April 28, 2016

Mr. Shane M. Marik, Vice President

and Chief Nuclear Officer

Omaha Public Power District

Fort Calhoun Station

P.O. Box 550

Fort Calhoun, NE 68023-0550

SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES,

TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS

INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION

Dear Mr. Marik:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)

staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant

modifications at your Fort Calhoun Station from July 25 through July 29 and August 8 through

August 12, 2016. The inspection will consist of three reactor inspectors from the NRCs Region

IV office for two weeks. The inspection will be conducted in accordance with NRC Inspection

Procedure 71111.17T, Evaluations of Changes, Tests, and Experiments and Permanent Plant

Modifications.

Experience has shown that this inspection is resource intensive for both the NRC inspectors

and your staff. In order to minimize the impact to your on-site resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

Please note that the documents are requested to be provided by July 18, 2016. Upon review of

these documents, the inspectors will select additional documentation for review upon arrival. It

is important that all of these documents are up-to-date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Corey Cameron of your licensing

organization. If there are any questions about this inspection or the material requested, please

contact the lead inspector, Robert Latta, by telephone at 817-200-1532 or by e-mail at

Robert.Latta@nrc.gov.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

S. Marik -2-

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-285

License No. DPR-40

Enclosure:

Request for Information

cc: Electronic Distribution

ML16119A486

SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:

By: RLatta Yes No Non-Publicly Available Sensitive NRC-002

OFFICE R4:SRI/EB1 R4:C/EB1

NAME RLatta TFarnholtz

SIGNATURE /RA/ /RA/

DATE 4/27/16 4/28/16

Letter to Shane M. Marik from Thomas R. Farnholtz, dated April 28, 2016

SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF EVALUATIONS OF CHANGES,

TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS

INSPECTION (05000285/2016007) AND REQUEST FOR INFORMATION

Electronic distribution by RIV:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Max.Schneider@nrc.gov)

Resident Inspector (Steven.Janicki@nrc.gov)

FCS Administrative Assistant (Dawn.Yancey@nrc.gov)

Branch Chief, DRP/D (Jeffrey.Josey@nrc.gov)

Project Engineer, DRP/D (Jan.Tice@nrc.gov)

Project Engineer, DRP/D (Jim.Melfi@nrc.gov)

RIV Public Affairs Officer (Victor.Dricks@nrc.gov)

NRR Project Manager (Fred.Lyon@nrc.gov)

Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

OEWEB Resource@nrc.gov

OEWEB Resource (Sue.Bogle@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Request for Information

Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications

Inspection

Fort Calhoun Station

Inspection Report: 05000285/2016007

Inspection Dates: On-site - July 25-29 and August 8-12, 2016

Inspection Procedure: IP 71111.17T, Evaluations of Changes, Tests, and Experiments

and Permanent Plant Modifications

Lead Inspector: Robert Latta, Senior Reactor Inspector

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (preferred) by July 18, 2016, to the attention of Robert Latta. We request that you

categorize the documents in your response with the numbered list below. If only hard copies of

the requested documents are available or if the electronic format is too large, please inform the

lead inspector and provide the documents on the first day of the on-site inspection. Also, the

inspectors will select specific items from the information requested below and request from your

staff additional documents needed during the on-site inspection weeks. We ask that the specific

items requested be available and ready for review on the first day of inspection. If you have any

questions regarding this information request, please contact the lead inspector as soon as

possible.

1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.

2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully

implemented changes, tests, and experiments performed since the last triennial

modification inspection that did not result in an evaluation.

3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,

tests, and experiments performed since the last triennial modification inspection that did

not result in an application for a license amendment.

4. A list with descriptions of all corrective action documents related to 10 CFR 50.59

screenings and evaluations since the last triennial modification inspection.

5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,

including qualification dates.

6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or

evaluations, including qualification dates.

-1- Enclosure

7. Procedure(s) for implementing permanent plant modifications.

8. A list with descriptions of all permanent plant modifications fully implemented since the

last triennial modification inspection.

9. A list with descriptions of all corrective action documents related to permanent plant

modifications fully implemented since the last triennial modification inspection.

10. Current revisions of the Technical Specifications and Bases and the Updated Final

Safety Analysis Report.

11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and

permanent plant modification programs.

12. A copy of the most recent submittal of the report containing a brief description of any

changes, tests, and experiments, including a summary of the evaluation of each,

required by 10 CFR 50.59(d)(2).

13. A list of systems and system designators and a set of one-line (i.e., simplified) system

diagrams.

Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can

determine the safety and/or risk significance of the screenings, evaluations, and modifications.

Note: For this inspection, permanent plant modifications include permanent plant changes,

design changes, set point changes, procedure changes, equivalency evaluations, suitability

analyses, calculations, and commercial grade dedications.

Inspector Contact Information:

Robert Latta Jonathan Braisted Samuel Graves

Senior Reactor Inspector Reactor Inspector Senior Reactor Inspector

817-200-1532 817-200-1194 817-200-8385

Robert.Latta@nrc.gov Jonathan.Braisted@nrc.gov Samual.Graves@nrc.gov

Mailing Address:

U.S. NRC, Region IV

Attn: Robert Latta

1600 East Lamar Blvd.

Arlington, TX 76011-4125

-2-