N Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 October 17, 2011 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
Watts Bar Nuclear Plant (WBN) Unit 2 - Revision of Commitment for Unit 2's Implementation of the Maintenance Rule
References:
1.
TVA to NRC letter dated January 29, 2008, "Watts Bar Nuclear Plant (WBN) -
Unit 2 - Regulatory Framework for the Completion of Construction and Licensing Activities for Unit 2" (ADAMS Accession No ML080320443)
- 2.
TVA to NRC letter dated November 17, 2010, "Watts Bar Nuclear Plant (WBN) Unit 2 - Revision of Commitment for Unit 2's Implementation of the Maintenance Rule" (ADAMS Accession No ML103210644)
Item 115 of Enclosure 2 of Reference 1 contained the following commitment: "Implement Maintenance Rule for Unit 2 systems 1 month prior to fuel load."
Reference 2 revised this commitment to read "Implement Maintenance Rule for Unit 2 systems by October 31, 2011."
Due to schedule changes, this letter revises this commitment to read "Implement Maintenance Rule for Unit 2 systems by October 31, 2012."
U.S. Nuclear Regulatory Commission Page 2 October 17, 2011 If you have any questions, please contact Gordon Arent at (423) 365-2004.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 171 day of October, 2011.
Respectfully, David Stinson Watts Bar Unit 2 Vice President cc:
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381