| number = ML081770470
| number = ML081770470
| issue date = 06/25/2008
| issue date = 06/25/2008
| title = McGuire May Examination 05000369 and 05000370/ 2008-301 Facilities Post-Examination Comments (Part 1 of 2)
| title = May Examination 05000369 and 05000370/ 2008-301 Facilities Post-Examination Comments (Part 1 of 2)
| author name =  
| author name =  
| author affiliation = NRC/RGN-II
| author affiliation = NRC/RGN-II
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Attachment 1a Common Question 53PageI of 8 After further investigation we propose that Question53be deletedduetono correct an swer.Theoriginal a s sumption w asduetothelo wering VI (InstrumentAir) pressure the S/G feedreg valveswouldfa il clo sed re sulting in increasingfeed pump di scharg e pressure to th e point wherethefeedpumpswou ldtriponhighdi scharge pressure.Whil ethefailur e mechani smfortheFRV's i s correctonalos s of air (closed), th e re sultin g Rea ctor trip occursduetolow S/G levelnotfeedpumpdi scharge pressure.Thiswas validatedonou r simulatorwithaloss ofVIrampedi noveraperiod of5to10 minutes which resulted in the reactor tripping on low S/GlevelwhenVIpress had degraded to appro x.40psig.WhileFWPdi scharge pressuredidincrease, the action oftheFWP control system to maintain th e program D IP at setpointre sulted in a decrea seinFWP speedasthe FRV's clo sed.This a ction delays the increase inFWPdi s charge pressure.tothe point where lowering S/G level willreach trip setpoint prior to increasing F WP dischargepress.In 4 different VIfailurescenarios withvarying leak sizes andramprates, the reactortr ipped du e to S/G levelpriorto FWPdischarge press reaching trip setpoint.Thefeedpumpspeedc ontrolsystemi s designed to maintain a D IP set point betweenMainSteam header pressure and Feedwater Header p ressure.This setpoint is ramped from40p sidat0%powe rto1 75 p sidat100%power.(seep age 5 ofthisatt a chment)Whena V I systemleaki s in serted , th e re sulting low ering VI header pres s c auses the FRV's to slowlyclose.As the y clo se ,FWPdischarge press increases.Thiscauses the S M/C F D IPtorapidly increaseandwas observed tobeashigha s400psid.TheFWP control systemre spond s to slowth eFWPspeedin a n attempt to maintain th e pro grammed D IP.In ev ery casee xcept a catastrophi c failur e wher e the V I header rapidly d epressurizesthisaction significantl ydelaysthe increaseinFWP dischar ge pressure.A catastrophic failure ofVIi snotconsistentwiththe conditionsestablishedinthestem of thi s question.Onefinaldat a point addedtotheend of thi s attachm ent is copyo fPIPM 87-0020 8 whi ch documentsa n actualloss of VIin1987wherethe reactor trippeddueto S/GLoLole vel afterappro x.5min.Thisisconsistent withwhat we ob served during our simulator validations.
{{#Wiki_filter:Attachment 1a                                                         Page I of 8 Common Question 53 After further investigation we propose that Question 53 be deleted due to no correct answer.
Question53asks,"WOOTFwillb e th e FIRSTtotripthere actor".LoLo S/Gleveli snotlistedin any of the proposed answers.Basedonthe informa tion aboveandthe attacheddo c umentation
The original assumption was due to the lowering VI (Instrument Air) pressure the S/G feed reg valves would fail closed resulting in increas ing feed pump discharge pressure to the point where the feed pumps wou ld trip on high discharge pressure. While the failur e mechani sm for the FRV 's is correct on a loss of air (closed), the resulting Reactor trip occurs due to low S/G level not feed pump discharge pressure. This was validated on our simulator with a loss of VI ramped in over a period of 5 to 10 minutes which resulted in the reactor tripping on low S/G level when VI press had degraded to approx. 40 psig.
, w efeelthi s q uestion should be delete dduetohavin g no correct answer.
While FWP discharge pressure did increase , the action of the FWP control system to maintain the program DIP at set point resulted in a decrease in FWP speed as the FRV' s closed. This action delays the increase in FWP discharge pressure. to the point where lowerin g S/G level will reach trip set point prior to increasing FWP discha rge press. In 4 different VI failure scenarios with varying leak sizes and ramp rates, the reactor tripped due to S/G level prior to FWP discharge press reaching trip set point.
Tier#Group#K/A#ImportanceRating 1 1 065 AA2.08 2.9 (Abilitytodetermineandint erpret thefollowingastheyappl ytotheLossof InstrumentAir:Failure mode sofair-operated equipment)ProposedQuestion:Common53BothUnitsareat100%powerwhen
The feed pump speed control system is designed to maintain a DIP set point between Main Steam header pressure and Feedwater Header pressure. This setpoint is ramped from 40 psid at 0 % powe r to 175 psid at 100% power. (see page 5 of this attachment)
:*MNS experiencesalossofVI.*VIHeaderpressureonbothunitsis30psigand continuestodecrease.WhichONE(1)ofthefollowingwillbeFIRSTtotripthe reactoranditsbasis?
When a VI system leak is inserted, the resulting lowering VI header pres s causes the FRV's to slowly close. As they close, FWP discharge press increa ses. This causes the SM/CF DIP to rapidl y increase and was observed to be as high as 400 psid. The FWP control sys tem responds to slow the FWP speed in an attempt to maintain the programmed DIP. In every case except a catastrophic failur e where the VI header rapidl y depressurizes this action significantly delays the increase in FWP discharge pressure. A catastrophic failure of VI is not consistent with the conditions established in the stem of this question.
A.OTDeltaTtripduetotheMSIVsfailingclosed.B.High-HighSGleveltripbecausethe FeedwaterRegVa lvesfailopen.C.TurbineTripduetoFeedPumpTripbecausethe FeedwaterRegValvesfailclosed.D.High pzrLeveltripduetotheChargingFlowControlValvefailingopenwithLetdownisolated.
One final data point added to the end of this attachment is copy of PIP M87-00208 which documents an actual loss of VI in 1987 where the reactor tripped due to S/G Lo Lo level after appro x. 5 min. This is consistent with what we observed during our simulator validations.
Proposed Answer: C Explanation (Optional)
Question 53 asks, " WOOTF will be the FIRST to trip the reactor". Lo Lo S/G level is not listed in any of the proposed answers. Based on the information above and the attached documentation , we feel this question should be deleted due to havin g no correct answer.
: A.Incorrect.IfMSIVsfailcloseditcouldcauseatriponLO-LOSGleveloronOTDTduetoTaverising.FRVsfailingwillcausethetrip significantly fasterthanMSIVfailure.Plausiblebecauseuntilarecentmod
,theMSIVs d idfailcloseonalossofVI.B.Incorrect.
Feedwaterregvalvesfailclosed,but plausible becausethisisthereactortrip mechanismiftheydidfailopen.
C.Correct.Reactortripwilloccurduetoturbinetrip.If fedwaterregvalvesfailclosed
,FeedPumpswilltriponhigh dischargepressure,whichdirectlycausesaturbinetrip
.D.Incorrect.Thiswouldcauseareactortrip,butata significantlylatertime than feedwaterregvalvefailure.Chargingflowcontrolvalvefailsopenandletdownisolatesonlossofair
,soPZRlevelwillberising TechnicalAP-22Background Reference(s)Document(p22Rev12)
AP/1/A/5500/22 Enclosure12p104106 ,Rev27 CF-CFp19Rev32 Proposed referencestobeprovidedto applicants during examination:
Learning Objective:QuestionSource
:CF-CFObj4 Bank#ModifiedBank
#New (Note changesorattach____parent)x Question History:LastNRCExam
---------------Question Cognitive Level:10CFRPart55 Content: Memory or Fundamental Knowledge Comprehension or Analysis55.415 55.43 x Comments:KAismatched because item evaluatesthefailuremodeofair operated equipmentthatwillcausea reactor tripRFAConcurs 4/24/08 DUKE POWER


==1.0 INTRODUCTION==
Tier #                          1 Group #                        1 K/A#                          065 AA2.08 Importance Rating              2.9 (Ability to determine and interpret the following as they apply to the Loss of Instrument Air: Failure modes of air-ope rated equipment)
Proposed Question:                    Common 53 Both Units are at 100% power when :
* MNS experiences a loss of VI.
* VI Header pressure on both units is 30 psig and continues to decrease.
Which ONE (1) of the following will be FIRST to trip the reactor and its basis?
A. OT Delta T trip due to the MSIVs failing closed.
B. High-High SG level trip because the Feedwater Reg Valves fail open .
C. Turbine Trip due to Feed Pump Trip because the Feedwater Reg Valves fail closed.
D. High pzr Level trip due to the Charging Flow Control Valve failing open with Letdown isolated.
Proposed Answer:                      C Explanation (Optional) :
A.        Incorrect. If MSIVs fail closed it could cause a trip on LO-LO SG level or on OTDT due to Tave rising. FRVs failing will cause the trip significantly faster than MSIV failure. Plausible because until a recent mod, the MSIVs did fail close on a loss of VI.
B.        Incorrect. Feedwater reg valves fail closed, but plausible because this is the reactor trip mechanism if they did fail open.
C.        Correct. Reactor trip will occur due to turbine trip. If fedwater reg valves fail closed , Feed Pumps will trip on high discharge pressure, which directly causes a turbine trip.
D.        Incorrect. This would cause a reactor trip, but at a significantly later time than feedwater reg valve failure. Charging flow control valve fails open and letdown isolates on loss of air, so PZR level will be rising Technical                            AP-22 Background


===1.1 Purpose===
Reference(s)            Document (p22 Rev 12)
Objective#1 MCGUIRE OPERATlONSTRAININGReferenceFig
AP/1/A/5500/22 Enclosure 12 p104 106, Rev 27 CF-CF p19 Rev 32 Proposed references to be provided to applicants during examination:
.7.1.The purpose of the Feedwater Pump Speed Control Systemisto provide a variable speed demand signaltothema in feedwater pump turbineswhichis programmed to maintain the Feedwater Regulating(FlowControl)Valvesin their opt imum throttling position.Thesystemalsooperatesthe FeedwaterPumpsinconjunctionwiththe FeedwaterControlValvestomaintainsteam generatorwaterlevelwithmaximumefficiency
Learning Objective:      CF-CF Obj 4 Question Source :      Bank#
.1.2 General DescriptionTheSteam GeneratorLevelControlSystemcomputesadesiredlevelthat isbasedonreactorpower
Modified Bank                (Note changes or attach
.Tomaintainthisdesiredlevel
                        #                _ _ __      parent)
,acontrolsignalis developed.Thesignalfunctionstopositionthe FeedwaterRegulatingValves
New              x Question History:        Last NRC Exam Question Cognitive        Memory or Fundamental Knowledge Level:
,andthuscontrolfeedflow
Comprehension or Analysis            x 10 CFR Part 55            55.41    5 Content:
, foreachofthesteam generators
55.43 Comments:
.TheMainFeedPumpSpeedControlSystemisdesignedto complementtheoperationoftheWaterLevelControlsystem
KA is matched because item evaluates the failure mode of air operated equipment that will cause a reactor trip RFA Concurs 4/24/08
.Itcomputesadesiredpumpspeedthatisbasedon auctioneeredHINCdeltaT (reactor power).Thissignalfunctionstoregulatethesteamflowtothemainfeedpumptu rbines,controllingtheirspeed.Variationofpumpspeedinthisfashionresults in:*Reducederosionof feedwater regulat ingvalveflowcontrolsurfaces
.*Improvedfeedregulat ingvalveflowcontrol(throttling) characteristics
.Variab lespeedmainfeedpumpsarefavoredbecausetheyaremore economical inlargeplants
.ThereislesslostenergywhenthespeedismatchedwiththedesiredDifferentialPressure(DeltaPorDP)
.Steamheaderpressure iscomparedtofeedpump dischargepressuregeneratinganActualDPsignal.TheDPsignaliscomparedtoaprogrammed setpoint determined from auctioneeredHINCdeltaT(reactorpower)and generatesthespeeddemand signal.Correctionsmaybeaddedforflowimbalancebetweenthepumps
.2.0 COMPONENT DESCRIPTION


===2.1 General===
DUKE POWER                                                 MCGUIRE OPERA TlONS TRAINING
Operation I Objective#6 IThesystemutilizesthreebasiccontrolloopstocontrolthefeedpump.The feedwater loop , the governorloop,andactuator loop.Theseloopsandtheir relationship areshownondrawing4
.1.Eachoftheseloopsisaproportionalplusintegralcontrolloop (P+I).Basicallythesearecascadingcontrolloopsinthatthe feedwatercontrolloopoutputistheinputtothe governorloopandtheoutputofthe governorloopistheinputtotheactuato rloop.Thisassumesthatthecontro lsareinauto.Theinputforthe feedwaterloopisthe feedwaterdemandsignalwhichisthe programmeddeltaPforthepowerlevelofthereactorassensedby auctioneeredhiNCloopdeltaT
.OP-MC-CF-IWEFORTRAINING PURPOSES ONL YPage9of57 REV.17 DUKE POWER MCGUIREOPERATlONSTRAINING


===7.3 Feedpump===
==1.0    INTRODUCTION==
ap Program w/AMSAC Avoidance (03/17/06) 205 2 00 1 95 190 18 5 1 80 175 17 0 165.1 60.155.15 0......14 5'8 1 4013 5 UJ en 130 Q.o 125 120 115 1 10.1 05 1 00 9 5 90.85 80.75 7 0 65.o 5 1 0 1 5 20 25 30 3 5 404 5 50 55 6 0 65707 5 80 85 90 95 100105 11 0 11 5 120 125%POWER OP-MC-CF-IWEFORTRAINING PURPOSES ONL Y Page49 of57 REV.17 AP/1 and 2/Al5500/022 (Loss of VI)STEP 13: PURPOSE:PrompttheoperatorstowatchS/GlevelsbecausetheCFcontrolvalvesfailclosedonalossofVI.IfS/Glevelscan
 
'tbecontrolled,theOperatorisdirectedtotripthereactor.
1.1    Purpose Objective # 1 Reference Fig. 7.1 . The purpose of the Feedwater Pump Speed Control System is to provide a variable speed demand signal to the main feedwater pump turbines which is programmed to maintain the Feedwater Regulating (Flow Control) Valves in their optimum throttling position. The system also operates the Feedwater Pumps in conjunction with the Feedwater Control Valves to maintain steam generator water level with maximum efficiency .
DISCUSSION:TheCFcontrolvalvesuse0-60#valveoperatingair.Dependingonthenatureoftheproblem w ithVIandconsideringlinelosses,etc
1.2    General Description The Steam Generator Level Control System computes a desired level that is based on reactor power . To maintain this desired level, a control signal is developed. The signal functions to position the Feedwater Regulating Valves , and thus control feed flow, for each of the steam generators. The Main Feed Pump Speed Control System is designed to complement the operation of the Water Level Control system . It computes a desired pump speed that is based on auctioneered HI NC delta T (reactor power) .
.,thesevalvescouldstartfailingat70#ormoreVIpressureasindicatedinthecontrolroom.Theoperating philosophyregardinglossofMain Feedwateratpoweristotripthereactor
This signal functions to regulate the steam flow to the main feed pump turbines, controlling their speed. Variation of pump speed in this fashion results in:
.ThiswillpreventchallengingtheLa-LaS/G automaticreactortr ipandwillresultinbetterinitialconditionsatthetimeofthemanualtrip.RefertoPIP2-M-87-0208wherea automaticreactortripoccurred5minafterlossofoffsitepowerdueto lossofVItotheCFvalves.IftheCFvalvesweretogettolessthan25%open(for30secormore)on3outof4S/Gs,anAMSACcouldalsobegenerated
* Reduced erosion of feedwater regulating valve flow control surfaces .
.Formostscenarios
* Improved feed regulating valve flow control (throttling) characteristics.
,it'slikelytheoperatorwillhavemanuallytrippedthereactorpriortothisoccurring.
Variable speed main feed pumps are favored because they are more economical in large plants. There is less lost energy when the speed is matched with the desired Differential Pressure (Delta P or DP).
REFERENCES
Steam header pressure is compared to feed pump discharge pressure generating an Actual DP signal. The DP signal is compared to a programmed setpoint determined from auctioneered HI NC delta T (reactor power) and generates the speed demand signal. Corrections may be added for flow imbalance between the pumps .
: PIP 2-M-87-0208Page15of46Rev12 MNSLOSSOFVIPAGENO.AP/1/N5500/228of120UNIT1Rev.27 A CTI ON/EX PECTEDRESPONSE 11.(Conti nued)m.ControlNC temperatureasfollows:*ThrottleNOflow.
2.0    COMPONENT DESCRIPTION 2.1 General Operation I    Objective # 6  I The system utilizes three basic control loops to control the feedpump. The feedwater loop, the governor loop, and actuator loop. These loops and their relationship are shown on drawing 4.1. Each of these loops is a proportional plus integral control loop (P+I). Basically these are cascading control loops in that the feedwater control loop output is the input to the governor loop and the output of the governor loop is the input to the actuato r loop. This assumes that the controls are in auto. The input for the feedwater loop is the feedwater demand signal which is the programmed delta P for the power level of the reactor as sensed by auctioneered hi NC loop delta T.
RESP ON S E N OT OBTAI N E D NOTE*KCtoNOHxflowshouldbeclosetoflowp riortolossof VI,sinceitisnormallycontrolledbymotoroperatedvalves.*KCtoNOHXflow indicationsfailslowdur ingalossofVI.Alternate indicationsareavailableatthefollowing locations ,ifneeded:*1A:1KCFT-5670(auxbldg,733+2',wes tofcolumnMM-54)*1B:1KCFT-5680(auxbldg
OP-MC-CF-IWE                  FOR TRAINING PURPOSES ONL Y                        REV. 17 Page 9 of 57
,733+4',westsideofcolumnJJ
 
-55).*IFNC temperature isgreaterthan 200°F ,THENmaintainKCflowtoNOHx greaterthan2000GPM
DUKE POWER                                                          MCGUIRE OPERA TlONS TRAINING 7.3       Feedpump ap Program w/AMSAC Avoidance (03/17/06) 205 200 195 190 185 180 175 170 165 .
.*ThrottleKCFlowtoNOHxas required.12.IFATANYTIMEVI pressure is less than70PSIG,THEN align B Train RN toSNSWPPER Enclosure 7 (Aligning B Train RN to Pond).CFControl ValveswillfailclosedonlowVIpressure
160 .
,whichmayresultinAMSACactuationandLoLo S/G level.13.Check S/G levels-AT PROGRAMMED LEVEL.IF S/G levels are going downinan uncontrolled manner, THEN perform the following:a.Tripreactor.
155 .
b.Continuewiththisprocedureastime allows.c.GOTO EP/1/N5000/E-0(ReactorT riporSafetyInjection)
150 .
.
    ..... 145 '
DUKE POWER Objective#4',C._.P6 6 b F'B"".MCGUIRE OPERA TJONS TRAINING The conditions which will result in both main feed pumps tripping:*if all three CBPs trip*ona Safety Injection actuation*on SIG Hi-Hi-Ievel (P-14)(83%)*onHiHiDog House level in either inner or outer Dog House (12 inches)The conditions which will result in tripping the associated main feed pump:*two out of three of its suction pressure switches are low (230 psig)*two out of three of its discharge pressure switches are high (1435 psig)*manual trip*two out of three low bearing oil pressure (7 psig)*two out of three low vacuum (14 inches Hg)*overspeed*fire lockout*thrust bearing wear (0.01 inch axial movement)The status of the suction and discharge pressure switches can be determined from the"Condensate 2 of 3 Logic Panel" located in the Turbine Building basement near the BB demineralizer room across for Column1F24(refertoDrawing7.3).When A(B)CF pump is tripped, solenoid valve 1CFSV0010 (1CFSV0040) is energized which closes A(B)CF Pump piston operated discharge check valveCF1(CF4).This will prevent flow reversals through the idle pump and prevent damage to the pump and piping due to waterhammer.TheCF pump suction (CM266 and CM272)and discharge (CF2 and CF4)valves are motor operated valves whichcanbe controlled using OPEN/CLOSE push buttons fromMC-10(refertoDrawing7.4).The A(B)CF pump turbine high and low pressure stop valves can not be raised (opened)until its suction valveCM266(CM272) and its discharge valveCF2(CF5)are open, as well as the CM Booster Pump recirc valve CM250andCF System Flush ValveCF124are closed.In additionCF124can not be opened unlessACFP suction valve(CM266)and discharge valve(CF2)are openORBCFP suction valve(CM272)and discharge valve(CF5)are open , and both CF pump turbines are tripped.OP-MC-CF-CF FOR TRAINING PURPOSESONLYPage19of107 REV.32 Problem Investigation Process McGuire Nuclear Station la Action Cate 0 Problem Identification Discovered TimelDate:
8     140
10:21 09116/19 87 Occurred TimelDate:
    ~ 135 UJ en 130 Q.
Unit(s)Affected: Unit 2 Mode I%Powe r UnitStatus R emarks Sy stem(s)Affected: CF EPB ND VI F e edwater Sy stem 6.9KVNormAu x&RCP Swgr P ower Sys ResidualHeatRemovalSystem Instrument A ir System Affected Equipment."::::: Equipment T i;g::.EcOde::::: M;!.nuf: eturer:'r_.I 0"_Location of Problem: Bld g: Column Line: EIev: Location Remarks: Method U sed to Discover Problem: Brief Problem
o 125 120 115 110 .
105 100 95 90 .
85 80 .
75 70 65 .
o 5 10 15 20 25 30 35 40 45 50 55 60  65  70 75 80 85 90 95 100 105 110 115 120 125
                                                  % POWE R OP-MC-CF-IWE                      FOR TRAINING PURPOSES ONL Y                                   REV. 17 Page 49 of 57
 
AP/1 and 2/Al5500/022 (Loss of VI)
STEP 13:
PURPOSE :
Prompt the operators to watch S/G levels because the CF control valves fail closed on a loss of VI. If S/G levels can't be controlled, the Operator is directed to trip the reactor.
DISCUSSION:
The CF control valves use 0 - 60# valve operating air. Depending on the nature of the problem with VI and considering line losses, etc., these valves could start failing at 70# or more VI pressure as indicated in the control room. The operating philosophy regarding loss of Main Feedwater at power is to trip the reactor . This will prevent challenging the La-La S/G automatic reactor trip and will result in better initial conditions at the time of the manual trip. Refer to PIP 2-M-87-0208 where a automatic reactor trip occurred 5 min after loss of offsite power due to loss of VI to the CF valves. If the CF valves were to get to less than 25% open (for 30 sec or more) on 3 out of 4 S/Gs, an AMSAC could also be generated . For most scenarios , it's likely the operator will have manually tripped the reactor prior to this occurring.
REFERENCES :
PIP 2-M-87-0208 Page 15 of 46                          Rev 12
 
MNS                                            LOSS OF VI                                  PAGE NO.
AP/1/N5500/22                                                                                    8 of 120 Rev. 27 UNIT 1 ACTI ON /EX PECTED RESPONSE                                  RESP ON SE NOT OBTAI NED 11 . (Continued)
: m. Control NC temperature as follows :
* Throttle NO flow .
NOTE
* KC to NO Hx flow should be close to flow prior to loss of VI, since it is normally controlled by motor operated valves.
* KC to NO HX flow indications fails low during a loss of VI. Alternate indications are available at the following locations, if needed :
* 1A: 1KCFT-5670 (aux bldg, 733 +2', west of column MM-54)
* 1B: 1KCFT-5680 (aux bldg, 733 +4', west side of column JJ-55).
* IF NC temperature is greater than 200°F, THEN maintain KC flow to NO Hx greater than 2000 GPM.
* Throttle KC Flow to NO Hx as required .
: 12. IF AT ANY TIME VI pressure is less than 70 PSIG, THEN align B Train RN to SNSWP PER Enclosure 7 (Aligning B Train RN to Pond).
CF Control Valves will fail closed on low VI pressure , which may result in AMSAC actuation and Lo Lo S/G level.
: 13. Check S/G levels - AT PROGRAMMED                         IF S/G levels are going down in an LEVEL.                                                    uncontrolled manner, THEN perform the following:
: a. Trip reactor.
: b. Continue with this procedure as time allows.
: c. GO TO EP/1/N5000/E-0 (Reactor Trip or Safety Injection) .
 
(\\\f>C~E:Nr~~ -    ' , C. _ . P6 6 bF' B " ".
DUKE POWER                                            MCGUIRE OPERA TJONS TRAINING Objective # 4 The conditions which will result in both main feed pumps tripping:
* if all three CBPs trip
* on a Safety Injection actuation
* on SIG Hi-Hi-Ievel (P-14)(83%)
* on Hi Hi Dog House level in either inner or outer Dog House (12 inches)
The conditions which will result in tripping the associated main feed pump:
* two out of three of its suction pressure switches are low (230 psig)
* two out of three of its discharge pressure switches are high (1435 psig)
* manual trip
* two out of three low bearing oil pressure (7 psig)
* two out of three low vacuum (14 inches Hg)
* overspeed
* fire lockout
* thrust bearing wear (0.01 inch axial movement)
The status of the suction and discharge pressure switches can be determined from the "Condensate 2 of 3 Logic Panel" located in the Turbine Building basement near the BB demineralizer room across for Column 1F24 (refer to Drawing 7.3).
When A(B) CF pump is tripped, solenoid valve 1CFSV0010 (1CFSV0040) is energized which closes A(B) CF Pump piston operated discharge check valve CF1 (CF4). This will prevent flow reversals through the idle pump and prevent damage to the pump and piping due to waterhammer.
The CF pump suction (CM266 and CM272) and discharge (CF2 and CF4) valves are motor operated valves which can be controlled using OPEN/CLOSE pushbuttons from MC-10 (refer to Drawing 7.4). The A(B) CF pump turbine high and low pressure stop valves can not be raised (opened) until its suction valve CM266 (CM272) and its discharge valve CF2(CF5) are open, as well as the CM Booster Pump recirc valve CM250 and CF System Flush Valve CF124 are closed. In addition CF124 can not be opened unless A CFP suction valve (CM266) and discharge valve (CF 2) are open OR B CFP suction valve (CM272) and discharge valve (CF 5) are open , and both CF pump turbines are tripped.
OP-MC-CF-CF                 FOR TRAINING PURPOSES ONL Y                    REV. 32 Page 19 of 107
 
la Problem Investigation Process McGuire Nuclear Station Action Cate 0 Problem Identification Discovered TimelDate:       10:21 09116/1987            Occurred TimelDate:
Unit(s) Affected:
Unit    Mode    %Power Unit Status Remarks 2         I System(s) Affected:
CF               Feedwater System EPB               6.9 KV Norm Aux & RCP Swgr Power Sys ND                Residual Heat Removal System VI                Instrument Air System Affected Equipment r _.I  0 Equipment Ti;g :   : . EcOde :   :   ::: M;!.nuf: eturer : ' ."::::: _
Location of Problem:
Bldg:             Column Line :               EIev:
Location Remarks:
Method Used to Discover Problem:
Brief Problem


== Description:==
== Description:==


APPROX.5 MIN UTESAFTERLOSSOF OFFSITE POWERTOUNITI , UNIT 2 E Detail Problem
APPROX. 5 MINUTES AFTER LOSS OF OFFSITE POWER TO UNIT I, UNIT 2 E Detail Problem


== Description:==
== Description:==


APPROX.5 MINUTESAFTERLOSSOF OFFSITE POWERTOUNITI ,UNIT2 EXPERIENCEDAREACTORTRIPDUETO S/G-LO LO LE VEL.FEEDWATER REGULATOR VALVES FAILED CLOS EDDUETOLOSSOFSTATIONAIR (VI)Other Units/Components/Sy stemslArea s Affected(Y,N,U):
APPROX. 5 MINUTES AFTER LOSS OF OFFSITE POWER TO UNIT I, UNIT 2 EXPERIENCED A REACTOR TRIP DUE TO S/G -LO LO LEVEL. FEEDWATER REGULATOR VALVES FAILED CLOS ED DUE TO LOSS OF STATION AIR (VI)
U Industrv Plants Affected(Y,N,U):
Other Units/Components/SystemslAreas Affected(Y,N,U): U Industrv Plants Affected(Y,N,U):
Immediate Corrective Actions: Immediate Corrective Action Documents 1 Work Orders: Problem Id entified B y: P roblem Entered B y: M-RGC M-SRG Date 0 911611987 0 911 6119 87 Screening Act ion Category:RootCause performed?051281200810
Immediate Corrective Actions:
:39Page1PIPNo: M-87-00208 Problem Investigation Process McGuire Nucl ear Station Significance C odes: OEPN o:OtherReportNos: M8 7-075-0 Event Codes: 88Convertoldpipdatat oNewPIPrelationaldatabase Screening Remarks: Assignments:
Immediate Corrective Action Documents 1 Work Orders:
Responsible Groups(s)forP roblem Evaluation: Respon sibleGroupf or Present Operability: Responsible Gro upforR eport Supp ort Info: Responsible Group forReportability: Responsible G roupforOver allPIPApp roval: M-SRG M-RGC N/A M-RGC M-SRG Safet y Review Regul atory Compliance Regu latory Compliance Indiv onfile Te am RJD4373 O rou M-SRG Dat e 0911611987 Present Operability Responsible G roup: M-RGC St atus: Closed Sys/Comp Operable?(Y,N,C,E,T): Y Requ ired Mod e: Comment s: R ep ortab ility Responsible Group: lndiv M-RGC Team St atus: Closed Grou M-RGC Date Problem Reportable(Y,N,E)
Date Problem Identified By:                                 M-RGC             0911611 987 Problem Entered By:                                    M-SRG             0911 611987 Screening Action Category: Root Cause performed?
: Y Reportable Per: Comments: LER , N/A SiRnature T voe Indiv Team Group Date Assigned To: M-RGCDueDate: Evalu ation Assigned To: M-RGC 09116119 87 Investigation Report: OS/28/200810:39 Page 2PIPNo:M-87
051281200810:39                                                   Page 1                                             PIP No: M-87-00208
-00208 Problem Investigation Process McGuire NuclearStation Respon s ible Group: ActDate: Inve stigator: Group: Due Date: 10/22/1987 Date DuetoV PorS ta.Mgr: Dat e Regulatoryo r AgencyRptD ue: Dat e Investigation ReportApproved: 10/29/I9 87 NR C Cause Code s: A3c3 A n ActionW as Perf orm ed With Insufficient Precision Report Support Info: Respon sible Group: I Signature TyPC Indiv St atus: Closed Team Group Date: Problem Evaluation I Event 1 88 188 Cause Cod e A3c3 N/ACaue Descripti on Old CauseCodea t McGuireNotApplicabl e Primary Ye s NoCauin g Group s V-UNK M-IAE Probl em Evalu ation From: Resp.Group: M-SRG OEDUComments: Stat us: Clos e d OEDBChecked: No Rem arks Comment s: Du e t otheelectronicuploadingofinformation, anymissingPIRinformationislocatedintheMaster Filea rea. Type Indiv Team Group Date Assigned To: M-SRG 09/19/1987 Due D ate: 10/16/1987 Corrective Actions No CorrectiveActionsforthi s PIP Final and Overall PIP Approval Resp onsibleGroup:M-SRG Status: C lose d Signatur e T ype Indi v Team Groun Dat e Assigned To: onfile M-SRG Appro ved B y: onfile M-SRG01/31/1990-AnySupplemental Concurrence Sign atures AboveDoNot Affect PIP Closure.OS/28/2008 10:39 Page 3 PIPN o: M-87-00208
***<I Problem Investigation Process McGuire Nuclear Statio" Microfilm RollI F rame: I Closure Document Tvpe Closure Document No Attachments Generi c Applicability Responsible Gr oup: G-OEAGOPIPNo: Statu s: Closed ks t l{A issessmen e rna r: Siznutur e TyDC Indiv Team Group Dale Assigned To: G-OEADueD ate: 0113111990 Approved By: G-OEA 09/23/199 3 Failure Prevention InvestigationNoFPIRecords for thisPIP.RemarksNoRemark sforthisPIP.
Maintenance Rule N o Maintenance Rul e RecordsforthisPIP.End oftheDocumentforPIPNo:Thest atu softhi s PIP i s:ThedurationofthisPIPwas: M-87-208 Closed868days[Duration=StatusDate(0 1/3 1/l 990)-Discov eryDate(09116/l987
)](Note:AllCorrecti v e Actionswereprinted inthisrep ort.)OS/28/200810
:39 Pa ge 4 PIP No: M-8 7-00208 Attachment 1 b Common Que stion 53 Page I of I.........The Post-e xam Item Analysis indicated that 7 of 12 applicants missed this question.*4 cho se"A"-clearl y wrongbecauset he MS IY sdonotfai l c lose d onloss ofYI*1 cho se"B"-clear l y wrongbecause theF RVs failed C L OSE D , not O PE N onloss of V I*2 chose" D"-plausible because thec harging flowvalve will fai l open and PZR level would eve ntua lly reachtherea ctor tr ip setpoin t.This distracteriswrong because the reactor will alreadybe tripped du e t oLoLo S/G levels pr ior to the PZR level reaching trip setpoint.N o applicant askedfor clarificationonthis ques t ion while takin g th e exa m.How did thi s question get through Validation?
Question53was revisedt o itsc urrent state around 2-26-08."C" distracter was validated onthe onthesimu lator where a loss of VId id r e sultinaF WP trip , turbinetrip, then r ea ctor tri p.Howe verwesimula tedacatastrophicbr eak on V I , where thepres sure dropped rapidly.Asa resulto f ourp o st-exam item analysis ,weranthes lowe r VIleakonthesimulator to more c loselyr e sembl e t he conditionsd e scri bed inth e question stem.That'swhen we realized thatt he FW P willn ot trip as describedonpa ge 1.During validation,six individuals took this vers ion of the que stion.*1 picked A*1 picked B*4 picked D Thevalidators admittedmemory decayon thefail ure mode ofva lves.Th er efore , we di d n'tqu e stion if"C" w as i n dee d c o rrec t.W e ha ve captur ed thi s le sson learned to ensure we validate written question scenariosonthesimulatorto more closely r e semble plant condition s in the question stem.
i----I'<'""NM'<tC C C C OJ OJ OJ OJ C/)C/)C/)C/).0.0.0.0 I!I o 0-0 M CI)>CI)...J I-0 0 I/)-N C'a I-CI)t: CI)o E 0 C'a 0 CI)N-(J)Q)E i=0 I/)......o o......o I/)o'<t o M o N o'<'"" o oI 2.9 065 AA2.08 1 1 Common 53 Tier#Group#KIA#Importance RatingRev.1tothe package (Ab ilitytodeterm ine and interpretthefollow ing a stheyapplytotheLossof Instrument A ir: Fa iluremodesofa ir-operated equipment)ProposedQuestion:BothUnitsareat100%
power when:*MNS experiencesalossofVI.*VI Headerpressureonbothunitsis30psigand continuestodecrease.WhichONE(1)ofthefollowingwillbeFIRSTtotripthe reactoranditsbasis?
A.OTDeltaTtripduetotheMSIVsfailingclosed.B.High-HighSGleveltripbecausethe FeedwaterRegValvesfailopen.C.TurbineTripduetoFeedPumpTripbecausethe FeedwaterRegValvesfailclosed.D.HighPzrLeveltripduetotheChargingFlowControlValvefailingopenwithLetdownisolated.ProposedAnswer:C Explanation (Optional):
A.Incorrect.IfMSIVsfailcloseditcouldcauseatriponLO-LOSGleveloronOTDTduetoTaverising
.FRVsfailingwillcausethetrip significantly fasterthanMSIVfailure.Plausiblebecauseuntilarecentmod
,theMSIVsdidfailcloseonalossofVI.
'".B.Incorrect.
Feedwaterregvalvesfailclosed,butplausiblebecausethisisthereactortrip mechanismiftheydidfailopen.
C.Correct.Reactortripwill occurduetoturbinetrip.If fedwaterregvalvesfailclosed,FeedPumpswilltriponhigh dischargepressure,wh ich directlycausesaturbinetrip.
D.Incorrect.Thiswouldcausea reactor trip ,butata significantlylatertime than feedwaterregvalvefailure.Chargingflowcontrolvalvefailsopenandletdownisolatesonlossofair,soPZRlevelwillberising TechnicalAP-22Background Reference(s)
Document(p22Rev12)
AP/1/A/5500/22 Enclosure12p104106,Rev27CF-CFp19Rev32 Proposed referencestobeprovidedto applicants during examination
:LearningObjective
:CF-CFObj4(Notechangesorattach parent)----Bank#ModifiedBank
#New X----QuestionSource
:QuestionHistory:LastNRCExam
---------------QuestionCognitive Level: Memory or Fundamental Knowledge ComprehensionorAnalysis X10CFRPart55 Content: 55.41 5 55.43 Comments:KAismatchedbecauseitem evaluatesthefailuremodeofairoperated equipmentthatw illcausea reactor tripRFA Concurs 4/24/08 Attachment la Common Question 53Page1 of8Afterfurther investigationweproposethatQuestion53bedeletedduetonocorrect answer.TheoriginalassumptionwasduetotheloweringVI(InstrumentAir)pressurethe S/Gfeedregvalveswouldfailclosedresultingin increasingfeedpumpdischargepressuretothepointwherethefeedpumpswouldtriponhighdischargepressure.Whilethefailure mechanismforthe FRV'siscorrectonaloss ofair(closed)
, the resultingReactortripoccursduetolow S/Glevelnotfeedpumpdischargepressure.Thiswasvalidatedonour simulatorwithaloss ofVIrampedinoveraperiod of5to10minuteswhichresultedinthereactortrippingonlow S/GlevelwhenVIpresshaddegradedtoapprox.40psig.WhileFWPdischarge pressuredidincrease,theaction oftheFWPcontrolsystemtomaintaintheprogram D IPatsetpointresultedinadecreaseinFWPspeedasthe FRV'sclosed.ThisactiondelaystheincreaseinFWPdischargepressure.tothepointwhere lowering S/GlevelwillreachtripsetpointpriortoincreasingFWPdischargepress.In4differentVIfailurescenarioswithvaryingleaksizesandramprates,thereactortrippeddueto S/GlevelpriortoFWPdischargepressreachingtripsetpoint.Thefeedpumpspeedcontrolsystemisdesignedto maintain a D IPsetpointbetweenMainSteamheaderpressureand FeedwaterHeaderpressure.Thissetpointisrampedfrom40psidat0%powerto175psidat100%power.(seepage5 ofthisattachment)WhenaVIsystemleakisinserted,the resultingloweringVI headerpresscausesthe FRV'stoslowlyclose.Astheyclose,FWPdischargepressincreases.Thiscausesthe SM/CF D IPtorapidlyincreaseandwasobservedtobeashighas400psid
.TheFWPcontrolsystemrespondstoslowtheFWPspeedinanattemptto maintain the programmed DIP.Ineverycaseexcepta catastrophicfailurewheretheVIheaderrapidly depressurizesthisaction significantlydelaystheincreaseinFWP dischargepressure.A catastrophic failure ofVIisnot consistentwiththeconditions establishedinthestem ofthisquestion
.Onefinaldatapointaddedtotheend ofthisattachmentiscopy ofPIPM87-00208whichdocumentsanactualloss ofVIin1987wherethereactortrippeddueto S/G LoLolevelafterapprox.5min
.Thisis consistentwithwhatweobservedduringour simulator validations.Question53asks,"WOOTFwillbetheFIRSTtotripthereactor".LoLo S/Glevelisnotlistedinany of the proposedanswers.Basedonthe informationaboveandthe attached documentation,wefeelthisquestionshouldbedeleteddueto havingnocorrect answer.
Attachment1b Common Question 53Page1 of 1 The Post-exam Item Analysis indicated that7of12 applicants missed this question.*4 chose"A"-clearl y wrong becausetheMSIVsdonotfailclosedonloss of VI*1chose"8"-clearlywrong becausetheFRVsfailedCLOSED
,notOPENonloss of VI*2chose"D"-plausible because th e charging flow valvewillfailopenandPZRlevelwoulde ventuallyreachthereactortripsetpoint.This distracteriswrongbecausethereactorwillalreadybetrippedduetoLoLoS
/OlevelspriortothePZRlevelreachingtripsetpoint.Noapplicantaskedfor clarificationonthisquestionwhiletakingtheexam
.How did this question get through Validation?Question53wasrevisedtoitscurrentstatearound2-26-08."C" distracter was validatedontheonthe simulatorwherealoss ofVIdidresultinaFWPtrip
,turbinetrip,thenreactortrip.Howeverwe simulated a catastrophicbreakonVI ,wherethepressuredroppedrapid ly.Asaresult of our post-examitemanalysis
,werantheslowerVIleakonthe simulator tomoreclosely resembletheconditionsdescribedinthequestionstem.
That'swhenwerealizedthattheFWPwillnottripa sdescribedonpage1.
During validation, six individuals took this version of the question.*1 picked A*1 picked 8*4 picked DThevalidatorsadmitted memorydecayonthefailuremode of valves.Therefore , we didn't question if"C"wasindeedcorrect.
We have capturedthislesson learned to ensure we validate written question scenarios on the simulator to more closely resemble plant conditions in the question stem.
Documentation of Post Exam Simulator Data for Common Question#53 The simulatorwasset up with a standard 100%MOC snap.A malfunction was inserted consisting of ramped 75%break of the Service Building VI (Instrument Air)header.Over the first30sec,VI pressure falls fairly rapidlytoa value of approximately 65 PSIG.At this point the FRV demand begins to increase indicating that the actual valve position is closing due to the lower VI header pressure.The result of the FRV's going closed shows that the FW header/Main Steam header DIP begins to increase due to the resulting increase in FWP discharge pressure.This resultsina control action by the FWPT Speed control system lower FWPT speed in an attempt to control the DIP at setpoint.These values are shown on the attached graph.At approx.65 psig the rateofVI pressure decrease slows which would be consistent with the automatic response of the standby VI compressors starting/loading attempting to restore VI pressure.Over the next 3 minutes, VI pressure continues to lower resulting in further closure of the FRV's thereby further reducingfeedflowto the S/G's.FWP discharge pressure continues to increase as the FRV's close but the FWPT control system is continuing to decrease the FWPT speed which dampens and slows this effect the to the point where the reductionoffeedflowto the S/G's resultsinalowlevel trip of the Reactor at 17%level approximately


===4.5 minutes===
Problem Investigation Process McGuire Nuclear Station Significance Codes:
into the failure with VI pressure indicating about 30PSIG.Just prior to the trip, FWP discharge pressure peaks at approx.1400 PSIG whichiswell below the trip setpointof1435 PSIG.BelowI have pasted Excel Spreadsheet trends converted from the Simulator Data Recorder depicting the behavior of S/G level, FWP Discharge pressure, and VI Header pressure during the malfunction described above.TheXAxisis showing the Time in seconds.I have also attached anExcelfileto this communication with the raw data of the selected parameters and additional trends created from this data.
OEPNo:
Steam Generator Level 70 60 50;;40->'"..J.9 e'" 30 c'" o E'"20 10 ,'I 50 100 150 200 2SO 300 3 a-10 TimeFWPTDischargePressure
Other Report Nos: M87-075-0 Event Codes:
88      Convert old pip data to NewPIP relational database Screening Remarks:
Assignments:
Responsible Groups(s) for Problem Evaluation : M-SRG                Safety Review Respon sible Group for Present Operability:    M-RGC                Regulatory Compliance Responsible Group for Report Support Info:    N/A Responsible Group for Reportability:            M-RGC                Regulatory Compliance Responsible Group for Overall PIP Approval:    M-SRG Indiv                        Team                        Orou  Date onfile                      RJD4373                    M-SRG 0911611987 Present Operability Responsible Group:            M-RGC            Status: Closed Sys/Comp Operab le? (Y,N,C,E,T): Y Required Mode:
Comment s:
lndiv                        Team                        Grou  Date M-RGC R eportab ility Responsible Group :          M-RGC            Status: Closed Problem Report able(Y,N,E):            Y Reportable Per:
Comments:
LER, N/A SiRnature Tvoe                Indiv                      Team                        Group Date Assigned To:                                                                          M-RGC Due Date:
Evaluation Assigned To:                                                                M-RGC 0911611987 Investigation Report:
OS/28/200810:39                                                        Page 2                            PIP No: M-87-00208
 
Problem In vestigation Process McG uire N uclear Station Responsible Group:                                Act Date:
Investigator:                            Group:
Due Date:                                          10/22/1987 Date Due to VP or Sta. Mgr:
Date Regulatory or Agency Rpt Due:
Date Investigation Report Approved:                10/29/ I987 NRC Cause Codes:
A3c3                  An Action Was Performed With Insufficient Precision Report Support Info:
Re spon sible Grou p:                              St atus: Closed ISignature TyPC                  Indiv                        Team                        Group              Date      :
Problem Evaluation IEvent          Cause Code Cau e Description                                Primary      Cau ing Groups 188              A3c3    Old Cause Code at McGuire                        Yes          V-UNK 188              N/A    Not Applicable                                  No            M-IAE Problem Evaluation From: Resp. Gro up: M -SRG                Status: Closed      OEDB Checked: No OEDU Comme nts:
Remarks Comments:
Due to the electronic up loading of information, any missing PIR information is located in the Master File area.
' SiJ~ n at u re Type            Indiv                        Team                        Group              Date Assigned To :                                                                            M-SRG              09/19/1987 Due Date:                      10/16/19 87 Corrective Actions No Corrective Actions for this PIP Final and Overall PIP Approval Respo nsible Gro up: M- SRG                        Status : C losed Signature T ype              Indiv                          Team                        Groun              Date Assigned To:                  onfile                                                      M-SRG Approved By:                  onfile                                                      M-SRG              01/31/1990 Any Supplemental Concurrence Signatures Above Do Not Affect PIP Closure.
OS/28/2008 10:39                                                        Page 3                                            PIP No: M-87-0020 8
 
*  **  <I Problem Investigation Process McGuire Nuclear Statio" Microfilm RollI Frame: I Closure Document Tvpe                  Closure Document No Attachments Generic Applicability Responsible Group: G-OEA                          Status: Closed GO PIP No:
Aissessmen t l{ernar ks :
Siznuture TyDC                Indiv                        Team                          Group            Dale Assigned To:                                                                              G-OEA Due Date:                    0113111990 Approved By:                                                                              G-OEA            09/23/199 3 Failure Prevention Investigation No FPI Records for this PIP.
Remarks No Remarks for this PIP.
Maintenance Rule No Maintenanc e Rule Record s for this PIP.
End of the Document for PIP No:        M-87-208 The status of this PIP is:              Closed The duration of this PIP was:          868 days [Duration = Status Date (0 1/31/l 990 ) - Discovery Date (09116/l 987 )]
(Note: All Corrective Actions were printed in this report.)
OS/28/200810:39                                                      Page 4                                              PIP No: M-8 7-00208
 
                                                                                              .. .. .. _.~.:. .. . b                                                                    Page I of I Common Question 53 The Post-exam Item A n a lysis indicated that 7 of 12 applicants missed this question.
* 4 chose "A" - clea rly wrong becau se the MS IYs do not fai l closed on loss of YI
* 1 chose " B" - clearly wro ng becau se the FRVs failed CLOSED, not OPEN on loss of VI
* 2 chose " D"- plaus ible because the charging flow valve will fai l op en and PZR level would eventually reach the rea ctor trip setpo int. This di stracter is wrong because the reactor will alrea dy be tripped du e to Lo Lo S/G levels prior to the PZR level reaching trip setpoint.
No applicant as ked for clarification on th is question while taking the exam.
How did this question get through Valid a tion ?
Ques tio n 53 was revised to its current state aro und 2-26-08 . "C" dist racter was va lida ted on the on the simulator whe re a loss of VI d id result in a FWP trip, tur bine tr ip, then reactor tri p. However we simulated a catas trophic break on VI, whe re the pressure dropp ed rap idl y.
As a resul t of our post- exam item analys is, we ran the slower VI leak on the si mulator to more closely resembl e the co nditio ns described in th e questi on stem. Th at' s whe n we real ized that the FWP wi ll not trip as describ ed on pa ge 1.
During validation, six individuals took this version of the question.
* 1 picked A
* 1 picked B
* 4 picked D Th e va lida tors admitted m em ory dec ay on the failure mode of va lves. Th erefore, we didn' t qu estion if "C" was indeed correct.
W e have captured this lesson learned to ensure we va lid a te written question scena r ios on th e sim u la to r to more clo sel y r esemble plant conditions in the question stem .
 
i
              ----I
              '<'""NM'<t
              ~~~~
C    C    C    C OJ  OJ    OJ  OJ C/)  C/)  C/)  C/)
              .0  .0    .0  .0 I!              I o
0
                                              - 0 M
CI)
CI)
...J
-I-0 C'a I-CI) t:
CI) 0 I/)
N o
E                                              0 0
C'a                                            N CI)
(J)                                                          Q)
E i=
0 I/)
o o
oI/) o            o            o o    o        o-e--
          '<t          M            N '<'""
I
 
Tier #                          1 Group #                        1 KIA #                          065 AA2.08 Importance Rating              2.9 Rev. 1 to the package (Ability to determ ine and interpret the follow ing as they apply to the Loss of Instrument Air: Failure modes of air-operated equipment )
Proposed Question:                      Common 53 Both Units are at 100% power when:
* MNS experiences a loss of VI.
* VI Header pressure on both units is 30 psig and continues to decrease.
Which ONE (1) of the following will be FIRST to trip the reactor and its basis?
A. OT Delta T trip due to the MSIVs failing closed.
B. High-High SG level trip because the Feedwater Reg Valves fail open.
C. Turbine Trip due to Feed Pump Trip because the Feedwater Reg Valves fail closed.
D. High Pzr Level trip due to the Charging Flow Control Valve failing open with Letdown isolated.
Proposed Answer:                        C Explanation (Optional):
A.        Incorrect. If MSIVs fail closed it could cause a trip on LO-LO SG level or on OTDT due to Tave rising . FRVs failing will cause the trip significantly faster than MSIV failure. Plausible because until a recent mod , the MSIVs did fail close on a loss of VI.                                        '".
B.        Incorrect. Feedwater reg valves fail closed, but plausible because this is the reactor trip mechanism if they did fail open.
C.        Correct. Reactor trip will occur due to turbine trip. If fedwater reg valves fail closed, Feed Pumps will trip on high discharge pressure, which directly causes a turbine trip.
D.        Incorrect. This would cause a reactor trip , but at a significantly later time than feedwater reg valve failure. Charging flow control valve fails open and letdown isolates on loss of air, so PZR level will be rising Technical                              AP-22 Background
 
Reference( s)          Document (p22 Rev 12)
AP/1/A/5500/22 Enclosure 12 p104 106, Rev 27 CF-CF p19 Rev 32 Proposed references to be provided to applicants during examination:
Learning Objective :    CF-CF Obj 4 Question Source :      Bank#
Modified Bank                (Note changes or attach
                        #                - - - - parent)
New                X Question History:      Last NRC Exam Question Cognitive        Memory or Fundamental Knowledge Level:
Comprehension or Analysis            X 10 CFR Part 55            55.41    5 Content:
55.43 Comments:
KA is matched because item evaluates the failure mode of air operated equipment that will cause a reactor trip RFA Concurs 4/24/08
 
Attachment la                                                        Page 1 of8 Common Question 53 After further investigation we propose that Question 53 be deleted due to no correct answer.
The original assumption was due to the lowering VI (Instrument Air) pressure the S/G feed reg valves would fail closed resulting in increasing feed pump discharge pressure to the point where the feed pumps would trip on high discharge pressure. While the failure mechanism for the FRV's is correct on a loss of air (closed), the resulting Reactor trip occurs due to low S/G level not feed pump discharge pressure. This was validated on our simulator with a loss of VI ramped in over a period of 5 to 10 minutes which resulted in the reactor tripping on low S/G level when VI press had degraded to approx. 40 psig.
While FWP discharge pressure did increase, the action of the FWP control system to maintain the program DIP at set point resulted in a decrease in FWP speed as the FRV's closed. This action delays the increase in FWP discharge pressure. to the point where lowering S/G level will reach trip set point prior to increasing FWP discharge press. In 4 different VI failure scenarios with varying leak sizes and ramp rates, the reactor tripped due to S/G level prior to FWP discharge press reaching trip set point.
The feed pump speed control system is designed to maintain a DIP set point between Main Steam header pressure and Feedwater Header pressure. This setpoint is ramped from 40 psid at 0 % power to 175 psid at 100% power. (see page 5 of this attachment)
When a VI system leak is inserted, the resulting lowering VI header press causes the FRV's to slowly close. As they close, FWP discharge press increases. This causes the SM/CF DIP to rapidly increase and was observed to be as high as 400 psid. The FWP control system responds to slow the FWP speed in an attempt to maintain the programmed DIP. In every case except a catastrophic failure where the VI header rapidly depressurizes this action significantly delays the increase in FWP discharge pressure. A catastrophic failure of VI is not consistent with the conditions established in the stem of this question .
One final data point added to the end of this attachment is copy of PIP M87-00208 which documents an actual loss of VI in 1987 where the reactor tripped due to S/G Lo Lo level after approx. 5 min. This is consistent with what we observed during our simulator validations.
Question 53 asks, "WOOTF will be the FIRST to trip the reactor". Lo Lo S/G level is not listed in any of the proposed answers. Based on the information above and the attached documentation, we feel this question should be deleted due to having no correct answer.
b                                                                Page 1 of 1 Common Question 53 The Post-exam Item Analysis indicated that 7 of 12 applicants missed this question.
* 4 chose "A" - clearly wrong because the MSIVs do not fail closed on loss of VI
* 1 chose " 8 " - clearly wrong because the FRVs failed CLOSED , not OPEN on loss of VI
* 2 chose " D"- plausible because the charging flow valve will fail open and PZR level would eventually reach the reactor trip setpoint. This distracter is wrong because the reactor will already be tripped due to Lo Lo S/O levels prior to the PZR level reaching trip setpoint.
No applicant asked for clarification on this question while taking the exam.
How did this question get through Validation?
Question 53 was revised to its current state around 2-26-08. "C" distracter was validated on the on the simulator where a loss of VI did result in a FWP trip, turbine trip, then reactor trip. However we simulated a catastrophic break on VI, where the pressure dropped rapidly.
As a result of our post-exam item analysis, we ran the slower VI leak on the simulator to more closely resemble the conditions described in the question stem. That's when we realized that the FWP will not trip as described on page 1.
During validation, six individuals took this version of the question.
* 1 picked A
* 1 picked 8
* 4 picked D The validators admitted memory decay on the failure mode of valves. Therefore, we didn 't question if "C" was indeed correct.
We have captured this lesson learned to ensure we validate written question scenarios on the simulator to more closely resemble plant conditions in the question stem.
 
Documentation of Post Exam Simulator Data for Common Question # 53 The simulator was set up with a standard 100% MOC snap. A malfunction was inserted consisting of ramped 75% break of the Service Building VI (Instrument Air) header. Over the first 30 sec, VI pressure falls fairly rapidly to a value of approximately 65 PSIG. At this point the FRV demand begins to increase indicating that the actual valve position is closing due to the lower VI header pressure. The result of the FRV's going closed shows that the FW header/Main Steam header DIP begins to increase due to the resulting increase in FWP discharge pressure. This results in a control action by the FWPT Speed control system lower FWPT speed in an attempt to control the DIP at setpoint. These values are shown on the attached graph. At approx. 65 psig the rate of VI pressure decrease slows which would be consistent with the automatic response of the standby VI compressors starting/loading attempting to restore VI pressure. Over the next 3 minutes, VI pressure continues to lower resulting in further closure of the FRV's thereby further reducing feed flow to the S/G's. FWP discharge pressure continues to increase as the FRV's close but the FWPT control system is continuing to decrease the FWPT speed which dampens and slows this effect the to the point where the reduction of feed flow to the S/G's results in a low level trip of the Reactor at 17% level approximately 4.5 minutes into the failure with VI pressure indicating about 30PSIG. Just prior to the trip, FWP discharge pressure peaks at approx. 1400 PSIG which is well below the trip setpoint of 1435 PSIG.
Below I have pasted Excel Spreadsheet trends converted from the Simulator Data Recorder depicting the behavior of S/G level, FWP Discharge pressure, and VI Header pressure during the malfunction described above. The X Axis is showing the Time in seconds. I have also attached an Excel file to this communication with the raw data of the selected parameters and additional trends created from this data.
 
Steam Generator Level 70 60 50
;; 40
..J
  ~
:-bsgnwl(1)
:-bsgnwl(1)
----.bsgnwl(2)bsgnwl(3),-_.bsgnwl(4)ieoo I 1400 , , 1200 til 1000 til e c, s: (,)800-til 0 f-c,u, 600 400 200 a a50100150 Time200250300350 I-pet 5080**...pcf 5090 Inst.AirHdr.Press 120__.....-............, 100 iii 80 Ul e ll.Ql"0 co Ql J: 60 I-pvi 5060<1: '" E 2 10 40 E: 20 350 300 250 200 150 100 50 O!.----------------...,..--------l o Time Attachment 2 SRO Question 77 DuringthePostExamItemAnalysi swehave determined that Question77hastwo correctan swerswithDi st racter"C"beinga subset of the Correct Answer"0".Dueto thi s determin ation w e proposethatboth"C"and'0" be accept ed a s correct.Inthisquestion the candid ate is asked to determin ealeakratefromtheK C (Component Cooling)System.The operatorisgi ven KC surgetanklevelsforT=OandT-+5min alongwitha copy oftheKCSurgetanklevelcurv efromtheData Book.Correctly performed ,theleakrateis determinedtobe approximately100GPM.Alsointhestem of the question the operato r is advised t hat"Operato rshavebeen dispatched to initiateYM makeuptoth e KC surge t ank",butarenottoldthatthis makeup has actually been established.Theinitialle velinthe surgetank is6.5ft.The candidateisthen askedto d etermine"the required actionand procedure use r equiredinAP/2l , Loss ofKCorK C SystemLeakage".Per paragraph 7 of Appendix E of N UREG-I0 21page2 of 6 which is part of the briefing givenpr iortotheexam, the candidate saregiventhe following instructions,"When answeringaque stion,donotmake assumptions regarding conditionsthatarenot specifiedinthe question unless they occurasacon sequence of other conditionsthatare statedinth e question.Similarly,you shouldassumethatno operator action s have been taken , unless the stem oftheque stionorthean swer choices sp ecificallystate otherwise.Finally, answerallque stionsbasedon actual plant operation , procedure sorthe answer choices specifically stated otherwise".Withthi s d i rectioninm ind the candid ate can corr ectly assumethatYM makeupisnot initially align ed but within a reason able period oftimeitwillbe
.9 e    30
.(Per the Time Critical Actions for our plant this should occur within10min of dispatch)Accordingtothe background documentforAP-21pg10 of23 ,"Per engineering
                                                                ----. bsgnwl(2)
, YM makeup should be sufficienttokeepupwiththe FSAR design basi s l eak of50GPM".After d eterminin gthata100 GPMleakexists, even withYMmakeup aligned the candidate would r ea sonablycometoth e conclu sionthatKCsurget ank levelwould continue to decrea se.Procedurallyw e would alignthe Nuclear Service Wat er as sured makeup ifYM wasnot sufficientt okeepup withtheleakbutthe candidatesaretoldtonota ssume an y operator act ions not stated,ther eforeitisrea sonableforthe candidate to assumethat thishasnot andwillnot happen unle ss otherwise stated.Procedural guidanceperAP-21 direct sthatonceithasbeen determined that aleakexists operator s b e di sp atched earlyto initiateYMmak eupperStep 11.The procedure then checks surget ank le vel greaterthan3 ftwhichforthe scenario givenit shouldbefo r the fir st passthruth is step.The operator is t hen dire cted to check the"sum ofbothtrains'KCsurget ank le vel drop s LESS THANOREQ UALTO0.10 FT/MIN".If true,which fortheleakrate calculat ed, it wouldbe,thecre w i s directedtoSt ep 20 which will Isolat e "A" K C train f rom" B" K C tr ain.Thisactionisconsistent withtheactions statedinth e Correct answer" D" makingita validcorrectanswer.Onceagai n , a s sumin g n o operator actionha s taken place , thesurgetan klevelswill continuetod ecreaseuntilthey reach a l evel of 2 ft.Atthisp oint the"foldout" page would direct th e operatortoisolate the affectedtra inPEREne.2.Thisactio n i s statedinDi stracter"C" and sinc e thestemdoes n ot refer t o the"First" o r"Next" actiontaken, this action i s actually a subset o f" 0" and therefore a CO ITec t a nswer.Basedonthediscussion aboveandtheattachedreferences,werecommendth at both"C" and" 0" beaccepted as correctanswers.
  '"c                                                                bsgnwl(3) o'"                                                            ,-_. bsgnwl(4)
.ES-401 A-+1 Hhrnl'r'ltPa ,j v 3SampleWrittenExaminationFormES-401-5 Question WorksheetExaminationOutline reference: Level RO SROProposedQuestion:SRO77 Tier#1----Group#1 KIA#(026)G2.1.25ImportanceRating 4.2----Page197 of271RevFinal
E
--..ES-401 Initial conditions:
~'"    20 10
Time=0 minutes Sample Written Examination Question Worksheet P OJ<'-'i Form ES-401-5*Unit1isat 100%power.*"A" Train KG pumps are running.*Operators have been dispatched to initiate YM makeuptotheKG Surge Tank.*"A"KG Surge Tanklevelis6.5 ft.*"B" KG Surge Tanklevelis6.5 ft.Current conditions:
        'I
Time=5 minutes*"A" KG Surge Tanklevelis5.6 feet*"B"KG Surge Tanklevelis6.4feet.
      -10 50  100 150 Time 200      2SO        300 3  a FWPT Discharge Pressure ieoo  I 1400 ,
WhichONE(1)ofthe following describes(1)the approximate KC system netleakrate ,and(2)the required action and procedure use requiredinAP/21, LossofKGorKG System Leakage?(Reference Provided)A.B.G.D.(1)(2)(1)(2)(1)(2)(1)(2)50 GPM Isolate KC Non-Essential Headers in accordance with Enclosure 2.50GPM Isolate"A"KGtrainfrom"B"KCtrain.
1200 til 1000 til e
100 GPM Isolate KG Non-Essential Headers in accordance with Enclosure 2.100 GPM Isolate"A"KGtrainfrom"B"KGtrain.
c, s:
Proposed Answer: 0 Explanation (Optional):Page19 8 of271 Rev Final ES-401Sample Written Examination Question Worksheet PC\5 c 5 Form ES-401-5Dis correct per conditions.
0
Applicant must interpretcurveand determine theleakrate indicationsbasedonlevel decreases A incorrect becauseleakrateiswrong (1/2ofactual,as interpreted by curve.)Also , action is incorrect , as procedurewilld irect splittingtrainsfor indication shown B incorrect becauseleakrateis incorrect.
(,)
Plausible because action is correct C incorrect because procedure use i s incorrect.
til  800 -                                                 I-pet      5080
Approximately 0.1 feet/minute
                                                              ** ... pcf 5090 f-c,
, performstep20tosplittrainsAP/21Step20Rev9 Technical Reference(s):(Attachifnot previously provided)-----------AP/21Basis DocumentRev3 Proposed referencestobe provided to applicants during examination:
~
OP/1lA/5100/22 Enclosure4.3Curve 7.31 Learning Objective:
u, 600                ------ -- - ----~
Question Source: NoneBank#Modified Bank#New x (Note changesorattach parent)Question History: Question Cognitive Level:LastNRCExam Modified from 2007NRCexam 78 Memory or Fundamental Knowledge Comprehension or Analysis x10CFRPart5555.41 Content:55.435---Comments: KA matched becauseuseofacurveisrequiredand interpretation of that curve i s required to determineKC(CCW)leakrate
400 200 a
.SROlevel because assessment of Page 199of271 Rev Final
a  50 100 150        200      250        300 350 Time
,.ES-401SampleWritten Examination Question WorksheetFormES-401-5 conditionsbasedon available indications,andselectionof procedures (attachments)isrequired RFA Concurs 4/17/08Page200 of271RevFinal 3.Foraninitialexamination
 
,thenominaltimelimitforcompletingtheexaminationis6hoursfortheROexam
Inst. Air Hdr. Press 120 ~ __.....- ......  ~=~~~                  ~                    ......,
;3hoursforthe25-question
100 iii Ul  80 e
,SRO-onlyexam;8hoursforthecomb inedRO/SROexam;and4hoursfortheSROexamlimitedtofuelhandling.Notifytheproctorifyouneedmoretime.Forarequalificationexamination,thetimelim itforcomplet ingbothsect ionsoftheexaminationis3hours.Ifbothsectionsareadministeredinthesimulatorduringasingle3-hourperiod,youmayreturntoasectionoftheexaminationthatyoualreadycompletedorretainbothsectionsoftheexaminationuntiltheallottedtimehasexpired.
ll.
4.Youmaybringpens
~
,pencils,andcalculatorsintotheexaminationroom
Ql "0
;however , programablememoriesmust be erased.Useblackinktoensure legible copies;darkpencilshouldbeusedonly ifnecessarytofacilitatemachinegrading
co Ql J:
.5.Printyournameintheblankprovidedontheexaminationcoversheet andtheanswersheet.Youmaybeaskedtoprovidetheexaminerwithsomeformofpos itive identification.
~    60                                                                            I-pvi 5060 1:
6.Markyouranswersontheanswersheet provided ,anddonotleaveanyquestion blank.Useonlythepaperprovided.anddonotwriteonthebacksideofthepages
E 2
.Ifyouareusinginkanddecidetochangeyouroriginalanswer,drawasinglelinethroughtheerror,enterthedesiredanswer,and initialthechange.Ifyouare recording youranswersona machine-gradableformthatoffersmorethanfouranswerchoices(e.g.,"a"through"e"),becarefultomarkthecorrectcolumn.
10 40 E:
7.Ifyouhaveanyquest ions concern ingtheintentortheinitialconditionsofaquestion
20 O!.-- - - - - - ---- - ----...,..-- -                            - - ---l o          50      100  150            200        250    300        350 Time
, do nothesitatetoaskthembeforeansweringthequestion.Notethatquestionsaskedduringtheexaminationaretakenintoconsiderationduringthegrad ing processandwhenreviewingapplicantappeals
 
.AskquestionsoftheNRCexaminerorthedesignatedfacility instructor only.Adictionaryisava ilableifyouneedit.Whenansweringaquestion,do notmakeassumptionsregardingconditionsthatarenotspecified inthequestionunlesstheyoccurasa consequenceofotherconditionsthatarestatedinthequestion
Attachment 2 SRO Question 77 During the Post Exam Item Analysi s we have determined that Question 77 has two corr ect answers with Distracter "C" being a subset of the Correct Answer "0". Due to this determination we propose that both "C" and ' 0" be accepted as correct.
.Forexample
In this que stion the candidate is asked to determine a leak rate from the KC (Component Cooling) System . The operator is given KC surge tank levels for T=O and T- +5 min along with a copy of the KC Surge tank level curv e from the Data Book. Correctly performed, the leak rate is determined to be approximately 100 GPM. Also in the stem of the question the operator is advised that "Operators have been dispatched to initiate YM makeup to the KC surge tank", but are not told that this makeup has actually been established. The initial level in the surge tank is 6.5 ft. The candidate is then asked to determine "the required action and procedure use required in AP/2l , Loss of KC or KC System Leakage".
,youshouldnotassumethatanyalarmhasactivatedunlessthequest ionsostatesorthealarmisexpectedtoactivateasaresultoftheconditionsthatarestatedinthequestion
Per paragraph 7 of Appendix E of NUREG-I021 page 2 of 6 which is part of the briefing given prior to the exam, the candidates are given the following instructions, "When answering a que stion, do not make assumptions regarding conditions that are not specified in the question unless they occur as a consequence of other conditions that are stated in the question. Similarly, you should assum e that no operator actions have been taken, unless the stem of the question or the answer choices specifically state otherwise.
.Similarly,youshouldassumethatno operatoractionshave beentaken,unlessthestemofth e questionortheanswerchoicesspecificallystateotherwise
Finally, answer all que stions based on actual plant operation, procedures or the answer choices speci fically stated otherwise".
.Finally,answerallquestionsbasedonactualplantoperation,procedures,andreferences.Ifyoubelievethattheanswerwouldbe differentbasedonsimulatoroperationortrainingreferences,youshouldanswe rthequestionbasedonthe actual plant.8.Restroomtripsarepermitted,butonlyoneapplicantatatimewillbeallowedtoleave
With this direction in mind the candidate can correctly assume that YM makeup is not initially align ed but within a reasonable period of time it will be. (Per the Time Critical Actions for our plant this should occur within 10 min of dispatch) According to the background document for AP-21 pg 10 of23 , "Per engineering, YM makeup should be sufficient to keep up with the FSAR design basis leak of 50 GPM ". After determining that a 100 GPM leak exists, even with YM make up aligned the candidate would reasonably come to the conclusion that KC surge tank level would continue to decrease.
.Avoidallcontactwithanyoneoutsidetheexaminationroomtoeliminateeventheappearanceor possibilityofcheating.AppendixE ,Page2of6 Information Only f+ttc.chml'/"\t
Procedurally we would align the Nuclear Service Water assured makeup ifYM was not sufficient to keep up with the leak but the candidates are told to not assume any operator act ions not stated, ther efore it is reasonable for the candidate to assume that this has not and will not happen unle ss otherwise stated.
;)..Paj G g Time Critical Operator Actions Information Only 17.Initiating makeup to the KC surge tank or isolate KC header leak Expectation:
Procedural guidance per AP-21 directs that once it has been determined that a leak exists operators be dispatched early to initiate YM make up per Step 11 . The procedure then checks surge tank level greater than 3 ft which for the scenario given it should be for the first pass thru this step . The operator is then directed to check the "sum of both train s' KC surge tank level drop s LESS THAN OR EQUAL TO 0.10 FT/MIN". If true , which for the leak rate calculated, it would be, the crew is directed to Step 20 which will Isolate
Operatorlocallyinitiatesmakeupwithin10 minutes of dispatch using eitherYMorRN,orgetsleak isolated prior to emptyingsurgetankfor designbasisleak of 50gpm.Follow-up planned: None.
 
"A" K C train from " B" K C train . This action is consistent with the actions stated in the Correct answe r "D" making it a valid correct answer. Onc e agai n, assuming no operator action has taken place, the surge tank levels will continue to decrease until they reach a level of 2 ft. At this point the "foldout" page would direct the operator to isolate the affected train PER Ene . 2. This actio n is stated in Distracter "C" and sinc e the stem does not refer to the "First" or "Nex t" action taken, this action is actually a subset of "0" and therefore a COITect answer.
Based on the discuss ion abov e and the attached references, we recommend that both "C" and " 0" be acce pted as correct answers.
 
~ .                                                    A- +1 Hhrnl'r'lt ~    Pa,j v 3 ES-401                    Sample Written Examination                 Form ES-401-5 Question Worksheet Examination Outline Cross-       Level              RO              SRO reference :
Tier #                            -
1-  -  -
Group #                              1 KIA #              (026) G2.1 .25 Importance Rating                  -
4.2 Proposed Question:    SRO 77 Page 197 of271 Rev Final
 
POJ<'- 'i ES-401                          Sample Written Examination                Form ES-401-5 Question Worksheet Initial conditions:
Time = 0 minutes
* Unit 1 is at 100% power.
          *  "A" Train KG pumps are running .
* Operators have been dispatched to initiate YM makeup to the KG Surge Tank.
          *  "A" KG Surge Tank level is 6.5 ft.
          *  "B " KG Surge Tank level is 6.5 ft.
Current conditions:
Time = 5 minutes
          *  "A" KG Surge Tank level is 5.6 feet
          *  "B" KG Surge Tank level is 6.4 feet.
Which ONE (1) of the following describes (1) the approximate KC system net leak rate , and (2) the required action and procedure use required in AP/21 , Loss of KG or KG System Leakage?
(Reference Provided)
A.       (1 )  50 GPM (2)    Isolate KC Non-Essential Headers in accordance with Enclosure 2.
B.       (1)    50 GPM (2)    Isolate "A" KG train from "B" KC train.
G.       (1 )  100 GPM (2)    Isolate KG Non-Essential Headers in accordance with Enclosure 2.
D.       (1)    100 GPM (2)    Isolate "A" KG train from "B" KG train.
Proposed Answer:            0 Explanation (Optional):
Page 198 of271 Rev Final
 
1+~t:Lh~("/J ~          PC\5 c  5 ES-401                          Sample Written Examination                        Form ES-401-5 Question Worksheet D is correct per conditions. Applicant must interpret curve and determine the leak rate indications based on level decreases A incorrect because leak rate is wrong (1/2 of actual, as interpreted by curve.)
Also , action is incorrect, as procedure will direct splitting trains for indication shown B incorrect because leak rate is incorrect. Plausible because action is correct C incorrect because procedure use is incorrect. Approximately 0.1 feet/minute, perform step 20 to split trains Technical                  AP/21 Step 20 Rev 9            (Attach if not previously Reference(s):                                              provided)
AP/21 Basis Document Rev 3 Proposed references to be provided to applicants during            OP/1 lA/51 00/22 examination:                                                      Enclosure 4.3 Curve 7.31 Learning Objective:        None Question Source :          Bank #
Modified Bank      x            (Note changes or attach
                          #                                parent)
New Question History:            Last NRC Exam      Modified from 2007 NRC exam 78 Question Cognitive          Memory or Fundamental Knowledge Level :
Comprehension or Analysis                  x 10 CFR Part 55              55.41 Content:
55.43  -
5-  -
Comments:
KA matched because use of a curve is required and interpretation of that curve is required to determine KC (CCW) leak rate . SRO level because assessment of Page 199 of 271 Rev Final
 
ES-401                      Sample Written Examination                Form ES-401-5 Question Worksheet conditions based on available indications, and selection of procedures (attachments) is required RFA Concurs 4/17/08 Page 200 of271 Rev Final
: 3. For an initial examination , the nominal time limit for completing the examination is 6 hours for the RO exam; 3 hours for the 25-question , SRO-only exam; 8 hours for the combined RO/SRO exam; and 4 hours for the SRO exam limited to fuel handling. Notify the proctor if you need more time.
For a requalification examination, the time limit for completing both sections of the examination is 3 hours. If both sections are administered in the simulator during a single 3-hour period, you may return to a section of the examination that you already completed or retain both sections of the examination until the allotted time has expired.
: 4. You may bring pens, pencils, and calculators into the examination room; however, programable memories must be erased. Use black ink to ensure legible copies; dark pencil should be used only if necessary to facilitate machine grading .
: 5. Print your name in the blank provided on the examination cover sheet and the answer sheet. You may be asked to provide the examiner with some form of positive identification.
: 6. Mark your answers on the answer sheet provided, and do not leave any question blank.
Use only the paper provided. and do not write on the back side of the pages.
If you are using ink and decide to change your original answer, draw a single line through the error, enter the desired answer, and initial the change. If you are recording your answers on a machine-gradable form that offers more than four answer choices (e.g.,
  "a" through "e"), be careful to mark the correct column.
: 7. If you have any questions concern ing the intent or the initial conditions of a question ,
do not hesitate to ask them before answering the question. Note that questions asked during the examination are taken into consideration during the grading process and when reviewing applicant appeals . Ask questions of the NRC examiner or the designated facility instructor only. A dictionary is available if you need it.
When answering a question, do not make assumptions regarding conditions that are not specified in the question unless they occur as a consequence of other conditions that are stated in the question. For example, you should not assume that any alarm has activated unless the question so states or the alarm is expected to activate as a result of the conditions that are stated in the question . Similarly, you should assume that no operator actions have been taken, unless the stem of the question or the answer choices specifically state otherwise . Finally, answer all questions based on actual plant operation, procedures, and references. If you believe that the answer would be different based on simulator operation or training references, you should answer the question based on the actual plant.
: 8. Restroom trips are permitted, but only one applicant at a time will be allowed to leave.
Avoid all contact with anyone outside the examination room to eliminate even the appearance or possibility of cheating.
Appendix E, Page 2 of 6
 
f+ ttc.chml'/"\t    ;).. Paj G        g Information                                                                                                Information Only                        Time Critical Operator Actions                                                Only
: 17. Initiating makeup to the KC surge tank or isolate KC header leak Expectation:
Operator locally initiates makeup within 10 minutes of dispatch using either YM or RN, or gets leak isolated prior to emptying surge tank for design basis leak of 50gpm.
Follow-up planned:
None.


==References:==
==References:==


FSAR 9.2.4.3 PIP M98-3618 PIP M99-3778 AP/1/A/5500/21 (Loss ofKCorKCSystem Leakage)Comments: The FSAR requiredtimeto isolateaKCleakis30 minutes to prevent emptyingKCsurgetankfora50gpmleak.Ifmakeupcan stabilizesurgetanklevel, operation can continue with header in service until individual componentcanbeisolated.A10minutelocaltasktoinitiatemakeupis basedon:1)Timeto dispatch an operatorinAP/21,and2)
FSAR 9.2.4.3 PIP M98-3618 PIP M99-3778 AP/1/A/5500/21 (Loss ofKC or KC System Leakage)
Ensuremarginto prevent reaching 2 ftinsurgetank(for50gpmleak).At2ft , AP/21 requires isolatingKCauxbldg non-essential header.This action has been validatedandtimes canbemet.18.Isolate letdown for a letdown header break: Expectation:
Comments:
The FSAR assumes isolation of NY letdown within 30 minutes of a complete severance of a letdown headerintheauxbldg.
The FSAR required time to isolate a KC leak is 30 minutes to prevent emptying KC surge tank for a 50 gpm leak. If makeup can stabilize surge tank level, operation can continue with header in service until individual component can be isolated.
Operations expectationisthatleakwillbe isolatedassoonasitis identified.
A 10 minute local task to initiate makeup is based on: 1) Time to dispatch an operator in AP/21 , and 2)
Follow-up planned: None.
Ensure margin to prevent reaching 2 ft in surge tank (for 50 gpm leak) . At 2 ft, AP/21 requires isolating KC aux bldg non-essential header. This action has been validated and times can be met.
: 18. Isolate letdown for a letdown header break:
Expectation:
The FSAR assumes isolation of NY letdown within 30 minutes of a complete severance of a letdown header in the aux bldg. Operations expectation is that leak will be isolated as soon as it is identified.
Follow-up planned:
None.


==References:==
==References:==


FSAR 15.6.2.2 AP/1/A/5500/10 (NC System LeakageWithinthe Capacity of BothNYPumps)Comments: The limitingcasein FSARisa complete severance, at rated power conditions, ofthe3inch letdown line just outside containment, betweenNY-7Bandthe letdown heat exchanger.Page19 of 40  
FSAR 15.6.2.2 AP/1/A/5500/10 (NC System Leakage Within the Capacity of Both NY Pumps)
Comments:
The limiting case in FSAR is a complete severance, at rated power conditions, of the 3 inch letdown line just outside containment, between NY-7B and the letdown heat exchanger.
Page 19 of 40
 
A~-c.(hme/)}-      d.. ~OjC    'i AP/1 and 2/Al5500/021 (Loss of KC or KC System Leakage)
If KC surge tank level is greater than 3 ft, time is given for the operators to attempt to initiate makeup and check results to see if the surge tank level can be maintained. Per engineering, YM makeup should be sufficient to keep up with the FSAR design basis leak of 50 GPM.
Operators should be able to initiate makeup prior to reaching 2 ft in the surge tanks (assuming makeup is initiated when KC 10 level alarms at 4.5 ft). If the trains are cross-tied, allowing leaving the cross-ties open doubles the volume (and time) to initiate makeup. Note that for larger leaks , or if level reaches 2 ft, the cross-ties will be closed to protect the other train. If makeup is initiated and level stabilizes, operator actions are greatly simplified.
STEP 16 NOTES:
PURPOSE:
Give operator information for determining leak rate.
DISCUSSION :
0.1 ft/min level drop is equivalent to the design basis leak (50 gpm) that YM makeup should be able to keep up with .
STEP 16:
PURPOSE:
Procedure flow path controlling step.
DISCUSSION:
If leak is greater than design basis leak, operators need to find the leak and isolate it.
Page 10 of 23                            Rev 3
 
A -\i Ac~ rY\('r, ~ ;).. PG5 c. I 0 AP/1 and 2/Al5500/021 (Loss of KC or KC System Leakage)
INTRODUCTION This procedure gives guidance on the actions required in the event of a loss of KG, or leakage on the KG System.
OVERVIEW OF AP-21 AP-21 is written for scenarios involving a loss of KG (like KG pump trips, etc.) and for scenarios involving KG leakage. For either case, the AP first addresses some immediate concerns, like isolating letdown if no KG pumps, making plant page, and securing any dilution.
For scenarios involving a loss of KG not due to leakage, the AP quickly attempts starting the standby KG train (Step 9). It is time critical to restore KG cooling to NG pumps (approx 10 minutes). If cooling is not restored, NG pumps and a reactor trip will be required.
The AP next addresses scenarios involving KG leakage. If KG leakage is small (within design basis of 50 gpm) when makeup is initiated, it should keep up with the leak and avoid the process of header isolations. If the leak is too big for makeup , then the AP goes through a process of header isolations in a preferred order. In any case, the AP ends up with an essential header in operation, and intact non-ess headers in service.
ENTRY CONDITIONS This procedure can be entered any time the listed symptoms are encountered.
Page 2 of 23                              Rev 3


d..'iAP/1and2/Al5500/021 (Loss of KC or KC System Leakage)IfKCsurgetanklevel i s greaterthan3ft ,timeisgivenforthe operators to attempttoinitiatemakeupandcheckresultstoseeifthesurgetanklevelcanbe maintained.
I      C    c /"\     po,I e MNS                            LOSS OF KC OR KC SYSTEM LEAKAGE                        PAGE NO.
Perengineering,YMmakeup shouldbe sufficienttokeepupwith the F SARdesignbasisleakof50G PM.Operatorsshouldbeabletoinitiatemakeuppriortoreaching2ftinthesurgetanks(assumingmakeupisinitiatedwhenKC 10levelalarmsat4.5ft).Ifthetrainsarecross-tied, allowingleavingthe cross-ties open doublesthevolume(andtime)toinitiatemakeup.Notethatforlargerleaks
AP/1/A/5500/21                                                                                28 of 78 Enclosure 1 - Page 1 of 1 Rev. 9 UNIT 1                                           Foldout
,oriflevelreaches2ft,thecross-tieswillbeclosedto protecttheothertrain.Ifmakeupisinitiatedandlevelstabilizes, operatoractionsare greatly simplified.STEP16NOTES:
: 1. KC header isolation criteria:
PURPOSE: Give operator information for determiningleakrate.DISCUSSION
* IF KC surge tank level goes below 2 ft due to KC system leak, THEN immediately isolate affected train PER Enclosure 2 (Isolation of KC Non-essential Headers ).
: 0.1ft/minleveldropis equivalenttothedesignbasisleak(50gpm)thatYMmakeupshouldbeabletokeepupwith
: 2. NC pump trip criteria:
.STEP16: PURPOSE:Procedureflowpathcontrollingstep.
* IF NC pump motor bearing temperature reaches 195&deg;F, THEN perform the following :
DISCUSSION:Ifleakis greaterthandesignbasisleak, operatorsneedtofindtheleakandisolateit.Page10of23Rev3 A-\irY\('r,;)..P G5 c.I 0AP/1and 2/Al5500/021 (Loss of KC or KC System Leakage)INTRODUCTIONThisproceduregives guidanceontheactionsrequiredintheeventofalossofKG,orleakageontheKGSystem.
: a. Trip the reactor .
OVERVIEWOFAP-21AP-21iswrittenfor scenariosinvolvingalossofKG(likeKGpumptrips,etc.)andfor scenariosinvolvingKGleakage.For eithercase,theAPfirst addresses some immediateconcerns,likeisolatingletdownifnoKGpumps,makingplantpage,and securinganydilution.
: b. WHEN reactor is tripped, THEN trip all NC pumps.
For scenariosinvolvingalossofKGnotduetoleakage,theAP quickly attemptsstartingthestandbyKGtrain(Step9).ItistimecriticaltorestoreKGcoolingtoNGpumps (approx 10minutes).Ifcoolingisnotrestored,NGpumpsanda reactortripwillberequired.TheAPnext addresses scenariosinvolvingKGleakage.If KG leakage issmall(withindesign basis of50gpm)whenmakeupisinitiated,itshouldkeepupwiththeleakandavoid the processof header iso lations.Iftheleakistoobigformakeup
: c. GO TO EP/1/A/5000/E-O (Reactor Trip or Safety Injection), while continuing in this procedure as time and conditions allow.
,thentheAPgoesthroughaprocessof header isolationsinapreferredord er.Inanycase,theAPendsupwithanessential headerinoperation,andintactnon-essheadersinservice.
: 3. ND pump trip and flow isolation criteria (Applies if ND aligned for RHR):
ENTRY CONDITIONSThisprocedurecanbeenteredanytimethelisted symptoms are encountered.Page2of23Rev3 po I C c/"\,Ie MNSLOSSOFKCORKCSYSTEMLEAKAGEPAGENO.AP/1/A/5500/21Enclosure1-Page1of128of78 UNIT 1 Foldout Rev.91.KC header isolation criteria:*IFKCsurgetank levelgoesbelow 2 ft duetoKCsystemleak,THEN imme diatelyisolateaffectedtrainPEREnclosure2(Isolationof K C Non-essential Headers).2.NC pump trip criteria:*IFNCpumpmotorbearing temperaturereaches195&deg;F,THENperformthefollowing
* IF KC cooling lost to either NO train's HX, AND NC temperature is greater than 150&deg;F, THEN perform the following on train of NO that lost KC flow to its NO HX:
:a.Tripthereactor
: a. Stop associated NO pump.
.b.WHENreactoristripped,THENtripallNCpumps.c.GOTOEP/1/A/5000/E-O (ReactorTriporSafetyInjection),whilecontinuinginthisprocedureastimeandconditionsallow
: b. IF 1A NO HX lost KC flow, THEN close:
.3.ND pump trip and flow isolation criteria (Applies if ND aligned for RHR):*IFKCcoolinglosttoeitherNOtrain'sHX,ANDNC temperature is greaterthan150&deg;F,THENperformthefollowingontrainofNOthatlostKCflowtoitsNOHX:
* 1NO-33 (A NO Hx Bypass)
a.StopassociatedNOpump
* 1NO-32 (A NO Hx To Letdown Hx).
.b.IF1ANOHXlostKCflow,THENclose:*1NO-33(ANOHxBypass)*1NO-32(ANOHxToLetdownHx).c.IF1BNOHXlostKCflow,THENclose:*1NO-18(BNOHxBypass)*1NO-17(BNOHxToLetdownHx)
: c. IF 1B NO HX lost KC flow, THEN close:
.d.IFbothNOpumpsoffTHENREFERTO AP/1/A/5500/19(LossofNOorNOSystemLeak).4.KC pump trip criteria:*IFKCsurgetanklevelgoesbelow.5 ftandvalid,THEN:
* 1NO-18 (B NO Hx Bypass)
a.Tripaffectedpumps
* 1NO-17 (B NO Hx To Letdown Hx).
.b.IsolateaffectedtrainPEREnclosure2(IsolationofKC Non-essential Headers).5.VCT high temperature:*IF"VCTHITEMP"alarm(1AO-7
: d. IF both NO pumps off THEN REFER TO AP/1/A/5500/19 (Loss of NO or NO System Leak).
, 0-1)isreceived,THENREFERTOEnclosure6(VCTHigh Temperature Actions).}}
: 4. KC pump trip criteria:
* IF KC surge tank level goes below .5 ft and valid, THEN:
: a. Trip affected pumps .
: b. Isolate affected train PER Enclosure 2 (Isolation of KC Non-essential Headers).
: 5. VCT high temperature:
* IF "VCT HI TEMP" alarm (1AO-7, 0-1) is received, THEN REFER TO Enclosure 6 (VCT High Temperature Actions) .}}

Latest revision as of 00:34, 13 March 2020

May Examination 05000369 and 05000370/ 2008-301 Facilities Post-Examination Comments (Part 1 of 2)
ML081770470
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 06/25/2008
From:
NRC/RGN-II
To:
Duke Energy Carolinas
References
50-369/08-301, 50-370/08-301
Download: ML081770470 (32)


Text

Attachment 1a Page I of 8 Common Question 53 After further investigation we propose that Question 53 be deleted due to no correct answer.

The original assumption was due to the lowering VI (Instrument Air) pressure the S/G feed reg valves would fail closed resulting in increas ing feed pump discharge pressure to the point where the feed pumps wou ld trip on high discharge pressure. While the failur e mechani sm for the FRV 's is correct on a loss of air (closed), the resulting Reactor trip occurs due to low S/G level not feed pump discharge pressure. This was validated on our simulator with a loss of VI ramped in over a period of 5 to 10 minutes which resulted in the reactor tripping on low S/G level when VI press had degraded to approx. 40 psig.

While FWP discharge pressure did increase , the action of the FWP control system to maintain the program DIP at set point resulted in a decrease in FWP speed as the FRV' s closed. This action delays the increase in FWP discharge pressure. to the point where lowerin g S/G level will reach trip set point prior to increasing FWP discha rge press. In 4 different VI failure scenarios with varying leak sizes and ramp rates, the reactor tripped due to S/G level prior to FWP discharge press reaching trip set point.

The feed pump speed control system is designed to maintain a DIP set point between Main Steam header pressure and Feedwater Header pressure. This setpoint is ramped from 40 psid at 0 % powe r to 175 psid at 100% power. (see page 5 of this attachment)

When a VI system leak is inserted, the resulting lowering VI header pres s causes the FRV's to slowly close. As they close, FWP discharge press increa ses. This causes the SM/CF DIP to rapidl y increase and was observed to be as high as 400 psid. The FWP control sys tem responds to slow the FWP speed in an attempt to maintain the programmed DIP. In every case except a catastrophic failur e where the VI header rapidl y depressurizes this action significantly delays the increase in FWP discharge pressure. A catastrophic failure of VI is not consistent with the conditions established in the stem of this question.

One final data point added to the end of this attachment is copy of PIP M87-00208 which documents an actual loss of VI in 1987 where the reactor tripped due to S/G Lo Lo level after appro x. 5 min. This is consistent with what we observed during our simulator validations.

Question 53 asks, " WOOTF will be the FIRST to trip the reactor". Lo Lo S/G level is not listed in any of the proposed answers. Based on the information above and the attached documentation , we feel this question should be deleted due to havin g no correct answer.

Tier # 1 Group # 1 K/A# 065 AA2.08 Importance Rating 2.9 (Ability to determine and interpret the following as they apply to the Loss of Instrument Air: Failure modes of air-ope rated equipment)

Proposed Question: Common 53 Both Units are at 100% power when :

  • MNS experiences a loss of VI.
  • VI Header pressure on both units is 30 psig and continues to decrease.

Which ONE (1) of the following will be FIRST to trip the reactor and its basis?

A. OT Delta T trip due to the MSIVs failing closed.

B. High-High SG level trip because the Feedwater Reg Valves fail open .

C. Turbine Trip due to Feed Pump Trip because the Feedwater Reg Valves fail closed.

D. High pzr Level trip due to the Charging Flow Control Valve failing open with Letdown isolated.

Proposed Answer: C Explanation (Optional) :

A. Incorrect. If MSIVs fail closed it could cause a trip on LO-LO SG level or on OTDT due to Tave rising. FRVs failing will cause the trip significantly faster than MSIV failure. Plausible because until a recent mod, the MSIVs did fail close on a loss of VI.

B. Incorrect. Feedwater reg valves fail closed, but plausible because this is the reactor trip mechanism if they did fail open.

C. Correct. Reactor trip will occur due to turbine trip. If fedwater reg valves fail closed , Feed Pumps will trip on high discharge pressure, which directly causes a turbine trip.

D. Incorrect. This would cause a reactor trip, but at a significantly later time than feedwater reg valve failure. Charging flow control valve fails open and letdown isolates on loss of air, so PZR level will be rising Technical AP-22 Background

Reference(s) Document (p22 Rev 12)

AP/1/A/5500/22 Enclosure 12 p104 106, Rev 27 CF-CF p19 Rev 32 Proposed references to be provided to applicants during examination:

Learning Objective: CF-CF Obj 4 Question Source : Bank#

Modified Bank (Note changes or attach

  1. _ _ __ parent)

New x Question History: Last NRC Exam Question Cognitive Memory or Fundamental Knowledge Level:

Comprehension or Analysis x 10 CFR Part 55 55.41 5 Content:

55.43 Comments:

KA is matched because item evaluates the failure mode of air operated equipment that will cause a reactor trip RFA Concurs 4/24/08

DUKE POWER MCGUIRE OPERA TlONS TRAINING

1.0 INTRODUCTION

1.1 Purpose Objective # 1 Reference Fig. 7.1 . The purpose of the Feedwater Pump Speed Control System is to provide a variable speed demand signal to the main feedwater pump turbines which is programmed to maintain the Feedwater Regulating (Flow Control) Valves in their optimum throttling position. The system also operates the Feedwater Pumps in conjunction with the Feedwater Control Valves to maintain steam generator water level with maximum efficiency .

1.2 General Description The Steam Generator Level Control System computes a desired level that is based on reactor power . To maintain this desired level, a control signal is developed. The signal functions to position the Feedwater Regulating Valves , and thus control feed flow, for each of the steam generators. The Main Feed Pump Speed Control System is designed to complement the operation of the Water Level Control system . It computes a desired pump speed that is based on auctioneered HI NC delta T (reactor power) .

This signal functions to regulate the steam flow to the main feed pump turbines, controlling their speed. Variation of pump speed in this fashion results in:

  • Reduced erosion of feedwater regulating valve flow control surfaces .
  • Improved feed regulating valve flow control (throttling) characteristics.

Variable speed main feed pumps are favored because they are more economical in large plants. There is less lost energy when the speed is matched with the desired Differential Pressure (Delta P or DP).

Steam header pressure is compared to feed pump discharge pressure generating an Actual DP signal. The DP signal is compared to a programmed setpoint determined from auctioneered HI NC delta T (reactor power) and generates the speed demand signal. Corrections may be added for flow imbalance between the pumps .

2.0 COMPONENT DESCRIPTION 2.1 General Operation I Objective # 6 I The system utilizes three basic control loops to control the feedpump. The feedwater loop, the governor loop, and actuator loop. These loops and their relationship are shown on drawing 4.1. Each of these loops is a proportional plus integral control loop (P+I). Basically these are cascading control loops in that the feedwater control loop output is the input to the governor loop and the output of the governor loop is the input to the actuato r loop. This assumes that the controls are in auto. The input for the feedwater loop is the feedwater demand signal which is the programmed delta P for the power level of the reactor as sensed by auctioneered hi NC loop delta T.

OP-MC-CF-IWE FOR TRAINING PURPOSES ONL Y REV. 17 Page 9 of 57

DUKE POWER MCGUIRE OPERA TlONS TRAINING 7.3 Feedpump ap Program w/AMSAC Avoidance (03/17/06) 205 200 195 190 185 180 175 170 165 .

160 .

155 .

150 .

..... 145 '

8 140

~ 135 UJ en 130 Q.

o 125 120 115 110 .

105 100 95 90 .

85 80 .

75 70 65 .

o 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125

% POWE R OP-MC-CF-IWE FOR TRAINING PURPOSES ONL Y REV. 17 Page 49 of 57

AP/1 and 2/Al5500/022 (Loss of VI)

STEP 13:

PURPOSE :

Prompt the operators to watch S/G levels because the CF control valves fail closed on a loss of VI. If S/G levels can't be controlled, the Operator is directed to trip the reactor.

DISCUSSION:

The CF control valves use 0 - 60# valve operating air. Depending on the nature of the problem with VI and considering line losses, etc., these valves could start failing at 70# or more VI pressure as indicated in the control room. The operating philosophy regarding loss of Main Feedwater at power is to trip the reactor . This will prevent challenging the La-La S/G automatic reactor trip and will result in better initial conditions at the time of the manual trip. Refer to PIP 2-M-87-0208 where a automatic reactor trip occurred 5 min after loss of offsite power due to loss of VI to the CF valves. If the CF valves were to get to less than 25% open (for 30 sec or more) on 3 out of 4 S/Gs, an AMSAC could also be generated . For most scenarios , it's likely the operator will have manually tripped the reactor prior to this occurring.

REFERENCES :

PIP 2-M-87-0208 Page 15 of 46 Rev 12

MNS LOSS OF VI PAGE NO.

AP/1/N5500/22 8 of 120 Rev. 27 UNIT 1 ACTI ON /EX PECTED RESPONSE RESP ON SE NOT OBTAI NED 11 . (Continued)

m. Control NC temperature as follows :
  • Throttle NO flow .

NOTE

  • KC to NO Hx flow should be close to flow prior to loss of VI, since it is normally controlled by motor operated valves.
  • KC to NO HX flow indications fails low during a loss of VI. Alternate indications are available at the following locations, if needed :
  • 1A: 1KCFT-5670 (aux bldg, 733 +2', west of column MM-54)
  • 1B: 1KCFT-5680 (aux bldg, 733 +4', west side of column JJ-55).
  • IF NC temperature is greater than 200°F, THEN maintain KC flow to NO Hx greater than 2000 GPM.
  • Throttle KC Flow to NO Hx as required .
12. IF AT ANY TIME VI pressure is less than 70 PSIG, THEN align B Train RN to SNSWP PER Enclosure 7 (Aligning B Train RN to Pond).

CF Control Valves will fail closed on low VI pressure , which may result in AMSAC actuation and Lo Lo S/G level.

13. Check S/G levels - AT PROGRAMMED IF S/G levels are going down in an LEVEL. uncontrolled manner, THEN perform the following:
a. Trip reactor.
b. Continue with this procedure as time allows.
c. GO TO EP/1/N5000/E-0 (Reactor Trip or Safety Injection) .

(\\\f>C~E:Nr~~ - ' , C. _ . P6 6 bF' B " ".

DUKE POWER MCGUIRE OPERA TJONS TRAINING Objective # 4 The conditions which will result in both main feed pumps tripping:

  • if all three CBPs trip
  • on a Safety Injection actuation
  • on SIG Hi-Hi-Ievel (P-14)(83%)
  • on Hi Hi Dog House level in either inner or outer Dog House (12 inches)

The conditions which will result in tripping the associated main feed pump:

  • two out of three of its suction pressure switches are low (230 psig)
  • two out of three of its discharge pressure switches are high (1435 psig)
  • two out of three low bearing oil pressure (7 psig)
  • two out of three low vacuum (14 inches Hg)
  • fire lockout
  • thrust bearing wear (0.01 inch axial movement)

The status of the suction and discharge pressure switches can be determined from the "Condensate 2 of 3 Logic Panel" located in the Turbine Building basement near the BB demineralizer room across for Column 1F24 (refer to Drawing 7.3).

When A(B) CF pump is tripped, solenoid valve 1CFSV0010 (1CFSV0040) is energized which closes A(B) CF Pump piston operated discharge check valve CF1 (CF4). This will prevent flow reversals through the idle pump and prevent damage to the pump and piping due to waterhammer.

The CF pump suction (CM266 and CM272) and discharge (CF2 and CF4) valves are motor operated valves which can be controlled using OPEN/CLOSE pushbuttons from MC-10 (refer to Drawing 7.4). The A(B) CF pump turbine high and low pressure stop valves can not be raised (opened) until its suction valve CM266 (CM272) and its discharge valve CF2(CF5) are open, as well as the CM Booster Pump recirc valve CM250 and CF System Flush Valve CF124 are closed. In addition CF124 can not be opened unless A CFP suction valve (CM266) and discharge valve (CF 2) are open OR B CFP suction valve (CM272) and discharge valve (CF 5) are open , and both CF pump turbines are tripped.

OP-MC-CF-CF FOR TRAINING PURPOSES ONL Y REV. 32 Page 19 of 107

la Problem Investigation Process McGuire Nuclear Station Action Cate 0 Problem Identification Discovered TimelDate: 10:21 09116/1987 Occurred TimelDate:

Unit(s) Affected:

Unit Mode %Power Unit Status Remarks 2 I System(s) Affected:

CF Feedwater System EPB 6.9 KV Norm Aux & RCP Swgr Power Sys ND Residual Heat Removal System VI Instrument Air System Affected Equipment r _.I 0 Equipment Ti;g :  : . EcOde :  :  ::: M;!.nuf: eturer : ' ."::::: _

Location of Problem:

Bldg: Column Line : EIev:

Location Remarks:

Method Used to Discover Problem:

Brief Problem

Description:

APPROX. 5 MINUTES AFTER LOSS OF OFFSITE POWER TO UNIT I, UNIT 2 E Detail Problem

Description:

APPROX. 5 MINUTES AFTER LOSS OF OFFSITE POWER TO UNIT I, UNIT 2 EXPERIENCED A REACTOR TRIP DUE TO S/G -LO LO LEVEL. FEEDWATER REGULATOR VALVES FAILED CLOS ED DUE TO LOSS OF STATION AIR (VI)

Other Units/Components/SystemslAreas Affected(Y,N,U): U Industrv Plants Affected(Y,N,U):

Immediate Corrective Actions:

Immediate Corrective Action Documents 1 Work Orders:

Date Problem Identified By: M-RGC 0911611 987 Problem Entered By: M-SRG 0911 611987 Screening Action Category: Root Cause performed?

051281200810:39 Page 1 PIP No: M-87-00208

Problem Investigation Process McGuire Nuclear Station Significance Codes:

OEPNo:

Other Report Nos: M87-075-0 Event Codes:

88 Convert old pip data to NewPIP relational database Screening Remarks:

Assignments:

Responsible Groups(s) for Problem Evaluation : M-SRG Safety Review Respon sible Group for Present Operability: M-RGC Regulatory Compliance Responsible Group for Report Support Info: N/A Responsible Group for Reportability: M-RGC Regulatory Compliance Responsible Group for Overall PIP Approval: M-SRG Indiv Team Orou Date onfile RJD4373 M-SRG 0911611987 Present Operability Responsible Group: M-RGC Status: Closed Sys/Comp Operab le? (Y,N,C,E,T): Y Required Mode:

Comment s:

lndiv Team Grou Date M-RGC R eportab ility Responsible Group : M-RGC Status: Closed Problem Report able(Y,N,E): Y Reportable Per:

Comments:

LER, N/A SiRnature Tvoe Indiv Team Group Date Assigned To: M-RGC Due Date:

Evaluation Assigned To: M-RGC 0911611987 Investigation Report:

OS/28/200810:39 Page 2 PIP No: M-87-00208

Problem In vestigation Process McG uire N uclear Station Responsible Group: Act Date:

Investigator: Group:

Due Date: 10/22/1987 Date Due to VP or Sta. Mgr:

Date Regulatory or Agency Rpt Due:

Date Investigation Report Approved: 10/29/ I987 NRC Cause Codes:

A3c3 An Action Was Performed With Insufficient Precision Report Support Info:

Re spon sible Grou p: St atus: Closed ISignature TyPC Indiv Team Group Date  :

Problem Evaluation IEvent Cause Code Cau e Description Primary Cau ing Groups 188 A3c3 Old Cause Code at McGuire Yes V-UNK 188 N/A Not Applicable No M-IAE Problem Evaluation From: Resp. Gro up: M -SRG Status: Closed OEDB Checked: No OEDU Comme nts:

Remarks Comments:

Due to the electronic up loading of information, any missing PIR information is located in the Master File area.

' SiJ~ n at u re Type Indiv Team Group Date Assigned To : M-SRG 09/19/1987 Due Date: 10/16/19 87 Corrective Actions No Corrective Actions for this PIP Final and Overall PIP Approval Respo nsible Gro up: M- SRG Status : C losed Signature T ype Indiv Team Groun Date Assigned To: onfile M-SRG Approved By: onfile M-SRG 01/31/1990 Any Supplemental Concurrence Signatures Above Do Not Affect PIP Closure.

OS/28/2008 10:39 Page 3 PIP No: M-87-0020 8

  • ** <I Problem Investigation Process McGuire Nuclear Statio" Microfilm RollI Frame: I Closure Document Tvpe Closure Document No Attachments Generic Applicability Responsible Group: G-OEA Status: Closed GO PIP No:

Aissessmen t l{ernar ks :

Siznuture TyDC Indiv Team Group Dale Assigned To: G-OEA Due Date: 0113111990 Approved By: G-OEA 09/23/199 3 Failure Prevention Investigation No FPI Records for this PIP.

Remarks No Remarks for this PIP.

Maintenance Rule No Maintenanc e Rule Record s for this PIP.

End of the Document for PIP No: M-87-208 The status of this PIP is: Closed The duration of this PIP was: 868 days [Duration = Status Date (0 1/31/l 990 ) - Discovery Date (09116/l 987 )]

(Note: All Corrective Actions were printed in this report.)

OS/28/200810:39 Page 4 PIP No: M-8 7-00208

.. .. .. _.~.:. .. . b Page I of I Common Question 53 The Post-exam Item A n a lysis indicated that 7 of 12 applicants missed this question.

  • 4 chose "A" - clea rly wrong becau se the MS IYs do not fai l closed on loss of YI
  • 1 chose " B" - clearly wro ng becau se the FRVs failed CLOSED, not OPEN on loss of VI
  • 2 chose " D"- plaus ible because the charging flow valve will fai l op en and PZR level would eventually reach the rea ctor trip setpo int. This di stracter is wrong because the reactor will alrea dy be tripped du e to Lo Lo S/G levels prior to the PZR level reaching trip setpoint.

No applicant as ked for clarification on th is question while taking the exam.

How did this question get through Valid a tion ?

Ques tio n 53 was revised to its current state aro und 2-26-08 . "C" dist racter was va lida ted on the on the simulator whe re a loss of VI d id result in a FWP trip, tur bine tr ip, then reactor tri p. However we simulated a catas trophic break on VI, whe re the pressure dropp ed rap idl y.

As a resul t of our post- exam item analys is, we ran the slower VI leak on the si mulator to more closely resembl e the co nditio ns described in th e questi on stem. Th at' s whe n we real ized that the FWP wi ll not trip as describ ed on pa ge 1.

During validation, six individuals took this version of the question.

  • 1 picked A
  • 1 picked B
  • 4 picked D Th e va lida tors admitted m em ory dec ay on the failure mode of va lves. Th erefore, we didn' t qu estion if "C" was indeed correct.

W e have captured this lesson learned to ensure we va lid a te written question scena r ios on th e sim u la to r to more clo sel y r esemble plant conditions in the question stem .

i


I

'<'""NM'<t

~~~~

C C C C OJ OJ OJ OJ C/) C/) C/) C/)

.0 .0 .0 .0 I! I o

0

- 0 M

CI)

CI)

...J

-I-0 C'a I-CI) t:

CI) 0 I/)

N o

E 0 0

C'a N CI)

(J) Q)

E i=

0 I/)

o o

oI/) o o o o o o-e--

'<t M N '<'""

I

Tier # 1 Group # 1 KIA # 065 AA2.08 Importance Rating 2.9 Rev. 1 to the package (Ability to determ ine and interpret the follow ing as they apply to the Loss of Instrument Air: Failure modes of air-operated equipment )

Proposed Question: Common 53 Both Units are at 100% power when:

  • MNS experiences a loss of VI.
  • VI Header pressure on both units is 30 psig and continues to decrease.

Which ONE (1) of the following will be FIRST to trip the reactor and its basis?

A. OT Delta T trip due to the MSIVs failing closed.

B. High-High SG level trip because the Feedwater Reg Valves fail open.

C. Turbine Trip due to Feed Pump Trip because the Feedwater Reg Valves fail closed.

D. High Pzr Level trip due to the Charging Flow Control Valve failing open with Letdown isolated.

Proposed Answer: C Explanation (Optional):

A. Incorrect. If MSIVs fail closed it could cause a trip on LO-LO SG level or on OTDT due to Tave rising . FRVs failing will cause the trip significantly faster than MSIV failure. Plausible because until a recent mod , the MSIVs did fail close on a loss of VI. '".

B. Incorrect. Feedwater reg valves fail closed, but plausible because this is the reactor trip mechanism if they did fail open.

C. Correct. Reactor trip will occur due to turbine trip. If fedwater reg valves fail closed, Feed Pumps will trip on high discharge pressure, which directly causes a turbine trip.

D. Incorrect. This would cause a reactor trip , but at a significantly later time than feedwater reg valve failure. Charging flow control valve fails open and letdown isolates on loss of air, so PZR level will be rising Technical AP-22 Background

Reference( s) Document (p22 Rev 12)

AP/1/A/5500/22 Enclosure 12 p104 106, Rev 27 CF-CF p19 Rev 32 Proposed references to be provided to applicants during examination:

Learning Objective : CF-CF Obj 4 Question Source : Bank#

Modified Bank (Note changes or attach

  1. - - - - parent)

New X Question History: Last NRC Exam Question Cognitive Memory or Fundamental Knowledge Level:

Comprehension or Analysis X 10 CFR Part 55 55.41 5 Content:

55.43 Comments:

KA is matched because item evaluates the failure mode of air operated equipment that will cause a reactor trip RFA Concurs 4/24/08

Attachment la Page 1 of8 Common Question 53 After further investigation we propose that Question 53 be deleted due to no correct answer.

The original assumption was due to the lowering VI (Instrument Air) pressure the S/G feed reg valves would fail closed resulting in increasing feed pump discharge pressure to the point where the feed pumps would trip on high discharge pressure. While the failure mechanism for the FRV's is correct on a loss of air (closed), the resulting Reactor trip occurs due to low S/G level not feed pump discharge pressure. This was validated on our simulator with a loss of VI ramped in over a period of 5 to 10 minutes which resulted in the reactor tripping on low S/G level when VI press had degraded to approx. 40 psig.

While FWP discharge pressure did increase, the action of the FWP control system to maintain the program DIP at set point resulted in a decrease in FWP speed as the FRV's closed. This action delays the increase in FWP discharge pressure. to the point where lowering S/G level will reach trip set point prior to increasing FWP discharge press. In 4 different VI failure scenarios with varying leak sizes and ramp rates, the reactor tripped due to S/G level prior to FWP discharge press reaching trip set point.

The feed pump speed control system is designed to maintain a DIP set point between Main Steam header pressure and Feedwater Header pressure. This setpoint is ramped from 40 psid at 0 % power to 175 psid at 100% power. (see page 5 of this attachment)

When a VI system leak is inserted, the resulting lowering VI header press causes the FRV's to slowly close. As they close, FWP discharge press increases. This causes the SM/CF DIP to rapidly increase and was observed to be as high as 400 psid. The FWP control system responds to slow the FWP speed in an attempt to maintain the programmed DIP. In every case except a catastrophic failure where the VI header rapidly depressurizes this action significantly delays the increase in FWP discharge pressure. A catastrophic failure of VI is not consistent with the conditions established in the stem of this question .

One final data point added to the end of this attachment is copy of PIP M87-00208 which documents an actual loss of VI in 1987 where the reactor tripped due to S/G Lo Lo level after approx. 5 min. This is consistent with what we observed during our simulator validations.

Question 53 asks, "WOOTF will be the FIRST to trip the reactor". Lo Lo S/G level is not listed in any of the proposed answers. Based on the information above and the attached documentation, we feel this question should be deleted due to having no correct answer.

b Page 1 of 1 Common Question 53 The Post-exam Item Analysis indicated that 7 of 12 applicants missed this question.

  • 4 chose "A" - clearly wrong because the MSIVs do not fail closed on loss of VI
  • 1 chose " 8 " - clearly wrong because the FRVs failed CLOSED , not OPEN on loss of VI
  • 2 chose " D"- plausible because the charging flow valve will fail open and PZR level would eventually reach the reactor trip setpoint. This distracter is wrong because the reactor will already be tripped due to Lo Lo S/O levels prior to the PZR level reaching trip setpoint.

No applicant asked for clarification on this question while taking the exam.

How did this question get through Validation?

Question 53 was revised to its current state around 2-26-08. "C" distracter was validated on the on the simulator where a loss of VI did result in a FWP trip, turbine trip, then reactor trip. However we simulated a catastrophic break on VI, where the pressure dropped rapidly.

As a result of our post-exam item analysis, we ran the slower VI leak on the simulator to more closely resemble the conditions described in the question stem. That's when we realized that the FWP will not trip as described on page 1.

During validation, six individuals took this version of the question.

  • 1 picked A
  • 1 picked 8
  • 4 picked D The validators admitted memory decay on the failure mode of valves. Therefore, we didn 't question if "C" was indeed correct.

We have captured this lesson learned to ensure we validate written question scenarios on the simulator to more closely resemble plant conditions in the question stem.

Documentation of Post Exam Simulator Data for Common Question # 53 The simulator was set up with a standard 100% MOC snap. A malfunction was inserted consisting of ramped 75% break of the Service Building VI (Instrument Air) header. Over the first 30 sec, VI pressure falls fairly rapidly to a value of approximately 65 PSIG. At this point the FRV demand begins to increase indicating that the actual valve position is closing due to the lower VI header pressure. The result of the FRV's going closed shows that the FW header/Main Steam header DIP begins to increase due to the resulting increase in FWP discharge pressure. This results in a control action by the FWPT Speed control system lower FWPT speed in an attempt to control the DIP at setpoint. These values are shown on the attached graph. At approx. 65 psig the rate of VI pressure decrease slows which would be consistent with the automatic response of the standby VI compressors starting/loading attempting to restore VI pressure. Over the next 3 minutes, VI pressure continues to lower resulting in further closure of the FRV's thereby further reducing feed flow to the S/G's. FWP discharge pressure continues to increase as the FRV's close but the FWPT control system is continuing to decrease the FWPT speed which dampens and slows this effect the to the point where the reduction of feed flow to the S/G's results in a low level trip of the Reactor at 17% level approximately 4.5 minutes into the failure with VI pressure indicating about 30PSIG. Just prior to the trip, FWP discharge pressure peaks at approx. 1400 PSIG which is well below the trip setpoint of 1435 PSIG.

Below I have pasted Excel Spreadsheet trends converted from the Simulator Data Recorder depicting the behavior of S/G level, FWP Discharge pressure, and VI Header pressure during the malfunction described above. The X Axis is showing the Time in seconds. I have also attached an Excel file to this communication with the raw data of the selected parameters and additional trends created from this data.

Steam Generator Level 70 60 50

40

..J

~

-bsgnwl(1)

.9 e 30


. bsgnwl(2)

'"c bsgnwl(3) o'" ,-_. bsgnwl(4)

E

~'" 20 10

'I

-10 50 100 150 Time 200 2SO 300 3 a FWPT Discharge Pressure ieoo I 1400 ,

1200 til 1000 til e

c, s:

0

(,)

til 800 - I-pet 5080

    • ... pcf 5090 f-c,

~

u, 600 ------ -- - ----~

400 200 a

a 50 100 150 200 250 300 350 Time

Inst. Air Hdr. Press 120 ~ __.....- ...... ~=~~~ ~ ......,

100 iii Ul 80 e

ll.

~

Ql "0

co Ql J:

~ 60 I-pvi 5060 1:

E 2

10 40 E:

20 O!.-- - - - - - ---- - ----...,..-- - - - ---l o 50 100 150 200 250 300 350 Time

Attachment 2 SRO Question 77 During the Post Exam Item Analysi s we have determined that Question 77 has two corr ect answers with Distracter "C" being a subset of the Correct Answer "0". Due to this determination we propose that both "C" and ' 0" be accepted as correct.

In this que stion the candidate is asked to determine a leak rate from the KC (Component Cooling) System . The operator is given KC surge tank levels for T=O and T- +5 min along with a copy of the KC Surge tank level curv e from the Data Book. Correctly performed, the leak rate is determined to be approximately 100 GPM. Also in the stem of the question the operator is advised that "Operators have been dispatched to initiate YM makeup to the KC surge tank", but are not told that this makeup has actually been established. The initial level in the surge tank is 6.5 ft. The candidate is then asked to determine "the required action and procedure use required in AP/2l , Loss of KC or KC System Leakage".

Per paragraph 7 of Appendix E of NUREG-I021 page 2 of 6 which is part of the briefing given prior to the exam, the candidates are given the following instructions, "When answering a que stion, do not make assumptions regarding conditions that are not specified in the question unless they occur as a consequence of other conditions that are stated in the question. Similarly, you should assum e that no operator actions have been taken, unless the stem of the question or the answer choices specifically state otherwise.

Finally, answer all que stions based on actual plant operation, procedures or the answer choices speci fically stated otherwise".

With this direction in mind the candidate can correctly assume that YM makeup is not initially align ed but within a reasonable period of time it will be. (Per the Time Critical Actions for our plant this should occur within 10 min of dispatch) According to the background document for AP-21 pg 10 of23 , "Per engineering, YM makeup should be sufficient to keep up with the FSAR design basis leak of 50 GPM ". After determining that a 100 GPM leak exists, even with YM make up aligned the candidate would reasonably come to the conclusion that KC surge tank level would continue to decrease.

Procedurally we would align the Nuclear Service Water assured makeup ifYM was not sufficient to keep up with the leak but the candidates are told to not assume any operator act ions not stated, ther efore it is reasonable for the candidate to assume that this has not and will not happen unle ss otherwise stated.

Procedural guidance per AP-21 directs that once it has been determined that a leak exists operators be dispatched early to initiate YM make up per Step 11 . The procedure then checks surge tank level greater than 3 ft which for the scenario given it should be for the first pass thru this step . The operator is then directed to check the "sum of both train s' KC surge tank level drop s LESS THAN OR EQUAL TO 0.10 FT/MIN". If true , which for the leak rate calculated, it would be, the crew is directed to Step 20 which will Isolate

"A" K C train from " B" K C train . This action is consistent with the actions stated in the Correct answe r "D" making it a valid correct answer. Onc e agai n, assuming no operator action has taken place, the surge tank levels will continue to decrease until they reach a level of 2 ft. At this point the "foldout" page would direct the operator to isolate the affected train PER Ene . 2. This actio n is stated in Distracter "C" and sinc e the stem does not refer to the "First" or "Nex t" action taken, this action is actually a subset of "0" and therefore a COITect answer.

Based on the discuss ion abov e and the attached references, we recommend that both "C" and " 0" be acce pted as correct answers.

~ . A- +1 Hhrnl'r'lt ~ Pa,j v 3 ES-401 Sample Written Examination Form ES-401-5 Question Worksheet Examination Outline Cross- Level RO SRO reference :

Tier # -

1- - -

Group # 1 KIA # (026) G2.1 .25 Importance Rating -

4.2 Proposed Question: SRO 77 Page 197 of271 Rev Final

POJ<'- 'i ES-401 Sample Written Examination Form ES-401-5 Question Worksheet Initial conditions:

Time = 0 minutes

  • Unit 1 is at 100% power.
  • "A" Train KG pumps are running .
  • Operators have been dispatched to initiate YM makeup to the KG Surge Tank.
  • "A" KG Surge Tank level is 6.5 ft.
  • "B " KG Surge Tank level is 6.5 ft.

Current conditions:

Time = 5 minutes

  • "A" KG Surge Tank level is 5.6 feet
  • "B" KG Surge Tank level is 6.4 feet.

Which ONE (1) of the following describes (1) the approximate KC system net leak rate , and (2) the required action and procedure use required in AP/21 , Loss of KG or KG System Leakage?

(Reference Provided)

A. (1 ) 50 GPM (2) Isolate KC Non-Essential Headers in accordance with Enclosure 2.

B. (1) 50 GPM (2) Isolate "A" KG train from "B" KC train.

G. (1 ) 100 GPM (2) Isolate KG Non-Essential Headers in accordance with Enclosure 2.

D. (1) 100 GPM (2) Isolate "A" KG train from "B" KG train.

Proposed Answer: 0 Explanation (Optional):

Page 198 of271 Rev Final

1+~t:Lh~("/J ~ PC\5 c 5 ES-401 Sample Written Examination Form ES-401-5 Question Worksheet D is correct per conditions. Applicant must interpret curve and determine the leak rate indications based on level decreases A incorrect because leak rate is wrong (1/2 of actual, as interpreted by curve.)

Also , action is incorrect, as procedure will direct splitting trains for indication shown B incorrect because leak rate is incorrect. Plausible because action is correct C incorrect because procedure use is incorrect. Approximately 0.1 feet/minute, perform step 20 to split trains Technical AP/21 Step 20 Rev 9 (Attach if not previously Reference(s): provided)

AP/21 Basis Document Rev 3 Proposed references to be provided to applicants during OP/1 lA/51 00/22 examination: Enclosure 4.3 Curve 7.31 Learning Objective: None Question Source : Bank #

Modified Bank x (Note changes or attach

  1. parent)

New Question History: Last NRC Exam Modified from 2007 NRC exam 78 Question Cognitive Memory or Fundamental Knowledge Level :

Comprehension or Analysis x 10 CFR Part 55 55.41 Content:

55.43 -

5- -

Comments:

KA matched because use of a curve is required and interpretation of that curve is required to determine KC (CCW) leak rate . SRO level because assessment of Page 199 of 271 Rev Final

ES-401 Sample Written Examination Form ES-401-5 Question Worksheet conditions based on available indications, and selection of procedures (attachments) is required RFA Concurs 4/17/08 Page 200 of271 Rev Final

3. For an initial examination , the nominal time limit for completing the examination is 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for the RO exam; 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> for the 25-question , SRO-only exam; 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> for the combined RO/SRO exam; and 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for the SRO exam limited to fuel handling. Notify the proctor if you need more time.

For a requalification examination, the time limit for completing both sections of the examination is 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. If both sections are administered in the simulator during a single 3-hour period, you may return to a section of the examination that you already completed or retain both sections of the examination until the allotted time has expired.

4. You may bring pens, pencils, and calculators into the examination room; however, programable memories must be erased. Use black ink to ensure legible copies; dark pencil should be used only if necessary to facilitate machine grading .
5. Print your name in the blank provided on the examination cover sheet and the answer sheet. You may be asked to provide the examiner with some form of positive identification.
6. Mark your answers on the answer sheet provided, and do not leave any question blank.

Use only the paper provided. and do not write on the back side of the pages.

If you are using ink and decide to change your original answer, draw a single line through the error, enter the desired answer, and initial the change. If you are recording your answers on a machine-gradable form that offers more than four answer choices (e.g.,

"a" through "e"), be careful to mark the correct column.

7. If you have any questions concern ing the intent or the initial conditions of a question ,

do not hesitate to ask them before answering the question. Note that questions asked during the examination are taken into consideration during the grading process and when reviewing applicant appeals . Ask questions of the NRC examiner or the designated facility instructor only. A dictionary is available if you need it.

When answering a question, do not make assumptions regarding conditions that are not specified in the question unless they occur as a consequence of other conditions that are stated in the question. For example, you should not assume that any alarm has activated unless the question so states or the alarm is expected to activate as a result of the conditions that are stated in the question . Similarly, you should assume that no operator actions have been taken, unless the stem of the question or the answer choices specifically state otherwise . Finally, answer all questions based on actual plant operation, procedures, and references. If you believe that the answer would be different based on simulator operation or training references, you should answer the question based on the actual plant.

8. Restroom trips are permitted, but only one applicant at a time will be allowed to leave.

Avoid all contact with anyone outside the examination room to eliminate even the appearance or possibility of cheating.

Appendix E, Page 2 of 6

f+ ttc.chml'/"\t  ;).. Paj G g Information Information Only Time Critical Operator Actions Only

17. Initiating makeup to the KC surge tank or isolate KC header leak Expectation:

Operator locally initiates makeup within 10 minutes of dispatch using either YM or RN, or gets leak isolated prior to emptying surge tank for design basis leak of 50gpm.

Follow-up planned:

None.

References:

FSAR 9.2.4.3 PIP M98-3618 PIP M99-3778 AP/1/A/5500/21 (Loss ofKC or KC System Leakage)

Comments:

The FSAR required time to isolate a KC leak is 30 minutes to prevent emptying KC surge tank for a 50 gpm leak. If makeup can stabilize surge tank level, operation can continue with header in service until individual component can be isolated.

A 10 minute local task to initiate makeup is based on: 1) Time to dispatch an operator in AP/21 , and 2)

Ensure margin to prevent reaching 2 ft in surge tank (for 50 gpm leak) . At 2 ft, AP/21 requires isolating KC aux bldg non-essential header. This action has been validated and times can be met.

18. Isolate letdown for a letdown header break:

Expectation:

The FSAR assumes isolation of NY letdown within 30 minutes of a complete severance of a letdown header in the aux bldg. Operations expectation is that leak will be isolated as soon as it is identified.

Follow-up planned:

None.

References:

FSAR 15.6.2.2 AP/1/A/5500/10 (NC System Leakage Within the Capacity of Both NY Pumps)

Comments:

The limiting case in FSAR is a complete severance, at rated power conditions, of the 3 inch letdown line just outside containment, between NY-7B and the letdown heat exchanger.

Page 19 of 40

A~-c.(hme/)}- d.. ~OjC 'i AP/1 and 2/Al5500/021 (Loss of KC or KC System Leakage)

If KC surge tank level is greater than 3 ft, time is given for the operators to attempt to initiate makeup and check results to see if the surge tank level can be maintained. Per engineering, YM makeup should be sufficient to keep up with the FSAR design basis leak of 50 GPM.

Operators should be able to initiate makeup prior to reaching 2 ft in the surge tanks (assuming makeup is initiated when KC 10 level alarms at 4.5 ft). If the trains are cross-tied, allowing leaving the cross-ties open doubles the volume (and time) to initiate makeup. Note that for larger leaks , or if level reaches 2 ft, the cross-ties will be closed to protect the other train. If makeup is initiated and level stabilizes, operator actions are greatly simplified.

STEP 16 NOTES:

PURPOSE:

Give operator information for determining leak rate.

DISCUSSION :

0.1 ft/min level drop is equivalent to the design basis leak (50 gpm) that YM makeup should be able to keep up with .

STEP 16:

PURPOSE:

Procedure flow path controlling step.

DISCUSSION:

If leak is greater than design basis leak, operators need to find the leak and isolate it.

Page 10 of 23 Rev 3

A -\i Ac~ rY\('r, ~ ;).. PG5 c. I 0 AP/1 and 2/Al5500/021 (Loss of KC or KC System Leakage)

INTRODUCTION This procedure gives guidance on the actions required in the event of a loss of KG, or leakage on the KG System.

OVERVIEW OF AP-21 AP-21 is written for scenarios involving a loss of KG (like KG pump trips, etc.) and for scenarios involving KG leakage. For either case, the AP first addresses some immediate concerns, like isolating letdown if no KG pumps, making plant page, and securing any dilution.

For scenarios involving a loss of KG not due to leakage, the AP quickly attempts starting the standby KG train (Step 9). It is time critical to restore KG cooling to NG pumps (approx 10 minutes). If cooling is not restored, NG pumps and a reactor trip will be required.

The AP next addresses scenarios involving KG leakage. If KG leakage is small (within design basis of 50 gpm) when makeup is initiated, it should keep up with the leak and avoid the process of header isolations. If the leak is too big for makeup , then the AP goes through a process of header isolations in a preferred order. In any case, the AP ends up with an essential header in operation, and intact non-ess headers in service.

ENTRY CONDITIONS This procedure can be entered any time the listed symptoms are encountered.

Page 2 of 23 Rev 3

I C c /"\ po,I e MNS LOSS OF KC OR KC SYSTEM LEAKAGE PAGE NO.

AP/1/A/5500/21 28 of 78 Enclosure 1 - Page 1 of 1 Rev. 9 UNIT 1 Foldout

1. KC header isolation criteria:
  • IF KC surge tank level goes below 2 ft due to KC system leak, THEN immediately isolate affected train PER Enclosure 2 (Isolation of KC Non-essential Headers ).
2. NC pump trip criteria:
  • IF NC pump motor bearing temperature reaches 195°F, THEN perform the following :
a. Trip the reactor .
b. WHEN reactor is tripped, THEN trip all NC pumps.
c. GO TO EP/1/A/5000/E-O (Reactor Trip or Safety Injection), while continuing in this procedure as time and conditions allow.
3. ND pump trip and flow isolation criteria (Applies if ND aligned for RHR):
  • IF KC cooling lost to either NO train's HX, AND NC temperature is greater than 150°F, THEN perform the following on train of NO that lost KC flow to its NO HX:
a. Stop associated NO pump.
b. IF 1A NO HX lost KC flow, THEN close:
  • 1NO-32 (A NO Hx To Letdown Hx).
c. IF 1B NO HX lost KC flow, THEN close:
  • 1NO-17 (B NO Hx To Letdown Hx).
d. IF both NO pumps off THEN REFER TO AP/1/A/5500/19 (Loss of NO or NO System Leak).
4. KC pump trip criteria:
  • IF KC surge tank level goes below .5 ft and valid, THEN:
a. Trip affected pumps .
b. Isolate affected train PER Enclosure 2 (Isolation of KC Non-essential Headers).
5. VCT high temperature:
  • IF "VCT HI TEMP" alarm (1AO-7, 0-1) is received, THEN REFER TO Enclosure 6 (VCT High Temperature Actions) .