Revision as of 15:58, 9 February 2019

Supplemental Safety Evaluation Report Related to the License Renewal of Beaver Valley Power Station, Units 1 and 2
ML092520550
Person / Time
Site: Beaver Valley
Issue date: 10/06/2009
From: Holian B E
Division of License Renewal
To: Sena P P
FirstEnergy Nuclear Operating Co
Howard K, NRR/DLR/RPB2, 415-2989
Shared Package
ML092520531 List:
References
Download: ML092520550 (2)


Text

October 6, 2009 Mr. Peter P. Sena III Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB-1 P.O. Box 4, Route 168 Shippingport, PA 105077

SUBJECT:

SUPPLEMENTAL SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2

Dear Mr. Sena:

By letter dated August 27, 2007, FirstEnergy Nuclear Operating Company (FENOC) submitted, for U.S. Nuclear Regulatory Commission (NRC) review, an application to renew the Beaver Valley Power Station, Units 1 and 2, operating licenses for up to an additional 20 years. The license renewal application (LRA) was submitted pursuant to Title 10 of the Code of Federal Regulations Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants." The NRC staff issued a safety evaluation report (SER) in June 2009. In order to clarify their position on supplemental volumetric examinations of the containment liners, FENOC provided the NRC supplemental information for the review of the Beaver Valley Power Station, Units 1 and 2 LRA on July 28, 2009, September 2, 2009, September 4, 2009, September 8, 2009, and September 14, 2009.

On the basis of its review, the staff has developed the enclosed Supplement 1 to the SER to document its findings associated with the safety review of the supplemental volumetric examinations on Beaver Valley Power Station, Units 1 and 2.

If you have any questions regarding this matter, please contact the license renewal Project Manager, Kent Howard by telephone at 301-415-2989 or by e-mail at Kent.Howard@nrc.gov. Sincerely,

/RA by Samson S. Lee Acting For/

Brian E. Holian, Director Division of License Renewal Office of Nuclear Reactor Regulation

Docket Nos. 50-334 and 50-412

Enclosure:

As stated

cc w/encl: See next page

ML092520531 (Pkg) ML092520550 (Ltr) ML092570014 (Encl) *concurred via e-mail OFFICE PM:RPB2:DLR LA:DLR TechEd* BC:RER2:DLR NAME KHoward IKing KAzariah-Kribbs RAuluck (BRogers for) DATE 09/16/09 09/16/09 09/09/09 09/17/09 OFFICE SrTA:DE: OGC BC:RPB2:DLR D:DLR NAME KManoly LSubin (NLO) DWrona (RKuntz for) BHolian (SLee for) DATE 09/22/09 09/30/09 09/28/09 10/06/09 Letter to Peter P Sena from Kent Howard dated October 6, 2009

SUBJECT:

SUPPLEMENTAL SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OF BEAVER VALLEY POWER STATION, UNITS 1 AND 2 DISTRIBUTION

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource ------------- KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI Beaver Valley Power Station, Units 1 and 2 cc: Mr. Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308

Mr. James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308

Mr. Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Ms. Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308

Mr. Paul A. Harden Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Mr. David W. Jenkins Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077

Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077

Mr. Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077

Mr. Steve Dort FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077

Mr. Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077