MONTHYEARNL-21-034, Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals2021-05-26026 May 2021 Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary NL-21-033, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2021-05-11011 May 2021 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-21-032, Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center2021-05-11011 May 2021 Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center NL-21-005, Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions2021-05-11011 May 2021 Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions NL-21-030, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0606 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NL-21-027, Registration of Spent Fuel Cask Use2021-04-20020 April 2021 Registration of Spent Fuel Cask Use NL-21-021, Registration of Spent Fuel Cask Use2021-04-19019 April 2021 Registration of Spent Fuel Cask Use NL-21-017, Pre-Notice of Disbursement from Decommissioning Trusts2021-04-0808 April 2021 Pre-Notice of Disbursement from Decommissioning Trusts NL-21-010, Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2021-02-17017 February 2021 Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-082, Notice of Planned Transfer of Decommissioning Funds2020-12-14014 December 2020 Notice of Planned Transfer of Decommissioning Funds NL-20-081, Pre-Notice of Disbursement from Decommissioning Trusts2020-12-0909 December 2020 Pre-Notice of Disbursement from Decommissioning Trusts NL-20-080, Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-93212020-11-19019 November 2020 Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-9321 NL-20-079, (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-12012 November 2020 (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-076, Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal2020-11-0202 November 2020 Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal NL-20-069, One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-10-0808 October 2020 One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-067, Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-09-16016 September 2020 Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-064, 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments2020-09-0101 September 2020 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments NL-20-060, Status of Remaining Actions for Generic Letter 2004-022020-08-11011 August 2020 Status of Remaining Actions for Generic Letter 2004-02 NL-20-057, Cancellation of Commitment Related to Large Break LOCA Reanalysis2020-07-30030 July 2020 Cancellation of Commitment Related to Large Break LOCA Reanalysis NL-20-0851, 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-07-22022 July 2020 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material NL-20-051, Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center2020-07-0707 July 2020 Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center NL-20-052, Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results2020-07-0707 July 2020 Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-041, Registration of Unit 3 Spent Fuel Cask Use2020-05-13013 May 2020 Registration of Unit 3 Spent Fuel Cask Use NL-20-042, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2020-05-12012 May 2020 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-20-033, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2020-04-28028 April 2020 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-20-038, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-04-23023 April 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-035, Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-16016 April 2020 Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-034, Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-13013 April 2020 Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-020, Submittal of 2019 Annual Fitness for Duty Performance Data Report Update2020-02-26026 February 2020 Submittal of 2019 Annual Fitness for Duty Performance Data Report Update NL-20-015, Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2020-02-10010 February 2020 Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-20-008, Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane2020-01-0606 January 2020 Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane NL-19-094, 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2019-12-16016 December 2019 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-092, Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-11-20020 November 2019 Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-043, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122019-10-22022 October 2019 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-078, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-10-22022 October 2019 Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-091, Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use2019-10-17017 October 2019 Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use NL-19-090, Registration of Unit 2 Spent Fuel Cask Use2019-10-0909 October 2019 Registration of Unit 2 Spent Fuel Cask Use NL-19-079, 50.59(d)(2) Summary Report of Changes, Tests and Experiments2019-09-26026 September 2019 50.59(d)(2) Summary Report of Changes, Tests and Experiments 2021-05-06
[Table view] Category:Schedule and Calendars
MONTHYEARML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML15147A1992015-06-11011 June 2015 Schedule Revision for the Environmental Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (TAC Nos. MD5411, and MD5412) ML14254A2072014-11-0303 November 2014 Proposed Schedule for the Review of Additional Information Regarding the Application from Entergy Nuclear Operations, Inc. for Renewal of Operating Licenses for Indian Point Nuclear Generating Unit Nos. 2 and 3 NL-12-092, Response to RIS 2012-007, Preparation and Scheduling of Operator Licensing Examinations2012-06-28028 June 2012 Response to RIS 2012-007, Preparation and Scheduling of Operator Licensing Examinations ML1023000922010-08-31031 August 2010 Revision of Schedule for Review of the Indian Point Nuclear Generating Units 2 and 3, License Renewal Application NL-10-077, Operator Licensing Examination Data2010-08-0202 August 2010 Operator Licensing Examination Data ML1012605362010-05-25025 May 2010 Revision of Schedule for Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application ML1001100632010-02-0202 February 2010 Revision of Schedule for Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application NL-09-105, Response to NRC Regulatory Issues Summary 2009-011, Preparation and Scheduling of Operator Licensing Examinations, Dated July 16, 20092009-08-0606 August 2009 Response to NRC Regulatory Issues Summary 2009-011, Preparation and Scheduling of Operator Licensing Examinations, Dated July 16, 2009 ML0824002142008-09-0202 September 2008 Revision of Schedule for the Conduct of Review of the Indian Point Nuclear Generating, Units 2 & 3, License Renewal Application ML0810004412008-04-23023 April 2008 Revision of Schedule for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application NL-08-032, Siren Project Milestone Schedule2008-02-0808 February 2008 Siren Project Milestone Schedule ML0802301152008-01-24024 January 2008 Revision of Schedule for the Conduct of Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application ML0729502682007-10-10010 October 2007 Siren Milestone Schedule Dtd 10/10/07 ML0729502662007-10-10010 October 2007 Siren Schedule 8 X 11 Dtd 10/10/07 NL-07-086, Regulatory Issues Summary 2007-017, Preparation and Scheduling of Operator Licensing Examinations, Dated July 12, 20072007-08-0808 August 2007 Regulatory Issues Summary 2007-017, Preparation and Scheduling of Operator Licensing Examinations, Dated July 12, 2007 ML0708804022006-11-0909 November 2006 E-mail from D. Croulet of Entergy to Various, Regarding NRC Groundwater Inspection 11/13-11/17 2023-11-02
[Table view] |
Text
--Entergy Entergy Nuclear Operations, Inc 440 Hamilton Avenue White Plains, NY 10601 Tel 914 272 3400 Fax 914 272 3205 Michael Balduzzi Senior Vice President & COO Regional Operations - Northeast February 08, 2008 Re: Indian Point Units 2 and 3 Docket Nos. 50-247 and 50-286 NL-08-032 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1 -17 Washington, D.C. 20555-0001
SUBJECT:
Siren Project Milestone Schedule
REFERENCES:
- 1. NRC Letter, "Notice of Violation and Proposed Imposition of Civil Penalty,"
dated January 24, 2008 (EA-08-006).
- 2. NRC Confirmatory Order dated January 31, 2006 (EA-05-190).
- 3. NRC Order dated July 30, 2007 (EA-07-189).
- 4. Entergy letter, Mr. Michael Balduzzi to Ms. Rebecca Thomson, FEMA Region II, "New Indian Point Energy Center Alert Notification System Installation, Testing and Implementation Schedule", dated January 9, 2008.
Dear Sir or Madam:
The purpose of this letter is to submit to NRC the siren project milestone schedule for the alert notification system (ANS) for the Indian Point Energy Center.
On January 24, 2008, (reference 1) the NRC issued a notice of violation and proposed imposition of civil penalty to Entergy Nuclear Operations, Inc. (ENOI) for failure to implement Orders issued by the NRC on January 31, 2006, (reference 2) and July 30, 2007 (reference 3). The two Orders, in part, require that ENOI place in service an ANS with a backup power capability.
On January 9, 2008, (reference 4) ENOI transmitted to FEMA for review and comment a proposed schedule setting out project milestones and completion dates. The milestone schedule included input from FEMA regarding the time estimates for FEMA review activities.
On January 30, 2008, a joint ENOI, FEMA and NRC meeting was held, during which the proposed milestone schedule was discussed. At this meeting, FEMA confirmed the time estimates for FEMA review activities with the presumption that ENOI will provide complete and accurate information. In addition, the NRC Regional Administrator requested at this meeting that ENOI formally submit the milestone schedule to the NRC. Accordingly, Attachment 1 to this letter contains the siren project milestone schedule. contains a listing of commitments made within this letter.
Dockets 50-247 and 50-286 NL-08-032 Page 2 of 2 If ENOI should become aware of any potential issues that may impact project completion, ENOI will promptly notify the NRC Staff of such issues. If you have any questions or require additional information, please contact me or Mr. John McCann, Director, Licensing at 914-272-3370.
Sincerely, Michael Balduzzi Senior Vice President & COO Regional Operations - Northeast cc: Mr. John P. Boska, Senior Project Manager, NRC NRR DORL Mr. Samuel J. Collins, Regional Administrator, NRC Region I NRC Resident Inspector's Office, Indian Point 2 NRC Resident Inspector's Office, Indian Point 3 Mr. Paul Eddy, NYS Department of Public Service Mr. Andrew X. Feeney, NY State Emergency Management Office Ms. Rebecca Thomson, FEMA, Region II
ATTACHMENT 1 TO NL-08-032 Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 1 of 2 Milestone Responsibility Activities Description Estimated Number of Estimated Party Days for Completion Completion (if applicable) Date 1 Submittal of steady and ENOI Completion and submission of February 1, 2008 repeatable design technical report section on siren (actual date report section to FEMA signal steadiness, repeatability, January 31, 2008, 4 4 4 and reproducibility 4 2 Review and approval of FEMA Review and approval of 35 calendar days after steady and repeatable technical report section on siren completion of milestone 1 design report section signal steadiness, repeatability, by FEMA and reproducibility 3 Submission of final ENOI design report to FEMA 4 FEMA review and FEMA FEMA technical review and 84 calendar days after approval of design management review completion of milestone 3 report 5 Installation of new ENOI Place poles and install sirens at sirens not requiring sites with existing poles as one permits __for one replacements 6 Inspection of installed ENOI Inspection scope covers sirens per commitment preventative and material condition of existing (155) siren poles, control boxes and siren heads 7 Permitting of new ENOI Permits need to be issued by sirens applicable governmental authorities 1 This completion date assumes that FEMA will not require any subsequent analyses or responses in connection with Milestone 2.
2 Completion of this activity is dependent upon ENOI obtaining third party governmental permits and approvals. The-estimated amount of days for completion are a rough estimate of 120 days based upon ENOI's prior experience but are subject to change. The timing of obtaining permits is highly variable based on the applicable jurisdiction and other factors determined by the relevant issuing governmental authority.
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 1 Page 2 of 2 8 Installation of new ENOI 35 days after the June 5, 2008 sirens requiring permits completion of milestone 7.
Note: the estimated amount of days for completion of installation of all new sirens is 35 days after the receipt of the applicable permit for the last siren required to be installed.
9 Far field ENOI Field measurements at selected 14 days after completion of June 19, 2008 measurements locations taken when all sirens milestone 8 are activated simultaneously 10 Prepare and submit ENOI Report of far field measurements 21 days* after completion July 10, 2008 field data report results of milestone 9 11 ENOI review far field ENOI/FEMA FEMA technical review of far 7 days after completion of July 17, 2008 measurements with field measurement data supplied milestone 10 FEMA by ENOI 12 FEMA and ENOI FEMA/ENOI Meeting with stakeholders to 7 days after completion of July 24, 20083 review in service review in service decision milestone 11 decision with stakeholders 13 Public outreach and ENOI Public outreach to inform the 5 days after completion of July 29, 2008 notification public that siren system will be milestone 12 placed in service 14 FEMA approval for FEMA 7 days after completion of August 6, 2008 placing system in milestones 4 and 11 service 15 System placed into ENOI 8 days after completion of August 14, 2008 service milestone 14 T ug 3
This completion date assumes that FEMA will not require any subsequent analysis or responses in connection with milestone 9 Corrected typo error to change 14 days to 21 days. This is consistent with the schedule estimated completion date.
ATTACHMENT 2 TO NL-08-032 Commitments for Siren Project Milestone Schedule ENTERGY NUCLEAR OPERATIONS, INC INDIAN POINT NUCLEAR GENERATING UNITS NO. 2 and 3 DOCKET NOS. 50-247 AND 50-286
Docket Nos. 50-247 and 50-286 NL-08-032 Attachment 2 Page 1 of 1 This table identified actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRC's information and are not commitments.
Number Commitment Type NL-08-032-1 Entergy will complete its activities required to One-time action place the siren system into service in accordance with the attached milestone schedule.