| | issue date = 05/22/2008 | | | issue date = 05/22/2008 |
| | title = Request for Additional Information, Renewal of Active or Expired N-Type Certificates for Plants | | | title = Request for Additional Information, Renewal of Active or Expired N-Type Certificates for Plants |
| | author name = Milano P D | | | author name = Milano P |
| | author affiliation = NRC/NRR/ADRO/DORL/WBSPB | | | author affiliation = NRC/NRR/ADRO/DORL/WBSPB |
| | addressee name = Bhatnagar A S | | | addressee name = Bhatnagar A |
| | addressee affiliation = Tennessee Valley Authority | | | addressee affiliation = Tennessee Valley Authority |
| | docket = 05000391 | | | docket = 05000391 |
Line 68: |
Line 68: |
| OFFICE LWPB/PM LWPB/LA EQVA/BC LWPB/BC NAME PMilano BClayton DThatcher LRaghavan DATE 5/12/08 5/12/08 5/19/08 5/22/08 OFFICIAL RECORD COPY ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION WATTS BAR NUCLEAR PLANT, UNIT 2 DOCKET NO. 50-391 | | OFFICE LWPB/PM LWPB/LA EQVA/BC LWPB/BC NAME PMilano BClayton DThatcher LRaghavan DATE 5/12/08 5/12/08 5/19/08 5/22/08 OFFICIAL RECORD COPY ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION WATTS BAR NUCLEAR PLANT, UNIT 2 DOCKET NO. 50-391 |
|
| |
|
| By letter dated February 1, 2008 (Agencywide Documents Access and Management System Accession No. ML080370185), Tennessee Valley Authority submitted a request for authorization to use of the provisions of American Society of Mechanical Engineers (ASME) Code Case N-520-2, "Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction, Section III, Division I," for Watts Bar Nuclear Plant, Unit 2 (WBN-2). In reviewing the application, the Nuclear Regulatory Commission staff has determined that the following information is needed in order to complete its review: | | By letter dated February 1, 2008 (Agencywide Documents Access and Management System Accession No. ML080370185), Tennessee Valley Authority submitted a request for authorization to use of the provisions of American Society of Mechanical Engineers (ASME) Code Case N-520-2, "Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction, Section III, Division I," for Watts Bar Nuclear Plant, Unit 2 (WBN-2). In reviewing the application, the Nuclear Regulatory Commission staff has determined that the following information is needed in order to complete its review: |
| : 1. In paragraph (c) of the ASM E Code Case N-520-2 it is stated that: "[t]he Quality Assurance program previously accepted by the society shall be continually implemented (NCA-8140) and any revisions to the program shall be acceptable to the Authorized Nuclear Inspection Agency." However, in the second paragraph of page 1 of to the application, it notes that the ASME Section III Quality Assurance (QA) | | : 1. In paragraph (c) of the ASM E Code Case N-520-2 it is stated that: "[t]he Quality Assurance program previously accepted by the society shall be continually implemented (NCA-8140) and any revisions to the program shall be acceptable to the Authorized Nuclear Inspection Agency." However, in the second paragraph of page 1 of to the application, it notes that the ASME Section III Quality Assurance (QA) |
| Manual was applied to WBN-2 only through October 25, 1996. It appears that the code | | Manual was applied to WBN-2 only through October 25, 1996. It appears that the code |
Line 74: |
Line 74: |
| case requires that the ASME Section III QA manual should have been applied post October 25, 1996, to such items as layup, maintenance, and removal of components for use on the other unit. | | case requires that the ASME Section III QA manual should have been applied post October 25, 1996, to such items as layup, maintenance, and removal of components for use on the other unit. |
|
| |
|
| Clarify whether the QA manual was applied after October 25, 1996, for such items as layup, maintenance, and removal of components. | | Clarify whether the QA manual was applied after October 25, 1996, for such items as layup, maintenance, and removal of components. |
| : 2. In Enclosure 1, the section entitled "Proposed Alternative and Basis for Use" states in Item No. 2 that: "[t]he Society will perform a survey of the limited scope quality assurance program and processes to ensure that the procedures are in place to accomplish the code data transfer in accordance with the provisions of the Code Case." | | : 2. In Enclosure 1, the section entitled "Proposed Alternative and Basis for Use" states in Item No. 2 that: "[t]he Society will perform a survey of the limited scope quality assurance program and processes to ensure that the procedures are in place to accomplish the code data transfer in accordance with the provisions of the Code Case." |
|
| |
|
| Since NRC staff has not yet reviewed this revised code case, nor has it approved its generic use by the industry through the usual processes of incorporation (i.e., Regulatory Guides, Title 10 of the Code of Federal Regulations, Section 50.55a), the staff's position is that a FULL ASME survey, and not a limited survey, should be performed. | | Since NRC staff has not yet reviewed this revised code case, nor has it approved its generic use by the industry through the usual processes of incorporation (i.e., Regulatory Guides, Title 10 of the Code of Federal Regulations, Section 50.55a), the staff's position is that a FULL ASME survey, and not a limited survey, should be performed. |
|
| |
|
| Clarify your definition of a "limited scope survey" to provide, in more detail, the scope of the survey of the QA program to be performed. | | Clarify your definition of a "limited scope survey" to provide, in more detail, the scope of the survey of the QA program to be performed. |
| : 3. In Enclosure 1, Item No. 6 of the section entitled "Proposed Alternative and Basis for Use," states that the term length of the temporary certificates will be of limited duration. Paragraph (f)(7) of the code case has specific requirements for the term of the temporary certificates and for renewals. | | : 3. In Enclosure 1, Item No. 6 of the section entitled "Proposed Alternative and Basis for Use," states that the term length of the temporary certificates will be of limited duration. Paragraph (f)(7) of the code case has specific requirements for the term of the temporary certificates and for renewals. |
| Clarify your definition of "limited duration" to a more detailed timeframe, and describe how this will comply with requirements of the code case. | | Clarify your definition of "limited duration" to a more detailed timeframe, and describe how this will comply with requirements of the code case. |
Letter Sequence RAI |
---|
TAC:MD8314, Clarify Application of Setpoint Methodology for LSSS Functions, Control Room Habitability, Steam Generator Tube Integrity (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement
Results
Other: CNL-14-154, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 12, CNL-15-137, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 13 (TAC No. MD6311) and Status of Generic Communications for Unit 2 - Revision 13, CNL-15-150, Pressurizer PORV Block Valves - Dynamic Testing Alternative, ML080370185, ML081490110, ML081490118, ML082140238, ML082560373, ML082750019, ML101200204, ML101260469, ML101680561, ML101760222, ML102170077, ML102290258, ML102700527, ML103010299, ML110210486, ML11213A130, ML11362A056, ML12234A688, ML13023A315, ML13213A194
|
MONTHYEARML0803701852008-02-0101 February 2008 Request to Use American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Code Case N-520-2, Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction. Project stage: Other ML0813008092008-05-22022 May 2008 Request for Additional Information, Renewal of Active or Expired N-Type Certificates for Plants Project stage: RAI ML0814901182008-05-28028 May 2008 NRC Review: Generic Communications Status for TVA Watts Bar Unit 2 Project stage: Other ML0814901102008-05-28028 May 2008 Status of Generic Communications for Review (Tac No. MD8314) Project stage: Other ML0818504592008-07-0202 July 2008 Response to Request for Additional Information Project stage: Response to RAI ML0821402382008-07-29029 July 2008 Generic Communications Status, Revision 1 Project stage: Other ML0827500192008-09-26026 September 2008 Regulatory Framework for the Completion of Construction and Licensing Activities for Unit 2 - Corrective Action and Special Programs, and Unresolved Safety Issues Project stage: Other ML0825603732008-10-0202 October 2008 Request for Relief Regarding Alternative Rules for Renewal of Active or Expired N-Type Certificates Project stage: Other ML1001204872009-11-12012 November 2009 Application for Special Nuclear Material License in Accordance with 10 CFR 70, Domestic Licensing of Special Nuclear Material Project stage: Request ML1001916842010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97, Section 3 - Design of Structures, Components, Equipment, and Systems, Page 3.8.5-1 Through Page 3.11-9 Project stage: Request ML1001914212010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97 Project stage: Request ML1012002042010-04-20020 April 2010 Preservice Inspection Program Plan and Additional Information Project stage: Other ML1012604692010-04-29029 April 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 2, and Status of Generic Communications for Unit 2 - Revision 2 Project stage: Other ML1016805612010-06-17017 June 2010 Preservice Inspection Program Plan and Additional Information Project stage: Other ML1019402362010-06-18018 June 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1017602222010-06-25025 June 2010 Request to Use ASME Boiler and Pressure Vessel Code, Code Case N-520-3, Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction, Section III, Division 1 Project stage: Other ML1021700772010-07-30030 July 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 3, and Status of Generic Communications for Unit 2 - Revision 3 Project stage: Other ML1022902582010-07-31031 July 2010 Final Safety Analysis Report - Response to Preliminary Requests for Additional Information and Requests for Additional Information Project stage: Other ML1025001712010-09-0101 September 2010 OL - TVA Letter to NRC - WBN U2 FSAR A100 Project stage: Request ML1027005272010-09-29029 September 2010 Request for Relief Regarding Alternative Rules for Renewal of Active or Expired N-Type Certification Project stage: Other ML1030102992010-10-28028 October 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 4, and Status of Generic Communications for Unit 2 - Revision 4 Project stage: Other ML1031207112010-10-29029 October 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1031207122010-10-29029 October 2010 Edcr 52321 Draft Scope and Intent, Unit Difference and Technical Evaluation, Enclosure 2, Attachment 1 Project stage: Request ML1031403142010-11-0101 November 2010 OL - TVA Letter to NRC_10-29-10_WBN U2 FSAR 101 Project stage: Request ML1032001462010-11-0909 November 2010 Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information Project stage: Response to RAI ML1032106442010-11-17017 November 2010 Revision of Commitment for Implementation of the Maintenance Rule Project stage: Request ML1035405602010-12-17017 December 2010 Safety Evaluation Report Supplement 22 (SSER22) - Response to Requests for Additional Information Project stage: Supplement ML1102104862011-01-21021 January 2011 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 5 and Status of Generic Communications for Unit 2 - Revision 5 Project stage: Other ML1106202192011-02-25025 February 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML1110500092011-04-0808 April 2011 OL - FW: Updated OI List Project stage: Request ML11136A0532011-04-18018 April 2011 OL - TVA Letter to NRC_04-15-11_I&C RAI Response Project stage: Request ML11129A2052011-05-0606 May 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML11178A1552011-06-0303 June 2011 Final Safety Analysis Report (Fsar), Amendment 104 Project stage: Request ML11167A1102011-06-10010 June 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML11213A1302011-07-27027 July 2011 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 6 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 6 Project stage: Other ML11213A2612011-07-28028 July 2011 Results from Cost-Benefit Analysis of Radwaste System Enhancements Project stage: Request ML11292A1992011-10-17017 October 2011 Revision of Commitment for Unit 2's Implementation of the Maintenance Rule Project stage: Request ML11362A0562011-12-20020 December 2011 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 7 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 7 Project stage: Other ML12234A6882012-08-15015 August 2012 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 8 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 8 Project stage: Other ML12249A1952012-08-30030 August 2012 Instrumentation and Controls Staff Request for Additional Information (RAI) Related to Supplemental Safety Evaluation Report (Sser) Open Item 80 Project stage: Supplement ML12284A5132012-10-0404 October 2012 NRC Bulletin No. 88-08, Thermal Stresses in Piping Connected to Reactor Coolant System (RCS) - Clarification Project stage: Request ML12284A5142012-10-0404 October 2012 Revision of Commitment for Unit 2's Implementation of the Maintenance Rule Project stage: Request ML12312A1672012-10-25025 October 2012 Unit 1 & 2, Watts Bar, Units 1 & 2, 90-Day Response to NRC Bulletin 2012-01, Design Vulnerability in Electric Power System. Project stage: Request ML12349A3792012-12-10010 December 2012 Instrumentation and Controls Staff Request for Additional Information (RAI) Related to Supplemental Safety Evaluation Report (Sser) Open Item 80 Project stage: Supplement ML13023A3152013-01-17017 January 2013 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 9 (TAC No. MD6311), and Status of Generic Communications for Unit 2 -Revision 9 Project stage: Other ML13030A0322013-01-24024 January 2013 Documentation of Liability Insurance Coverage Requested Per Supplemental Safety Evaluation Report (Sser) Open Item 25 Project stage: Request ML13213A1942013-07-25025 July 2013 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 10 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 10 Project stage: Other CNL-13-149, Updated Inservice Test (IST) Program (Unit 1) and Ist/Preservice Test (Pst) Program2013-12-12012 December 2013 Updated Inservice Test (IST) Program (Unit 1) and Ist/Preservice Test (Pst) Program Project stage: Request CNL-14-154, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 122014-09-0202 September 2014 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 12 Project stage: Other CNL-15-063, Supplement Safety Evaluation Report - Open Item 33 - Completion of Dcns 53421 and 546362015-04-0707 April 2015 Supplement Safety Evaluation Report - Open Item 33 - Completion of Dcns 53421 and 54636 Project stage: Request 2010-09-01
[Table View] |
|
---|
Category:Letter
MONTHYEARCNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) CNL-24-031, Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance2024-03-18018 March 2024 Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance CNL-24-028, Response to Request for Additional Information Regarding Watts Bar Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Watts Bar Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 IR 05000390/20240102024-03-0808 March 2024 Age-Related Degradation Inspection Report 05000390/2024010 and 05000391/2024010 2024-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21102A1312021-04-19019 April 2021 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 ML21095A0402021-04-0202 April 2021 NRR E-mail Capture - Request for Additional Information Re Generic Letter 95-05 90-Day Report and LAR to Adjust Growth Rate for Thot (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0422021-04-0202 April 2021 NRR E-mail Capture - Added Clarification to RAI 2 for Thot LAR ML21091A0772021-04-0101 April 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Technical Specification 5.7.2.19, Containment Leakage Rate Testing Program ML21095A0442021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0412021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0462021-03-22022 March 2021 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Generic Letter 95-05 90-Day Report for Watts Bar Unit 2 ML21039A6402021-02-0808 February 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 1 Technical Specifications Related to Steam Generator Tube Inspection Frequency ML21012A2032021-01-11011 January 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar UFSAR to Use Alternate Probability of Detection ML20350B5592020-12-15015 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Adopt Traveler TSTF-490 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20322A4412020-11-17017 November 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20322A4392020-11-0505 November 2020 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20308A3512020-11-0202 November 2020 Request for Additional Information on WBN Request for Exemption from 10 CFR Part 73, Appendix B, Section VI for the Conduct of an Annual Force-on-Force Exercise (EPID L-2020-LLE-0165 (COVID-19)) ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information ML20196L8622020-07-14014 July 2020 NRR E-mail Capture - Watts Bar Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Implement the Full Spectrum LOCA Methodology ML20086G4802020-03-26026 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) - Part 2 ML20085G3572020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20084M1942020-03-24024 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20083J3952020-03-12012 March 2020 NRR E-mail Capture - Draft Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML19340A6842019-12-0505 December 2019 NRR E-mail Capture - Request for Additional Information for WBN2 Request for One-Time Extension of Completion Time for TS 3.7.8 (L-2019-LLA-0020) ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19186A4352019-07-0505 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Correction to Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19169A3592019-06-18018 June 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19106A0462019-04-15015 April 2019 NRR E-mail Capture - Watts BAR, Units 1 and 2 Request for Additional Informatin (RAI) Regarding Changes to Technical Specifications Sections 3.8.1, 3.8.7, 3.8.8, and 3.8.9 ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program ML18313A2202018-11-0707 November 2018 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML18282A6372018-10-0909 October 2018 NRR E-mail Capture - RAIs (Final) - LAR to Revise the Steam Generator Technical Specifications for Watts Bar Nuclear Plant, Unit 2 ML18270A2362018-09-26026 September 2018 NRR E-mail Capture - Watts Bar Units 1 and 2 RAIs - Modify TS 3.8.9 Completion Time for Inoperable 120V AC Vital Buses (L-2018-LLA-0050) ML18240A0702018-08-27027 August 2018 NRR E-mail Capture - RAI for Watts Bar Unit 2 Tpbars LAR and Watts Bar Units 1 and 2 LAR Related to Fuel Storage ML18199A1822018-07-17017 July 2018 NRR E-mail Capture - Request for Additional Information Regarding Watts Bar Unit 1 Extension of Surveillance Requirement Intervals 2024-09-10
[Table view] |
Text
May 22, 2008
Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNIT 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING RENEWAL OF ACTIVE OR EXPIRED N-TYPE CERTIFICATES FOR PLANTS NOT IN ACTIVE CONSTRUCTION (TAC NO. MD8314)
Dear Mr. Bhatnagar:
By letter to the Nuclear Regulatory Commission (NRC) dated February 1, 2008, Tennessee Valley Authority (TVA) submitted a request for authorization to use an alternative to the requirements in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section III. Specifically, T VA requested to use the provisions of ASME Code Case N-520-2, "Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active C onstruction,Section III, Division I." Code Case N-520-2 would allow TVA to obtain a temporary Certificate of Authorization from ASME to complete and transfer documentation of the partially completed ASME Section III system s and components to the jurisdiction of a subcontractor, who will be an ASME Section III N-Certificate holder.
The NRC staff is reviewing your submittal and has determined that additional information is needed to complete its review. The specific information requested is addressed in the enclosure to this letter.
This request for additional information was discussed with members of your staff, and it was agreed that a response would be provided within 45 days of the date of this letter. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket No. 50-391
Enclosure:
Request for Additional Information
cc w/encl: See next page
This request for additional information was discussed with members of your staff, and it was agreed that a response would be provided within 45 days of the date of this letter. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket No. 50-391
Enclosure:
Request for Additional Information
cc w/encl: See next page
DISTRIBUTION:
PUBLIC RidsOgcRp RidsNrrDorlLwpb RidsNrrPMPMilano RidsNroDcipCqvb RidsNrrDorlDpr RidsNrrPMJUribe RidsNrrDciCpnb R. McIntyre, NRO RidsNrrDeEqva RidsAcrsAcnw&mMailCenter RidRgn2MailCenter (R. Haag) RidsNrrLABClayton (Hard Copy)
ADAMS Accession Number: ML081300809
OFFICE LWPB/PM LWPB/LA EQVA/BC LWPB/BC NAME PMilano BClayton DThatcher LRaghavan DATE 5/12/08 5/12/08 5/19/08 5/22/08 OFFICIAL RECORD COPY ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION WATTS BAR NUCLEAR PLANT, UNIT 2 DOCKET NO. 50-391
By letter dated February 1, 2008 (Agencywide Documents Access and Management System Accession No. ML080370185), Tennessee Valley Authority submitted a request for authorization to use of the provisions of American Society of Mechanical Engineers (ASME) Code Case N-520-2, "Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction,Section III, Division I," for Watts Bar Nuclear Plant, Unit 2 (WBN-2). In reviewing the application, the Nuclear Regulatory Commission staff has determined that the following information is needed in order to complete its review:
- 1. In paragraph (c) of the ASM E Code Case N-520-2 it is stated that: "[t]he Quality Assurance program previously accepted by the society shall be continually implemented (NCA-8140) and any revisions to the program shall be acceptable to the Authorized Nuclear Inspection Agency." However, in the second paragraph of page 1 of to the application, it notes that the ASME Section III Quality Assurance (QA)
Manual was applied to WBN-2 only through October 25, 1996. It appears that the code
case requires that the ASME Section III QA manual should have been applied post October 25, 1996, to such items as layup, maintenance, and removal of components for use on the other unit.
Clarify whether the QA manual was applied after October 25, 1996, for such items as layup, maintenance, and removal of components.
- 2. In Enclosure 1, the section entitled "Proposed Alternative and Basis for Use" states in Item No. 2 that: "[t]he Society will perform a survey of the limited scope quality assurance program and processes to ensure that the procedures are in place to accomplish the code data transfer in accordance with the provisions of the Code Case."
Since NRC staff has not yet reviewed this revised code case, nor has it approved its generic use by the industry through the usual processes of incorporation (i.e., Regulatory Guides, Title 10 of the Code of Federal Regulations, Section 50.55a), the staff's position is that a FULL ASME survey, and not a limited survey, should be performed.
Clarify your definition of a "limited scope survey" to provide, in more detail, the scope of the survey of the QA program to be performed.
- 3. In Enclosure 1, Item No. 6 of the section entitled "Proposed Alternative and Basis for Use," states that the term length of the temporary certificates will be of limited duration. Paragraph (f)(7) of the code case has specific requirements for the term of the temporary certificates and for renewals.
Clarify your definition of "limited duration" to a more detailed timeframe, and describe how this will comply with requirements of the code case.
Ashok S. Bhatnagar Tennessee Valley Authority WATTS BAR NUCLEAR PLANT UNIT 2 cc:
Mr. Gordon P. Arent New Generation Licensing Manager Tennessee Valley Authority 5A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
Senior Resident Inspector, Unit 2 Watts Bar Nuclear Plant U.S. Nuclear Regulatory Commission 1260 Nuclear Plant Road Spring City, TN 37381
Mr. Michael K. Brandon, Manager Licensing and Industry Affairs Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. William R. Campbell, Jr.
Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
County Executive 375 Church Street Suite 215 Dayton, TN 37321
County Mayor P. O. Box 156 Decatur, TN 37322
Mr. John C. Fornicola, General Manager Nuclear Assurance Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 General Counsel Tennessee Valley Authority 6A West Tower 400 West Summit Hill Drive Knoxville, TN 37902
Mr. Michael J. Lorek, Plant Manager Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. Lawrence E. Nanney, Director Tennessee Dept. of Environmental Health &
Conservation Division of Radiological Health 3rd Floor, L&C Annex 401 Church Street Nashville, TN 37243-1532
Mr. Larry E. Nicholson, General Manager Performance Improvement Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
Mr. Masoud Bajestani, Vice President Watts Bar Unit 2 Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381
Mr. Michael D. Skaggs Site Vice President Watts Bar Nuclear Plant Tennessee Valley Authority P. O. Box 2000 Spring City, TN 37381
Ms. Ann P. Harris 341 Swing Loop Road Rockwood, TN 37854