ML11273A026: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 09/29/2011
| issue date = 09/29/2011
| title = Fy 2012 University of Michigan Ford Nuclear Reactor Master Inspection Plan
| title = Fy 2012 University of Michigan Ford Nuclear Reactor Master Inspection Plan
| author name = Lipa C A
| author name = Lipa C
| author affiliation = NRC/RGN-III/DNMS/DB
| author affiliation = NRC/RGN-III/DNMS/DB
| addressee name = Alexander T
| addressee name = Alexander T

Revision as of 08:32, 29 June 2019

Fy 2012 University of Michigan Ford Nuclear Reactor Master Inspection Plan
ML11273A026
Person / Time
Site: University of Michigan
Issue date: 09/29/2011
From: Christine Lipa
NRC/RGN-III/DNMS/DB
To: Alexander T
University of Michigan
References
Download: ML11273A026 (3)


Text

September 29, 2011

Mr. Terry Alexander Executive Director Department of Occupation Safety & Environmental Health 1239 Kipke Drive University of Michigan Ann Arbor, MI 48109-1010

SUBJECT:

UNIVERSITY OF MICHIGAN FORD NUCLEAR REACTOR MASTER INSPECTION PLAN FISCAL YEAR 2012

Dear Mr. Alexander:

In accordance with U.S. Nuclear Regulatory Commission (NRC) Inspection Manual, Chapter 2545, "Research and Test Reactor Inspection Program," the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for the Ford Nuclear Reactor.

The plan is based on your current performance and schedule of significant decommissioning activities planned for the site for the period of October 2011 through December 2012. The plan outlines how we intend to focus our regional inspection resources to address significant ongoing decommissioning activities.

Because this MIP is based, in part, on your proposed schedule of significant decommissioning activities for fiscal year (FY) 2012; the plan and focus of the NRC inspection activities may change to reflect a change in your planned decommissioning activities or your performance. In order to ensure that this MIP remains current, we request that you keep the Materials Control, ISFSI and Decommissioning Branch staff informed of any significant changes in your proposed schedule of decommissioning activities. You will be informed of any significant changes to the Ford Reactor Inspection Schedule.

We currently project the region will conduct approximately two inspections at the Ford Reactor through December 2012 to evaluate final status surveys and conduct confirmatory surveys if they are underway. The region will conduct approximately one inspection of routine activities if final status surveys do not start in FY 2012. The following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted.

Inspection Procedure Title IP 69013 Research and Test Reactor Decommissioning IP 83801 Inspection of Final Surveys of Permanently Shutdown Reactors

In accordance with Title 10 Code of Federal Regulations (CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact Jeremy Tapp of my staff at (630) 829-9862.

Sincerely, /RA/ Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch Division of Nuclear Materials Safety Docket No. 050-00002 License No. R-28

cc: S. L. Ceccio, University of Michigan M. L. Driscoll, University of Michigan K. Yale, State of Michigan

In accordance with Title 10 Code of Federal Regulations (CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact Jeremy Tapp of my staff at (630) 829-9862.

Sincerely, /RA/ Christine A. Lipa, Chief Materials Control, ISFSI and Decommissioning Branch Division of Nuclear Materials Safety Docket No. 050-00002 License No. R-28

cc: S. L. Ceccio, University of Michigan M. L. Driscoll, University of Michigan K. Yale, State of Michigan

DISTRIBUTION

Bruce Watson Theodore Smith Dominick Orlando Cynthia Pederson

Anne Boland Patrick Louden Allan Barker Harral Logaras Viktoria Mitlyng Prema Chandrathil MCID Branch

  • See previous concurrence DOCUMENT NAME: G:\DNMSIII\Work in progress\MIP - University of Michigan Ford Nuclear Reactor FY2012.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII DNMS E RIII DNMS E RIII RIII NAME JETapp:jm JET CALipa CAL DATE 09/29/2011 09/29/2011 OFFICIAL RECORD COPY