{{#Wiki_filter:May 30, 2006Mr. Karl E. SingerChief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
{{#Wiki_filter:May 30, 2006 Mr. Karl E. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801


==SUBJECT:==
==SUBJECT:==
BROWNS FERRY NUCLEAR PLANT UNIT 1 - SUPPLEMENTAL RESPONSETO GENERIC LETTER 88-01, NRC POSITION ON INTERGRANULAR STRESS CORROSION CRACKING IN BWR [BOILING WATER REACTOR]
BROWNS FERRY NUCLEAR PLANT UNIT 1 - SUPPLEMENTAL RESPONSE TO GENERIC LETTER 88-01, NRC POSITION ON INTERGRANULAR STRESS CORROSION CRACKING IN BWR [BOILING WATER REACTOR]
AUSTENITIC STAINLESS STEEL PIPING (TAC NO. MC4891)
AUSTENITIC STAINLESS STEEL PIPING (TAC NO. MC4891)


==Dear Mr. Singer:==
==Dear Mr. Singer:==


The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated the informationsubmitted by Tennessee Valley Authority (TVA, the licensee), in its letter dated July 21, 2004, and supplemental letters dated April 25, 2005, and February 22, 2006. The letters were in response to Generic Letter (GL) 88-01, "NRC Position on Intergranular Stress CorrosionCracking in BWR Austenitic Stainless Steel Piping." The NRC staff has completed its review of the response, and concluded in the enclosed safetyevaluation that TVA has provided an acceptable resolution to the GL 88-01 concerns. If you have any questions regarding this matter, please contact me at (301) 415-4041.Sincerely,/RA by B. Mozafari for/Margaret H. Chernoff, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-259
The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated the information submitted by Tennessee Valley Authority (TVA, the licensee), in its letter dated July 21, 2004, and supplemental letters dated April 25, 2005, and February 22, 2006. The letters were in response to Generic Letter (GL) 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR Austenitic Stainless Steel Piping.
The NRC staff has completed its review of the response, and concluded in the enclosed safety evaluation that TVA has provided an acceptable resolution to the GL 88-01 concerns.
If you have any questions regarding this matter, please contact me at (301) 415-4041.
Sincerely,
                                            /RA by B. Mozafari for/
Margaret H. Chernoff, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-259


==Enclosure:==
==Enclosure:==
Safety Evaluation cc w/encl: See next page  
Safety Evaluation cc w/encl: See next page


ML061280456                                             NRR-088OFFICELPL2-2/PMLPL2-2/PMLPL2-2/LACPNB/BCLPL2-2/BCNAMEBMozafari/emBMozafari forMChernoffBClaytonTChan -Memo dated MMarshallDATE  5/19/06 5/19/06 5/19/0604/18/06     5/30/06 EnclosureSAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATIONSUPPLEMENTAL RESPONSE TO GENERIC LETTER 88-01BROWNS FERRY NUCLEAR PLANT, UNIT 1TENNESSEE VALLEY AUTHORITYDOCKET NO: 50-25
ML061280456                                                 NRR-088 OFFICE      LPL2-2/PM    LPL2-2/PM        LPL2-2/LA        CPNB/BC          LPL2-2/BC NAME        BMozafari/em BMozafari for      BClayton          TChan -           MMarshall MChernoff                          Memo dated DATE          5/19/06       5/19/06         5/19/06          04/18/06             5/30/06 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION SUPPLEMENTAL RESPONSE TO GENERIC LETTER 88-01 BROWNS FERRY NUCLEAR PLANT, UNIT 1 TENNESSEE VALLEY AUTHORITY DOCKET NO: 50-259


==91.0 INTRODUCTION==
==1.0     INTRODUCTION==
By letter dated July 21, 2004, as supplemented by letters dated April 25, 2005, andFebruary 22, 2006, Tennessee Valley Authority (TVA, the licensee), submitted responses to Generic Letter (GL) 88-01, "NRC Position on Intergranular Stress Corrosion Cracking inBWR [Boiling-Water Reactor] Austenitic Stainless Steel Piping."  The Nuclear Regulatory Commission (NRC) staff notes that Browns Ferry Nuclear Plant, Unit 1 (BFN 1), deferred responding to GL 88-01 until now because it has been in an extended outage since March 1985, and is now preparing for restart. The NRC staff reviewed the information provi ded byTVA. The staff evaluation of the response follows.


==2.0 REGULATORY EVALUATION==
By letter dated July 21, 2004, as supplemented by letters dated April 25, 2005, and February 22, 2006, Tennessee Valley Authority (TVA, the licensee), submitted responses to Generic Letter (GL) 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR [Boiling-Water Reactor] Austenitic Stainless Steel Piping. The Nuclear Regulatory Commission (NRC) staff notes that Browns Ferry Nuclear Plant, Unit 1 (BFN 1), deferred responding to GL 88-01 until now because it has been in an extended outage since March 1985, and is now preparing for restart. The NRC staff reviewed the information provided by TVA. The staff evaluation of the response follows.
The licensee stated that nondestructive examinations, repairs, stress improvement and pipereplacement with corrosion resistant materials are being implemented at BFN1. These activities are being performed to reduce the potential for Intergranular Stress Corrosion Cracking (IGSCC) and are consistent with the guidelines in GL 88-01 and prevailing BWRindustry practice.As required in GL 88-01 the licensee has provided a supplemental response to the NRC. The licensee response includes the following topics:(1) Plans regarding long-term mitigation of IGSCC.
(2) A discussion of the inservice inspection program.
(3) A verification of the adequacy of the Browns Ferry NuclearTechnical Specifications (TSs).(4) Confirmation of leakage detection methods.
(5) Reporting requirements to NRC for flaws. 2.1 Plans Regarding Long-Term Mitigation of IGSCCThe licensee stated the following measures are being taken at BFN1 to improve inspectionquality and reduce/control IGSCC:
!Inspections using nondestructive examination equipment, qualified examiners andqualified techniques in accordance with the American Society of Mechanical Engineers Code are being used. Weld crown reduction is also being employed to enhance the quality of the examination. In a letter dated February 22, 2006, the licensee stated thatthe personnel qualified for inspecting for IGSCC were qualified in accordance with the Tri-party agreement and re-qualification of personnel would be performed every 3 years.
!Repair of IGSCC indications is being performed by using replacement piping. Replacement piping materials are resistant to IGSCC as defined in GL 88-01. In a letter dated April 25, 2005, the licensee stated that no weld overlays were used on thereplacement piping.
!Where practical, mechanical stress improvement of susceptible piping and replacementpiping is being performed.
!A reduction in the number of welds is being achieved by using designs which employintegral bends and branches in replacement piping where possible.
!Hydrogen water chemistry is being implemented to reduce susceptibility to IGSCC. Additionally, in a letter dated February 22, 2006, the licensee stated that the inspectionschedule for IGSCC weldments follows the guidelines in BWRVIP [BWR Vessel and Internals Project] -75, including hydrogen water chemistry (HWC) effectiveness, where credit for HWC is taken.The NRC staff considers these measures acceptable because the measures would mitigate theeffects of IGSCC.The wrought austenitic stainless steel piping systems and components that are consideredsusceptible to IGSCC according to the guidelines given in GL 88-01 are as follows:
!Reactor Recirculation from the recirculation inlet and outlet nozzles to the connectionswith residual heat removal.
!Residual Heat Removal (RHR) from the recirculation system to the first isolation valveoutside of the drywell penetration.
!Reactor Water Cleanup (RWCU) from its connection to the RHR system to the firstisolation valve outside of the drywell penetration.
!Core Spray (CS) from the core spray inlet nozzles to the drywell penetration, includingthe core spray inlet safe ends. The piping within and upstream of the penetration is not considered susceptible due the low-operating temperature, generally 130F or less.
!Jet pump instrument safe ends. The licensee stated that the head spray system is not included because it will be removed fromUnit 1 prior to restart. Similarly, the control rod drive return and recirculation discharge valve bypass have been removed from Unit 1 and are, therefore, not considered. The NRC stafffinds that the licensee has adequately defined the piping systems that are susceptible toIGSCC, as required by GL 88-01.The licensee also stated that IGSCC susceptible weldments are being inspected or are beingremoved from service and replaced. The inaccessible welds will be inspected as described in aletter to the NRC dated November 25, 1992. This methodology was approved by the NRC in aletter dated February 18, 1993. In a response to a request for additional information (RAI) dated April 25, 2005, concerning inspection techniques and methods for weld overlays, the licensee stated there will be no weld overlays in Unit 1 since all of the previously affected piping with weld overlays has been removed and replaced.The licensee indicated that the following piping will be replaced at BFN1:


!Reactor recirculation inlet and outlet safe ends are being replaced due to concerns ofcrevice corrosion attack. The replacement safe ends utilize an improved designemploying resistant material and a crevice-free configuration.
==2.0      REGULATORY EVALUATION==
!Reactor recirculation piping is being replaced. This includes the 28-inch pump suctionand discharge piping, the 12-inch risers and 22-inch ringheader. The replacement piping is 316NG stainless steel, which is less susceptible to IGSCC. Improved construction methods and bent pipe result in fewer welds. The ringheader design eliminates the ringheader cross-tie valves.
!CS and RHR piping inside the containment are being replaced. The replacement pipingis 316NG stainless steel for the RHR system and American Society for Testing andMaterials SA-333 Grade 6, hi gh toughness grade of carbon steel for the CS system,which is less susceptible to IGSCC.
!RWCU piping is being replaced both inside and outside containment, as was discussedin a letter to the NRC dated May 22, 1989. This replacement included the penetrationprocess piping and eliminated the uninspectable weld located inside the penetration. The replacement material utilized is resistant to IGSCC. The licensee stated that 316NG stainless steel is being used for all piping operating above 200F.!Jet pump instrumentation nozzle safe ends and seal assemblies are being replaced toremove cracking and overlays. The replacement assemblies are an improved design, fabricated from IGSCC resistant materials.The NRC staff finds the licensee's plan acceptable because piping susceptible to IGSCC wouldbe replaced with piping that is resistant to IGSCC.Also, the licensee stated that welds containing indications of cracking were replaced with316NG IGSCC resistant material. 2.2 Discussion of the Inservice Inspection (ISI) ProgramThe licensee stated that future inspections performed on piping within the scope of GL 88-01will conform to the NRC staff positions on methods, personnel, schedules and expansion plans. The NRC staff considers this program to be acceptable.2.3 Conformance to the ISI Requirements of GL 88-01GL 88-01 requested a change to the TSs to include a statement in the section on ISI that theISI program for piping covered by the scope of this letter will be in conformance with the staffposition on schedule, methods, and personnel. The licensee submitted this TS change to the NRC on December 9, 1988 as TS 262; it was approved on May 19, 1989, as Amendment 166for Unit 1.The licensee has since submitted Unit 1 TS Change 362 - Improved TSs (ITSs). The licenseestated this change was TVA's conversion package from Custom TSs to ITSs. The NRC approved this change in a letter to the licensee on July 14, 1998. The licensee stated the TS requirements for the ISI program are no longer part of ITSs or the BFN TSs. As discussed in the GL, the licensee stated the requirements regarding schedule, methods, and personnel willbe included in the Unit 1 ISI program.The NRC staff finds this program meets the ISI requirements of GL 88-01 and is, therefore,acceptable.2.4 TSs on Conformance to Staff Positions on Leak DetectionThe licensee stated the TS conformance to the staff positions on leak detection was previouslysubmitted to the NRC on December 15, 1986, as TS-222 and approved on August 26, 1987, asAmendment 137 for Unit 1.As stated previously, TVA submitted Unit 1 TS Change 362 - ITS. The NRC approved thischange in a letter to the licensee dated July 14, 1998.The NRC staff finds the licensee's program on leak detection meets the NRC position and is,therefore, acceptable.2.5 Plans to Notify NRC of FlawsThe licensee stated that in the past, the NRC has been notified of the inspection results, flawevaluations and repair mitigation measures associated with the BFN units through a comprehensive report submitted before plant startup. The licensee stated this report covers Unit 1 activities. The licensee stated that after the IGSCC mitigation work scopes have been fully implemented, reports will be made only in the event of the discovery of new flaws or achange is found in the condition of flaws previously detected. For these events, a full report of the flaw evaluation and strategy and technical justification for repair or continued operation willbe submitted prior to plant startup. Additionally, a 90-day ISI summary report will still besubmitted to the NRC for review.The NRC staff finds the licensee's program for NRC notification of flaws to be acceptable. 2.6 Differences Between the Unit 1 Program and the Program Previously Approved forUnits 2 and 3The licensee stated that replacement of piping susceptible to IGSCC with piping resistant toIGSCC is more extensive in BFN1 than in Units 2 or 3. The licensee stated that Unit 1 has replaced more piping. To support the statement, the licensee has provided a general description of the piping replaced in Unit 1 and a comparison with the piping replacement efforts of Units 2 and 3.
!Reactor Water Recirculation piping in Unit 1 is being completely replaced with resistantmaterials versus a partial replacement scope for this system in Units 2 and 3. Recirculation riser piping was replaced in Unit 2, and the riser piping, header arms and crosses were replaced in Unit 3. The Unit 1 replacement piping material is the same material as used in Unit 3.
!RWCU piping is also being completely replaced in Unit 1, including the containmentpenetration piping, similar to the replacement effort scope in Unit 3. Unit 2 piping was partially replaced inside the drywell, penetration piping and a portion of the piping adjacent to valve FCV 69-01, in conjunction with replacement of RWCU piping outside the drywell. The Unit 1 replacement piping material is the same material as used in Unit 3.!CS piping replacement scope inside the drywell for Unit 1 extends to the containmentpenetration piping. The Units 2 and 3 CS piping replacement inside the drywell extended to the inboard containment isolation valve. One loop of the Unit 1 CS pipereplacement also included replacement of a piping section containing a weld overlay outside containment between the penetration and an outboard containment isolationvalve. The Unit 1 replacement piping material is the same material as used in Unit 3.
!RHR piping replacement inside the drywell for Unit 1 extends to the containmentpenetration piping for the two injection lines and the shutdown cooling suction line.
The RHR piping on Unit 3 was replaced between the manual isolation valves for the twoinjection lines and the tie-in to the Recirculation tee connection for the 24-inch piping.
The licensee stated that the Unit 2 RHR piping was not replaced. The replacement piping used in Unit 1 is the same material as used in Unit 3.Additionally, the licensee provided clarifications to three RAIs in a letter dated February 22,2006. The RAIs referred to the Table 1 listing of piping identified in the supplemental response to GL 88-01.RAI No. 2 requested clarification or justification as to why two welds with limited accessibility(DRHR-1-3 and DRHR-1-12) are listed in Category D and not in Category G.The licensee stated that IGSCC Category D weldments are defined as those not madewith resistant materials and have not been given a Stress Improvement (SI) treatment, but have been inspected by examiners and procedures in conformance with Section 5.2.1 (NUREG-0313, Rev.2), and found to be free of cracks. IGSCCCategory G weldments are those not made of resistant materials, have not been given an SI treatment and have not been inspected in accordance with Section 5.2.1. Stress  improved welds that were not inspected after the SI treatments are considered to beCategory G weldments until the post-SI inspection has been performed.The licensee stated that the two Category D welds, DRHR-1-3 and DRHR-1-12, arecomposed of nonresistant materials and have no stress improvement. This categorization is consistent with Units 2 and 3 for their corresponding weldments. These weldments were examined to the maximum extent practical utilizing qualifiedpersonnel and procedures in accordance with their classification as Category D.RAI No. 3 requested clarification that Category G and D welds listed in Table 1 that are havingMechanical Stress Improvement Process (MSIP) performed would undergo an inservice examination prior to MSIP to ensure that no unacceptable flaws are present.The licensee stated that ultrasonic examinations that are capable of IGSCC detectionare performed prior to application of MSIP to ensure a flaw does not exist, which could propagate in the weldment during the application of the stress improvement process. Existing weldments that were made prior to the current BFN1 recovery effort, which were categorized as Category G or D, were ultrasonically examined utilizing qualifiedpersonnel and procedures for IGSCC detection both prior to and following MSIP application. The weldments made in the process of BFN1 recovery, for all IGSCC categories, were ultrasonically examined on a sampling basis (13 welds examined) prior to MSIP application and ultrasonically examined on a 100-percent basis following MSIP application. There were no relevant indications detected in the post-MSIP IGSCC examinations.RAI No. 4 requested clarification concerning why a number of Category D welds arecharacterized as new welds, since all new piping is made of IGSCC resistant materials.The licensee stated that there were two cases where replacement materials wereinitially categorized as Category D weldments. In the first case, existing cast stainless valves were refurbished and reinstalled in the system in conjunction with the installationof IGSCC resistant piping. The subsequent weldments were conservatively listed as Category D. A subsequent review of the NRC safety evaluation of BWRVIP-75, datedSeptember 15, 2000, indicated that these weldments may be upgraded to Category A. In the second case, the IGSCC-resistant piping was connected to nonresistant piping atpenetrations. In this case, the weldment remains Category D, until stress improvement is performed and then it is reclassified as Category C.The NRC staff finds the response to the above RAIs, which clarified the categorization of thewelds, to be acceptable.


==3.0 CONCLUSION==
The licensee stated that nondestructive examinations, repairs, stress improvement and pipe replacement with corrosion resistant materials are being implemented at BFN1. These activities are being performed to reduce the potential for Intergranular Stress Corrosion Cracking (IGSCC) and are consistent with the guidelines in GL 88-01 and prevailing BWR industry practice.
Based upon the information provided above, the NRC staff concludes that the supplementalresponse to GL 88-01 from BFN 1 is in compliance with the staff's position on IGSCC in BWR Austenitic Stainless Steel Piping.
As required in GL 88-01 the licensee has provided a supplemental response to the NRC.
Mr. Karl W. SingerBROWNS FERRY NUCLEAR PLANTTennessee Valley Authority cc:
The licensee response includes the following topics:
Mr. Ashok S. Bhatnagar, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN  37402-2801  Mr. Larry S. Bryant, Vice PresidentNuclear Engineering & Technical Services Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN  37402-2801Brian O'Grady, Site Vice PresidentBrowns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL  35609Mr. Robert J. Beecken, Vice PresidentNuclear Support Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801   General CounselTennessee Valley Authority ET 11A 400 West Summit Hill DriveKnoxville, TN 37902Mr. John C. Fornicola, ManagerNuclear Assurance and Licensing Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN  37402-2801Mr. Bruce Aukland, Plant ManagerBrowns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609Mr. Masoud Bajestani, Vice PresidentBrowns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL  35609Mr. Robert G. Jones, General ManagerBrowns Ferry Site Operations Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL  35609Mr. Scott M. ShaefferBrowns Ferry Unit 1 Project Engineer Division of Reactor Projects, Branch 6 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.
(1)    Plans regarding long-term mitigation of IGSCC.
Suite 23T85 Atlanta, GA 30303-8931Mr. Larry S. MellenBrowns Ferry Unit 1 Project Engineer Division of Reactor Projects, Branch 6 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.
(2)    A discussion of the inservice inspection program.
Suite 23T85 Atlanta, GA 30303-8931 Mr. Glenn W. Morris, Manager Corporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801Mr. William D. Crouch, M anagerLicensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609Senior Resident InspectorU.S. Nuclear Regulatory Commission Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970State Health OfficerAlabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017ChairmanLimestone County Commission 310 West Washington Street Athens, AL 35611}}
(3)    A verification of the adequacy of the Browns Ferry Nuclear Technical Specifications (TSs).
(4)    Confirmation of leakage detection methods.
(5)    Reporting requirements to NRC for flaws.
Enclosure
 
2.1    Plans Regarding Long-Term Mitigation of IGSCC The licensee stated the following measures are being taken at BFN1 to improve inspection quality and reduce/control IGSCC:
!      Inspections using nondestructive examination equipment, qualified examiners and qualified techniques in accordance with the American Society of Mechanical Engineers Code are being used. Weld crown reduction is also being employed to enhance the quality of the examination. In a letter dated February 22, 2006, the licensee stated that the personnel qualified for inspecting for IGSCC were qualified in accordance with the Tri-party agreement and re-qualification of personnel would be performed every 3 years.
!      Repair of IGSCC indications is being performed by using replacement piping.
Replacement piping materials are resistant to IGSCC as defined in GL 88-01. In a letter dated April 25, 2005, the licensee stated that no weld overlays were used on the replacement piping.
!      Where practical, mechanical stress improvement of susceptible piping and replacement piping is being performed.
!      A reduction in the number of welds is being achieved by using designs which employ integral bends and branches in replacement piping where possible.
!      Hydrogen water chemistry is being implemented to reduce susceptibility to IGSCC.
Additionally, in a letter dated February 22, 2006, the licensee stated that the inspection schedule for IGSCC weldments follows the guidelines in BWRVIP [BWR Vessel and Internals Project] -75, including hydrogen water chemistry (HWC) effectiveness, where credit for HWC is taken.
The NRC staff considers these measures acceptable because the measures would mitigate the effects of IGSCC.
The wrought austenitic stainless steel piping systems and components that are considered susceptible to IGSCC according to the guidelines given in GL 88-01 are as follows:
!      Reactor Recirculation from the recirculation inlet and outlet nozzles to the connections with residual heat removal.
!      Residual Heat Removal (RHR) from the recirculation system to the first isolation valve outside of the drywell penetration.
!      Reactor Water Cleanup (RWCU) from its connection to the RHR system to the first isolation valve outside of the drywell penetration.
!      Core Spray (CS) from the core spray inlet nozzles to the drywell penetration, including the core spray inlet safe ends. The piping within and upstream of the penetration is not considered susceptible due the low-operating temperature, generally 130EF or less.
!      Jet pump instrument safe ends.
 
The licensee stated that the head spray system is not included because it will be removed from Unit 1 prior to restart. Similarly, the control rod drive return and recirculation discharge valve bypass have been removed from Unit 1 and are, therefore, not considered. The NRC staff finds that the licensee has adequately defined the piping systems that are susceptible to IGSCC, as required by GL 88-01.
The licensee also stated that IGSCC susceptible weldments are being inspected or are being removed from service and replaced. The inaccessible welds will be inspected as described in a letter to the NRC dated November 25, 1992. This methodology was approved by the NRC in a letter dated February 18, 1993. In a response to a request for additional information (RAI) dated April 25, 2005, concerning inspection techniques and methods for weld overlays, the licensee stated there will be no weld overlays in Unit 1 since all of the previously affected piping with weld overlays has been removed and replaced.
The licensee indicated that the following piping will be replaced at BFN1:
!        Reactor recirculation inlet and outlet safe ends are being replaced due to concerns of crevice corrosion attack. The replacement safe ends utilize an improved design employing resistant material and a crevice-free configuration.
!        Reactor recirculation piping is being replaced. This includes the 28-inch pump suction and discharge piping, the 12-inch risers and 22-inch ringheader. The replacement piping is 316NG stainless steel, which is less susceptible to IGSCC. Improved construction methods and bent pipe result in fewer welds. The ringheader design eliminates the ringheader cross-tie valves.
!        CS and RHR piping inside the containment are being replaced. The replacement piping is 316NG stainless steel for the RHR system and American Society for Testing and Materials SA-333 Grade 6, high toughness grade of carbon steel for the CS system, which is less susceptible to IGSCC.
!        RWCU piping is being replaced both inside and outside containment, as was discussed in a letter to the NRC dated May 22, 1989. This replacement included the penetration process piping and eliminated the uninspectable weld located inside the penetration.
The replacement material utilized is resistant to IGSCC. The licensee stated that 316NG stainless steel is being used for all piping operating above 200EF.
!        Jet pump instrumentation nozzle safe ends and seal assemblies are being replaced to remove cracking and overlays. The replacement assemblies are an improved design, fabricated from IGSCC resistant materials.
The NRC staff finds the licensees plan acceptable because piping susceptible to IGSCC would be replaced with piping that is resistant to IGSCC.
Also, the licensee stated that welds containing indications of cracking were replaced with 316NG IGSCC resistant material.
 
2.2    Discussion of the Inservice Inspection (ISI) Program The licensee stated that future inspections performed on piping within the scope of GL 88-01 will conform to the NRC staff positions on methods, personnel, schedules and expansion plans.
The NRC staff considers this program to be acceptable.
2.3    Conformance to the ISI Requirements of GL 88-01 GL 88-01 requested a change to the TSs to include a statement in the section on ISI that the ISI program for piping covered by the scope of this letter will be in conformance with the staff position on schedule, methods, and personnel. The licensee submitted this TS change to the NRC on December 9, 1988 as TS 262; it was approved on May 19, 1989, as Amendment 166 for Unit 1.
The licensee has since submitted Unit 1 TS Change 362 - Improved TSs (ITSs). The licensee stated this change was TVAs conversion package from Custom TSs to ITSs. The NRC approved this change in a letter to the licensee on July 14, 1998. The licensee stated the TS requirements for the ISI program are no longer part of ITSs or the BFN TSs. As discussed in the GL, the licensee stated the requirements regarding schedule, methods, and personnel will be included in the Unit 1 ISI program.
The NRC staff finds this program meets the ISI requirements of GL 88-01 and is, therefore, acceptable.
2.4    TSs on Conformance to Staff Positions on Leak Detection The licensee stated the TS conformance to the staff positions on leak detection was previously submitted to the NRC on December 15, 1986, as TS-222 and approved on August 26, 1987, as Amendment 137 for Unit 1.
As stated previously, TVA submitted Unit 1 TS Change 362 - ITS. The NRC approved this change in a letter to the licensee dated July 14, 1998.
The NRC staff finds the licensees program on leak detection meets the NRC position and is, therefore, acceptable.
2.5    Plans to Notify NRC of Flaws The licensee stated that in the past, the NRC has been notified of the inspection results, flaw evaluations and repair mitigation measures associated with the BFN units through a comprehensive report submitted before plant startup. The licensee stated this report covers Unit 1 activities. The licensee stated that after the IGSCC mitigation work scopes have been fully implemented, reports will be made only in the event of the discovery of new flaws or a change is found in the condition of flaws previously detected. For these events, a full report of the flaw evaluation and strategy and technical justification for repair or continued operation will be submitted prior to plant startup. Additionally, a 90-day ISI summary report will still be submitted to the NRC for review.
The NRC staff finds the licensees program for NRC notification of flaws to be acceptable.
 
2.6    Differences Between the Unit 1 Program and the Program Previously Approved for Units 2 and 3 The licensee stated that replacement of piping susceptible to IGSCC with piping resistant to IGSCC is more extensive in BFN1 than in Units 2 or 3. The licensee stated that Unit 1 has replaced more piping. To support the statement, the licensee has provided a general description of the piping replaced in Unit 1 and a comparison with the piping replacement efforts of Units 2 and 3.
!      Reactor Water Recirculation piping in Unit 1 is being completely replaced with resistant materials versus a partial replacement scope for this system in Units 2 and 3.
Recirculation riser piping was replaced in Unit 2, and the riser piping, header arms and crosses were replaced in Unit 3. The Unit 1 replacement piping material is the same material as used in Unit 3.
!      RWCU piping is also being completely replaced in Unit 1, including the containment penetration piping, similar to the replacement effort scope in Unit 3. Unit 2 piping was partially replaced inside the drywell, penetration piping and a portion of the piping adjacent to valve FCV 69-01, in conjunction with replacement of RWCU piping outside the drywell. The Unit 1 replacement piping material is the same material as used in Unit 3.
!      CS piping replacement scope inside the drywell for Unit 1 extends to the containment penetration piping. The Units 2 and 3 CS piping replacement inside the drywell extended to the inboard containment isolation valve. One loop of the Unit 1 CS pipe replacement also included replacement of a piping section containing a weld overlay outside containment between the penetration and an outboard containment isolation valve. The Unit 1 replacement piping material is the same material as used in Unit 3.
!      RHR piping replacement inside the drywell for Unit 1 extends to the containment penetration piping for the two injection lines and the shutdown cooling suction line.
The RHR piping on Unit 3 was replaced between the manual isolation valves for the two injection lines and the tie-in to the Recirculation tee connection for the 24-inch piping.
The licensee stated that the Unit 2 RHR piping was not replaced. The replacement piping used in Unit 1 is the same material as used in Unit 3.
Additionally, the licensee provided clarifications to three RAIs in a letter dated February 22, 2006. The RAIs referred to the Table 1 listing of piping identified in the supplemental response to GL 88-01.
RAI No. 2 requested clarification or justification as to why two welds with limited accessibility (DRHR-1-3 and DRHR-1-12) are listed in Category D and not in Category G.
The licensee stated that IGSCC Category D weldments are defined as those not made with resistant materials and have not been given a Stress Improvement (SI) treatment, but have been inspected by examiners and procedures in conformance with Section 5.2.1 (NUREG-0313, Rev.2), and found to be free of cracks. IGSCC Category G weldments are those not made of resistant materials, have not been given an SI treatment and have not been inspected in accordance with Section 5.2.1. Stress
 
improved welds that were not inspected after the SI treatments are considered to be Category G weldments until the post-SI inspection has been performed.
The licensee stated that the two Category D welds, DRHR-1-3 and DRHR-1-12, are composed of nonresistant materials and have no stress improvement. This categorization is consistent with Units 2 and 3 for their corresponding weldments.
These weldments were examined to the maximum extent practical utilizing qualified personnel and procedures in accordance with their classification as Category D.
RAI No. 3 requested clarification that Category G and D welds listed in Table 1 that are having Mechanical Stress Improvement Process (MSIP) performed would undergo an inservice examination prior to MSIP to ensure that no unacceptable flaws are present.
The licensee stated that ultrasonic examinations that are capable of IGSCC detection are performed prior to application of MSIP to ensure a flaw does not exist, which could propagate in the weldment during the application of the stress improvement process.
Existing weldments that were made prior to the current BFN1 recovery effort, which were categorized as Category G or D, were ultrasonically examined utilizing qualified personnel and procedures for IGSCC detection both prior to and following MSIP application. The weldments made in the process of BFN1 recovery, for all IGSCC categories, were ultrasonically examined on a sampling basis (13 welds examined) prior to MSIP application and ultrasonically examined on a 100-percent basis following MSIP application. There were no relevant indications detected in the post-MSIP IGSCC examinations.
RAI No. 4 requested clarification concerning why a number of Category D welds are characterized as new welds, since all new piping is made of IGSCC resistant materials.
The licensee stated that there were two cases where replacement materials were initially categorized as Category D weldments. In the first case, existing cast stainless valves were refurbished and reinstalled in the system in conjunction with the installation of IGSCC resistant piping. The subsequent weldments were conservatively listed as Category D. A subsequent review of the NRC safety evaluation of BWRVIP-75, dated September 15, 2000, indicated that these weldments may be upgraded to Category A.
In the second case, the IGSCC-resistant piping was connected to nonresistant piping at penetrations. In this case, the weldment remains Category D, until stress improvement is performed and then it is reclassified as Category C.
The NRC staff finds the response to the above RAIs, which clarified the categorization of the welds, to be acceptable.
 
==3.0   CONCLUSION==
 
Based upon the information provided above, the NRC staff concludes that the supplemental response to GL 88-01 from BFN 1 is in compliance with the staffs position on IGSCC in BWR Austenitic Stainless Steel Piping.
 
Mr. Karl W. Singer                              BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority cc:
Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Robert G. Jones, General Manager Nuclear Operations                            Browns Ferry Site Operations Tennessee Valley Authority                   Browns Ferry Nuclear Plant 6A Lookout Place                             Tennessee Valley Authority 1101 Market Street                           P.O. Box 2000 Chattanooga, TN 37402-2801                   Decatur, AL 35609 Mr. Larry S. Bryant, Vice President          Mr. Scott M. Shaeffer Nuclear Engineering & Technical Services      Browns Ferry Unit 1 Project Engineer Tennessee Valley Authority                    Division of Reactor Projects, Branch 6 6A Lookout Place                              U.S. Nuclear Regulatory Commission 1101 Market Street                            61 Forsyth Street, SW.
Chattanooga, TN 37402-2801                    Suite 23T85 Atlanta, GA 30303-8931 Brian OGrady, Site Vice President Browns Ferry Nuclear Plant                    Mr. Larry S. Mellen Tennessee Valley Authority                    Browns Ferry Unit 1 Project Engineer P.O. Box 2000                                Division of Reactor Projects, Branch 6 Decatur, AL 35609                            U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.
Mr. Robert J. Beecken, Vice President        Suite 23T85 Nuclear Support                              Atlanta, GA 30303-8931 Tennessee Valley Authority 6A Lookout Place                              Mr. Glenn W. Morris, Manager 1101 Market Street                            Corporate Nuclear Licensing Chattanooga, TN 37402-2801                      and Industry Affairs Tennessee Valley Authority General Counsel                              4X Blue Ridge Tennessee Valley Authority                    1101 Market Street ET 11A                                        Chattanooga, TN 37402-2801 400 West Summit Hill Drive Knoxville, TN 37902                          Mr. William D. Crouch, Manager Licensing and Industry Affairs Mr. John C. Fornicola, Manager                Browns Ferry Nuclear Plant Nuclear Assurance and Licensing              Tennessee Valley Authority Tennessee Valley Authority                   P.O. Box 2000 6A Lookout Place                              Decatur, AL 35609 1101 Market Street Chattanooga, TN 37402-2801                    Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. Bruce Aukland, Plant Manager              Browns Ferry Nuclear Plant Browns Ferry Nuclear Plant                    10833 Shaw Road Tennessee Valley Authority                    Athens, AL 35611-6970 P.O. Box 2000 Decatur, AL 35609                            State Health Officer Alabama Dept. of Public Health Mr. Masoud Bajestani, Vice President          RSA Tower - Administration Browns Ferry Unit 1 Restart                  Suite 1552 Browns Ferry Nuclear Plant                    P.O. Box 303017 Tennessee Valley Authority                    Montgomery, AL 36130-3017 P.O. Box 2000 Decatur, AL 35609                            Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611}}

Latest revision as of 06:30, 14 March 2020

Supplemental Response to Generic Letter 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR Austenitic Stainless Steel Piping
ML061280456
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 05/30/2006
From: Chernoff M
NRC/NRR/ADRO/DORL/LPLD
To: Singer K
Tennessee Valley Authority
Chernoff M, NRR/DORL, 415-4041
References
GL-88-001, TAC MC4891
Download: ML061280456 (9)


Text

May 30, 2006 Mr. Karl E. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801

SUBJECT:

BROWNS FERRY NUCLEAR PLANT UNIT 1 - SUPPLEMENTAL RESPONSE TO GENERIC LETTER 88-01, NRC POSITION ON INTERGRANULAR STRESS CORROSION CRACKING IN BWR [BOILING WATER REACTOR]

AUSTENITIC STAINLESS STEEL PIPING (TAC NO. MC4891)

Dear Mr. Singer:

The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated the information submitted by Tennessee Valley Authority (TVA, the licensee), in its letter dated July 21, 2004, and supplemental letters dated April 25, 2005, and February 22, 2006. The letters were in response to Generic Letter (GL) 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR Austenitic Stainless Steel Piping.

The NRC staff has completed its review of the response, and concluded in the enclosed safety evaluation that TVA has provided an acceptable resolution to the GL 88-01 concerns.

If you have any questions regarding this matter, please contact me at (301) 415-4041.

Sincerely,

/RA by B. Mozafari for/

Margaret H. Chernoff, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-259

Enclosure:

Safety Evaluation cc w/encl: See next page

ML061280456 NRR-088 OFFICE LPL2-2/PM LPL2-2/PM LPL2-2/LA CPNB/BC LPL2-2/BC NAME BMozafari/em BMozafari for BClayton TChan - MMarshall MChernoff Memo dated DATE 5/19/06 5/19/06 5/19/06 04/18/06 5/30/06 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION SUPPLEMENTAL RESPONSE TO GENERIC LETTER 88-01 BROWNS FERRY NUCLEAR PLANT, UNIT 1 TENNESSEE VALLEY AUTHORITY DOCKET NO: 50-259

1.0 INTRODUCTION

By letter dated July 21, 2004, as supplemented by letters dated April 25, 2005, and February 22, 2006, Tennessee Valley Authority (TVA, the licensee), submitted responses to Generic Letter (GL) 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR [Boiling-Water Reactor] Austenitic Stainless Steel Piping. The Nuclear Regulatory Commission (NRC) staff notes that Browns Ferry Nuclear Plant, Unit 1 (BFN 1), deferred responding to GL 88-01 until now because it has been in an extended outage since March 1985, and is now preparing for restart. The NRC staff reviewed the information provided by TVA. The staff evaluation of the response follows.

2.0 REGULATORY EVALUATION

The licensee stated that nondestructive examinations, repairs, stress improvement and pipe replacement with corrosion resistant materials are being implemented at BFN1. These activities are being performed to reduce the potential for Intergranular Stress Corrosion Cracking (IGSCC) and are consistent with the guidelines in GL 88-01 and prevailing BWR industry practice.

As required in GL 88-01 the licensee has provided a supplemental response to the NRC.

The licensee response includes the following topics:

(1) Plans regarding long-term mitigation of IGSCC.

(2) A discussion of the inservice inspection program.

(3) A verification of the adequacy of the Browns Ferry Nuclear Technical Specifications (TSs).

(4) Confirmation of leakage detection methods.

(5) Reporting requirements to NRC for flaws.

Enclosure

2.1 Plans Regarding Long-Term Mitigation of IGSCC The licensee stated the following measures are being taken at BFN1 to improve inspection quality and reduce/control IGSCC:

! Inspections using nondestructive examination equipment, qualified examiners and qualified techniques in accordance with the American Society of Mechanical Engineers Code are being used. Weld crown reduction is also being employed to enhance the quality of the examination. In a letter dated February 22, 2006, the licensee stated that the personnel qualified for inspecting for IGSCC were qualified in accordance with the Tri-party agreement and re-qualification of personnel would be performed every 3 years.

! Repair of IGSCC indications is being performed by using replacement piping.

Replacement piping materials are resistant to IGSCC as defined in GL 88-01. In a letter dated April 25, 2005, the licensee stated that no weld overlays were used on the replacement piping.

! Where practical, mechanical stress improvement of susceptible piping and replacement piping is being performed.

! A reduction in the number of welds is being achieved by using designs which employ integral bends and branches in replacement piping where possible.

! Hydrogen water chemistry is being implemented to reduce susceptibility to IGSCC.

Additionally, in a letter dated February 22, 2006, the licensee stated that the inspection schedule for IGSCC weldments follows the guidelines in BWRVIP [BWR Vessel and Internals Project] -75, including hydrogen water chemistry (HWC) effectiveness, where credit for HWC is taken.

The NRC staff considers these measures acceptable because the measures would mitigate the effects of IGSCC.

The wrought austenitic stainless steel piping systems and components that are considered susceptible to IGSCC according to the guidelines given in GL 88-01 are as follows:

! Reactor Recirculation from the recirculation inlet and outlet nozzles to the connections with residual heat removal.

! Residual Heat Removal (RHR) from the recirculation system to the first isolation valve outside of the drywell penetration.

! Reactor Water Cleanup (RWCU) from its connection to the RHR system to the first isolation valve outside of the drywell penetration.

! Core Spray (CS) from the core spray inlet nozzles to the drywell penetration, including the core spray inlet safe ends. The piping within and upstream of the penetration is not considered susceptible due the low-operating temperature, generally 130EF or less.

! Jet pump instrument safe ends.

The licensee stated that the head spray system is not included because it will be removed from Unit 1 prior to restart. Similarly, the control rod drive return and recirculation discharge valve bypass have been removed from Unit 1 and are, therefore, not considered. The NRC staff finds that the licensee has adequately defined the piping systems that are susceptible to IGSCC, as required by GL 88-01.

The licensee also stated that IGSCC susceptible weldments are being inspected or are being removed from service and replaced. The inaccessible welds will be inspected as described in a letter to the NRC dated November 25, 1992. This methodology was approved by the NRC in a letter dated February 18, 1993. In a response to a request for additional information (RAI) dated April 25, 2005, concerning inspection techniques and methods for weld overlays, the licensee stated there will be no weld overlays in Unit 1 since all of the previously affected piping with weld overlays has been removed and replaced.

The licensee indicated that the following piping will be replaced at BFN1:

! Reactor recirculation inlet and outlet safe ends are being replaced due to concerns of crevice corrosion attack. The replacement safe ends utilize an improved design employing resistant material and a crevice-free configuration.

! Reactor recirculation piping is being replaced. This includes the 28-inch pump suction and discharge piping, the 12-inch risers and 22-inch ringheader. The replacement piping is 316NG stainless steel, which is less susceptible to IGSCC. Improved construction methods and bent pipe result in fewer welds. The ringheader design eliminates the ringheader cross-tie valves.

! CS and RHR piping inside the containment are being replaced. The replacement piping is 316NG stainless steel for the RHR system and American Society for Testing and Materials SA-333 Grade 6, high toughness grade of carbon steel for the CS system, which is less susceptible to IGSCC.

! RWCU piping is being replaced both inside and outside containment, as was discussed in a letter to the NRC dated May 22, 1989. This replacement included the penetration process piping and eliminated the uninspectable weld located inside the penetration.

The replacement material utilized is resistant to IGSCC. The licensee stated that 316NG stainless steel is being used for all piping operating above 200EF.

! Jet pump instrumentation nozzle safe ends and seal assemblies are being replaced to remove cracking and overlays. The replacement assemblies are an improved design, fabricated from IGSCC resistant materials.

The NRC staff finds the licensees plan acceptable because piping susceptible to IGSCC would be replaced with piping that is resistant to IGSCC.

Also, the licensee stated that welds containing indications of cracking were replaced with 316NG IGSCC resistant material.

2.2 Discussion of the Inservice Inspection (ISI) Program The licensee stated that future inspections performed on piping within the scope of GL 88-01 will conform to the NRC staff positions on methods, personnel, schedules and expansion plans.

The NRC staff considers this program to be acceptable.

2.3 Conformance to the ISI Requirements of GL 88-01 GL 88-01 requested a change to the TSs to include a statement in the section on ISI that the ISI program for piping covered by the scope of this letter will be in conformance with the staff position on schedule, methods, and personnel. The licensee submitted this TS change to the NRC on December 9, 1988 as TS 262; it was approved on May 19, 1989, as Amendment 166 for Unit 1.

The licensee has since submitted Unit 1 TS Change 362 - Improved TSs (ITSs). The licensee stated this change was TVAs conversion package from Custom TSs to ITSs. The NRC approved this change in a letter to the licensee on July 14, 1998. The licensee stated the TS requirements for the ISI program are no longer part of ITSs or the BFN TSs. As discussed in the GL, the licensee stated the requirements regarding schedule, methods, and personnel will be included in the Unit 1 ISI program.

The NRC staff finds this program meets the ISI requirements of GL 88-01 and is, therefore, acceptable.

2.4 TSs on Conformance to Staff Positions on Leak Detection The licensee stated the TS conformance to the staff positions on leak detection was previously submitted to the NRC on December 15, 1986, as TS-222 and approved on August 26, 1987, as Amendment 137 for Unit 1.

As stated previously, TVA submitted Unit 1 TS Change 362 - ITS. The NRC approved this change in a letter to the licensee dated July 14, 1998.

The NRC staff finds the licensees program on leak detection meets the NRC position and is, therefore, acceptable.

2.5 Plans to Notify NRC of Flaws The licensee stated that in the past, the NRC has been notified of the inspection results, flaw evaluations and repair mitigation measures associated with the BFN units through a comprehensive report submitted before plant startup. The licensee stated this report covers Unit 1 activities. The licensee stated that after the IGSCC mitigation work scopes have been fully implemented, reports will be made only in the event of the discovery of new flaws or a change is found in the condition of flaws previously detected. For these events, a full report of the flaw evaluation and strategy and technical justification for repair or continued operation will be submitted prior to plant startup. Additionally, a 90-day ISI summary report will still be submitted to the NRC for review.

The NRC staff finds the licensees program for NRC notification of flaws to be acceptable.

2.6 Differences Between the Unit 1 Program and the Program Previously Approved for Units 2 and 3 The licensee stated that replacement of piping susceptible to IGSCC with piping resistant to IGSCC is more extensive in BFN1 than in Units 2 or 3. The licensee stated that Unit 1 has replaced more piping. To support the statement, the licensee has provided a general description of the piping replaced in Unit 1 and a comparison with the piping replacement efforts of Units 2 and 3.

! Reactor Water Recirculation piping in Unit 1 is being completely replaced with resistant materials versus a partial replacement scope for this system in Units 2 and 3.

Recirculation riser piping was replaced in Unit 2, and the riser piping, header arms and crosses were replaced in Unit 3. The Unit 1 replacement piping material is the same material as used in Unit 3.

! RWCU piping is also being completely replaced in Unit 1, including the containment penetration piping, similar to the replacement effort scope in Unit 3. Unit 2 piping was partially replaced inside the drywell, penetration piping and a portion of the piping adjacent to valve FCV 69-01, in conjunction with replacement of RWCU piping outside the drywell. The Unit 1 replacement piping material is the same material as used in Unit 3.

! CS piping replacement scope inside the drywell for Unit 1 extends to the containment penetration piping. The Units 2 and 3 CS piping replacement inside the drywell extended to the inboard containment isolation valve. One loop of the Unit 1 CS pipe replacement also included replacement of a piping section containing a weld overlay outside containment between the penetration and an outboard containment isolation valve. The Unit 1 replacement piping material is the same material as used in Unit 3.

! RHR piping replacement inside the drywell for Unit 1 extends to the containment penetration piping for the two injection lines and the shutdown cooling suction line.

The RHR piping on Unit 3 was replaced between the manual isolation valves for the two injection lines and the tie-in to the Recirculation tee connection for the 24-inch piping.

The licensee stated that the Unit 2 RHR piping was not replaced. The replacement piping used in Unit 1 is the same material as used in Unit 3.

Additionally, the licensee provided clarifications to three RAIs in a letter dated February 22, 2006. The RAIs referred to the Table 1 listing of piping identified in the supplemental response to GL 88-01.

RAI No. 2 requested clarification or justification as to why two welds with limited accessibility (DRHR-1-3 and DRHR-1-12) are listed in Category D and not in Category G.

The licensee stated that IGSCC Category D weldments are defined as those not made with resistant materials and have not been given a Stress Improvement (SI) treatment, but have been inspected by examiners and procedures in conformance with Section 5.2.1 (NUREG-0313, Rev.2), and found to be free of cracks. IGSCC Category G weldments are those not made of resistant materials, have not been given an SI treatment and have not been inspected in accordance with Section 5.2.1. Stress

improved welds that were not inspected after the SI treatments are considered to be Category G weldments until the post-SI inspection has been performed.

The licensee stated that the two Category D welds, DRHR-1-3 and DRHR-1-12, are composed of nonresistant materials and have no stress improvement. This categorization is consistent with Units 2 and 3 for their corresponding weldments.

These weldments were examined to the maximum extent practical utilizing qualified personnel and procedures in accordance with their classification as Category D.

RAI No. 3 requested clarification that Category G and D welds listed in Table 1 that are having Mechanical Stress Improvement Process (MSIP) performed would undergo an inservice examination prior to MSIP to ensure that no unacceptable flaws are present.

The licensee stated that ultrasonic examinations that are capable of IGSCC detection are performed prior to application of MSIP to ensure a flaw does not exist, which could propagate in the weldment during the application of the stress improvement process.

Existing weldments that were made prior to the current BFN1 recovery effort, which were categorized as Category G or D, were ultrasonically examined utilizing qualified personnel and procedures for IGSCC detection both prior to and following MSIP application. The weldments made in the process of BFN1 recovery, for all IGSCC categories, were ultrasonically examined on a sampling basis (13 welds examined) prior to MSIP application and ultrasonically examined on a 100-percent basis following MSIP application. There were no relevant indications detected in the post-MSIP IGSCC examinations.

RAI No. 4 requested clarification concerning why a number of Category D welds are characterized as new welds, since all new piping is made of IGSCC resistant materials.

The licensee stated that there were two cases where replacement materials were initially categorized as Category D weldments. In the first case, existing cast stainless valves were refurbished and reinstalled in the system in conjunction with the installation of IGSCC resistant piping. The subsequent weldments were conservatively listed as Category D. A subsequent review of the NRC safety evaluation of BWRVIP-75, dated September 15, 2000, indicated that these weldments may be upgraded to Category A.

In the second case, the IGSCC-resistant piping was connected to nonresistant piping at penetrations. In this case, the weldment remains Category D, until stress improvement is performed and then it is reclassified as Category C.

The NRC staff finds the response to the above RAIs, which clarified the categorization of the welds, to be acceptable.

3.0 CONCLUSION

Based upon the information provided above, the NRC staff concludes that the supplemental response to GL 88-01 from BFN 1 is in compliance with the staffs position on IGSCC in BWR Austenitic Stainless Steel Piping.

Mr. Karl W. Singer BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority cc:

Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Robert G. Jones, General Manager Nuclear Operations Browns Ferry Site Operations Tennessee Valley Authority Browns Ferry Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Decatur, AL 35609 Mr. Larry S. Bryant, Vice President Mr. Scott M. Shaeffer Nuclear Engineering & Technical Services Browns Ferry Unit 1 Project Engineer Tennessee Valley Authority Division of Reactor Projects, Branch 6 6A Lookout Place U.S. Nuclear Regulatory Commission 1101 Market Street 61 Forsyth Street, SW.

Chattanooga, TN 37402-2801 Suite 23T85 Atlanta, GA 30303-8931 Brian OGrady, Site Vice President Browns Ferry Nuclear Plant Mr. Larry S. Mellen Tennessee Valley Authority Browns Ferry Unit 1 Project Engineer P.O. Box 2000 Division of Reactor Projects, Branch 6 Decatur, AL 35609 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.

Mr. Robert J. Beecken, Vice President Suite 23T85 Nuclear Support Atlanta, GA 30303-8931 Tennessee Valley Authority 6A Lookout Place Mr. Glenn W. Morris, Manager 1101 Market Street Corporate Nuclear Licensing Chattanooga, TN 37402-2801 and Industry Affairs Tennessee Valley Authority General Counsel 4X Blue Ridge Tennessee Valley Authority 1101 Market Street ET 11A Chattanooga, TN 37402-2801 400 West Summit Hill Drive Knoxville, TN 37902 Mr. William D. Crouch, Manager Licensing and Industry Affairs Mr. John C. Fornicola, Manager Browns Ferry Nuclear Plant Nuclear Assurance and Licensing Tennessee Valley Authority Tennessee Valley Authority P.O. Box 2000 6A Lookout Place Decatur, AL 35609 1101 Market Street Chattanooga, TN 37402-2801 Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. Bruce Aukland, Plant Manager Browns Ferry Nuclear Plant Browns Ferry Nuclear Plant 10833 Shaw Road Tennessee Valley Authority Athens, AL 35611-6970 P.O. Box 2000 Decatur, AL 35609 State Health Officer Alabama Dept. of Public Health Mr. Masoud Bajestani, Vice President RSA Tower - Administration Browns Ferry Unit 1 Restart Suite 1552 Browns Ferry Nuclear Plant P.O. Box 303017 Tennessee Valley Authority Montgomery, AL 36130-3017 P.O. Box 2000 Decatur, AL 35609 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611