Latest revision as of 12:17, 15 September 2025
Letter Sequence Approval |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML20280A970, ML20343A224, ML21147A547, ML21160A221, ML21218A045, ML22018A300, ML23097A123, ML23097A127, ML24103A224, ML24212A030, ML24262A066, ML24297A138, ML25017A130, ML25023A086, ML25028A267, ML25161A172
|
MONTHYEARML21263A2362020-08-0505 August 2020 Safety Evaluation by the Office of Nuclear Reactor Regulation Regarding the Terrapower, LLC Quality Assurance Topical Report Project stage: Approval ML20280A9702020-10-21021 October 2020 Terrapower - Acceptance Topical Report Quality Assurance Program Description Project stage: Other ML20294A3372020-11-10010 November 2020 Letter and Final Safety Evaluation for Kairos Power, LLC Topical Report-KP Fhr Risk-Informed Performance-Based Licensing Basis Development Methodology (Revision 1) (EPID No. L-2019-TOP-0009/CAC No. 000431) Project stage: Approval ML20343A2242020-12-0808 December 2020 Verification Letter of the Approval Version of Kairos Power LLC Topical Report KP-TR-O09-NP, - KP-FHR Risk-Informed Performance-Based Licensing Basis Development Methodology - (Revision 1) (CAC No. 000431) Project stage: Other ML21005A0152020-12-23023 December 2020 Revision to Terrapower, LLC - Quality Assurance Topical Report Project stage: Request ML21021A3642021-01-21021 January 2021 Enclosure 2: Presentation Materials About Construction Permit Application for the KP-FHR (Non-Proprietary) Project stage: Request ML21071A0822021-03-0808 March 2021 Kairos Power, LLC - Quality Assurance Program for the Kairos Power Flouride Salt-Cooled High Temperature Reactor Topical Report (Revision 1) Project stage: Request ML21071A0832021-03-31031 March 2021 Kairos Power, LLC - KP-TR-007-NP, Quality Assurance Program for the Kairos Power Flouride Salt-Cooled High Temperature Reactor Topical Report, Revision 1 (Non-Proprietary) Project stage: Request ML21105A5182021-04-15015 April 2021 Kairos Power LLC, Quality Assurance Program for the Flouride Salt-Cooled High Temperature Reactor Topical Report (Revision 2) Project stage: Request ML21117A0472021-04-26026 April 2021 Kairos Power LLC, Quality Assurance Program for the Flouride Salt-Cooled High Temperature Reactor Topical Report(Revision 3) Project stage: Request ML21117A0482021-04-26026 April 2021 Quality Assurance Program for the Kairos Power Flouride Salt Cooled High Temperature Reactor Topical Report, Revision 3 Project stage: Request ML21105A5192021-04-30030 April 2021 Kairos Power LLC, Quality Assurance Program for the Flouride Salt-Cooled High Temperature Reactor Topical Report Revision 2 Project stage: Request ML21148A2362021-05-28028 May 2021 Response to Request for Additional Information on NRCs Assessment of the Quality Assurance Program Description for Terrapower, LLCs Quality Assurance Topical Report Project stage: Response to RAI ML21147A5472021-06-0909 June 2021 Kairos Power Hermes Test Reactor Psotulated Events Audit Plan Project stage: Other ML21160A2212021-06-22022 June 2021 Letter SE Kairos Fuel Performance Methodology Topical Project stage: Other ML21183A2002021-07-0202 July 2021 Revised Response to Request for Additional Information on NRCs Assessment of the Quality Assurance Program Description for Terrapower, LLCs Quality Assurance Topical Report Project stage: Response to RAI ML21218A0452021-08-17017 August 2021 Kairos Hermes PSAR Pre-Submittal Audit Plan - Rev. 3 Project stage: Other ML21194A4392021-08-20020 August 2021 Draft Kairos Flibe Thermophisical Properties Audit Plan 6 30 21 Project stage: Draft Other ML21308A5982021-11-16016 November 2021 Letter - Kairos Power, LLC - Safety Evaluation for Kairos Power, LLC Topical Report KP-TR-007-NP, Quality Assurance Program Project stage: Approval ML21308A5972021-11-16016 November 2021 Enclosure - Safety Evaluation for Kairos Power LLC Topical Report KP-TR-007-NP, Quality Assurance Program for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor, Revision 3 Project stage: Approval ML22018A3002022-01-21021 January 2022 Letter - NRC Feedback on Terrapower Advanced SER QAPD Project stage: Other ML22018A1612022-01-31031 January 2022 Kairos Power LLC, Kp& 8208;TR& 8208;004& 8208;NP, Regulatory Analysis for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor, Rev. 4 Project stage: Request ML22024A4852022-02-0808 February 2022 OEDO-21-00545 -Safety Evaluation of the Kairos Power LLC Topical Report KP-TR-012-P, Revision 1, KP-FHR Mechanistic Source Term Methodology Project stage: Request ML22088A2312022-03-28028 March 2022 KP-TR-012-NP, Revision 3, KP-FHR Mechanistic Source Term Methodology Topical Report Project stage: Request ML22112A1332022-04-22022 April 2022 Kairos Power, LLC, Safety Evaluation for KP-TR-012 KP-FHR Mechanistic Source Term Methodology Topical Report, Revision 3 (EPID L-2020-TOP-0051/CAC 000431) Project stage: Approval ML22136A0892022-05-26026 May 2022 Safety Evaluation for Kairos Regulatory Analysis Topical Report Kp TR-004, Revision 4 Project stage: Approval ML22186A2132022-07-0505 July 2022 Kairos Power LLC, Fuel Qualification Methodology for Fluoride Salt-Cooled High Temperature Reactor (KP-FHR), Revision 2 Project stage: Request ML22216A1792022-07-29029 July 2022 Submission of X Energy, LLC (X-energy) TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML22265A2182022-09-21021 September 2022 Withdrawal of X Energy, LLC (X-energy) Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revisions 1 and 2 Project stage: Request ML22266A2862022-09-23023 September 2022 Submittal of Revised Terrapower, LLC Quality Assurance Topical Report, Revision 14 Project stage: Request ML22318A2362022-11-10010 November 2022 Submission of X Energy, LLC (X-energy) Xe-100 Licensing White Paper Probabilistic Risk Assessment Technical Adequacy Approach Project stage: Request ML23024A2632023-02-0808 February 2023 Staff Response to Advisory Committee on Reactor Safeguards Letter on Safety Evaluation of the Kairos TR Project stage: Request ML23048A3262023-03-0202 March 2023 Final Safety Evaluation for Kairos Fuel Qualification TR Project stage: Approval ML22327A1982023-03-0909 March 2023 Cover Letter – X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Approval ML22327A2012023-03-0909 March 2023 X Energy LLC - Safety Evaluation of XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Revision No. 3 (EPID No. L-2021-TOP-0011) - Redacted Project stage: Approval ML23062A7282023-03-13013 March 2023 Redacted Final Safety Evaluation of Metallic Material Qualification for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor (KP-TR-013) Project stage: Approval ML23062A7332023-03-14014 March 2023 Redacted Final Safety Evaluation of Graphite Material Qualification for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor (KP-TR-014) Project stage: Approval ML24325A3772023-03-20020 March 2023 Revised Draft SE Natrium EPZ TR Project stage: Draft Approval ML23116A1832023-05-0909 May 2023 Enclosure - Safety Evaluation of Quality Assurance Topical Report TP-QA-PD-0001, Terrapower QA Program Description, Revisions 13 and 14 Project stage: Approval ML23116A1782023-05-0909 May 2023 Letter - Safety Evaluation of Quality Assurance Topical Report TP-QA-PD-0001, Terrapower QA Program Description, Revisions 13 and 14 Project stage: Approval ML23097A1232023-05-31031 May 2023 Letter - X Energy, LLC - U.S. NRC Observations Regarding Xe-100 White Paper - Probabilistic Risk Assessment Technical Adequacy Approach Project stage: Other ML23097A1272023-05-31031 May 2023 Enclosure - X Energy, LLC – NRC Feedback Regarding Xe-100 Licensing White Paper Probabilistic Risk Assessment Technical Adequacy Approach (EPID L-2022-LRO-0150/CAC 000431) Project stage: Other ML23174A1752023-07-0606 July 2023 Transmittal Letter of Safety Evaluation for General Atomics Electromagnetic Systems Topical Report 30599T00005, Revision 2 Project stage: Approval ML23194A2332023-07-17017 July 2023 Email Acceptance Kairos Setpoint TR Project stage: Other 2022-01-31
[Table View] |
Text
April 4, 2024 Mr. Peter Hastings Vice President, Regulatory Affairs and Quality Kairos Power LLC 707 W Tower Ave Alameda, CA 94501
SUBJECT:
KAIROS POWER LLC - FINAL SAFETY EVALUATION OF TOPICAL REPORT, INSTRUMENT SETPOINT METHODOLOGY FOR THE KAIROS POWER FLUORIDE SALT-COOLED HIGH-TEMPERATURE REACTOR, REVISION 1 (CAC NO. 000431 / EPID NO: L-2023-TOP-0033)
Dear Mr. Hastings:
By letter dated May 31, 2023 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML23152A181), Kairos Power LLC (Kairos) requested the U.S. Nuclear Regulatory Commission (NRC) staffs review and approval of topical report (TR)
KP-TR-021-NP, Instrument Setpoint Methodology for the Kairos Power Fluoride Salt-Cooled High-Temperature Reactor, Revision 0. By letter dated October 4, 2023, Kairos submitted Revision 1 of KP-TR-021-NP (ML23277A313).
In an email dated March 15, 2024 (ML24086A549) the NRC staff provided Kairos with a draft of its safety evaluation (SE) (ML24033A263) for the purpose of identifying proprietary information.
In an email dated March 21, 2024 (ML24086A551), Kairos confirmed that there was no proprietary information in the draft SE. The NRC staffs final SE for KP-TR-021-NP, Revision 1, is enclosed.
The NRC staff requests that Kairos publish an accepted version of this TR within 3 months of receipt of this letter. The accepted version shall incorporate this letter and the enclosed SE after the title page. The accepted version shall include an "-A" (designated accepted) following the TR identification number.
If you have any questions, please contact Samuel Cuadrado via email at Samuel.CuadradodeJesus@nrc.gov.
Sincerely, William Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Project No.: 99902069
Enclosure:
Safety Evaluation William T.
Jessup Digitally signed by William T. Jessup Date: 2024.04.03 16:40:07 -04'00'
Pkg: ML24091A004 Letter: ML24091A005 Safety Evaluation: ML24091A006 OFFICE NRR/DANU/UAL1:PM NRR/DANU/UAL1:LA OGC/NLO NAME CSantos DGreene AGhosh DATE 4/1/2024 4/1/2024 4/2/2024 OFFICE NRR/DEX/EICB:BC NRR/DANU/UAL1:BC NAME FSacko WJessup DATE 4/2/2024 4/3/2024