Mr. Ray Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 North State, Route 2 Oak Harbor, OH 43449-9760 | Mr. Ray Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 North State, Route 2 Oak Harbor, OH 43449-9760 | ||
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1- CORRECTION LETTER FOR SAFETY EVALUATION FOR RELIEF REQUESTS RP-6 AND RV-1 (TAC NOS. MF0754 AND MF0755)(L-13-067) | SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1- CORRECTION LETTER FOR SAFETY EVALUATION FOR RELIEF REQUESTS RP-6 AND RV-1 (TAC NOS. MF0754 AND MF0755)(L-13-067) | ||
Dear Mr. Lieb: | |||
By letter dated August 1, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No ML13210A467), the Nuclear Regulatory Commission (NRC) approved requests for relief RP-6 and RV-1 at Davis-Besse Nuclear Power Station (DBNPS) | By letter dated August 1, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No ML13210A467), the Nuclear Regulatory Commission (NRC) approved requests for relief RP-6 and RV-1 at Davis-Besse Nuclear Power Station (DBNPS) | ||
Unit 1. On August 6, 2013, Mr. Phil Lashley notified the NRC staff of a minor error in the safety evaluation. On page 7 at the top of the page, the sentence should be revised to read: | Unit 1. On August 6, 2013, Mr. Phil Lashley notified the NRC staff of a minor error in the safety evaluation. On page 7 at the top of the page, the sentence should be revised to read: | ||
Alternative testing in accordance with ASME Code Case OMN-1 (2006 Addenda) is requested for MOV assemblies included in the DBNPS MOV program listed on pages 4-9 of Attachment F to the letter dated February 27, 2013. | Alternative testing in accordance with ASME Code Case OMN-1 (2006 Addenda) is requested for MOV assemblies included in the DBNPS MOV program listed on pages 4-9 of Attachment F to the letter dated February 27, 2013. | ||
Additionally on page 8 the second section under Section 4.0 should be revised to read: In addition, the NRC staff has concluded that the proposed alternative RV-1 to implement ASME OM Code 2006 Addenda Code Case OMN-1, with the conditions specified in RG 1.192 for MOV assemblies listed on pages 4-9 of Attachment F to the letter dated February 27, 2013, provides an acceptable level of quality and safety. These corrections do not alter any findings or conclusions | |||
Sincerely, | |||
/ RA / | |||
Eva A. Brown, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | |||
Eva A. Brown, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | |||
Docket No. 50-346 | Docket No. 50-346 | ||
August 28, 2013 Mr. Ray Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 North State, Route 2 Oak Harbor, OH 43449-9760 | August 28, 2013 Mr. Ray Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 North State, Route 2 Oak Harbor, OH 43449-9760 | ||
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1- CORRECTION LETTER FOR SAFETY EVALUATION FOR RELIEF REQUESTS RP-6 AND RV-1 (TAC NOS. MF0754 AND MF0755)(L-13-067) | SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1- CORRECTION LETTER FOR SAFETY EVALUATION FOR RELIEF REQUESTS RP-6 AND RV-1 (TAC NOS. MF0754 AND MF0755)(L-13-067) | ||
Dear Mr. Lieb: | |||
By letter dated August 1, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No ML13210A467), the Nuclear Regulatory Commission (NRC) approved requests for relief RP-6 and RV-1 at Davis-Besse Nuclear Power Station (DBNPS) | By letter dated August 1, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No ML13210A467), the Nuclear Regulatory Commission (NRC) approved requests for relief RP-6 and RV-1 at Davis-Besse Nuclear Power Station (DBNPS) | ||
Unit 1. On August 6, 2013, Mr. Phil Lashley notified the NRC staff of a minor error in the safety evaluation. On page 7 at the top of the page, the sentence should be revised to read: | Unit 1. On August 6, 2013, Mr. Phil Lashley notified the NRC staff of a minor error in the safety evaluation. On page 7 at the top of the page, the sentence should be revised to read: | ||
Alternative testing in accordance with ASME Code Case OMN-1 (2006 Addenda) is requested for MOV assemblies included in the DBNPS MOV program listed on pages 4-9 of Attachment F to the letter dated February 27, 2013. | Alternative testing in accordance with ASME Code Case OMN-1 (2006 Addenda) is requested for MOV assemblies included in the DBNPS MOV program listed on pages 4-9 of Attachment F to the letter dated February 27, 2013. | ||
Additionally on page 8 the second section under Section 4.0 should be revised to read: In addition, the NRC staff has concluded that the proposed alternative RV-1 to implement ASME OM Code 2006 Addenda Code Case OMN-1, with the conditions specified in RG 1.192 for MOV assemblies listed on pages 4-9 of Attachment F to the letter dated February 27, 2013, provides an acceptable level of quality and safety. These corrections do not alter any findings or conclusions in the issued safety evaluation. | |||
Sincerely, / RA / | |||
Eva A. Brown, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346 | |||
Sincerely,/ RA / | |||
Eva A. Brown, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346 | |||
Distribution: PUBLIC LPL3-2 R/F RidsRgn3MailCenter Resource RidsAcrsAcnw_MailCTR MFarnan RidsNrrDorlLpl3-2 Resource RidsNrrDeEpnb Resource RidsNrrDavisBesse Resource VCampbell, EDO, RIII RidsNrrLASRorher ADAMS ACCESSION NUMBER:ML13228A039 | Distribution: PUBLIC LPL3-2 R/F RidsRgn3MailCenter Resource RidsAcrsAcnw_MailCTR MFarnan RidsNrrDorlLpl3-2 Resource RidsNrrDeEpnb Resource RidsNrrDavisBesse Resource VCampbell, EDO, RIII RidsNrrLASRorher ADAMS ACCESSION NUMBER:ML13228A039 NRR-028 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC(A) NAME EBrown SRorher (SFiguroa) JBowen (JWiebe for) DATE 8/26/13 8/26/13 8/28/13 OFFICIAL RECORD COPY | ||
}} |
Revision as of 14:10, 22 March 2018
ML13228A039 | |
Person / Time | |
---|---|
Site: | Davis Besse |
Issue date: | 08/28/2013 |
From: | Brown E A Plant Licensing Branch III |
To: | Lieb R FirstEnergy Nuclear Operating Co |
Eva Brown, NRR/DORL 415-2315 | |
References | |
L-13-067, TAC MF0754, TAC NF0755 | |
Download: ML13228A039 (3) | |
Text
August 28, 2013 !
Mr. Ray Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 North State, Route 2 Oak Harbor, OH 43449-9760
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1- CORRECTION LETTER FOR SAFETY EVALUATION FOR RELIEF REQUESTS RP-6 AND RV-1 (TAC NOS. MF0754 AND MF0755)(L-13-067)
Dear Mr. Lieb:
By letter dated August 1, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No ML13210A467), the Nuclear Regulatory Commission (NRC) approved requests for relief RP-6 and RV-1 at Davis-Besse Nuclear Power Station (DBNPS)
Unit 1. On August 6, 2013, Mr. Phil Lashley notified the NRC staff of a minor error in the safety evaluation. On page 7 at the top of the page, the sentence should be revised to read:
Alternative testing in accordance with ASME Code Case OMN-1 (2006 Addenda) is requested for MOV assemblies included in the DBNPS MOV program listed on pages 4-9 of Attachment F to the letter dated February 27, 2013.
Additionally on page 8 the second section under Section 4.0 should be revised to read: In addition, the NRC staff has concluded that the proposed alternative RV-1 to implement ASME OM Code 2006 Addenda Code Case OMN-1, with the conditions specified in RG 1.192 for MOV assemblies listed on pages 4-9 of Attachment F to the letter dated February 27, 2013, provides an acceptable level of quality and safety. These corrections do not alter any findings or conclusions
Sincerely,
/ RA /
Eva A. Brown, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket No. 50-346
August 28, 2013 Mr. Ray Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 North State, Route 2 Oak Harbor, OH 43449-9760
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1- CORRECTION LETTER FOR SAFETY EVALUATION FOR RELIEF REQUESTS RP-6 AND RV-1 (TAC NOS. MF0754 AND MF0755)(L-13-067)
Dear Mr. Lieb:
By letter dated August 1, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No ML13210A467), the Nuclear Regulatory Commission (NRC) approved requests for relief RP-6 and RV-1 at Davis-Besse Nuclear Power Station (DBNPS)
Unit 1. On August 6, 2013, Mr. Phil Lashley notified the NRC staff of a minor error in the safety evaluation. On page 7 at the top of the page, the sentence should be revised to read:
Alternative testing in accordance with ASME Code Case OMN-1 (2006 Addenda) is requested for MOV assemblies included in the DBNPS MOV program listed on pages 4-9 of Attachment F to the letter dated February 27, 2013.
Additionally on page 8 the second section under Section 4.0 should be revised to read: In addition, the NRC staff has concluded that the proposed alternative RV-1 to implement ASME OM Code 2006 Addenda Code Case OMN-1, with the conditions specified in RG 1.192 for MOV assemblies listed on pages 4-9 of Attachment F to the letter dated February 27, 2013, provides an acceptable level of quality and safety. These corrections do not alter any findings or conclusions in the issued safety evaluation.
Sincerely, / RA /
Eva A. Brown, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346
Distribution: PUBLIC LPL3-2 R/F RidsRgn3MailCenter Resource RidsAcrsAcnw_MailCTR MFarnan RidsNrrDorlLpl3-2 Resource RidsNrrDeEpnb Resource RidsNrrDavisBesse Resource VCampbell, EDO, RIII RidsNrrLASRorher ADAMS ACCESSION NUMBER:ML13228A039 NRR-028 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC(A) NAME EBrown SRorher (SFiguroa) JBowen (JWiebe for) DATE 8/26/13 8/26/13 8/28/13 OFFICIAL RECORD COPY