier@nrc.gov) | Technical Support Assistant (Loretta.Williams@nrc.gov) RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov) | ||
ACES (R4Enforcement.Resource@nrc.gov) | RIV RSLO (Bill.Maier@nrc.gov) | ||
- 1 - Enclosure Request for Information Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications Inspection Fort Calhoun Station | |||
ACES (R4Enforcement.Resource@nrc.gov) | |||
- 1 - Enclosure | |||
Request for Information | |||
Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications | |||
Inspection Fort Calhoun Station | |||
Inspection Report: 05000285/2016007 | Inspection Report: 05000285/2016007 | ||
Inspection Dates: On-site - July 25-29 and August 8-12, 2016 | |||
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications" Lead Inspector: Robert Latta, Senior Reactor Inspector | Inspection Dates: On-site - July 25-29 and August 8-12, 2016 | ||
Information Requested for the In-Office Preparation Week | |||
The following information should be sent to the Region IV office in hard copy or electronic format (preferred) by July 18, 2016, to the attention of Robert Latta. We request that you categorize the documents in your response with the numbered list below. If only hard copies of | Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications" | ||
Lead Inspector: Robert Latta, Senior Reactor Inspector | |||
Information Requested for the In-Office Preparation Week | |||
The following information should be sent to the Region IV office in hard copy or electronic | |||
format (preferred) by July 18, 2016, to the attention of Robert Latta. We request that you categorize the documents in your response with the numbered list below. If only hard copies of | |||
the requested documents are available or if the electronic format is too large, please inform the | the requested documents are available or if the electronic format is too large, please inform the | ||
lead inspector and provide the documents on the first day of the on-site inspection. Also, the | lead inspector and provide the documents on the first day of the on-site inspection. Also, the | ||
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks. We ask that the specific items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as | inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks. We ask that the specific items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as | ||
possible. | possible. | ||
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations. 2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation. | |||
not result in an application for a license amendment. | 1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations. | ||
- 2 - 7. Procedure(s) for implementing permanent plant modifications. 8. A list with descriptions of all permanent plant modifications fully implemented since the last triennial modification inspection. | 2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation. | ||
11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and permanent plant modification programs. | 3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did | ||
required by 10 CFR 50.59(d)(2). | not result in an application for a license amendment. | ||
4. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial modification inspection. | |||
5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates. | |||
6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates. | |||
- 2 - 7. Procedure(s) for implementing permanent plant modifications. | |||
8. A list with descriptions of all permanent plant modifications fully implemented since the last triennial modification inspection. | |||
9. A list with descriptions of all corrective action documents related to permanent plant modifications fully implemented since the last triennial modification inspection. | |||
10. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report. | |||
11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and permanent plant modification programs. | |||
12. A copy of the most recent submittal of the report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, | |||
required by 10 CFR 50.59(d)(2). | |||
13. A list of systems and system designators and a set of one-line (i.e., simplified) system | |||
diagrams. | |||
Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can | Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can | ||
determine the safety and/or risk significance of the screenings, evaluations, and modifications. | determine the safety and/or risk significance of the screenings, evaluations, and modifications. | ||
Note: For this inspection, permanent plant modifications include permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability | Note: For this inspection, permanent plant modifications include permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability | ||
analyses, calculations, and commercial grade dedications. | analyses, calculations, and commercial grade dedications. | ||
Inspector Contact Information: | |||
Robert Latta Jonathan Braisted Samuel Graves | Robert Latta Jonathan Braisted Samuel Graves | ||
Senior Reactor Inspector Reactor Inspector Senior Reactor Inspector | Senior Reactor Inspector Reactor Inspector Senior Reactor Inspector | ||
817-200-1532 817-200-1194 817-200-8385 | 817-200-1532 817-200-1194 817-200-8385 | ||
Robert.Latta@nrc.gov Jonathan.Braisted@nrc.gov Samual.Graves@nrc.gov | Robert.Latta@nrc.gov Jonathan.Braisted@nrc.gov Samual.Graves@nrc.gov | ||
Mailing Address: | Mailing Address: | ||
U.S. NRC, Region IV Attn: Robert Latta 1600 East Lamar Blvd. | U.S. NRC, Region IV | ||
Attn: Robert Latta 1600 East Lamar Blvd. | |||
Arlington, TX 76011-4125 | Arlington, TX 76011-4125 | ||
}} | }} |
Revision as of 10:27, 30 June 2018
ML16119A486 | |
Person / Time | |
---|---|
Site: | Fort Calhoun ![]() |
Issue date: | 04/28/2016 |
From: | Thomas Farnholtz Region 4 Engineering Branch 1 |
To: | Marik S M Omaha Public Power District |
References | |
IR 2016007 | |
Download: ML16119A486 (6) | |
See also: IR 05000285/2016007
Text
April 28, 2016
Mr. Shane M. Marik, Vice President
and Chief Nuclear Officer Omaha Public Power District
Fort Calhoun Station
P.O. Box 550
Fort Calhoun, NE 68023-0550
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS
INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION
Dear Mr. Marik:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)
staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant modifications at your Fort Calhoun Station from July 25 through July 29 and August 8 through August 12, 2016. The inspection will consist of three reactor inspectors from the NRC's Region IV office for two weeks. The inspection will be conducted in accordance with NRC Inspection
Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications."
Experience has shown that this
inspection is resource intens
ive for both the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to
be provided by July 18, 2016. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It
is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Corey Cameron of your licensing
organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Robert Latta, by telephone at 817-200-1532 or by e-mail at
Robert.Latta@nrc.gov.
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
S. Marik - 2 -
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1
Division of Reactor Safety
Docket No. 50-285 License No. DPR-40
Enclosure:
Request for Information
cc: Electronic Distribution
S. Marik - 2 -
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1
Division of Reactor Safety
Docket No. 50-285 License No. DPR-40
Enclosure:
Request for Information
cc: Electronic Distribution
Distribution
- See next page
ADAMS ACCESSION NUMB
ER: ML16119A486 SUNSI Review By: RLatta
ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword: NRC-002 OFFICE R4:SRI/EB1 R4:C/EB1 NAME RLatta TFarnholtz SIGNATURE /RA/ /RA/ DATE 4/27/16 4/28/16 OFFICIAL RECORD COPY
Letter to Shane M. Marik from Thomas R. Farnholtz, dated April 28, 2016
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS
INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION
Electronic distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov) Deputy Regional Administrator (Kriss.Kennedy@nrc.gov) DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov) Senior Resident Inspector (Max.Schneider@nrc.gov) Resident Inspector (Steven.Janicki@nrc.gov)
FCS Administrative Assistant (Dawn.Yancey@nrc.gov)
Branch Chief, DRP/D (Jeffrey.Josey@nrc.gov)
Project Engineer, DRP/D (Jan.Tice@nrc.gov) Project Engineer, DRP/D (Jim.Melfi@nrc.gov) RIV Public Affairs Officer (Victor.Dricks@nrc.gov)
NRR Project Manager (Fred.Lyon@nrc.gov)
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov) Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov) RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
OEWEB Resource@nrc.gov
OEWEB Resource (Sue.Bogle@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov) RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)
RIV RSLO (Bill.Maier@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
- 1 - Enclosure
Request for Information
Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
Inspection Fort Calhoun Station
Inspection Report: 05000285/2016007
Inspection Dates: On-site - July 25-29 and August 8-12, 2016
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications"
Lead Inspector: Robert Latta, Senior Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
format (preferred) by July 18, 2016, to the attention of Robert Latta. We request that you categorize the documents in your response with the numbered list below. If only hard copies of
the requested documents are available or if the electronic format is too large, please inform the
lead inspector and provide the documents on the first day of the on-site inspection. Also, the
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks. We ask that the specific items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as
possible.
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation.
3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did
not result in an application for a license amendment.
4. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial modification inspection.
5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates.
6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates.
- 2 - 7. Procedure(s) for implementing permanent plant modifications.
8. A list with descriptions of all permanent plant modifications fully implemented since the last triennial modification inspection.
9. A list with descriptions of all corrective action documents related to permanent plant modifications fully implemented since the last triennial modification inspection.
10. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report.
11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and permanent plant modification programs.
12. A copy of the most recent submittal of the report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each,
required by 10 CFR 50.59(d)(2).
13. A list of systems and system designators and a set of one-line (i.e., simplified) system
diagrams.
Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can
determine the safety and/or risk significance of the screenings, evaluations, and modifications.
Note: For this inspection, permanent plant modifications include permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability
analyses, calculations, and commercial grade dedications.
Inspector Contact Information:
Robert Latta Jonathan Braisted Samuel Graves
Senior Reactor Inspector Reactor Inspector Senior Reactor Inspector
817-200-1532 817-200-1194 817-200-8385
Robert.Latta@nrc.gov Jonathan.Braisted@nrc.gov Samual.Graves@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Robert Latta 1600 East Lamar Blvd.
Arlington, TX 76011-4125