| number = ML103010523 | | number = ML103010523 | ||
| issue date = 11/16/2010 | | issue date = 11/16/2010 | ||
| title = | | title = Summary of Teleconference Held on Between the U.S. NRC and Arizona Public Service Company, Concerning Draft Follow-Up Request for Additional Information Pertaining to the Palo Verde Nuclear Generating Station, Units 1, 2 and 3, LRA | ||
| author name = Regner L | | author name = Regner L | ||
| author affiliation = NRC/NRR/DLR/RPB2 | | author affiliation = NRC/NRR/DLR/RPB2 | ||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:LICENSEE: | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 16,2010 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1, 2, and 3 | ||
FACILITY: | |||
==SUBJECT:== | ==SUBJECT:== | ||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28,2010 , | OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING DRAFT FOLLOW-UP REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION , | ||
The telephone conference call was useful in clarifying the | UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Arizona Public Service Company (the applicant) held a telephone conference call on October 28, 2010, to discuss and clarify the staff's draft follow-up request for additional information (RAI) concerning the Palo Verde Nuclear Generating Station , Units 1, 2, and 3, license renewal application. The telephone conference call was useful in clarifying the intent of the staff's draft RAI. provides a listing of the participants and Enclosure 2 contains a listing of the draft RAI discussed with the applicant, including a brief description on the status of the items . | ||
The applicant had an opportunity to comment on this summary. | |||
isa M. Rea , Sr. r,:;,ject Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos 50-528, 50-529, and 50-530 | |||
==Enclosures:== | ==Enclosures:== | ||
As stated cc w/encls: Distribution via Listserv | As stated cc w/encls: Distribution via Listserv | ||
TELEPHONE CONFERENCE CALL PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS OCTOBER 28, 2010 PARTICIPANTS AFFILIATIONS Lisa Regner U.S. Nuclear Regulatory Commission (NRC) | |||
William Holston NRC Angela Krainik Arizona Public Service Company (APS) | |||
Glenn Michael APS Shabbir Pittalwala APS Roger Fongemie APS Eric Blocher Strategic Teaming and Resource Sharing Alliance ENCLOSURE 1 | |||
DRAFT REQUEST FOR ADDITIONAL INFORMATION PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION OCTOBER 28, 2010 The U.S. Nuclear Regulatory Commission (the staff) and representatives of Arizona Public Service Company (APS or the applicant) held a telephone conference call on October 28, 2010, to discuss and clarify the following draft request for additional information (RAI) concerning the Palo Verde Nuclear Generating Station , Units 1, 2, and 3, license renewal application (LRA) . | |||
: 1. Justify why the inspections of in-scope diesel fuel oil piping , discussed in a letter from APS dated October 13, 2010, is not included in the Updated Final Safety Analysis Report Supplement, Appendix A of the LRA. | |||
: 2. How many feet of in-scope buried fuel oil piping are located at each unit? How many feet of in-scope buried diesel fuel oil piping are not under concrete or asphalt? | |||
: 3. Justify how aging of underground buried fuel oil piping will be managed in the 30-40 year, 40-50 year, and 50-60 year license renewal periods. | |||
Discussion: The applicant stated that it understood the questions and would provide a follow-up response to RAI 82.1.18-1. | |||
ENCLOSURE 2 | |||
..' ML103010523 *concurred via e-mail OFFICE LARPOB:DLR | |||
* PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME IKing LRegner DWrona LRegner (Signature) 11/5/10 11/15/10 11116/10 11/16/10 DATE Memorandum to Arizona Public Service Company from Lisa M. Regner dated November 16, 2010 | |||
*concurred via e-mail OFFICE LARPOB: DLR | |||
* PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME IKing LRegner DWrona LRegner (Signature) | |||
==SUBJECT:== | ==SUBJECT:== | ||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING DRAFT FOLLOW-UP REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION , UNITS 1 , 2, AND 3 , LICENSE RENEWAL APPLICATION DISTRIBUTION: | OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING DRAFT FOLLOW-UP REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION , | ||
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource | UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION DISTRIBUTION: | ||
HARD COPY: | |||
DLR RF E-MAIL: | |||
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource L. Regner D. Drucker R. Hall B. Mizuno, OGC J. H. Bashore, RIV G. Pick, RIV}} |
Latest revision as of 13:22, 11 March 2020
ML103010523 | |
Person / Time | |
---|---|
Site: | Palo Verde |
Issue date: | 11/16/2010 |
From: | Lisa Regner License Renewal Projects Branch 2 |
To: | Office of Nuclear Reactor Regulation |
Regner L M, NRR/DLR, 415-1906 | |
References | |
Download: ML103010523 (5) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 16,2010 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1, 2, and 3
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING DRAFT FOLLOW-UP REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION ,
UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Arizona Public Service Company (the applicant) held a telephone conference call on October 28, 2010, to discuss and clarify the staff's draft follow-up request for additional information (RAI) concerning the Palo Verde Nuclear Generating Station , Units 1, 2, and 3, license renewal application. The telephone conference call was useful in clarifying the intent of the staff's draft RAI. provides a listing of the participants and Enclosure 2 contains a listing of the draft RAI discussed with the applicant, including a brief description on the status of the items .
The applicant had an opportunity to comment on this summary.
isa M. Rea , Sr. r,:;,ject Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos 50-528, 50-529, and 50-530
Enclosures:
As stated cc w/encls: Distribution via Listserv
TELEPHONE CONFERENCE CALL PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS OCTOBER 28, 2010 PARTICIPANTS AFFILIATIONS Lisa Regner U.S. Nuclear Regulatory Commission (NRC)
William Holston NRC Angela Krainik Arizona Public Service Company (APS)
Glenn Michael APS Shabbir Pittalwala APS Roger Fongemie APS Eric Blocher Strategic Teaming and Resource Sharing Alliance ENCLOSURE 1
DRAFT REQUEST FOR ADDITIONAL INFORMATION PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION OCTOBER 28, 2010 The U.S. Nuclear Regulatory Commission (the staff) and representatives of Arizona Public Service Company (APS or the applicant) held a telephone conference call on October 28, 2010, to discuss and clarify the following draft request for additional information (RAI) concerning the Palo Verde Nuclear Generating Station , Units 1, 2, and 3, license renewal application (LRA) .
- 1. Justify why the inspections of in-scope diesel fuel oil piping , discussed in a letter from APS dated October 13, 2010, is not included in the Updated Final Safety Analysis Report Supplement, Appendix A of the LRA.
- 2. How many feet of in-scope buried fuel oil piping are located at each unit? How many feet of in-scope buried diesel fuel oil piping are not under concrete or asphalt?
- 3. Justify how aging of underground buried fuel oil piping will be managed in the 30-40 year, 40-50 year, and 50-60 year license renewal periods.
Discussion: The applicant stated that it understood the questions and would provide a follow-up response to RAI 82.1.18-1.
ENCLOSURE 2
..' ML103010523 *concurred via e-mail OFFICE LARPOB:DLR
- PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME IKing LRegner DWrona LRegner (Signature) 11/5/10 11/15/10 11116/10 11/16/10 DATE Memorandum to Arizona Public Service Company from Lisa M. Regner dated November 16, 2010
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 28,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING DRAFT FOLLOW-UP REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE PALO VERDE NUCLEAR GENERATING STATION ,
UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource L. Regner D. Drucker R. Hall B. Mizuno, OGC J. H. Bashore, RIV G. Pick, RIV