Summary of Tele Conf Call Held on 4/12/10, Btw the USNRC and APS, Concerning the PVNGS, Units 1, 2, and 3, License Renewal Application
ML101340666
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/02/2010
From: Lisa Regner
License Renewal Projects Branch 2
To:
Arizona Public Service Co
Ferrer, N B, NRR/DLR, 415-1045
References
Download: ML101340666 (6)


Text

June 2, 2010 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1, 2, and 3

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON APRIL 12, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Arizona Public Service Company (the applicant) held a telephone conference call on April 12, 2010, to discuss and clarify the staffs follow-up draft request for additional information (RAI). This follow-up draft RAI questioned the applicants April 1, 2010, response to an RAI dated December 29, 2009, concerning the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs draft RAI. provides a listing of the participants and Enclosure 2 contains a listing of the draft RAI discussed with the applicant, including a brief description on the status of the items.

The applicant had an opportunity to comment on this summary.

/RA/

Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, and 50-530

Enclosures:

As stated cc w/encls: See next page

ML101340666 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME IKing LRegner DWrona LRegner DATE 05/19/10 05/24/10 05/26/10 06/02/10

Memorandum to Arizona Public Service Company from L. Regner dated June 2, 2010

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON APRIL 12, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ARIZONA PUBLIC SERVICE COMPANY, CONCERNING THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail Resource


L. Regner D. Drucker R. Hall B. Mizuno, OGC R. Treadway, RIV G. Pick, RIV

TELEPHONE CONFERENCE CALL PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS APRIL 12, 2010 PARTICIPANTS AFFILIATIONS Lisa Regner U.S. Nuclear Regulatory Commission (NRC)

Greg Pick NRC Bryce Lehman NRC Hans Ashar NRC Angela Krainik Arizona Public Service Company (APS)

Glenn Michael APS Marianne Webb APS Fara Oreshack APS Ken Schrecker APS Keith Jackson APS Eric Blocher Strategic Teaming and Resource Sharing (STARS) Alliance Jim Johnson STARS ENCLOSURE 1

DRAFT REQUEST FOR ADDITIONAL INFORMATION PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION APRIL 12, 2010 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Arizona Public Service Company (APS or the applicant) held a telephone conference call on April 12, 2010, to discuss and clarify the following draft request for additional information (RAI) concerning the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, license renewal application.

DRAFT Follow-Up RAI B2.1.32-1

Background

By letter dated April 1, 2010, the applicant supplemented its response to RAI B2.1.32-1 regarding the Structures Monitoring Program inspection interval.

Issue In the supplement, the applicant enhanced the Structures Monitoring Program to inspect structures within the scope of license renewal at intervals not to exceed 10 years. The spray pond inspections and settlement monitoring surveillances both remained at five years. The applicant did not include structures exposed to a natural environment or structures inside primary containment within the five year inspection interval as suggested in ACI 349.3R. The supplement included a brief explanation of why the applicant believed a ten year inspection frequency was adequate for structures exposed to a natural environment; however, the explanation did not consider environmental factors and no discussion was provided for structures inside primary containment.

Request Align the Structures Monitoring Program inspection interval with the guidance in ACI 349.3R, or provide a detailed technical justification for a longer inspection interval for structures inside primary containment or exposed to a natural environment. An adequate explanation needs to address all environmental factors to which a structure may be exposed, as well as relevant operating experience (e.g. humidity, high winds, temperature fluctuations, cracking, spalling, etc.).

Discussion: Following discussion with APS staff, NRC staff agreed to allow the applicant to provide an additional supplemental response to RAI B2.1.32-1 addressing the above concern.

DRAFT Follow-Up RAI B2.1.32-1 will not be sent as a formal RAI.

ENCLOSURE 2

Palo Verde Nuclear Generating Station, Units 1, 2, and 3 cc:

Mr. Steve Olea Mr. John C. Taylor, Director, Nuclear Arizona Corporation Commission Generation 1200 W. Washington Street El Paso Electric Company Phoenix, AZ 85007 340 E. Palm Lane, Suite 310 Phoenix, AZ 85004 Mr. Douglas Kent Porter, Senior Counsel Southern California Edison Company Mr. James Ray Law Department, Generation Resources Public Service Company of New Mexico P.O. Box 800 2401 Aztec NE, MS Z110 Rosemead, CA 91770 Albuquerque, NM 87107-4224 Senior Resident Inspector Mr. Geoffrey M. Cook U.S. Nuclear Regulatory Commission Southern California Edison Company P.O. Box 40 5000 Pacific Coast Highway, Bldg. D21 Buckeye, AZ 85326 San Clemente, CA 92672 Regional Administrator, Region IV Mr. Robert Henry U.S. Nuclear Regulatory Commission Salt River Project 612 E. Lamar Blvd., Suite 400 6504 E. Thomas Road Arlington, TX 76011-4125 Scottsdale, AZ 85251 Chairman Mr. Jeffrey T. Weikert Maricopa County Board of Supervisors Assistant General Counsel 301 W. Jefferson, 10th Floor El Paso Electric Company Phoenix, AZ 85003 Mail Location 167 123 W. Mills Mr. Aubrey V. Godwin, Director El Paso, TX 79901 Arizona Radiation Regulatory Agency 4814 S. 40th Street Mr. Eric Tharp Phoenix, AZ 85040 Los Angeles Department of Water & Power Southern California Public Power Authority Mr. Ron Barnes, Director P.O. Box 51111, Room 1255-C Regulatory Affairs Los Angeles, CA 90051-0100 Palo Verde Nuclear Generating Station Mail Station 7636 Mr. Brian Almon P.O. Box 52034 Public Utility Commission Phoenix, AZ 85072-2034 William B. Travis Building P.O. Box 13326 Mr. Dwight C. Mims, Vice President 1701 N. Congress Avenue Regulatory Affairs and Plant Improvement Austin, TX 78701-3326 Palo Verde Nuclear Generating Station Mail Station 7605 Mr. Randall K. Edington P.O. Box 52034 Executive Vice President Phoenix, AZ 85072-2034 Nuclear/CNO Arizona Public Service Company P.O. Box 52034, Mail Station 7602 Phoenix, AZ 85072-2034