{{#Wiki_filter:ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 | {{#Wiki_filter:ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Point Beach Date of Examination: May 2017 a Exam Level: RO SRO-I SRO-U Operating Test No.: 2017 a Control Room Systems: 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code* Safety Function | ||
: a. Control Rod Drive System / Perform Rod Exercise Test A, D, S 1 001A3.05 (3.5/3.5) | |||
: b. Chemical and Volume Control System / Manually Makeup to the VCT A, D, P, S 2 004A4.12 (3.8/3.3) 2012 NRC Exam | |||
: c. Emergency Core Cooling System / Fill the SI Accumulators D, S 3 006A1.13 (3.5/3.7) | |||
: d. Steam Dump System/Turbine Bypass Control / Establish Feed Flow from Condensate System (using steam dump valve test switches) A, L, N, S 4S 041A4.08 (3.0/3.1) | |||
: e. Containment Spray System / Secure Containment Spray D, EN, L, S 5 026A2.08 (3.2/3.7) | |||
: f. Emergency Diesel Generator / Secure the Diesel Generator D, S 6 064A4.01 (4.0/4.03) | |||
: g. Nuclear Instrumentation System / Test High Flux at Shutdown Alarm D, L, S 7 015A3.02 (3.7/3.9) | |||
: h. Circulation Water System / Respond to Circulating Water Malfunction A, D, P, S 8 075A2.02 (2.5/2.7) 2015 NRC Exam In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U) | |||
: i. Chemical and Volume Control System / Locally Operate Charging Pump D, R 2 004A1.11 (3.0/3.0) | |||
: j. Emergency Diesel Generator / Transfer Fuel Oil Between Day Tanks N 6 064K1.03 (3.6/4.0) | |||
: k. Instrument Air System / Start an Air Compressor to a Depressurized Receiver A, D, E, P 8 078A3.01 (3.1/3.2) 2012 NRC Exam | |||
* All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room. | * All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room. | ||
* Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path | * Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature 1 / 1 / 1 (control room system) | ||
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected) | |||
(R)CA 1/1/1 (S)imulator | |||
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Point Beach Date of Examination: May 2017 a Exam Level: RO SRO-I SRO-U Operating Test No.: 2017 a Control Room Systems: 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code* Safety Function | |||
: a. Control Rod Drive System / Perform Rod Exercise Test A, D, S 1 001A3.05 (3.5/3.5) | |||
: b. Chemical and Volume Control System / Manually Makeup to the VCT A, D, P, S 2 004A4.12 (3.8/3.3) 2012 NRC Exam | |||
: c. Emergency Core Cooling System / Fill the SI Accumulators D, S 3 006A1.13 (3.5/3.7) | |||
: d. Steam Dump System/Turbine Bypass Control / Establish Feed Flow from Condensate System (using steam dump valve test switches) A, L, N, S 4S 041A4.08 (3.0/3.1) | |||
: e. Containment Spray System / Secure Containment Spray D, EN, L, S 5 026A2.08 (3.2/3.7) | |||
: f. Emergency Diesel Generator / Secure the Diesel Generator D, S 6 064A4.01 (4.0/4.03) | |||
: g. Nuclear Instrumentation System / Test High Flux at Shutdown Alarm D, L, S 7 015A3.02 (3.7/3.9) h. | |||
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U) | |||
: i. Chemical and Volume Control System / Locally Operate Charging Pump D, R 2 004A1.11 (3.0/3.0) | |||
: j. Emergency Diesel Generator / Transfer Fuel Oil Between Day Tanks N 6 064K1.03 (3.6/4.0) | |||
: k. Instrument Air System / Start an Air Compressor to a Depressurized Receiver A, D, E, P 8 078A3.01 (3.1/3.2) 2012 NRC Exam | |||
* All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room. | * All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room. | ||
* Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path | * Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature 1 / 1 / 1 (control room system) | ||
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected) | |||
(R)CA 1/1/1 (S)imulator | |||
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Point Beach Date of Examination: May 2017 a Exam Level: RO SRO-I SRO-U Operating Test No.: 2017 a Control Room Systems: 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code* Safety Function | |||
: a. Control Rod Drive System / Perform Rod Exercise Test A, D, S 1 001A3.05 (3.5/3.5) b. | |||
c. | |||
: d. Steam Dump System/Turbine Bypass Control / Establish Feed Flow from Condensate System (using steam dump valve test switches) A, L, N, S 4S 041A4.08 (3.0/3.1) | |||
: e. Containment Spray System / Secure Containment Spray D, EN, L, S 5 026A2.08 (3.2/3.7) f. | |||
g. | |||
h. | |||
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U) | |||
: i. Chemical and Volume Control System / Locally Operate Charging Pump D, R 2 004A1.11 (3.0/3.0) j. | |||
: k. Instrument Air System / Start an Air Compressor to a Depressurized Receiver A, D, E, P 8 078A3.01 (3.1/3.2) 2012 NRC Exam | |||
* All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room. | * All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room. | ||
* Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path | * Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature 1 / 1 / 1 (control room system) | ||
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected) | |||
(R)CA 1/1/1 (S)imulator}} |
Latest revision as of 15:27, 4 February 2020
ML17201Q533 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 05/23/2017 |
From: | Jesse Seymour Operations Branch III |
To: | Point Beach |
Shared Package | |
ML16319A342 | List: |
References | |
Download: ML17201Q533 (3) | |
Text
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Point Beach Date of Examination: May 2017 a Exam Level: RO SRO-I SRO-U Operating Test No.: 2017 a Control Room Systems: 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code* Safety Function
- a. Control Rod Drive System / Perform Rod Exercise Test A, D, S 1 001A3.05 (3.5/3.5)
- b. Chemical and Volume Control System / Manually Makeup to the VCT A, D, P, S 2 004A4.12 (3.8/3.3) 2012 NRC Exam
- c. Emergency Core Cooling System / Fill the SI Accumulators D, S 3 006A1.13 (3.5/3.7)
- d. Steam Dump System/Turbine Bypass Control / Establish Feed Flow from Condensate System (using steam dump valve test switches) A, L, N, S 4S 041A4.08 (3.0/3.1)
- e. Containment Spray System / Secure Containment Spray D, EN, L, S 5 026A2.08 (3.2/3.7)
- f. Emergency Diesel Generator / Secure the Diesel Generator D, S 6 064A4.01 (4.0/4.03)
- g. Nuclear Instrumentation System / Test High Flux at Shutdown Alarm D, L, S 7 015A3.02 (3.7/3.9)
- h. Circulation Water System / Respond to Circulating Water Malfunction A, D, P, S 8 075A2.02 (2.5/2.7) 2015 NRC Exam In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Chemical and Volume Control System / Locally Operate Charging Pump D, R 2 004A1.11 (3.0/3.0)
- j. Emergency Diesel Generator / Transfer Fuel Oil Between Day Tanks N 6 064K1.03 (3.6/4.0)
- k. Instrument Air System / Start an Air Compressor to a Depressurized Receiver A, D, E, P 8 078A3.01 (3.1/3.2) 2012 NRC Exam
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature 1 / 1 / 1 (control room system)
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)
(R)CA 1/1/1 (S)imulator
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Point Beach Date of Examination: May 2017 a Exam Level: RO SRO-I SRO-U Operating Test No.: 2017 a Control Room Systems: 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code* Safety Function
- a. Control Rod Drive System / Perform Rod Exercise Test A, D, S 1 001A3.05 (3.5/3.5)
- b. Chemical and Volume Control System / Manually Makeup to the VCT A, D, P, S 2 004A4.12 (3.8/3.3) 2012 NRC Exam
- c. Emergency Core Cooling System / Fill the SI Accumulators D, S 3 006A1.13 (3.5/3.7)
- d. Steam Dump System/Turbine Bypass Control / Establish Feed Flow from Condensate System (using steam dump valve test switches) A, L, N, S 4S 041A4.08 (3.0/3.1)
- e. Containment Spray System / Secure Containment Spray D, EN, L, S 5 026A2.08 (3.2/3.7)
- f. Emergency Diesel Generator / Secure the Diesel Generator D, S 6 064A4.01 (4.0/4.03)
- g. Nuclear Instrumentation System / Test High Flux at Shutdown Alarm D, L, S 7 015A3.02 (3.7/3.9) h.
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Chemical and Volume Control System / Locally Operate Charging Pump D, R 2 004A1.11 (3.0/3.0)
- j. Emergency Diesel Generator / Transfer Fuel Oil Between Day Tanks N 6 064K1.03 (3.6/4.0)
- k. Instrument Air System / Start an Air Compressor to a Depressurized Receiver A, D, E, P 8 078A3.01 (3.1/3.2) 2012 NRC Exam
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature 1 / 1 / 1 (control room system)
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)
(R)CA 1/1/1 (S)imulator
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Point Beach Date of Examination: May 2017 a Exam Level: RO SRO-I SRO-U Operating Test No.: 2017 a Control Room Systems: 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code* Safety Function
- a. Control Rod Drive System / Perform Rod Exercise Test A, D, S 1 001A3.05 (3.5/3.5) b.
c.
- d. Steam Dump System/Turbine Bypass Control / Establish Feed Flow from Condensate System (using steam dump valve test switches) A, L, N, S 4S 041A4.08 (3.0/3.1)
- e. Containment Spray System / Secure Containment Spray D, EN, L, S 5 026A2.08 (3.2/3.7) f.
g.
h.
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Chemical and Volume Control System / Locally Operate Charging Pump D, R 2 004A1.11 (3.0/3.0) j.
- k. Instrument Air System / Start an Air Compressor to a Depressurized Receiver A, D, E, P 8 078A3.01 (3.1/3.2) 2012 NRC Exam
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature 1 / 1 / 1 (control room system)
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)