Letter Sequence Approval |
---|
|
|
MONTHYEARML0635204432006-12-18018 December 2006 License Pg 3 and Technical Specification Pg - Issuance of Amendment 269 for Modifications to T.S. Surveillance Requirement 4.6.1.1 Regarding Containment Isolation Valve Position Verification, MD0059 Project stage: Approval ML0629104352006-12-18018 December 2006 License Amendment, Issuance of Amendment 269 for Modifications to Technical Specifications Surveillance Requirement 4.6.1.1 Regarding Containment Isolation Valve Position Verification, MD0059 Project stage: Approval 2006-12-18
[Table View] |
|
---|
Category:Letter
MONTHYEARML24295A1202024-10-21021 October 2024 Relief Request ANO2-RR-24-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 71 ML24185A2602024-10-0404 October 2024 Issuance of Amendment No. 335 to Revise Typographical Errors in Technical Specifications IR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification 05000313/LER-2024-001, Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications2024-07-0101 July 2024 Source Range Nuclear Instrument Failure Resulting in Condition Prohibited by Technical Specifications ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24099A1912024-04-0808 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000313/2024404 and 05000368/2024404) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 2024-09-09
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24185A2602024-10-0404 October 2024 Issuance of Amendment No. 335 to Revise Typographical Errors in Technical Specifications ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23020A9362023-01-27027 January 2023 Audit Plan to Support Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML22263A1912022-12-0909 December 2022 Issuance of Amendment No. 278 Revision to Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations (EPID L-2021-LLA-0181) - Non-Proprietary ML22291A2392022-10-28028 October 2022 Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed Nshcd, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI (EPID L-2021-LLA-0181) Letter ML22165A2442022-07-19019 July 2022 Issuance of Amendment No. 331 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22138A4312022-06-23023 June 2022 Issuance of Amendment No. 277 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML22104A2222022-05-12012 May 2022 Issuance of Amendments Revise Technical Specifications to Adopt TSTF 554 ML22083A1242022-04-28028 April 2022 Arkansas, Units 1 and 2; Grand Gulf Nuclear Station; River Bend Station; and Waterford Steam Electric Station - Issuance of Amendments Revise Technical Specifications to Adopt TSTF-541, Revision 2 ML22039A2822022-03-15015 March 2022 Issuance of Amendment Nos. 274 and 328 One-Time Change to Support Proactive Upgrade of the Emergency Cooling Pond Supply Piping ML21225A0552021-12-17017 December 2021 Issuance of Amendment No. 327 Addition of Technical Specification Limiting Condition for Operation 3.0.6 and Adoption of Safety Function Determination Program ML21341B2262021-12-13013 December 2021 Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations ML21313A0082021-12-0808 December 2021 Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21320A2122021-11-17017 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request Concerning Revised Dose Calculations ML21281A2542021-10-15015 October 2021 Audit Meeting Agenda & Audit Questions for LAR to Adopt 10 CFR 50.69,Risk-Informed Categorization and Treatment of Structures, System, and Components for Nuclear Power Reactors (EPIDs L-2021-LLA-0105, L-2021-LLA-0106 ML21208A4492021-09-20020 September 2021 Issuance of Amendment No. 325 Revise Loss of Voltage Relay Allowable Values and Number of Degraded Voltage Channels ML21088A4332021-04-14014 April 2021 Issuance of Amendment No. 324 Adoption of Technical Specification Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition ML21027A4282021-03-23023 March 2021 Issuance of Amendment No. 272 Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent ML21040A5132021-03-10010 March 2021 Issuance of Amendment No. 271 Revision to Loss of Voltage Relay Allowable Values ML20351A1532021-02-0808 February 2021 Issuance of Amendment No. 323 Technical Specification Deletions, Additions, and Relocations NUREG-1432, Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-14322020-10-30030 October 2020 Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-1432 ML20135H1412020-06-30030 June 2020 Issuance of Amendment Nos. 269 and 321 Request to Incorporate the Tornado Missile Risk Evaluator Into the Licensing Basis ML20160A1472020-06-30030 June 2020 Issuance of Amendment No. 270 to Adopt TSTF 563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20087L8032020-04-0808 April 2020 Issuance of Amendment No. 320 to Revise Control Element Assembly Drop Times ML19231A2972020-01-29029 January 2020 Issuance of Amendment No. 318 Addition of Technical Specification Actions to Address Inoperability of the Containment Building Sump ML19269B6722019-10-22022 October 2019 Issuance of Amendment Nos. 267 and 317 to Extend Implementation Dates for Amendment Nos. 263 and 314, Revision to Emergency Action Level Scheme ML19220A9382019-09-27027 September 2019 Issuance of Amendment No. 266 Adoption of Technical Specifications Task Force Traveler TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19098A9552019-05-22022 May 2019 Issuance of Amendment No. 264 Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3 ML19127A2992019-05-15015 May 2019 Correction to Amendment No. 315 Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3 ML19063B9482019-04-23023 April 2019 Issuance of Amendment No. 315 Adoption of Technical Specification Task Force Traveler TSTF-425, Revision 3 ML18337A2472019-01-17017 January 2019 Issuance of Amendment Nos. 263 and 314 Revision to Emergency Action Level Scheme ML18317A3822018-12-19019 December 2018 Issuance of Amendment No. 313, Revise Technical Specification 3.3.3.6, Post-Accident Instrumentation ML18306A5132018-11-30030 November 2018 Issuance of Conforming Amendment Nos. 262, 312 and 215 Transfers of Renewed Facility Operating Licenses ML18298A0122018-11-27027 November 2018 Issuance of Amendment No. 311 Updating the Reactor Coolant System Pressure Temperature Limits ML18260A3392018-10-24024 October 2018 Issuance of Amendment No. 261 Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves ML18115A2822018-06-19019 June 2018 Issuance of Amendment No. 260 Technical Specification Changes Pursuant to Technical Specifications Task Force (TSTF) Traveler TSTF-412 Revision 3 (CAC No. MG0009; EPID L-2017-LLA-0267) ML18134A2532018-06-19019 June 2018 Issuance of Amendment No. 310 Technical Specification Changes to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-1432, Revision 4 (CAC No. MG0016; EPID L-2017-LLA-0268) ML18033A1752018-02-26026 February 2018 Issuance of Amendment No. 259 to Adopt TSTF-427, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability (CAC No. MG0132; EPID L-2017-LLA-0301) ML18051A5892018-02-26026 February 2018 Issuance of Amendment No. 309 to Adopt TSTF-427, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability (CAC No. MG0131; EPID L-2017-LLA-0302) ML18011A0642018-01-18018 January 2018 Issuance of Amendment No. 308 to Exclude Exercise of Control Element Assembly 4 with Respect to Surveillance Requirement 4.1.3.1.2 for the Remainder of Cycle 26 (Exigent Circumstances) ML17235A5192017-10-10010 October 2017 Issuance of Amendment No. 258 Revision of Steam Generator Technical Specifications to Reflect Adoption of TSTF-510 (CAC MF9653; EPID L-2017-LLA-0221) ML17251A2112017-10-10010 October 2017 Issuance of Amendment No. 307 Revision of Steam Generator Technical Specifications to Reflect Adoption of Technical Specifications Task Force Traveler TSTF-510 (CAC MF9654; EPID L-2017-LLA-0222) ML17096A2352017-05-12012 May 2017 Issuance of Amendment No. 306 Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications ML16215A3712017-03-29029 March 2017 Issuance of Amendment No. 305 to Adopt Technical Specifications Task Force Traveler TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing... ML16165A4232017-03-10010 March 2017 Issuance of Amendment No. 257 Adoption of Technical Specifications Task Force Traveler TSTF-545, Revision 3, 2024-08-13
[Table view] Category:Safety Evaluation
MONTHYEARML24185A2602024-10-0404 October 2024 Issuance of Amendment No. 335 to Revise Typographical Errors in Technical Specifications ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23142A1062023-05-24024 May 2023 Authorization and Safety Evaluation for Alternative Request No. ANO1-ISI-035 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML22342B1602023-01-10010 January 2023 Requests for Relief ANO2-ISI-023, -024, -025, -026, -027, and -028 to Permit Reduction of Inspection Area Due to Interference (EPIDs L-2022-LLR-0022,-0023, -0024, -0025, -0026, and -0027) ML22263A1912022-12-0909 December 2022 Issuance of Amendment No. 278 Revision to Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations (EPID L-2021-LLA-0181) - Non-Proprietary ML22236A5452022-08-26026 August 2022 Correction to Issuance of Amendment No. 331 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22138A4312022-06-23023 June 2022 Issuance of Amendment No. 277 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML22104A2222022-05-12012 May 2022 Issuance of Amendments Revise Technical Specifications to Adopt TSTF 554 ML22083A1242022-04-28028 April 2022 Arkansas, Units 1 and 2; Grand Gulf Nuclear Station; River Bend Station; and Waterford Steam Electric Station - Issuance of Amendments Revise Technical Specifications to Adopt TSTF-541, Revision 2 ML22039A2822022-03-15015 March 2022 Issuance of Amendment Nos. 274 and 328 One-Time Change to Support Proactive Upgrade of the Emergency Cooling Pond Supply Piping ML22007A3172022-01-18018 January 2022 1, River Bend Station 1, and Waterford Steam Electric Station 3 - Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ML21225A0552021-12-17017 December 2021 Issuance of Amendment No. 327 Addition of Technical Specification Limiting Condition for Operation 3.0.6 and Adoption of Safety Function Determination Program ML21341B2262021-12-13013 December 2021 Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations ML21313A0082021-12-0808 December 2021 Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21208A4492021-09-20020 September 2021 Issuance of Amendment No. 325 Revise Loss of Voltage Relay Allowable Values and Number of Degraded Voltage Channels ML21132A2792021-05-19019 May 2021 Request for Approval of Change to the Entergy Quality Assurance Program Manual ML21088A4332021-04-14014 April 2021 Issuance of Amendment No. 324 Adoption of Technical Specification Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition ML21027A4282021-03-23023 March 2021 Issuance of Amendment No. 272 Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent ML21040A5132021-03-10010 March 2021 Issuance of Amendment No. 271 Revision to Loss of Voltage Relay Allowable Values ML20351A1532021-02-0808 February 2021 Issuance of Amendment No. 323 Technical Specification Deletions, Additions, and Relocations ML20288A8242020-11-16016 November 2020 Regulatory Audit Summary Concerning License Amendment Request to Replace the Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent NUREG-1432, Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-14322020-10-30030 October 2020 Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-1432 ML20226A2722020-08-18018 August 2020 Request to Use a Provision of a Later Edition of the ASME BPV Code, Section XI ML20160A1472020-06-30030 June 2020 Issuance of Amendment No. 270 to Adopt TSTF 563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20135H1412020-06-30030 June 2020 Issuance of Amendment Nos. 269 and 321 Request to Incorporate the Tornado Missile Risk Evaluator Into the Licensing Basis ML20121A1932020-05-0606 May 2020 Alternative Requests for the Fifth 10 Year Interval Inservice Testing of Low Pressure Safety Injection Pumps and Service Water Valves ML20107J3172020-04-23023 April 2020 Relief Request ANO1-ISI-033 Related to ASME Code Case N-729-4 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles ML20087L8032020-04-0808 April 2020 Issuance of Amendment No. 320 to Revise Control Element Assembly Drop Times ML20083J9682020-03-26026 March 2020 Approval of Request for Alternative ANO 2-PT-002 End-of-Internal System Leakage Test for Extended Reactor Coolant Pressure Boundary Piping ML19231A2972020-01-29029 January 2020 Issuance of Amendment No. 318 Addition of Technical Specification Actions to Address Inoperability of the Containment Building Sump ML19220A9382019-09-27027 September 2019 Issuance of Amendment No. 266 Adoption of Technical Specifications Task Force Traveler TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML19254A6032019-09-19019 September 2019 Units 2 and 3; Palisades Nuclear Plant; River Bend; and Waterford Steam Electric Station, Unit 3 - Relief Request No. EN-19-RR-1, Use of ASME Code Case N-831-1 ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19184A5542019-07-15015 July 2019 Request for Relief ANO1-ISI-032 from the ASME Code Section XI Visual Examination Requirements for the Fourth 10-Year Inservice Inspection Interval ML19156A4002019-06-11011 June 2019 Request for Alternative ANO2-ISI-021 to Permit Continued Application of the 2007 Edition Through the 2008 Addenda of ASME Code ML19098A9552019-05-22022 May 2019 Issuance of Amendment No. 264 Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3 ML19063B9482019-04-23023 April 2019 Issuance of Amendment No. 315 Adoption of Technical Specification Task Force Traveler TSTF-425, Revision 3 ML18337A2472019-01-17017 January 2019 Issuance of Amendment Nos. 263 and 314 Revision to Emergency Action Level Scheme ML18346A3142019-01-0707 January 2019 Relief Nos. ANO1-ISI-027, -028, -029, -030, and -031 from ASME Code, Section XI, Examination Requirements for Fourth 10-Year Inservice Inspection Interval (EPID L-2018-LLR-0063, -0064, -0065, -0066, -0067) ML18317A3822018-12-19019 December 2018 Issuance of Amendment No. 313, Revise Technical Specification 3.3.3.6, Post-Accident Instrumentation ML18298A0122018-11-27027 November 2018 Issuance of Amendment No. 311 Updating the Reactor Coolant System Pressure Temperature Limits ML18260A3392018-10-24024 October 2018 Issuance of Amendment No. 261 Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves 2024-08-13
[Table view] |
Text
December 18, 2006Mr. Jeffrey S. ForbesSite Vice President Arkansas Nuclear One Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT NO. 2 - ISSUANCE OF AMENDMENTFOR MODIFICATIONS TO TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENT 4.6.1.1 REGARDING CONTAINMENT ISOLATION VALVE POSITION VERIFICATION (TAC NO. MD0059)
Dear Mr. Forbes:
The Commission has issued the enclosed Amendment No. 269 to Facility Operating LicenseNo. NPF-6 for Arkansas Nuclear One, Unit No. 2 (ANO-2). The amendment consists of changes to the Technical Specifications (TSs) in response to your application dated February 14, 2006. Specifically, the proposed amendment would eliminate the requirement to verify containmentisolation valves that are maintained locked, sealed, or otherwise secured closed from the monthly position verification. A new surveillance requirement, (SR) 4.6.1.1.d, would also be added to replace the existing note and would reflect the SR for similar devices located inside containment. In addition, a new note would be included that will allow verification by use of administrative means of the valves and blind flanges that are located in high-radiation areas. In this regard, the amendment adopts TS Task Force (TSTF) Improved Standard TS Change Traveler No. 45 (TSTF-45-A), "Exempt Verification of Containment Isolation Valves that are Not Locked, Sealed, or Otherwise Secured."
J. Forbes-2-A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will beincluded in the Commission's next biweekly Federal Register notice.Sincerely,/RA/Farideh E. Saba, Project ManagerPlant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-368
Enclosures:
- 1. Amendment No. 269 to NPF-62. Safety Evaluationcc w/encls:See next page J. Forbes-2-A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will beincluded in the Commission's next biweekly Federal Register notice.Sincerely,/RA/Farideh E. Saba, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-368
Enclosures:
- 1. Amendment No. 269 to NPF-62. Safety Evaluationcc w/encls:See next pageDISTRIBUTIONPUBLICLPLIV RF GHill RidsNrrDirsItsb RidsNrrDorlLpl4 RidsNrrPMFSaba RidsNrrLALFeizollahiRidsAcrsAcnwMailCenterRidsOgcRp BLee, NRR JPulsifer, NRR RidsNrrDssScvb (RDennig)
RidsNrrDorlDpr RidsRgn4MailCenterPackage: ML062910450Accession No.: ML062910435TS Page: ML063520443OFFICENRR/LPL4/PMNRR/LPL4/LANRR/SCVBOGC-NLONRR/LPL4/BCNAMEFSabaLFeizollahiRDennigPMouldingDTerao DATE12/16/0611/29/068/14/0612/70612/16/06OFFICIAL RECORD COPY ENTERGY OPERATIONS, INC.DOCKET NO. 50-368ARKANSAS NUCLEAR ONE, UNIT NO. 2AMENDMENT TO RENEWED FACILITY OPERATING LICENSEAmendment No. 269 Renewed License No. NPF-61.The Nuclear Regulatory Commission (the Commission) has found that:A.The application for amendment by Entergy Operations, Inc. (the licensee), datedFebruary 14, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I;B.The facility will operate in conformity with the application, the provisions of theAct, and the rules and regulations of the Commission;C.There is reasonable assurance (i) that the activities authorized by thisamendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations;D.The issuance of this license amendment will not be inimical to the commondefense and security or to the health and safety of the public; and E.The issuance of this amendment is in accordance with 10 CFR Part 51 of theCommission's regulations and all applicable requirements have been satisfied. 2.Accordingly, the license is amended by changes to the Technical Specifications asindicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-6 is hereby amended to read as follows:(2)Technical SpecificationsThe Technical Specifications contained in Appendix A, as revised throughAmendment No. 269, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications. 3.The license amendment is effective as of its date of issuance and shall be implementedwithin 60 days from the date of issuance.FOR THE NUCLEAR REGULATORY COMMISSION/RA/David Terao, ChiefPlant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Renewed Facility Operating License No. NPF-6 and the Technical SpecificationsDate of Issuance: December 18, 2006 ATTACHMENT TO LICENSE AMENDMENT NO. 269RENEWED FACILITY OPERATING LICENSE NO. NPF-6DOCKET NO. 50-368Replace the following page of the License with the attached revised page. The revised page isidentified by an amendment number and contains a marginal line indicating the area of change. RemoveInsert 33Replace the following page of the Appendix A Technical Specifications with the attached revised page. The revised page is identified by an amendment number and contains marginal lines indicating the areas of change. RemoveInsert3/4 6-13/4 6-1 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATIONRELATED TO AMENDMENT NO. 269 TORENEWED FACILITY OPERATING LICENSE NO. NPF-6ENTERGY OPERATIONS, INC.ARKANSAS NUCLEAR ONE, UNIT NO. 2DOCKET NO. 50-36
81.0INTRODUCTION
By application dated February 14, 2006 (Agencywide Documents Access and ManagementSystem (ADAMS) Accession No. ML060530391), Entergy Operations, Inc. (the licensee, Entergy), requested changes to the Technical Specifications (TSs) for Arkansas Nuclear One,Unit No. 2 (ANO-2). The staff's original proposed no significant hazards considerationdetermination was published in the Federal Register on April 11, 2006 (71 FR 18373). The proposed changes will revise the ANO-2 TS surveillance requirement (SR) 4.6.1.1.a. toeliminate the requirement to verify containment isolation valves that are maintained locked, sealed, or otherwise secured closed from the monthly position verification. A new surveillance requirement, (SR) 4.6.1.1.d, would also be added to replace the existing "*note" and would reflect the SR for similar devices located inside containment. In addition, a new note would be included that will allow verification by use of administrative means of the valves and blind flanges that are located in high-radiation areas. In these respects, the amendment adopts TS Task Force (TSTF) Improved Standard TS Change Traveler No. 45 (TSTF-45-A), "Exempt Verification of Containment Isolation Valves that are Not Locked, Sealed, or Otherwise Secured."
2.0REGULATORY EVALUATION
On July 26, 1999, the U.S. Nuclear Regulatory Commission (NRC) approved TSTF Improved"Standard TS Change Traveler No. 45 (TSTF-45-A)," which revised the Standard Technical Specifications. NUREG-1432, "Standard Technical Specifications Combustion EngineeringPlants," Revision 3.1, SR 3.6.3.3 and SR 3.6.3.4 reflected in TSTF-45-A the elimination from the TS of the surveillance requirements for containment isolation valves that were verified to be in the closed position upon locking, sealing or securing. NRC Generic Letter 91-08, "Removal of Component Lists from Technical Specifications," provided the guidance for the administrative requirements associated with opening manual containment isolation valves intermittently.
3.0TECHNICAL EVALUATION
3.1Proposed ChangeThe proposed change will specifically exclude verification of normally locked, sealed, orotherwise secured closed valves, blind flanges, and the deactivated automatic valves.
SR 4.6.1.1.d will be modified to replace the existing "*note" since the note contains a requirement to perform the surveillance for physically secured valves and flanges that are closed and located inside containment. The change also allows administrative means for performing valve verification when the valve is located in a high-radiation area. The proposed change reflects the wording that is included in NUREG-1432 with consideration for the difference in TS format.3.2Evaluation of TS Change The proposed TS change is consistent with the NRC-approved TSTF-45-A, which wasapproved by the NRC for use by licensees on July 26, 1999. This TSTF was approved by the NRC staff for the use of licensees in proposing changes to plant-specific TSs based onNUREG-1432. TSTF-45-A was revised to exclude locked, sealed, or otherwise secured closed valves that are located outside containment from the monthly verification. TSTF-45-A stated that the proposed change was consistent with the valve position verificationrequirement for valves that have a function during an accident in other system TSs. Consistent with the logic of the TSTF, ANO-2 TS SR 4.5.2.b requires that each emergency core cooling system subsystem be demonstrated operable, in part, by performance of a valve alignment of each valve that is in the flow path that is not locked, sealed, or otherwise secured valves. The emergency feedwater system and the service water system are also demonstrated to be operable, in part, by verifying that each valve in the flow path of the system is not locked, sealed, or otherwise secured in position, and is in its correct position (SR 4.7.1.2.a.1 and SR 4.7.3.1.a, respectively). The addition of the note that allows an alternate (administrative) means of verifying valves that are located in high-radiation areas is in accordance with the requirements of ANO-2 TS 6.7, "High Radiation Area."The NRC staff finds that the proposed change to SR 4.6.1.1 is acceptable since it is consistentwith other ANO-2 TS SRs and the NRC-approved TSTF-45-A.
4.0STATE CONSULTATION
In accordance with the Commission's regulations, the Arkansas State official was notified of theproposed issuance of the amendment. The State official had no comments.
5.0ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facilitycomponent located within the restricted area as defined in 10 CFR Part 20 and changes a surveillance requirement. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The NRC has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding published April 11, 2006 (71 FR 18373) . Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0CONCLUSION
The NRC staff finds that the licensee's proposed change to SR 4.6.1.1 reflects the wording inNUREG-1432 with consideration of the different TS format and is, therefore, acceptable.The NRC has concluded, based on the considerations discussed above, that: (1) there isreasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.Principal Contributor: B. Lee Date: December 18, 2006 October 2006Arkansas Nuclear One cc:Executive Vice President
& Chief Operating Officer Entergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995General Manager PlantOperations Entergy Operations, Inc.
Arkansas Nuclear One 1448 SR 333 Russellville, AR 72802Director, Nuclear Safety AssuranceEntergy Operations, Inc.
Arkansas Nuclear One 1448 SR 333 Russellville, AR 72802Manager, LicensingEntergy Operations, Inc.
Arkansas Nuclear One 1448 SR 333 Russellville, AR 72802Director, Nuclear Safety & LicensingEntergy Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213-8298Section Chief, Division of HealthRadiation Control Section Arkansas Department of Health and Human Services 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867Section Chief, Division of HealthEmergency Management Section Arkansas Department of Health and Human Services 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 310 London, AR 72847Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064County Judge of Pope County Pope County Courthouse Russellville, AR 72801Vice President, Operations SupportEntergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995