ML15140A640: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 2
| page count = 2
| project = TAC:MF6120, TAC:MF6121
| project = TAC:MF6120, TAC:MF6121
| stage = Acceptance Review
}}
}}



Revision as of 06:52, 30 March 2018

2015/05/20 NRR E-mail Capture - Diablo Canyon, Units 1 and 2 - Acceptance Review of LAR 15-02 to Revise UFSAR for Beacon Power Dist Monitoring System Methodology and TS 5.6.5 for the Paragon and Nexus Core Design Methods (TAC Nos. MF6120 an
ML15140A640
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/20/2015
From: Lingam S P
Plant Licensing Branch IV
To: Richardson M
Pacific Gas & Electric Co
References
TAC MF6120, TAC MF6121
Download: ML15140A640 (2)


Text

1NRR-PMDAPEm ResourceFrom:Lingam, SivaSent:Wednesday, May 20, 2015 2:52 PMTo:mjrm@pge.comCc:Markley, Michael; Dean, Jeremy; Forsaty, Fred; West, Khadijah; Soenen, Philippe R (PNS3@pge.com); Schrader, Kenneth (KJSe@pge.com); cjm2@pge.com; adh6@pge.com; Burkhardt, JanetSubject:Diablo Canyon, Units 1 and 2 - Acceptance Review of LAR 15-02 to Revise UFSAR for BEACON Power Dist Monitoring System Methodology and TS 5.6.5 for the PARAGON and NEXUS Core Design Methods (TAC Nos. MF6120 and MF6121)By letter dated April 16, 2015 (ADAMS Accession No. ML15107A333), Pacific Gas and Electric Company (PG&E, the licensee) submitted a license amendment request (LAR) 15-02 for Diablo Canyon Power Plant (DCPP), Units 1 and 2, requesting an approval to revise the Best Estimate Analyzer for the Core Operations-Nuclear (BEACON) power distribution monitoring system methodology described in the DCPP Updated Final Safety Analysis Report (UFSAR) Section 4.3.2.2, "Power Distribution," to the method described in WCAP-12472-P-A, Addendum 4, "BEACON Core Monitoring and Operation Support System." This LAR also proposes to revise Technical Specification (TS) 5.6.5, "Core Operating Limits Report (COLR)," Section b to replace WCAP-11596-P-A, "Qualification of the PHOENIX-P/ANC Nuclear Design System for Pressurized Water Reactor Cores," with U.S. Nuclear Regulatory Commission (NRC)-approved WCAP-16045-P-A, "Qualification of the Two-Dimensional Transport Code PARAGON," and NRC-approved WCAP-16045-P-A, Addendum 1-A, "Qualification of the NEXUS Nuclear Data Methodology." The purpose of this e-mail is to provide the results of the NRC staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me.

Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager (NRR/DORL/LPL4-1)

Cooper Nuclear Station Diablo Canyon Nuclear Power Plant Location: O8-D5; Mail Stop: O8-B3 Telephone: 301-415-1564; Fax: 301-415-1222 E-mail address: siva.lingam@nrc.gov Hearing Identifier: NRR_PMDA Email Number: 2094 Mail Envelope Properties (Siva.Lingam@nrc.gov20150520145100)

Subject:

Diablo Canyon, Units 1 and 2 - Acceptance Review of LAR 15-02 to Revise UFSAR for BEACON Power Dist Monitoring System Methodology and TS 5.6.5 for the PARAGON and NEXUS Core Design Methods (TAC Nos. MF6120 and MF6121)

Sent Date: 5/20/2015 2:51:44 PM Received Date: 5/20/2015 2:51:00 PM From: Lingam, Siva Created By: Siva.Lingam@nrc.gov Recipients: "Markley, Michael" <Michael.Markley@nrc.gov> Tracking Status: None "Dean, Jeremy" <Jeremy.Dean@nrc.gov> Tracking Status: None "Forsaty, Fred" <Fred.Forsaty@nrc.gov> Tracking Status: None "West, Khadijah" <Khadijah.West@nrc.gov>

Tracking Status: None "Soenen, Philippe R (PNS3@pge.com)" <PNS3@pge.com> Tracking Status: None "Schrader, Kenneth (KJSe@pge.com)" <KJSe@pge.com> Tracking Status: None "cjm2@pge.com" <cjm2@pge.com>

Tracking Status: None "adh6@pge.com" <adh6@pge.com> Tracking Status: None "Burkhardt, Janet" <Janet.Burkhardt@nrc.gov> Tracking Status: None "mjrm@pge.com" <mjrm@pge.com> Tracking Status: None Post Office: Files Size Date & Time MESSAGE 2701 5/20/2015 2:51:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: