{{#Wiki_filter:--Entergy Entergy Nuclear Operations, Inc 440 Hamilton Avenue White Plains, NY 10601 Tel 914 272 3400 Fax 914 272 3205 Michael Balduzzi Senior Vice President  
{{#Wiki_filter:--Entergy                                                         Entergy Nuclear Operations, Inc 440 Hamilton Avenue White Plains, NY 10601 Tel 914 272 3400 Fax 914 272 3205 Michael Balduzzi Senior Vice President & COO Regional Operations - Northeast February 08, 2008 Re:     Indian Point Units 2 and 3 Docket Nos. 50-247 and 50-286 NL-08-032 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1 -17 Washington, D.C. 20555-0001
& COO Regional Operations  
-Northeast February 08, 2008 Re: Indian Point Units 2 and 3 Docket Nos. 50-247 and 50-286 NL-08-032 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1 -17 Washington, D.C. 20555-0001


==SUBJECT:==
==SUBJECT:==
Siren Project Milestone Schedule


==REFERENCES:==
==REFERENCES:==
 
: 1. NRC Letter, "Notice of Violation and Proposed Imposition of Civil Penalty,"
Siren Project Milestone Schedule 1. NRC Letter, "Notice of Violation and Proposed Imposition of Civil Penalty," dated January 24, 2008 (EA-08-006).
dated January 24, 2008 (EA-08-006).
: 2. NRC Confirmatory Order dated January 31, 2006 (EA-05-190).
: 2. NRC Confirmatory Order dated January 31, 2006 (EA-05-190).
: 3. NRC Order dated July 30, 2007 (EA-07-189).
: 3. NRC Order dated July 30, 2007 (EA-07-189).
Line 30: Line 29:


==Dear Sir or Madam:==
==Dear Sir or Madam:==
The purpose of this letter is to submit to NRC the siren project milestone schedule for the alert notification system (ANS) for the Indian Point Energy Center.On January 24, 2008, (reference
 
: 1) the NRC issued a notice of violation and proposed imposition of civil penalty to Entergy Nuclear Operations, Inc. (ENOI) for failure to implement Orders issued by the NRC on January 31, 2006, (reference
The purpose of this letter is to submit to NRC the siren project milestone schedule for the alert notification system (ANS) for the Indian Point Energy Center.
: 2) and July 30, 2007 (reference 3). The two Orders, in part, require that ENOI place in service an ANS with a backup power capability.
On January 24, 2008, (reference 1) the NRC issued a notice of violation and proposed imposition of civil penalty to Entergy Nuclear Operations, Inc. (ENOI) for failure to implement Orders issued by the NRC on January 31, 2006, (reference 2) and July 30, 2007 (reference 3). The two Orders, in part, require that ENOI place in service an ANS with a backup power capability.
On January 9, 2008, (reference
On January 9, 2008, (reference 4) ENOI transmitted to FEMA for review and comment a proposed schedule setting out project milestones and completion dates. The milestone schedule included input from FEMA regarding the time estimates for FEMA review activities.
: 4) ENOI transmitted to FEMA for review and comment a proposed schedule setting out project milestones and completion dates. The milestone schedule included input from FEMA regarding the time estimates for FEMA review activities.
On January 30, 2008, a joint ENOI, FEMA and NRC meeting was held, during which the proposed milestone schedule was discussed. At this meeting, FEMA confirmed the time estimates for FEMA review activities with the presumption that ENOI will provide complete and accurate information. In addition, the NRC Regional Administrator requested at this meeting that ENOI formally submit the milestone schedule to the NRC. Accordingly, Attachment 1 to this letter contains the siren project milestone schedule. contains a listing of commitments made within this letter.
On January 30, 2008, a joint ENOI, FEMA and NRC meeting was held, during which the proposed milestone schedule was discussed.
 
At this meeting, FEMA confirmed the time estimates for FEMA review activities with the presumption that ENOI will provide complete and accurate information.
In addition, the NRC Regional Administrator requested at this meeting that ENOI formally submit the milestone schedule to the NRC. Accordingly, Attachment 1 to this letter contains the siren project milestone schedule.Attachment 2 contains a listing of commitments made within this letter.
Dockets 50-247 and 50-286 NL-08-032 Page 2 of 2 If ENOI should become aware of any potential issues that may impact project completion, ENOI will promptly notify the NRC Staff of such issues. If you have any questions or require additional information, please contact me or Mr. John McCann, Director, Licensing at 914-272-3370.
Dockets 50-247 and 50-286 NL-08-032 Page 2 of 2 If ENOI should become aware of any potential issues that may impact project completion, ENOI will promptly notify the NRC Staff of such issues. If you have any questions or require additional information, please contact me or Mr. John McCann, Director, Licensing at 914-272-3370.
Sincerely, Michael Balduzzi Senior Vice President  
Sincerely, Michael Balduzzi Senior Vice President & COO Regional Operations - Northeast cc:     Mr. John P. Boska, Senior Project Manager, NRC NRR DORL Mr. Samuel J. Collins, Regional Administrator, NRC Region I NRC Resident Inspector's Office, Indian Point 2 NRC Resident Inspector's Office, Indian Point 3 Mr. Paul Eddy, NYS Department of Public Service Mr. Andrew X. Feeney, NY State Emergency Management Office Ms. Rebecca Thomson, FEMA, Region II
& COO Regional Operations  
 
-Northeast cc: Mr. John P. Boska, Senior Project Manager, NRC NRR DORL Mr. Samuel J. Collins, Regional Administrator, NRC Region I NRC Resident Inspector's Office, Indian Point 2 NRC Resident Inspector's Office, Indian Point 3 Mr. Paul Eddy, NYS Department of Public Service Mr. Andrew X. Feeney, NY State Emergency Management Office Ms. Rebecca Thomson, FEMA, Region II ATTACHMENT 1 TO NL-08-032 Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286 Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 1 of 2 Milestone Responsibility Activities Description Estimated Number of Estimated Party Days for Completion Completion (if applicable)
ATTACHMENT 1 TO NL-08-032 Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286
Date 1 Submittal of steady and repeatable design report section to FEMA ENOI Completion and submission of technical report section on siren signal steadiness, repeatability, and reproducibility February 1, 2008 (actual date January 31, 2008, 4 4 4 4 2 Review and approval of steady and repeatable design report section by FEMA FEMA Review and approval of technical report section on siren signal steadiness, repeatability, and reproducibility 35 calendar days after completion of milestone 1 3 Submission of final ENOI design report to FEMA 4 FEMA review and FEMA FEMA technical review and 84 calendar days after approval of design management review completion of milestone 3 report 5 Installation of new ENOI Place poles and install sirens at sirens not requiring sites with existing poles as one permits __for one replacements 6 Inspection of installed ENOI Inspection scope covers sirens per commitment preventative and material condition of existing (155) siren poles, control boxes and siren heads 7 Permitting of new ENOI Permits need to be issued by sirens applicable governmental authorities 1 This completion date assumes that FEMA will not require any subsequent analyses or responses in connection with Milestone 2.2 Completion of this activity is dependent upon ENOI obtaining third party governmental permits and approvals.
 
The-estimated amount of days for completion are a rough estimate of 120 days based upon ENOI's prior experience but are subject to change. The timing of obtaining permits is highly variable based on the applicable jurisdiction and other factors determined by the relevant issuing governmental authority.
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 1 of 2 Milestone             Responsibility             Activities Description             Estimated Number of               Estimated Party                                                     Days for Completion           Completion (if applicable)                 Date 1   Submittal of steady and             ENOI             Completion and submission of                                         February 1, 2008 repeatable design                                    technical report section on siren                                   (actual date report section to FEMA                                signal steadiness, repeatability,                                   January 31, 2008, 4                             4                       4 and reproducibility                4 2   Review and approval of             FEMA             Review and approval of               35 calendar days after steady and repeatable                                technical report section on siren     completion of milestone 1 design report section                                signal steadiness, repeatability, by FEMA                                              and reproducibility 3   Submission of final                 ENOI design report to FEMA 4   FEMA review and                     FEMA             FEMA technical review and             84 calendar days after approval of design                                   management review                     completion of milestone 3 report 5   Installation of new                 ENOI             Place poles and install sirens at sirens not requiring                                 sites with existing poles as one permits                       __for                       one replacements 6   Inspection of installed             ENOI             Inspection scope covers sirens per commitment                                 preventative and material condition of existing (155) siren poles, control boxes and siren heads 7   Permitting of new                   ENOI             Permits need to be issued by sirens                                               applicable governmental authorities 1   This completion date assumes that FEMA will not require any subsequent analyses or responses in connection with Milestone 2.
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 2 of 2 8 Installation of new ENOI 35 days after the June 5, 2008 sirens requiring permits completion of milestone 7.Note: the estimated amount of days for completion of installation of all new sirens is 35 days after the receipt of the applicable permit for the last siren required to be installed.
2   Completion of this activity is dependent upon ENOI obtaining third party governmental permits and approvals. The-estimated amount of days for completion are a rough estimate of 120 days based upon ENOI's prior experience but are subject to change. The timing of obtaining permits is highly variable based on the applicable jurisdiction and other factors determined by the relevant issuing governmental authority.
9 Far field ENOI Field measurements at selected 14 days after completion of June 19, 2008 measurements locations taken when all sirens milestone 8 are activated simultaneously 10 Prepare and submit ENOI Report of far field measurements 21 days* after completion July 10, 2008 field data report results of milestone 9 11 ENOI review far field ENOI/FEMA FEMA technical review of far 7 days after completion of July 17, 2008 measurements with field measurement data supplied milestone 10 FEMA by ENOI 12 FEMA and ENOI FEMA/ENOI Meeting with stakeholders to 7 days after completion of July 24, 20083 review in service review in service decision milestone 11 decision with stakeholders 13 Public outreach and ENOI Public outreach to inform the 5 days after completion of July 29, 2008 notification public that siren system will be milestone 12 placed in service 14 FEMA approval for FEMA 7 days after completion of August 6, 2008 placing system in milestones 4 and 11 service 15 System placed into ENOI 8 days after completion of August 14, 2008 service milestone 14 T ug 3 This completion date assumes that FEMA will not require any subsequent analysis or responses in connection with milestone 9 Corrected typo error to change 14 days to 21 days. This is consistent with the schedule estimated completion date.
 
ATTACHMENT 2 TO NL-08-032 Commitments for Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286 Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 2 Page 1 of 1 This table identified actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRC's information and are not commitments.
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 2 of 2 8   Installation of new               ENOI                                                   35 days after the             June 5, 2008 sirens requiring permits                                                                 completion of milestone 7.
Number Commitment Type NL-08-032-1 Entergy will complete its activities required to One-time action place the siren system into service in accordance with the attached milestone schedule.}}
Note: the estimated amount of days for completion of installation of all new sirens is 35 days after the receipt of the applicable permit for the last siren required to be installed.
9   Far field                         ENOI           Field measurements at selected         14 days after completion of   June 19, 2008 measurements                                     locations taken when all sirens         milestone 8 are activated simultaneously 10 Prepare and submit                 ENOI           Report of far field measurements       21 days* after completion     July 10, 2008 field data report                                 results                                 of milestone 9 11 ENOI review far field         ENOI/FEMA         FEMA technical review of far           7 days after completion of   July 17, 2008 measurements with                                 field measurement data supplied         milestone 10 FEMA                                             by ENOI 12 FEMA and ENOI                 FEMA/ENOI         Meeting with stakeholders to           7 days after completion of   July 24, 20083 review in service                                 review in service decision             milestone 11 decision with stakeholders 13 Public outreach and               ENOI           Public outreach to inform the           5 days after completion of   July 29, 2008 notification                                     public that siren system will be       milestone 12 placed in service 14 FEMA approval for                 FEMA                                                   7 days after completion of   August 6, 2008 placing system in                                                                         milestones 4 and 11 service 15 System placed into                 ENOI                                                   8 days after completion of   August 14, 2008 service                                                                                   milestone 14               T   ug 3
This completion date assumes that FEMA will not require any subsequent analysis or responses in connection with milestone 9 Corrected typo error to change 14 days to 21 days. This is consistent with the schedule estimated completion date.
 
ATTACHMENT 2 TO NL-08-032 Commitments for Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286
 
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 2 Page 1 of 1 This table identified actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRC's information and are not commitments.
Number                         Commitment                             Type NL-08-032-1       Entergy will complete its activities required to One-time action place the siren system into service in accordance with the attached milestone schedule.}}

Latest revision as of 20:39, 14 November 2019

Siren Project Milestone Schedule
ML080430045
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 02/08/2008
From: Balduzzi M
Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-08-032
Download: ML080430045 (7)


Text

--Entergy Entergy Nuclear Operations, Inc 440 Hamilton Avenue White Plains, NY 10601 Tel 914 272 3400 Fax 914 272 3205 Michael Balduzzi Senior Vice President & COO Regional Operations - Northeast February 08, 2008 Re: Indian Point Units 2 and 3 Docket Nos. 50-247 and 50-286 NL-08-032 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1 -17 Washington, D.C. 20555-0001

SUBJECT:

Siren Project Milestone Schedule

REFERENCES:

1. NRC Letter, "Notice of Violation and Proposed Imposition of Civil Penalty,"

dated January 24, 2008 (EA-08-006).

2. NRC Confirmatory Order dated January 31, 2006 (EA-05-190).
3. NRC Order dated July 30, 2007 (EA-07-189).
4. Entergy letter, Mr. Michael Balduzzi to Ms. Rebecca Thomson, FEMA Region II, "New Indian Point Energy Center Alert Notification System Installation, Testing and Implementation Schedule", dated January 9, 2008.

Dear Sir or Madam:

The purpose of this letter is to submit to NRC the siren project milestone schedule for the alert notification system (ANS) for the Indian Point Energy Center.

On January 24, 2008, (reference 1) the NRC issued a notice of violation and proposed imposition of civil penalty to Entergy Nuclear Operations, Inc. (ENOI) for failure to implement Orders issued by the NRC on January 31, 2006, (reference 2) and July 30, 2007 (reference 3). The two Orders, in part, require that ENOI place in service an ANS with a backup power capability.

On January 9, 2008, (reference 4) ENOI transmitted to FEMA for review and comment a proposed schedule setting out project milestones and completion dates. The milestone schedule included input from FEMA regarding the time estimates for FEMA review activities.

On January 30, 2008, a joint ENOI, FEMA and NRC meeting was held, during which the proposed milestone schedule was discussed. At this meeting, FEMA confirmed the time estimates for FEMA review activities with the presumption that ENOI will provide complete and accurate information. In addition, the NRC Regional Administrator requested at this meeting that ENOI formally submit the milestone schedule to the NRC. Accordingly, Attachment 1 to this letter contains the siren project milestone schedule. contains a listing of commitments made within this letter.

Dockets 50-247 and 50-286 NL-08-032 Page 2 of 2 If ENOI should become aware of any potential issues that may impact project completion, ENOI will promptly notify the NRC Staff of such issues. If you have any questions or require additional information, please contact me or Mr. John McCann, Director, Licensing at 914-272-3370.

Sincerely, Michael Balduzzi Senior Vice President & COO Regional Operations - Northeast cc: Mr. John P. Boska, Senior Project Manager, NRC NRR DORL Mr. Samuel J. Collins, Regional Administrator, NRC Region I NRC Resident Inspector's Office, Indian Point 2 NRC Resident Inspector's Office, Indian Point 3 Mr. Paul Eddy, NYS Department of Public Service Mr. Andrew X. Feeney, NY State Emergency Management Office Ms. Rebecca Thomson, FEMA, Region II

ATTACHMENT 1 TO NL-08-032 Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286

Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 1 of 2 Milestone Responsibility Activities Description Estimated Number of Estimated Party Days for Completion Completion (if applicable) Date 1 Submittal of steady and ENOI Completion and submission of February 1, 2008 repeatable design technical report section on siren (actual date report section to FEMA signal steadiness, repeatability, January 31, 2008, 4 4 4 and reproducibility 4 2 Review and approval of FEMA Review and approval of 35 calendar days after steady and repeatable technical report section on siren completion of milestone 1 design report section signal steadiness, repeatability, by FEMA and reproducibility 3 Submission of final ENOI design report to FEMA 4 FEMA review and FEMA FEMA technical review and 84 calendar days after approval of design management review completion of milestone 3 report 5 Installation of new ENOI Place poles and install sirens at sirens not requiring sites with existing poles as one permits __for one replacements 6 Inspection of installed ENOI Inspection scope covers sirens per commitment preventative and material condition of existing (155) siren poles, control boxes and siren heads 7 Permitting of new ENOI Permits need to be issued by sirens applicable governmental authorities 1 This completion date assumes that FEMA will not require any subsequent analyses or responses in connection with Milestone 2.

2 Completion of this activity is dependent upon ENOI obtaining third party governmental permits and approvals. The-estimated amount of days for completion are a rough estimate of 120 days based upon ENOI's prior experience but are subject to change. The timing of obtaining permits is highly variable based on the applicable jurisdiction and other factors determined by the relevant issuing governmental authority.

Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 2 of 2 8 Installation of new ENOI 35 days after the June 5, 2008 sirens requiring permits completion of milestone 7.

Note: the estimated amount of days for completion of installation of all new sirens is 35 days after the receipt of the applicable permit for the last siren required to be installed.

9 Far field ENOI Field measurements at selected 14 days after completion of June 19, 2008 measurements locations taken when all sirens milestone 8 are activated simultaneously 10 Prepare and submit ENOI Report of far field measurements 21 days* after completion July 10, 2008 field data report results of milestone 9 11 ENOI review far field ENOI/FEMA FEMA technical review of far 7 days after completion of July 17, 2008 measurements with field measurement data supplied milestone 10 FEMA by ENOI 12 FEMA and ENOI FEMA/ENOI Meeting with stakeholders to 7 days after completion of July 24, 20083 review in service review in service decision milestone 11 decision with stakeholders 13 Public outreach and ENOI Public outreach to inform the 5 days after completion of July 29, 2008 notification public that siren system will be milestone 12 placed in service 14 FEMA approval for FEMA 7 days after completion of August 6, 2008 placing system in milestones 4 and 11 service 15 System placed into ENOI 8 days after completion of August 14, 2008 service milestone 14 T ug 3

This completion date assumes that FEMA will not require any subsequent analysis or responses in connection with milestone 9 Corrected typo error to change 14 days to 21 days. This is consistent with the schedule estimated completion date.

ATTACHMENT 2 TO NL-08-032 Commitments for Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286

Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 2 Page 1 of 1 This table identified actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRC's information and are not commitments.

Number Commitment Type NL-08-032-1 Entergy will complete its activities required to One-time action place the siren system into service in accordance with the attached milestone schedule.