| {{#Wiki_filter:VogtleReadiness Group (VRG)Construction Inspection Program Public MeetingApril 12, 2018Tim McGinty, Victor Hall, & Andrea Johnson VogtleReadiness GroupIntroduction and Welcome by Tim McGinty, VRG Co-Chair 2 VogtleReadiness GroupGoal is to Identify and Resolve Challenges in:LicensingInspectionRegulatory Challenges or Gaps that could impact Vogtle'sscheduleVRGinstituted consistent with:Watts Bar Construction Lessons Learned (ML17356A269 | | {{#Wiki_filter:Vogtle Readiness Group (VRG) |
| )July 2017, ITAACClosure and Verification Demonstration (Recommendation 10
| | Construction Inspection Program Public Meeting April 12, 2018 Tim McGinty, Victor Hall, & Andrea Johnson |
| -ML17135A415 | | |
| )3WHO and WHAT VogtleReadiness Group Co-chaired by two NRO Division Directors and one Region II Division DirectorMembers include:Office of New Reactors (NRO)Region IIOffice of Nuclear Reactor Regulation (NRR)Office of Nuclear Security and Incident Response (NSIR)Office of the General Counsel (OGC)4WHO and WHAT VogtleReadiness GroupNRC issued the Charter for Instituting the VogtleReadiness Group To Oversee the VogtleUnits 3 and 4 Transition to OperationsPublicly Issued on March 12, 2018ADAMS Accession No. ML18059A273 5VRGCHARTER VogtleReadiness GroupWill serve as the hub for communications with:The CommissionThe Executive Director for Operations and Offices The LicenseeExternal Stakeholders 6Communications VogtleReadiness Group 7LINKS VogtleReadiness GroupWHAT IT IS:Tool to Identify and Track Key Activities Up To and Afterthe 10 CFR 52.103(g) FindingExamples of Milestones: CybersecurityEmergency PreparednessTransition to OperationsITAACIncludes Key Interfaces Between NRC, Licensee and Other Stakeholders 8Integrated Project Plan 9Integrated Project PlanTitle (what)Due No later Than
| | Vogtle Readiness Group Introduction and Welcome by Tim McGinty, VRG Co-Chair 2 |
| * All dates based upon calendar daysMilestone Tied to Activity/Row # (when)Role (who)Basis of activity (what is the purpose of the milestone and the rationale behind the date)10CFR 52.103(g) ProcessAll UINs submitted225 days before SFLScheduledFuel LoadNRO/DNRL10 CFR 52.99(c)(3), a licensee must submit uncompleted ITAAC notifications (UINs) at least 225 days before scheduled fuel load (SFL) for ITAAC that have not yet been completed.Licensee submits "All ITAAC Complete" Letter x days before SFLScheduledFuel LoadNRO/RIIThe licensee must also notify the NRC when all ITAAC are complete as required by 10 CFR 52.99(c)(4). Licensee's Scheduled Construction ActivitiesScheduled Fuel Load (SFL)From licensee's scheduleALLBased upon licensee's scheduleFirst full participation EP exercise From licensee's scheduleALLBased upon licensee's scheduleNRO-REG-105, "U.S. NRC Commission Staff Support of ITAAC Hearing Process"Transition to Operations ReadinessCombined License (COL) Operational Programs and Other License Conditions Implementation Schedule Transition to OperationsSeptember 2014: Published the "Assessment of the Staff's Readiness to Transition Regulatory Oversight and Licensing as New Reactors Proceed from Construction to Operation," | | |
| (ML14031A387 | | Vogtle Readiness Group WHO and WHAT Goal is to Identify and Resolve Challenges in: |
| )Identified 21 Readiness Issues with 29 RecommendationsNovember 2017: Published the "Implementation Plan to Ensure NRC Staff Readiness for AP1000Operations" (ML17215A436
| | Licensing Inspection Regulatory Challenges or Gaps that could impact Vogtles schedule VRG instituted consistent with: |
| )10Implementation Plan Implementation Plan(continued)Clarifies New Reactor Operational Regulatory Oversight and Licensing Responsibilities as the Units Transition from Construction to Operations. Incorporates Nuclear Energy Institute Comments on the Reactor Oversight ProcessIntended to be a Living Document. NRC will Revise to Addresses Issues:NRO/NRR Merger , ITAACClosure Processes Enhancements , First Plant Only Tests, and Other Key Issues Impacting Transition to Operations 11 QUESTIONS?
| | Watts Bar Construction Lessons Learned (ML17356A269) |
| | July 2017, ITAAC Closure and Verification Demonstration (Recommendation 10 - ML17135A415) 3 |
| | |
| | Vogtle Readiness Group WHO and WHAT Co-chaired by two NRO Division Directors and one Region II Division Director Members include: |
| | Office of New Reactors (NRO) |
| | Region II Office of Nuclear Reactor Regulation (NRR) |
| | Office of Nuclear Security and Incident Response (NSIR) |
| | Office of the General Counsel (OGC) 4 |
| | |
| | Vogtle Readiness Group VRG CHARTER NRC issued the Charter for Instituting the Vogtle Readiness Group To Oversee the Vogtle Units 3 and 4 Transition to Operations Publicly Issued on March 12, 2018 ADAMS Accession No. ML18059A273 5 |
| | |
| | Vogtle Readiness Group Communications Will serve as the hub for communications with: |
| | The Commission The Executive Director for Operations and Offices The Licensee External Stakeholders 6 |
| | |
| | Vogtle Readiness Group LINKS 7 |
| | |
| | Vogtle Readiness Group Integrated Project Plan WHAT IT IS: |
| | Tool to Identify and Track Key Activities Up To and After the 10 CFR 52.103(g) Finding Examples of Milestones: |
| | Cybersecurity Emergency Preparedness Transition to Operations ITAAC Includes Key Interfaces Between NRC, Licensee and Other Stakeholders 8 |
| | |
| | Integrated Project Plan Due No later Than Milestone Tied to Basis of activity (what is the purpose of the |
| | * All dates Title (what) Activity/Row # Role (who) milestone and the rationale behind the based upon (when) date) calendar days 10CFR 52.103(g) Process 10 CFR 52.99(c)(3), a licensee must submit 225 days uncompleted ITAAC notifications (UINs) at least All UINs submitted Scheduled Fuel Load NRO/DNRL before SFL 225 days before scheduled fuel load (SFL) for ITAAC that have not yet been completed. |
| | x days before Licensee submits "All ITAAC Complete" SFL The licensee must also notify the NRC when all Scheduled Fuel Load NRO/RII ITAAC are complete as required by 10 CFR Letter 52.99(c)(4). |
| | Licensee's Scheduled Construction Activities From licensee's Scheduled Fuel Load (SFL) ALL Based upon licensee's schedule schedule From licensee's First full participation EP exercise ALL Based upon licensee's schedule schedule NRO-REG-105, "U.S. NRC Commission Staff Support of ITAAC Hearing Process" Transition to Operations Readiness 9 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule |
| | |
| | Transition to Operations Implementation Plan September 2014: Published the Assessment of the Staffs Readiness to Transition Regulatory Oversight and Licensing as New Reactors Proceed from Construction to Operation, (ML14031A387) |
| | Identified 21 Readiness Issues with 29 Recommendations November 2017: Published the Implementation Plan to Ensure NRC Staff Readiness for AP1000 Operations (ML17215A436) 10 |
| | |
| | Implementation Plan (continued) |
| | Clarifies New Reactor Operational Regulatory Oversight and Licensing Responsibilities as the Units Transition from Construction to Operations. |
| | Incorporates Nuclear Energy Institute Comments on the Reactor Oversight Process Intended to be a Living Document. NRC will Revise to Addresses Issues: |
| | NRO/NRR Merger, ITAAC Closure Processes Enhancements, First Plant Only Tests, and Other Key Issues Impacting Transition to Operations 11 |
| | |
| | QUESTIONS? |
| 12}} | | 12}} |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24164A2942024-06-17017 June 2024 Licensee Slides for Pre-submittal Meeting for VEGP Units 3 and 4 for a Proposed License Amendment Request Regarding TS 3.3.8 ML24158A3832024-06-0606 June 2024 SNC Slides - Vogtle 3 and 4 - TS 3-8-2 - Pre-Submittal Meeting - 06-27-2024 ML24120A2202024-04-30030 April 2024 Annual Assessment Meeting Presentation Slides - April 30, 2024 ML24089A1492024-04-0404 April 2024 Slides - SNC Presentation - Pre-Submittal Meeting on April 4, 2024 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML24060A2732024-03-0707 March 2024 SNC Slides - Pre-Submittal Meeting on March 7, 2024 - Vogtle 3 & 4 TSTF-577 LAR ML24022A1192024-01-24024 January 2024 Slides - SNC Slides - Pre-Submittal Meeting on January 24, 2024 - Vogtle 3 & 4 Explosively Actuated Valves Relief Request ML23361A0812024-01-0808 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR ML24004A1852024-01-0404 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR Revised ML23257A2322023-09-28028 September 2023 SNC Presentation - Pre-Submittal Meeting on September 28, 2023 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML23137A1162023-06-0202 June 2023 Draft Slides for Advisory Committee on Reactor Safeguards Subcommittee Meeting Regarding Use of Accident Tolerant Fuel Lead Test Assemblies ML23094A1402023-04-0404 April 2023 4 -- 2022 Aam Slides ML23055A0402023-02-24024 February 2023 VEGP, Unit 4, Potential License Amendment Request for Prior to Initial Criticality Overview Presentation ML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22329A0192022-12-0101 December 2022 Southern Nuclear Company Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request 1 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ML22332A0012022-11-28028 November 2022 SNC Slides - Pre-Submittal Meeting on November 30, 2022 - Vogtle TS 5.5.11 License Amendment Request ML22319A1232022-11-15015 November 2022 Kozak Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22319A0052022-11-15015 November 2022 NEI Slides for November 15 2022 Public Meeting on Part 52 Lessons Learned ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22251A0002022-09-30030 September 2022 Pre-Submittal Meeting on September 13, 2022 - Vogtle Online Monitoring LAR ML22265A0972022-09-22022 September 2022 Southern Nuclear Company Slides on Lessons Learned from Part 52 Implementation for Public Meeting on 9/27/2022 ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML22138A3952022-05-24024 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 24, 2022 - Vogtle RR RWST Suction Check Valves ML22137A2812022-05-23023 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 23, 2022 - Vogtle TS 3.8.1 and TSTF-163 LAR ML22126A0102022-05-11011 May 2022 Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemption Requests - Licensing Questions ML22123A3332022-05-10010 May 2022 Pre-Submittal Meeting 2: TSTF-51, TSTF-471, TSTF-490, and Alternative Source Term License Amendment Request - May 10, 2022 (EPID L-2022-LRM-0033)(slides) ML22110A1702022-04-20020 April 2022 4 2022 Annual Assessment Meeting.Final ML22021B6472022-01-27027 January 2022 Pre-Submittal for Westinghouse Increased Enrichment Accident Tolerant Fuel Lead Test Assemblies (EPID L-2022-LRM-0003) (Slides) ML21306A0242021-11-30030 November 2021 SNC Pre-Submittal Meeting for LAR to Relocate Augmented Piping Inspection Program Details from TSs to a Licensee Controlled Document for Farley Nuclear Plant, Units 1 & 2; and Vogtle Electric Generating Plant, Units 1 & 2 (EPID L-2021-LRM-0 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21230A2842021-08-18018 August 2021 SNC Slides - Vogtle MSIV Elimination LAR - Pre-submittal Meeting Part 2 - 08-25-2021 ML21193A0762021-07-0808 July 2021 ITAAC Related to Incore Instrument Thimble Assembly (Iita) ML21187A0972021-07-0808 July 2021 Late Filed Allegations (Lfa) Process ML21172A1312021-07-0101 July 2021 Pre-Submittal Meeting Alternate Source Term and TSTF-490 ML21193A0772021-06-24024 June 2021 Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses, 6-24-21 Pre-submittal Meeting ML21085A4902021-05-19019 May 2021 Risk-informed Resolution of Generic Letter 2004-02 ML21064A3652021-03-0101 March 2021 Dashboard Report 3-1-2021 ML21027A2062021-02-28028 February 2021 Fixed 8-Hour Emergency Light Deviation Pre-Submittal Meeting, February 2021 (Slides) ML21057A0182021-02-26026 February 2021 Pre-Submittal Meeting Revise Technical Specification 3.2.1 Heat Flux Hot Channel Factor (Fq(Z)) (EPID L-2021-LRM-0023) (Slides) ML21036A1172021-02-0505 February 2021 SNC Slides - Pre-Submittal Meeting on February 16, 2021 - Beacon LAR ML20343A0742020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20318A1032020-11-12012 November 2020 SNC ERO Staffing LAR RAI Responses ML20314A0962020-11-0202 November 2020 Dashboard Report 11/02/2020 ML20217L4312020-08-13013 August 2020 Edwin I Hatch, Units 1 and 2; and Vogtle Electric Plant, Units 1, 2, 3, and 4 - Meeting Slides a License Amendment Request for the Emergency Plan (EPID Nos L-2020-LLA-0150 and L-2020-LLA-051 ML20136A2832020-05-15015 May 2020 4 EOC Slides ML20114E3032020-04-23023 April 2020 Risk-Informed GL 2004--02 Pre-Submittal NRC Meeting - May 2020 ML20007D6772020-01-0808 January 2020 AP1000 Public Presentation Entitled Reactor Oversight Process (ROP) for Inspecting Vogtle Site with AP1000 Design ML19303A0252019-11-0404 November 2019 Risk-Informed GSI-191 NRC Public Meeting ML19295D4672019-10-30030 October 2019 Public Meeting for ITAAC Hearing Process, October 30, 2019 2024-06-06
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24164A2942024-06-17017 June 2024 Licensee Slides for Pre-submittal Meeting for VEGP Units 3 and 4 for a Proposed License Amendment Request Regarding TS 3.3.8 ML24158A3832024-06-0606 June 2024 SNC Slides - Vogtle 3 and 4 - TS 3-8-2 - Pre-Submittal Meeting - 06-27-2024 ML24120A2202024-04-30030 April 2024 Annual Assessment Meeting Presentation Slides - April 30, 2024 ML24089A1492024-04-0404 April 2024 Slides - SNC Presentation - Pre-Submittal Meeting on April 4, 2024 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML24060A2732024-03-0707 March 2024 SNC Slides - Pre-Submittal Meeting on March 7, 2024 - Vogtle 3 & 4 TSTF-577 LAR ML24022A1192024-01-24024 January 2024 Slides - SNC Slides - Pre-Submittal Meeting on January 24, 2024 - Vogtle 3 & 4 Explosively Actuated Valves Relief Request ML23361A0812024-01-0808 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR ML24004A1852024-01-0404 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR Revised ML23311A2452023-11-0707 November 2023 Pre-Submittal Meeting on November 7, 2023 - License Amendment Request to Revise the Ultimate Heat Sink Mission Time (Slides) ML23304A2682023-11-0707 November 2023 License Amendment Request to Revise the Ultimate Heat Sink Mission Time Pre Submittal Meeting on November 7, 2023 ML23293A0052023-10-20020 October 2023 Lessons Learned from the ITAAC Hearing Process for Vogtle 3 and 4 ML23257A2322023-09-28028 September 2023 SNC Presentation - Pre-Submittal Meeting on September 28, 2023 - Proposed Vogtle 3 and 4 TS 3.7.6 LAR ML23137A1162023-06-0202 June 2023 Draft Slides for Advisory Committee on Reactor Safeguards Subcommittee Meeting Regarding Use of Accident Tolerant Fuel Lead Test Assemblies ML23094A1402023-04-0404 April 2023 4 -- 2022 Aam Slides ML23072A1802023-03-13013 March 2023 2023 RIC Powerpoint Slide Presentation, Vogtle 3: Journey from Construction to Operations ML23055A0402023-02-24024 February 2023 VEGP, Unit 4, Potential License Amendment Request for Prior to Initial Criticality Overview Presentation ML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22335A5542022-12-0101 December 2022 Slides - SNC Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request - ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22329A0192022-12-0101 December 2022 Southern Nuclear Company Slides - Pre-Submittal Meeting on December 1, 2022 - Vogtle SR 3.4.14.1 LAR and Alternative Relief Request 1 ML22332A0012022-11-28028 November 2022 SNC Slides - Pre-Submittal Meeting on November 30, 2022 - Vogtle TS 5.5.11 License Amendment Request ML22319A1232022-11-15015 November 2022 Kozak Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22319A0052022-11-15015 November 2022 NEI Slides for November 15 2022 Public Meeting on Part 52 Lessons Learned ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML22251A0002022-09-30030 September 2022 Pre-Submittal Meeting on September 13, 2022 - Vogtle Online Monitoring LAR ML22265A0972022-09-22022 September 2022 Southern Nuclear Company Slides on Lessons Learned from Part 52 Implementation for Public Meeting on 9/27/2022 ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML22206A1712022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22206A1682022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22201A0442022-07-20020 July 2022 Voices Dashboard Report for Vogtle Unit 3 as of July 20, 2022 ML22138A3952022-05-24024 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 24, 2022 - Vogtle RR RWST Suction Check Valves ML22144A0492022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22144A0502022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22137A2812022-05-23023 May 2022 Slides - SNC Slides - Pre-Submittal Meeting on May 23, 2022 - Vogtle TS 3.8.1 and TSTF-163 LAR ML22126A0102022-05-11011 May 2022 Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemption Requests - Licensing Questions ML22123A3332022-05-10010 May 2022 Pre-Submittal Meeting 2: TSTF-51, TSTF-471, TSTF-490, and Alternative Source Term License Amendment Request - May 10, 2022 (EPID L-2022-LRM-0033)(slides) ML22126A0012022-05-0606 May 2022 SNC Slides - Pre-Submittal Meeting on May 11, 2022 - Vogtle ATF LTAs LAR and Exemptions ML22110A1702022-04-20020 April 2022 4 2022 Annual Assessment Meeting.Final ML22060A0062022-02-28028 February 2022 4Q 2021 Performance Summary U3 ML22021B6472022-01-27027 January 2022 Pre-Submittal for Westinghouse Increased Enrichment Accident Tolerant Fuel Lead Test Assemblies (EPID L-2022-LRM-0003) (Slides) ML22026A0582022-01-26026 January 2022 Dashboard Report 1-26-2022 ML21306A0242021-11-30030 November 2021 SNC Pre-Submittal Meeting for LAR to Relocate Augmented Piping Inspection Program Details from TSs to a Licensee Controlled Document for Farley Nuclear Plant, Units 1 & 2; and Vogtle Electric Generating Plant, Units 1 & 2 (EPID L-2021-LRM-0 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21230A2842021-08-18018 August 2021 SNC Slides - Vogtle MSIV Elimination LAR - Pre-submittal Meeting Part 2 - 08-25-2021 ML21197A0032021-08-0606 August 2021 Slides - SNC Slides - Pre-Submittal Meeting on August 13, 2021 - Vogtle TS 3.3.1 and 3.3.2 LAR ML21193A0762021-07-0808 July 2021 ITAAC Related to Incore Instrument Thimble Assembly (Iita) ML21187A0972021-07-0808 July 2021 Late Filed Allegations (Lfa) Process ML21188A3592021-07-0606 July 2021 1Q 2021 Performance Summary U3 ML21188A3612021-07-0606 July 2021 1Q 2021 Performance Summary U4 2024-06-06
[Table view] |
Text
Vogtle Readiness Group (VRG)
Construction Inspection Program Public Meeting April 12, 2018 Tim McGinty, Victor Hall, & Andrea Johnson
Vogtle Readiness Group Introduction and Welcome by Tim McGinty, VRG Co-Chair 2
Vogtle Readiness Group WHO and WHAT Goal is to Identify and Resolve Challenges in:
Licensing Inspection Regulatory Challenges or Gaps that could impact Vogtles schedule VRG instituted consistent with:
Watts Bar Construction Lessons Learned (ML17356A269)
July 2017, ITAAC Closure and Verification Demonstration (Recommendation 10 - ML17135A415) 3
Vogtle Readiness Group WHO and WHAT Co-chaired by two NRO Division Directors and one Region II Division Director Members include:
Office of New Reactors (NRO)
Region II Office of Nuclear Reactor Regulation (NRR)
Office of Nuclear Security and Incident Response (NSIR)
Office of the General Counsel (OGC) 4
Vogtle Readiness Group VRG CHARTER NRC issued the Charter for Instituting the Vogtle Readiness Group To Oversee the Vogtle Units 3 and 4 Transition to Operations Publicly Issued on March 12, 2018 ADAMS Accession No. ML18059A273 5
Vogtle Readiness Group Communications Will serve as the hub for communications with:
The Commission The Executive Director for Operations and Offices The Licensee External Stakeholders 6
Vogtle Readiness Group LINKS 7
Vogtle Readiness Group Integrated Project Plan WHAT IT IS:
Tool to Identify and Track Key Activities Up To and After the 10 CFR 52.103(g) Finding Examples of Milestones:
Cybersecurity Emergency Preparedness Transition to Operations ITAAC Includes Key Interfaces Between NRC, Licensee and Other Stakeholders 8
Integrated Project Plan Due No later Than Milestone Tied to Basis of activity (what is the purpose of the
- All dates Title (what) Activity/Row # Role (who) milestone and the rationale behind the based upon (when) date) calendar days 10CFR 52.103(g) Process 10 CFR 52.99(c)(3), a licensee must submit 225 days uncompleted ITAAC notifications (UINs) at least All UINs submitted Scheduled Fuel Load NRO/DNRL before SFL 225 days before scheduled fuel load (SFL) for ITAAC that have not yet been completed.
x days before Licensee submits "All ITAAC Complete" SFL The licensee must also notify the NRC when all Scheduled Fuel Load NRO/RII ITAAC are complete as required by 10 CFR Letter 52.99(c)(4).
Licensee's Scheduled Construction Activities From licensee's Scheduled Fuel Load (SFL) ALL Based upon licensee's schedule schedule From licensee's First full participation EP exercise ALL Based upon licensee's schedule schedule NRO-REG-105, "U.S. NRC Commission Staff Support of ITAAC Hearing Process" Transition to Operations Readiness 9 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule
Transition to Operations Implementation Plan September 2014: Published the Assessment of the Staffs Readiness to Transition Regulatory Oversight and Licensing as New Reactors Proceed from Construction to Operation, (ML14031A387)
Identified 21 Readiness Issues with 29 Recommendations November 2017: Published the Implementation Plan to Ensure NRC Staff Readiness for AP1000 Operations (ML17215A436) 10
Implementation Plan (continued)
Clarifies New Reactor Operational Regulatory Oversight and Licensing Responsibilities as the Units Transition from Construction to Operations.
Incorporates Nuclear Energy Institute Comments on the Reactor Oversight Process Intended to be a Living Document. NRC will Revise to Addresses Issues:
NRO/NRR Merger, ITAAC Closure Processes Enhancements, First Plant Only Tests, and Other Key Issues Impacting Transition to Operations 11
QUESTIONS?