| | title = Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 | | | title = NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 |
| | author name = Schaaf R | | | author name = Schaaf R |
| | author affiliation = NRC/NRR/DORL/LPLII-2 | | | author affiliation = NRC/NRR/DORL/LPLII-2 |
Line 23: |
Line 23: |
| Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 (EPID L-2018-LLA-0494) | | Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 (EPID L-2018-LLA-0494) |
| Attachments: Watts Bar TSTF-500 Draft Second Round RAIs (L-2018-LLA-0494).pdf | | Attachments: Watts Bar TSTF-500 Draft Second Round RAIs (L-2018-LLA-0494).pdf |
| : Russ, By letter dated November 29, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. | | : Russ, By letter dated November 29, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18334A389), as supplemented by letter dated June 7, 2019 (ADAMS Accession No. ML19158A394), the Tennessee Valley Authority (TVA) submitted a license amendment request for the Watts Bar Nuclear Plant (Watts Bar), Units 1 and |
| ML18334A389), as supplemented by letter dated June 7, 2019 (ADAMS Accession No. ML19158A394), the Tennessee Valley Authority (TVA) submitted a license amendment request for the Watts Bar Nuclear Plant (Watts Bar), Units 1 and | |
| : 2. The requested amendments would modify TS requirements related to direct current (DC) electrical systems in accordance with Technical Specification Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360. | | : 2. The requested amendments would modify TS requirements related to direct current (DC) electrical systems in accordance with Technical Specification Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360. |
| The licensees letter dated June 7, 2019, responded to a U.S. Nuclear Regulatory Commission (NRC) staff request for additional information (RAI) dated May 3, 2019 (ADAMS Accession No. ML19126A121). The staff has reviewed the licensees responses and has determined that additional information, as described in the attached second-round RAI, is needed to complete the review of the Watts Bar license amendment request. | | The licensees letter dated June 7, 2019, responded to a U.S. Nuclear Regulatory Commission (NRC) staff request for additional information (RAI) dated May 3, 2019 (ADAMS Accession No. ML19126A121). The staff has reviewed the licensees responses and has determined that additional information, as described in the attached second-round RAI, is needed to complete the review of the Watts Bar license amendment request. |
Letter Sequence Draft Approval |
---|
|
|
MONTHYEARCNL-19-056, Response to NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-3602019-06-0707 June 2019 Response to NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 Project stage: Response to RAI ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 Project stage: Draft Approval ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 Project stage: RAI ML19235A2862019-09-0303 September 2019 Summary of Meeting with Tennessee Valley Authority Regarding Request to Adopt Technical Specifications Task Force Traveler TSTF-500 at Watts Bar, Units 1 and 2 Project stage: Meeting CNL-19-062, Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09)2019-09-0404 September 2019 Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09) Project stage: Request ML19241A2962019-09-0606 September 2019 Transmittal of Individual Federal Register Renotice for License Amendment Request TSTF-50 Project stage: Other ML19241A2952019-09-0606 September 2019 Individual Federal Register Renotice for License Amendment Request TSTF-500 Project stage: Other ML19249C6672019-10-0808 October 2019 Revision of Schedule and Level-of-Effort Estimates for Review of License Amendment Requests Project stage: Approval CNL-19-105, Supplemental Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09)2019-10-10010 October 2019 Supplemental Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09) Project stage: Supplement ML19276E5572019-12-0909 December 2019 Issuance of Amendment Nos. 130 and 33 Regarding Adoption of Technical Specifications Task Force Traveler, TSTF-500, DC Electrical Rewrite - Update to TSTF-360 Project stage: Approval 2019-07-25
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24274A2762024-09-24024 September 2024 Email from K.Green to S.Hughes, Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, Hydrologic LAR to Revise the UFSAR ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24215A3152024-07-24024 July 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-276-A, Revision 2 TS 3.8.1, AC Sources ML24177A1412024-06-11011 June 2024 NRR E-mail Capture - Audit Plan Related to Review of the Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, LAR to Revise Technical Specification Table 3.3.2-1 Function 5 ML24157A3152024-06-0303 June 2024 2024 Sequoyah Commercial Grade Dedication Inspection Information Request ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24156A0062024-05-22022 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Recapture Low-Power Testing Time ML24130A0132024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.11 for MCR Chiller Completion Time ML24123A0882024-05-0202 May 2024 NRR E-mail Capture - Correction Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24122B4872024-04-30030 April 2024 NRR E-mail Capture - Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24082A0662024-04-17017 April 2024 Email to Stuart Rymer on Exemption Decision for Watts Bar ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24082A0682024-04-10010 April 2024 Email to Stuart Rymer Re_ Availability of EA-FONSI for Watts Bar ML24100A8392024-04-0909 April 2024 Response from State of Tn Regarding Review of Environmental Assessment for Watts Bar Exemption Request ML24100A8402024-04-0808 April 2024 Email to State of Tn Requesting Review of Environmental Assessment for Watts Bar Exemption Request ML24071A0982024-03-0707 March 2024 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate ML24058A0962024-02-26026 February 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant License Amendment Request to Revise UFSAR for Hydrologic Analysis ML24047A2792024-02-15015 February 2024 RAI Related to the Exemption Request for 10 CFR 37.11 ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24033A0562024-02-0101 February 2024 NRR E-mail Capture - Correction Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-427-A, Revision 2 Regarding Degraded Barriers ML24036A0132024-01-23023 January 2024 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar Nuclear Plants, License Amendment Request to Revise TS Table 3.3.2-1, Function 5, Turbine Trip and Feedwater Isolation ML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22356A2982022-12-22022 December 2022 Email Response to Letter, Dated November 22, 2022 Regarding Watts Bar Integrated Inspection Report ML22353A0812022-12-15015 December 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Alternative Request WBN-2-ISI-01 Regarding Examination of Upper Head Injection Nozzle Dissimilar Metal Piping Butt Welds ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 2024-09-24
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21102A1312021-04-19019 April 2021 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 ML21095A0422021-04-0202 April 2021 NRR E-mail Capture - Added Clarification to RAI 2 for Thot LAR ML21095A0402021-04-0202 April 2021 NRR E-mail Capture - Request for Additional Information Re Generic Letter 95-05 90-Day Report and LAR to Adjust Growth Rate for Thot (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21091A0772021-04-0101 April 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Technical Specification 5.7.2.19, Containment Leakage Rate Testing Program ML21095A0412021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0442021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0462021-03-22022 March 2021 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Generic Letter 95-05 90-Day Report for Watts Bar Unit 2 ML21039A6402021-02-0808 February 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 1 Technical Specifications Related to Steam Generator Tube Inspection Frequency ML21012A2032021-01-11011 January 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar UFSAR to Use Alternate Probability of Detection ML20350B5592020-12-15015 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Adopt Traveler TSTF-490 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20322A4412020-11-17017 November 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20322A4392020-11-0505 November 2020 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20308A3512020-11-0202 November 2020 Request for Additional Information on WBN Request for Exemption from 10 CFR Part 73, Appendix B, Section VI for the Conduct of an Annual Force-on-Force Exercise (EPID L-2020-LLE-0165 (COVID-19)) ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information ML20196L8622020-07-14014 July 2020 NRR E-mail Capture - Watts Bar Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Implement the Full Spectrum LOCA Methodology ML20086G4802020-03-26026 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) - Part 2 ML20085G3572020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20084M1942020-03-24024 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20083J3952020-03-12012 March 2020 NRR E-mail Capture - Draft Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML19340A6842019-12-0505 December 2019 NRR E-mail Capture - Request for Additional Information for WBN2 Request for One-Time Extension of Completion Time for TS 3.7.8 (L-2019-LLA-0020) ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19186A4352019-07-0505 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Correction to Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19169A3592019-06-18018 June 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19106A0462019-04-15015 April 2019 NRR E-mail Capture - Watts BAR, Units 1 and 2 Request for Additional Informatin (RAI) Regarding Changes to Technical Specifications Sections 3.8.1, 3.8.7, 3.8.8, and 3.8.9 ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program ML18313A2202018-11-0707 November 2018 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML18282A6372018-10-0909 October 2018 NRR E-mail Capture - RAIs (Final) - LAR to Revise the Steam Generator Technical Specifications for Watts Bar Nuclear Plant, Unit 2 ML18270A2362018-09-26026 September 2018 NRR E-mail Capture - Watts Bar Units 1 and 2 RAIs - Modify TS 3.8.9 Completion Time for Inoperable 120V AC Vital Buses (L-2018-LLA-0050) 2024-09-10
[Table view] |
Text
NRR-DRMAPEm Resource From: Schaaf, Robert Sent: Thursday, July 25, 2019 10:18 AM To: 'Wells, Russell Douglas' Cc: Hulvey, Kimberly Dawn; 'Edmondson, Carla'; Shoop, Undine; Wentzel, Michael; Saba, Farideh
Subject:
Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 (EPID L-2018-LLA-0494)
Attachments: Watts Bar TSTF-500 Draft Second Round RAIs (L-2018-LLA-0494).pdf
- Russ, By letter dated November 29, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18334A389), as supplemented by letter dated June 7, 2019 (ADAMS Accession No. ML19158A394), the Tennessee Valley Authority (TVA) submitted a license amendment request for the Watts Bar Nuclear Plant (Watts Bar), Units 1 and
- 2. The requested amendments would modify TS requirements related to direct current (DC) electrical systems in accordance with Technical Specification Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360.
The licensees letter dated June 7, 2019, responded to a U.S. Nuclear Regulatory Commission (NRC) staff request for additional information (RAI) dated May 3, 2019 (ADAMS Accession No. ML19126A121). The staff has reviewed the licensees responses and has determined that additional information, as described in the attached second-round RAI, is needed to complete the review of the Watts Bar license amendment request.
This RAI is identified as draft at this time to confirm your understanding of the information that the NRC staff needs to complete its evaluation. The NRC staff proposes that TVA respond to this RAI within approximately 30 days of the date of this request (i.e, by August 23, 2019).
The staff is evaluating the effect of this second-round RAI on the current planned completion date for the review of November 2019 and may determine that additional time is needed to complete the review. We will inform TVA promptly of any review schedule impact determination.
Please call me at 301-415-6020 or Michael Wentzel at 301-415-6459 to set up a teleconference to clarify this request or to discuss an alternative schedule for TVAs response, as needed. If TVA determines that a clarification teleconference regarding the draft second-round RAI is needed, it should be requested to occur within approximately 5 business days of this e-mail transmittal.
- Regards, Robert G. Schaaf Senior Project Manager
====================
U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Operating Reactor Licensing Mail Stop O-8B1A
====================
301-415-6020 Robert.Schaaf@nrc.gov 1
2 Hearing Identifier: NRR_DRMA Email Number: 157 Mail Envelope Properties (BY5PR09MB4309FAE537A7FEF4CED2E6CBF9C10)
Subject:
Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 (EPID L-2018-LLA-0494)
Sent Date: 7/25/2019 10:18:12 AM Received Date: 7/25/2019 10:18:16 AM From: Schaaf, Robert Created By: Robert.Schaaf@nrc.gov Recipients:
"Hulvey, Kimberly Dawn" <kdhulvey@tva.gov>
Tracking Status: None
"'Edmondson, Carla'" <cedmondson@tva.gov>
Tracking Status: None "Shoop, Undine" <Undine.Shoop@nrc.gov>
Tracking Status: None "Wentzel, Michael" <Michael.Wentzel@nrc.gov>
Tracking Status: None "Saba, Farideh" <Farideh.Saba@nrc.gov>
Tracking Status: None
"'Wells, Russell Douglas'" <rdwells0@tva.gov>
Tracking Status: None Post Office: BY5PR09MB4309.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2310 7/25/2019 10:18:16 AM Watts Bar TSTF-500 Draft Second Round RAIs (L-2018-LLA-0494).pdf 119376 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
DRAFT REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO ADOPT TECHNICAL SPECIFICATIONS TASK FORCE (TSTF) TRAVELER TSTF-500, REVISION 2, DC ELECTRICAL REWRITE - UPDATE TO TSTF-360 TENNESSE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-390 AND 50-391
Background
By letter dated November 29, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18334A389), as supplemented by letter dated June 7, 2019 (ADAMS Accession No. ML19158A394), Tennessee Valley Authority (the licensee), requested an amendment to Facility Operating Licenses NPF-90 and NPF-96 for Watts Bar Nuclear Plant (WBN), Units 1 and 2. The proposed license amendment request would revise the WBN Units 1 and 2 Technical Specifications (TSs) to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, "DC [direct current] Electrical Rewrite - Update to TSTF-360 (ADAMS Accession No. ML092670242). Specifically, the licensee proposed changes to the TS requirements related to DC electrical power systems in TS 3.8.4, DC sources - Operating, TS 3.8.5, DC Sources - Shutdown, and TS 3.8.6, Battery Cell Parameters. Additionally, the licensee proposed to add to the TS Section 5.7, Procedures, Programs, and Manuals, a new program titled Battery Monitoring and Maintenance Program.
The licensees letter dated June 7, 2019, responded to the Electrical Engineering Operating Reactors Branch (EEOB) staffs request for additional information (RAI) dated May 3, 2019 (ADAMS Accession No. ML19126A121). The EEOB staff has reviewed the licensees responses and has determined that the following additional information is needed to complete the review of the WBN license amendment request.
Regulatory Requirements Title 10 of the Code of Federal Regulations (10 CFR), Section 50.36, Technical Specifications, requires, in part, that the operating license of a nuclear production facility include TSs.
Section 50.36(c)(2) of 10 CFR requires that the TS include limiting conditions for operation (LCOs) which are the lowest functional capability or performance levels of equipment required for safe operation of the facility. When an LCO of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the technical specifications until the condition can be met.
Appendix A, General Design Criteria [GDC] for Nuclear Power Plants, to 10 CFR Part 50.
GDC-17, Electric power systems, states, in part:
An onsite electric power system and an offsite electric power system shall be provided to permit functioning of structures, systems, and components important to safety. [] The 1
onsite electric power supplies, including the batteries, and the onsite electric distribution system, shall have sufficient independence, redundancy, and testability to perform their safety functions assuming a single failure.
Regulatory Guidance TSTF-500, Revision 2.
EEOB RAI-7.b.01 In its June 7, 2019, letter, in response to EEOB RAI-7, the licensee proposed to revise the TS LCO 3.8.4 statement for the diesel generator (DG) DC electrical power subsystems from four DG DC electrical power subsystems to Train A and Train B DG DC electrical power subsystems; and to revise the TS 3.8.4 and TS 3.8.6 conditions related to the DG electrical power subsystems. The licensee stated that the proposed change to the LCO 3.8.4 with respect to the DG DC electrical power subsystem supports the redundancy of the standby electrical power subsystem. The licensee provided the following explanation (emphasis added):
Each DG DC electrical power system is independent and dedicated to its respective DG.
The DGs that are supported by the DG DC electrical power systems are arranged in redundant trains (i.e., DG 1A-A and DG 2A-A are in Train A, and DG 1B-B and DG 2B-B are in Train B). When one or two DGs in a train are inoperable, that train of standby electrical power is incapable of performing the safety function and must rely on the redundant DG train to mitigate an event. Likewise, if one or two of the DG DC trains that support the DGs in that train are inoperable, that train of standby electrical power is incapable of performing the safety function and must rely on the redundant train to mitigate an event. Therefore, the LCO requires Train A and Train B DG DC electrical power subsystems to be OPERABLE to support the redundancy of the standby electrical power system.
In its November 29, 2018, letter, Enclosure 1, Section 2.0, Assessment, the licensee states (emphasis added):
A DG battery subsystem is provided for each DG. Each subsystem is comprised of a battery, dual battery charger assembly, distribution center, and cabling.
The NRC staff has identified the following apparent discrepancies:
x It appears that the DC power for a DG is provided by a DG DC electrical power system in the June 7, 2019, letter but by a DG battery subsystem in the November 29, 2018, letter.
x It appears that a discussion provided in the June 7, 2019, letter did not describe the relationship between the DG DC trains and the DG DC subsystems.
The NRC staff requests the following information to address these discrepancies:
1- Clarify whether a DG DC subsystem or DG DC system supports each DG.
2- Clarify the relationship between the DG DC trains and the DG DC electrical power subsystems in the above-mentioned paragraph in the June 7, 2019, letter.
2
EEOB RAI-9 In its June 7, 2019, letter, the licensee proposed a revised TS 3.8.4 Condition D and associated Required Actions D.1, D.2, and D.3 to state:
CONDITION REQUIRED ACTION COMPLETION TIME D. One or two DG DC D.1 Restore DG battery 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> battery charger(s) on terminal voltage to one train inoperable greater than or equal to the minimum established float voltage.
AND D.2 Verify battery float Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> cuUUHQWDPS
AND D.3 Restore DG battery 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> charger(s) to OPERABLE status.
In its November 29, 2018, letter, Enclosure 1, Section 2.0, the licensee states:
A DG battery subsystem is provided for each DG. Each subsystem is comprised of a battery, dual battery charger assembly, distribution center, and cabling. [] Each of the chargers (normal and alternate) in the dual charger assembly has a dedicated AC source from two respective 480V AC Diesel Generator Auxiliary Boards. If the normal charger is unavailable, the alternate charger is selected by the 125V DC transfer switch included in the assembly.
The TSTF-500, Revision 2, allows for a 72-hour CT for an inoperable battery charger based on the condition that an alternate means (e.g. spare battery charger) of restoring battery terminal voltage to greater than or equal to the minimum established float voltage has been used.
The NRC staff has identified the following apparent discrepancies:
x If the WBN DG dual battery charger for each DG battery subsystem on one train is designed such that the alternate battery charger is selected automatically when the normal battery charger becomes inoperable, TS 3.8.4 Condition D will be entered only after both the normal and alternate battery chargers become inoperable. In this case, it appears that there would be no alternate charger that would be used to restore the DG battery terminal voltage to greater than or equal to the minimum established float voltage within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> (Required Action D.1); and thus, the proposed 72-hour CT for restoring the inoperable DG battery charger to operable status (Required Action D.3) could not be used.
3
The NRC staff requests the following information
- 1. Discuss the TS requirements for an operable DG battery subsystem and an operable DG DC train. Include in the discussion the number of operable battery charger in the dual assembly that is required for an operable DG battery subsystem and for an operable DG DC train.
- 2. Discuss the case(s) when Condition D will be entered and provide the alternate means that will be used to restore DG battery terminal voltage to greater than or equal to the minimum established float voltage within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to allow the 72-hour CT for the inoperable DG battery charger in each case.
4