{{#Wiki_filter:Appendix D                                      Scenario Outline                              Form ES-D-1 Facility: _Point Beach_____        Scenario No.:      _1___________          Op-Test No.: _2017____
{{#Wiki_filter:Appendix D                                      Scenario Outline                              Form ES-D-1 Facility: _Point Beach_____        Scenario No.:      _1___________          Op-Test No.: _2017____
Examiners: ___________________________ Operators:                  _____________________________
Examiners: ___________________________ Operators:                  _____________________________
___________________________                          _____________________________
___________________________                          _____________________________
Initial Conditions: _Unit 1 is at approximately 100%. Unit 2 is on ice melt. 1PT-950, Loop B Containment Pressure has been removed from service. Repairs are expected to be complete during the upcoming refueling outage. 1W-3B, Control Rod Shroud Fan is OOS due to imminent motor failure. ____
Initial Conditions: _Unit 1 is at approximately 100%. Unit 2 is on ice melt. 1PT-950, Loop B Containment Pressure has been removed from service. Repairs are expected to be complete during the upcoming refueling outage. 1W-3B, Control Rod Shroud Fan is OOS due to imminent motor failure. ____
Turnover: Normal Shift routine. Lower power utilizing OP 3A, Power Operation to Hot Standby at _
Turnover: Normal Shift routine. Lower power utilizing OP 3A, Power Operation to Hot Standby at _
30%/hr in preparation for refueling outage _______________________________________________
30%/hr in preparation for refueling outage _______________________________________________
_________________________________________________________________________________
Event      Malf. No. Event                                              Event No.                  Type*                                        Description I-BOP 1      XMT1CNM014A  I-SRO            1PT-947, Loop A Containment Pressure Transmitter fails low TS-SRO I-BOP            1PC-2273, Feedwater Heater Emergency Bypass Valve Controller 2      CNH1CFW003F I-SRO            oscillates in automatic 3      XMT1AFW005A  TS-SRO          0LT-4040, T-24A CST Level Transmitter fails low R-RO 4      ANN-C02D-A09 N-BOP            1X01, Main Transformer loss of cooling (rapid down power)
Event      Malf. No. Event                                              Event No.                  Type*                                        Description I-BOP 1      XMT1CNM014A  I-SRO            1PT-947, Loop A Containment Pressure Transmitter fails low TS-SRO I-BOP            1PC-2273, Feedwater Heater Emergency Bypass Valve Controller 2      CNH1CFW003F I-SRO            oscillates in automatic 3      XMT1AFW005A  TS-SRO          0LT-4040, T-24A CST Level Transmitter fails low R-RO 4      ANN-C02D-A09 N-BOP            1X01, Main Transformer loss of cooling (rapid down power)
R-SRO C-RO 5      CNH1PCS004F                  1P-2A, Auto Charging Pump controller oscillation failure C-SRO 6      MAL1RCS001  M-ALL            Large Break LOCA BKR1RHR001 C-BOP            1P-10A, RHR pump fails to start in Auto 7      MOT1RHR002 1P-10B, RHR pump trips upon starting RLY1PPL020 8      RLY1PPL021  C-BOP            Containment Spray fails to actuate, manual alignment required.
R-SRO C-RO 5      CNH1PCS004F                  1P-2A, Auto Charging Pump controller oscillation failure C-SRO 6      MAL1RCS001  M-ALL            Large Break LOCA BKR1RHR001 C-BOP            1P-10A, RHR pump fails to start in Auto 7      MOT1RHR002 1P-10B, RHR pump trips upon starting RLY1PPL020 8      RLY1PPL021  C-BOP            Containment Spray fails to actuate, manual alignment required.
Line 30: Line 27:
Appendix D                                      Scenario Outline                            Form ES-D-1 Facility: _Point Beach_____        Scenario No.:      _2___________          Op-Test No.: _2017____
Appendix D                                      Scenario Outline                            Form ES-D-1 Facility: _Point Beach_____        Scenario No.:      _2___________          Op-Test No.: _2017____
Examiners: ___________________________ Operators:                  _____________________________
Examiners: ___________________________ Operators:                  _____________________________
___________________________                        _____________________________
___________________________                        _____________________________
Initial Conditions: _Unit 1 is in OP 1C, Startup to Power Operation, at approximately 29% post        _
Initial Conditions: _Unit 1 is in OP 1C, Startup to Power Operation, at approximately 29% post        _
chemistry hold coming out of a forced outage. At Chemistrys request B Train of Main Feed and _
chemistry hold coming out of a forced outage. At Chemistrys request B Train of Main Feed and _
Line 38: Line 33:
from service. Repairs are expected to be complete during the upcoming refueling outage.__________
from service. Repairs are expected to be complete during the upcoming refueling outage.__________
Turnover: Secure 1P-28B, SGFP and 1P-25B, Condensate Pump. Raise power to 50%. _________
Turnover: Secure 1P-28B, SGFP and 1P-25B, Condensate Pump. Raise power to 50%. _________
_________________________________________________________________________________
Event      Malf. No. Event                                              Event No.                  Type*                                        Description N-BOP 1                                    Secure SG Feed Pump and Condensate Pump N-SRO R-RO 2                  N-BOP            Raise power to 50%
Event      Malf. No. Event                                              Event No.                  Type*                                        Description N-BOP 1                                    Secure SG Feed Pump and Condensate Pump N-SRO R-RO 2                  N-BOP            Raise power to 50%
R-SRO I-BOP 3      XMT1SGN001A  I-SRO            1FI-464, SG Steam Flow fails slowly high TS-SRO I-BOP 4      XMT1MSS009A  I-SRO            1PT-486, Turbine First Stage Pressure fails low TS-SRO C-RO            1P-1B, RCP Seal leak develops, which degrades requiring reactor 5      MAL1RCP001B C-SRO            trip 6      MAL1RCS003F  M-ALL            Small Break LOCA from RTD Bypass Line occurs on reactor trip MAL1PPL001A C-RO            Reactor fails to trip 7      MAL1PPL001B (CSP-S.1, Response to Nuclear Power Generation/ATWS)
R-SRO I-BOP 3      XMT1SGN001A  I-SRO            1FI-464, SG Steam Flow fails slowly high TS-SRO I-BOP 4      XMT1MSS009A  I-SRO            1PT-486, Turbine First Stage Pressure fails low TS-SRO C-RO            1P-1B, RCP Seal leak develops, which degrades requiring reactor 5      MAL1RCP001B C-SRO            trip 6      MAL1RCS003F  M-ALL            Small Break LOCA from RTD Bypass Line occurs on reactor trip MAL1PPL001A C-RO            Reactor fails to trip 7      MAL1PPL001B (CSP-S.1, Response to Nuclear Power Generation/ATWS)
Line 46: Line 40:
Appendix D                                      Scenario Outline                              Form ES-D-1 Facility: _Point Beach_____          Scenario No.:      _3___________          Op-Test No.: _2017____
Appendix D                                      Scenario Outline                              Form ES-D-1 Facility: _Point Beach_____          Scenario No.:      _3___________          Op-Test No.: _2017____
Examiners: ___________________________ Operators:                    _____________________________
Examiners: ___________________________ Operators:                    _____________________________
___________________________                          _____________________________
___________________________                          _____________________________
Initial Conditions: _Unit 1 was lowered to approximately 75% at the request of MISO/ATC due to grid stability issues. Grid stability has been restored and the unit is ready to be returned to full power in__
Initial Conditions: _Unit 1 was lowered to approximately 75% at the request of MISO/ATC due to grid stability issues. Grid stability has been restored and the unit is ready to be returned to full power in__
accordance with OP 1C, Startup to Power Operations. 1P-2B, Charging Pump is OOS and isolated _
accordance with OP 1C, Startup to Power Operations. 1P-2B, Charging Pump is OOS and isolated _
Line 54: Line 46:
Repairs are expected to be complete during the upcoming refueling outage. ____________________
Repairs are expected to be complete during the upcoming refueling outage. ____________________
Turnover: Commence raising power to 100%                                                                _
Turnover: Commence raising power to 100%                                                                _
_________________________________________________________________________________
Event        Malf. No. Event                                          Event No.                    Type*                                        Description C-BOP C-SRO          P-32A, Service Water Pump trip with reduced head capacity on two 1      BKR1SWS001 running SW pumps TS-SRO C-BOP          1RE-219, SG Blowdown Monitor fails high off scale 2      XMT1RMS076A C-SRO          1MS-2083, HX-1A SG Sample Isolation Control Valve fails open R-RO N-BOP 3      MAL1RCS008A                  SG A Tube Leak approximately 10 gpm (rapid down power)
Event        Malf. No. Event                                          Event No.                    Type*                                        Description C-BOP C-SRO          P-32A, Service Water Pump trip with reduced head capacity on two 1      BKR1SWS001 running SW pumps TS-SRO C-BOP          1RE-219, SG Blowdown Monitor fails high off scale 2      XMT1RMS076A C-SRO          1MS-2083, HX-1A SG Sample Isolation Control Valve fails open R-RO N-BOP 3      MAL1RCS008A                  SG A Tube Leak approximately 10 gpm (rapid down power)
R-SRO TS-SRO C-BOP C-SRO          Running CCW Pump seal leak, lowering surge tank 4      MAL1CCW002A (Pumps need to be shifted)
R-SRO TS-SRO C-BOP C-SRO          Running CCW Pump seal leak, lowering surge tank 4      MAL1CCW002A (Pumps need to be shifted)
Line 62: Line 53:
Appendix D                                      Scenario Outline                                  Form ES-D-1 Facility: _Point Beach_____        Scenario No.:      _4___________            Op-Test No.: _2017____
Appendix D                                      Scenario Outline                                  Form ES-D-1 Facility: _Point Beach_____        Scenario No.:      _4___________            Op-Test No.: _2017____
Examiners: ___________________________ Operators:                    _____________________________
Examiners: ___________________________ Operators:                    _____________________________
___________________________                          _____________________________
___________________________                          _____________________________
Initial Conditions: _Unit 1 is at approximately 100%. 1LT-112 VCT Level Transmitter has failed low, _
Initial Conditions: _Unit 1 is at approximately 100%. 1LT-112 VCT Level Transmitter has failed low, _
I&C expect repairs to be completed within the hour and returned to service by the end of shift. 1W-3B, Control Rod Shroud Fan is OOS due to imminent motor failure._______________________________
I&C expect repairs to be completed within the hour and returned to service by the end of shift. 1W-3B, Control Rod Shroud Fan is OOS due to imminent motor failure._______________________________
Turnover: Start 1P-27A, Heater Drain Tank Pump, and secure 1P-27C Heater Drain Tank Pump____
Turnover: Start 1P-27A, Heater Drain Tank Pump, and secure 1P-27C Heater Drain Tank Pump____
per OP 2A, Normal Power Operations, Attachment M, in preparations for maintenance. Lower power utilizing OP 3A, Power Operation to Hot Standby, in preparation for TS 3, Main Turbine Stop and Governor Valve with Turbine Trip_(Biannual)
per OP 2A, Normal Power Operations, Attachment M, in preparations for maintenance. Lower power utilizing OP 3A, Power Operation to Hot Standby, in preparation for TS 3, Main Turbine Stop and Governor Valve with Turbine Trip_(Biannual)
_________________________________________________________________
Event      Malf. No. Event                                              Event No.                  Type*                                          Description N-BOP 1                                    Shift Heater Drain Tank Pumps, start 1P-27A, secure 1P-27C N-SRO R-RO 2                  N-BOP            Down Power for TS-3 R-SRO I-RO I-SRO            NI-43, PR NI fails low fast enough to cause outward rod motion near 3      MAL1NIS007C 12-15 steps/min.
Event      Malf. No. Event                                              Event No.                  Type*                                          Description N-BOP 1                                    Shift Heater Drain Tank Pumps, start 1P-27A, secure 1P-27C N-SRO R-RO 2                  N-BOP            Down Power for TS-3 R-SRO I-RO I-SRO            NI-43, PR NI fails low fast enough to cause outward rod motion near 3      MAL1NIS007C 12-15 steps/min.
TS-SRO I-BOP I-SRO            1LT-471, SG Level fails low slowly 4      XMT1SGN012A (Manual SG level control)
TS-SRO I-BOP I-SRO            1LT-471, SG Level fails low slowly 4      XMT1SGN012A (Manual SG level control)
TS-SRO I-RO            1LT-141, VCT Level Transmitter fails low, causing an auto shift to XMT1CVC020A I-SRO            the RWST. (Manual reactor trip required) 5      See SEG The first set of Reactor Trip push buttons fails to cause a reactor trip, TS-SRO          but the second set used is successful 6      MAL1SGN003B  M-ALL            Steam Generator Fault in Containment on Reactor Trip 1P-53, Motor Driven Auxiliary Feedwater Pump sheared shaft and PMP1AFW004 C-BOP            1P-29, Turbine Driven Auxiliary Feedwater Pump trips on over 7      PMP1AFW002 speed (CSP-H.1, Response to Loss of Secondary Heat Sink)
TS-SRO I-RO            1LT-141, VCT Level Transmitter fails low, causing an auto shift to XMT1CVC020A I-SRO            the RWST. (Manual reactor trip required) 5      See SEG The first set of Reactor Trip push buttons fails to cause a reactor trip, TS-SRO          but the second set used is successful 6      MAL1SGN003B  M-ALL            Steam Generator Fault in Containment on Reactor Trip 1P-53, Motor Driven Auxiliary Feedwater Pump sheared shaft and PMP1AFW004 C-BOP            1P-29, Turbine Driven Auxiliary Feedwater Pump trips on over 7      PMP1AFW002 speed (CSP-H.1, Response to Loss of Secondary Heat Sink)
  *        (N)ormal,  (R)eactivity, (I)nstrument,  (C)omponent,  (M)ajor}}
  *        (N)ormal,  (R)eactivity, (I)nstrument,  (C)omponent,  (M)ajor}}

Latest revision as of 15:27, 4 February 2020

2017 Point Beach Nuclear Plant Initial License Examination Forms ES-D-1 Revision 1
ML17201Q548
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/23/2017
From: Jesse Seymour
Operations Branch III
To:
Point Beach
Shared Package
ML16319A342 List:
References
Download: ML17201Q548 (4)


Text

Appendix D Scenario Outline Form ES-D-1 Facility: _Point Beach_____ Scenario No.: _1___________ Op-Test No.: _2017____

Examiners: ___________________________ Operators: _____________________________

Initial Conditions: _Unit 1 is at approximately 100%. Unit 2 is on ice melt. 1PT-950, Loop B Containment Pressure has been removed from service. Repairs are expected to be complete during the upcoming refueling outage. 1W-3B, Control Rod Shroud Fan is OOS due to imminent motor failure. ____

Turnover: Normal Shift routine. Lower power utilizing OP 3A, Power Operation to Hot Standby at _

30%/hr in preparation for refueling outage _______________________________________________

Event Malf. No. Event Event No. Type* Description I-BOP 1 XMT1CNM014A I-SRO 1PT-947, Loop A Containment Pressure Transmitter fails low TS-SRO I-BOP 1PC-2273, Feedwater Heater Emergency Bypass Valve Controller 2 CNH1CFW003F I-SRO oscillates in automatic 3 XMT1AFW005A TS-SRO 0LT-4040, T-24A CST Level Transmitter fails low R-RO 4 ANN-C02D-A09 N-BOP 1X01, Main Transformer loss of cooling (rapid down power)

R-SRO C-RO 5 CNH1PCS004F 1P-2A, Auto Charging Pump controller oscillation failure C-SRO 6 MAL1RCS001 M-ALL Large Break LOCA BKR1RHR001 C-BOP 1P-10A, RHR pump fails to start in Auto 7 MOT1RHR002 1P-10B, RHR pump trips upon starting RLY1PPL020 8 RLY1PPL021 C-BOP Containment Spray fails to actuate, manual alignment required.

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 Facility: _Point Beach_____ Scenario No.: _2___________ Op-Test No.: _2017____

Examiners: ___________________________ Operators: _____________________________

Initial Conditions: _Unit 1 is in OP 1C, Startup to Power Operation, at approximately 29% post _

chemistry hold coming out of a forced outage. At Chemistrys request B Train of Main Feed and _

Condensate have been running for 5 minutes for iron flushing. 1W-3B, Control Rod Shroud Fan _

is OOS due to imminent motor failure. 1PT-950, Loop B Containment Pressure has been removed _

from service. Repairs are expected to be complete during the upcoming refueling outage.__________

Turnover: Secure 1P-28B, SGFP and 1P-25B, Condensate Pump. Raise power to 50%. _________

Event Malf. No. Event Event No. Type* Description N-BOP 1 Secure SG Feed Pump and Condensate Pump N-SRO R-RO 2 N-BOP Raise power to 50%

R-SRO I-BOP 3 XMT1SGN001A I-SRO 1FI-464, SG Steam Flow fails slowly high TS-SRO I-BOP 4 XMT1MSS009A I-SRO 1PT-486, Turbine First Stage Pressure fails low TS-SRO C-RO 1P-1B, RCP Seal leak develops, which degrades requiring reactor 5 MAL1RCP001B C-SRO trip 6 MAL1RCS003F M-ALL Small Break LOCA from RTD Bypass Line occurs on reactor trip MAL1PPL001A C-RO Reactor fails to trip 7 MAL1PPL001B (CSP-S.1, Response to Nuclear Power Generation/ATWS)

MOT1SIS001 C-BOP 1P-15A, SI Pump trips upon starting 8 BKR1SIS002 1P-15B, SI Pump fails to start in Auto

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 Facility: _Point Beach_____ Scenario No.: _3___________ Op-Test No.: _2017____

Examiners: ___________________________ Operators: _____________________________

Initial Conditions: _Unit 1 was lowered to approximately 75% at the request of MISO/ATC due to grid stability issues. Grid stability has been restored and the unit is ready to be returned to full power in__

accordance with OP 1C, Startup to Power Operations. 1P-2B, Charging Pump is OOS and isolated _

per OI 50, Charging Pump Isolation for pump repairs. 1W-3B, Control Rod Shroud Fan is OOS due_

to imminent motor failure. 1PT-950, Loop B Containment Pressure has been removed from service._

Repairs are expected to be complete during the upcoming refueling outage. ____________________

Turnover: Commence raising power to 100% _

Event Malf. No. Event Event No. Type* Description C-BOP C-SRO P-32A, Service Water Pump trip with reduced head capacity on two 1 BKR1SWS001 running SW pumps TS-SRO C-BOP 1RE-219, SG Blowdown Monitor fails high off scale 2 XMT1RMS076A C-SRO 1MS-2083, HX-1A SG Sample Isolation Control Valve fails open R-RO N-BOP 3 MAL1RCS008A SG A Tube Leak approximately 10 gpm (rapid down power)

R-SRO TS-SRO C-BOP C-SRO Running CCW Pump seal leak, lowering surge tank 4 MAL1CCW002A (Pumps need to be shifted)

TS-SRO 5 MAL1GEN006 M-ALL Voltage Regulator Trouble leading to a Main Generator Lockout MALCRF001-B6 MALCRF001-B8 6 MALCRF001-C5 C-RO Multiple (4) Stuck Rods post trip MALCRF001-E11 7 MAL1RCS008A M-ALL SGTL turns into SGTR CNH1PCS007B 8 CNH1PCS008B C-RO Spray valves fail causing use of the PORV for RCS depressurization

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 Facility: _Point Beach_____ Scenario No.: _4___________ Op-Test No.: _2017____

Examiners: ___________________________ Operators: _____________________________

Initial Conditions: _Unit 1 is at approximately 100%. 1LT-112 VCT Level Transmitter has failed low, _

I&C expect repairs to be completed within the hour and returned to service by the end of shift. 1W-3B, Control Rod Shroud Fan is OOS due to imminent motor failure._______________________________

Turnover: Start 1P-27A, Heater Drain Tank Pump, and secure 1P-27C Heater Drain Tank Pump____

per OP 2A, Normal Power Operations, Attachment M, in preparations for maintenance. Lower power utilizing OP 3A, Power Operation to Hot Standby, in preparation for TS 3, Main Turbine Stop and Governor Valve with Turbine Trip_(Biannual)

Event Malf. No. Event Event No. Type* Description N-BOP 1 Shift Heater Drain Tank Pumps, start 1P-27A, secure 1P-27C N-SRO R-RO 2 N-BOP Down Power for TS-3 R-SRO I-RO I-SRO NI-43, PR NI fails low fast enough to cause outward rod motion near 3 MAL1NIS007C 12-15 steps/min.

TS-SRO I-BOP I-SRO 1LT-471, SG Level fails low slowly 4 XMT1SGN012A (Manual SG level control)

TS-SRO I-RO 1LT-141, VCT Level Transmitter fails low, causing an auto shift to XMT1CVC020A I-SRO the RWST. (Manual reactor trip required) 5 See SEG The first set of Reactor Trip push buttons fails to cause a reactor trip, TS-SRO but the second set used is successful 6 MAL1SGN003B M-ALL Steam Generator Fault in Containment on Reactor Trip 1P-53, Motor Driven Auxiliary Feedwater Pump sheared shaft and PMP1AFW004 C-BOP 1P-29, Turbine Driven Auxiliary Feedwater Pump trips on over 7 PMP1AFW002 speed (CSP-H.1, Response to Loss of Secondary Heat Sink)

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor