November 19, 2013 MEMORANDUM TO: Ho K. Nieh, Jr., Director Division of Inspection and Regional Support Office of Nuclear Reactor Regulation FROM:
Kriss M. Kennedy, Director /RA/ Troy Pruitt for Division of Reactor Projects Region IV
SUBJECT:
DEFERRAL OF BASELINE INSPECTION ACTIVITIES Region IV plans to defer two required inspection activities from 2013 into the first quarter of 2014. The region will satisfy Baseline Inspection Program Completion criteria of Inspection Manual Chapter (IMC) 2515 for the 2013 inspection cycle.
Due to the lapse in agency funding, two component design basis inspections (CDBIs) could not begin as scheduled. As a result, these triennial inspections will not be complete by the end of the 2011-2013 triennial inspection cycle. In accordance with IMC 2515 requirements, Region IV will complete these inspections during the first quarter of Calendar Year 2014:
The CDBI at South Texas Project Electric Generating Station will be completed on February 14, 2014. It will be documented in NRC Inspection Report 05000498/2013007, and 05000499/2013007.
The CDBI at Palo Verde Nuclear Generating Station inspection will be completed on February 7, 2014. It will be documented in NRC Inspection Report 05000528/2013009, 05000529/2013009, and 05000530/2013009.
Both South Texas Project and Palo Verde are in the licensee response column of the action matrix. Completion of the two CDBIs will be tracked by the regions Technical Support Branch.
They will count for the 2011-2013 triennial cycle only; an additional CDBI will be scheduled for each site during the 2014-2016 triennial cycle.
This plan meets the requirements of IMC 2515 § 08.06 for deferral of baseline inspections.
Completion of these inspections as rescheduled will result in baseline inspection program completion as defined by IMC 2515 § 04.07. This memorandum satisfies the notification requirement of IMC 2515 § 08.06.e.
cc: M. Dapas, RIV T. Blount, RIV CONTACT: Eric A. Ruesch, RIV/DRS 817-200-1126 UNITED STATES NUCLEAR REGULATORY COMMISSION RE G IO N I V 1600 EAST LAMAR BLVD ARLINGTON, TEXAS 76011-4511
ADAMS Accession Number: ML13324A494 SUNSI Rev Compl.
Yes No ADAMS Yes No Reviewer Initials EAR Publicly Avail Yes No Sensitive Yes No Sens. Type Initials EAR TSB TSB C:TSB D:DRS D:DRP PHolder EARuesch RLKellar TBlount KMKennedy
/RA/
/RA/
/RA/
/RA/
/RA/ TWP for 11/13/13 11/14/13 11/15/13 11/15/13 11/19/13 OFFICIAL RECORD COPY November 19, 2013 MEMORANDUM TO: Ho K. Nieh, Jr., Director Division of Inspection and Regional Support Office of Nuclear Reactor Regulation FROM:
Kriss M. Kennedy, Director /RA/ Troy Pruitt for Division of Reactor Projects Region IV
SUBJECT:
DEFERRAL OF BASELINE INSPECTION ACTIVITIES Region IV plans to defer two required inspection activities from 2013 into the first quarter of 2014. The region will satisfy Baseline Inspection Program Completion criteria of Inspection Manual Chapter (IMC) 2515 for the 2013 inspection cycle.
Due to the lapse in agency funding, two component design basis inspections (CDBIs) could not begin as scheduled. As a result, these triennial inspections will not be complete by the end of the 2011-2013 triennial inspection cycle. In accordance with IMC 2515 requirements, Region IV will complete these inspections during the first quarter of Calendar Year 2014:
The CDBI at South Texas Project Electric Generating Station will be completed on February 14, 2014. It will be documented in NRC Inspection Report 05000498/2013007, and 05000499/2013007.
The CDBI at Palo Verde Nuclear Generating Station inspection will be completed on February 7, 2014. It will be documented in NRC Inspection Report 05000528/2013009, 05000529/2013009, and 05000530/2013009.
Both South Texas Project and Palo Verde are in the licensee response column of the action matrix. Completion of the two CDBIs will be tracked by the regions Technical Support Branch.
They will count for the 2011-2013 triennial cycle only; an additional CDBI will be scheduled for each site during the 2014-2016 triennial cycle.
This plan meets the requirements of IMC 2515 § 08.06 for deferral of baseline inspections.
Completion of these inspections as rescheduled will result in baseline inspection program completion as defined by IMC 2515 § 04.07. This memorandum satisfies the notification requirement of IMC 2515 § 08.06.e.
cc: M. Dapas, RIV T. Blount, RIV CONTACT: Eric A. Ruesch, RIV/DRS 817-200-1126 UNITED STATES NUCLEAR REGULATORY COMMISSION RE G IO N I V 1600 EAST LAMAR BLVD ARLINGTON, TEXAS 76011-4511