Letter Sequence Approval |
|---|
|
|
MONTHYEARCNL-18-067, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (WBN-TS-18-14)2018-10-12012 October 2018 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (WBN-TS-18-14) Project stage: Request ML18324A8912018-11-20020 November 2018 NRR E-mail Capture - Watts Bar Units 1 and 2 - Acceptance for Review - Application for TS Change - Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (L-2018-LLA-0279) Project stage: Acceptance Review CNL-18-118, Application to Revise Technical Specifications Regarding DC Electrical Systems TStf-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 (WBN-TS-18-09)2018-11-29029 November 2018 Application to Revise Technical Specifications Regarding DC Electrical Systems TStf-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 (WBN-TS-18-09) Project stage: Request CNL-18-068, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors (WBN-TS-17-24)2018-11-29029 November 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors (WBN-TS-17-24) Project stage: Request ML19011A3492019-01-0707 January 2019 NRR E-mail Capture - Watts Bar Units 1 and 2 - Acceptance for Review - Application to Revise Technical Specifications Regarding DC Electrical Systems Consistent with TSTF-500, Revision 2 (L-2018-LLA-0494) Project stage: Acceptance Review ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program Project stage: RAI CNL-19-054, Correction to Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (WBN-TS-18-14)2019-06-0606 June 2019 Correction to Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (WBN-TS-18-14) Project stage: Request CNL-19-038, License Amendment Request to Make Miscellaneous Administrative Changes (WBN-TS-19-02)2019-06-0707 June 2019 License Amendment Request to Make Miscellaneous Administrative Changes (WBN-TS-19-02) Project stage: Request CNL-19-056, Response to NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-3602019-06-0707 June 2019 Response to NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 Project stage: Response to RAI ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 Project stage: Draft Approval ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 Project stage: RAI ML19227A0932019-08-15015 August 2019 Draft Responses to Second Round Requests for Additional Information Related to Request to Adopt TSTF-500 Project stage: Draft Other CNL-19-060, Supplement to Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (WBN-TS-18-14)2019-08-29029 August 2019 Supplement to Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (WBN-TS-18-14) Project stage: Supplement ML19235A2862019-09-0303 September 2019 Summary of Meeting with Tennessee Valley Authority Regarding Request to Adopt Technical Specifications Task Force Traveler TSTF-500 at Watts Bar, Units 1 and 2 Project stage: Meeting CNL-19-062, Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09)2019-09-0404 September 2019 Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09) Project stage: Request ML19241A2962019-09-0606 September 2019 Transmittal of Individual Federal Register Renotice for License Amendment Request TSTF-50 Project stage: Other ML19241A2952019-09-0606 September 2019 Individual Federal Register Renotice for License Amendment Request TSTF-500 Project stage: Other ML19249C6672019-10-0808 October 2019 Revision of Schedule and Level-of-Effort Estimates for Review of License Amendment Requests Project stage: Approval CNL-19-105, Supplemental Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09)2019-10-10010 October 2019 Supplemental Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09) Project stage: Supplement ML19276E5572019-12-0909 December 2019 Issuance of Amendment Nos. 130 and 33 Regarding Adoption of Technical Specifications Task Force Traveler, TSTF-500, DC Electrical Rewrite - Update to TSTF-360 Project stage: Approval CNL-19-084, Second Supplement to Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program.2020-01-17017 January 2020 Second Supplement to Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program. Project stage: Supplement ML20028F7332020-02-28028 February 2020 Issuance of Amendment Nos. 132 and 36 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-425, Revision 3 Project stage: Approval 2019-06-07
[Table View] |
Text
October 8, 2019 Mr. James Barstow Vice President, Nuclear Regulatory Affairs and Support Services Tennessee Valley Authority 1101 Market Street, LP 4A-C Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 - REVISION OF SCHEDULE AND LEVEL-OF-EFFORT ESTIMATES FOR THE REVIEW OF LICENSE AMENDMENT REQUESTS (EPID L-2018-LLA-0279 AND EPID L-2018-LLA-0494)
Dear Mr. Barstow:
By letter dated October 12, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18288A352), as supplemented by letters dated May 7, 2019; June 6, 2019; and August 29, 2019 (ADAMS Accession Nos. ML19127A323, ML19157A302, and ML19242D967, respectively), Tennessee Valley Authority (TVA, the licensee) submitted a license amendment request for the Watts Bar Nuclear Plant, Units 1 and 2 (Watts Bar), to modify the Watts Bar Technical Specifications to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control
- RITSTF Initiative 5b (ADAMS Accession No. ML090850642).
By letter dated November 29, 2018 (ADAMS Accession No. ML18334A389), as supplemented by letters dated June 7, 2019; and September 4, 2019 (ADAMS Accession Nos. ML19158A394 and ML19247C981), TVA submitted a license amendment request for Watts Bar to adopt TSTF Traveler TSTF-500, Revision 2, DC [Direct Current] Electrical Rewrite - Update to TSTF-360 (ADAMS Accession No. ML092670242).
In its August 29, 2019, letter, TVA requested the U.S. Nuclear Regulatory Commission (NRC) staff to delay the completion of its review of the licensees request to adopt TSTF-425, Revision 3, until after the completion of the staffs review of the licensees request to adopt TSTF-500, but no later than December 28, 2019. The NRC staffs current schedule for completion of review of these applications is October 31, 2019, for the request to adopt TSTF-425, and November 29, 2019, for the request to adopt TSTF-500. TVA stated that the basis for this request is to properly sequence the proposed amendments to address the interaction between the two license amendment requests that was not fully accounted for during their development. TVA further stated that it intended to provide an additional supplement for its TSTF-425 request to account for the TSTF-500 amendments once those had been issued.
The NRC staff has reviewed the schedule and resource impacts of the licensees request for delay and agrees to delay approval of the licensees request to adopt TSTF-425 until after the completion of its review of the licensees request to adopt TSTF-500. However, the NRC staff has determined that additional changes are necessary to the schedule and level-of-effort estimates previously communicated to the licensee.
In its January 7, 2019, e-mail transmitting the acceptance review results for the license amendment request to adopt TSTF-500 (ADAMS Accession No. ML19011A349), the NRC staff estimated that it could complete review of the licensees request by November 2019 and would require approximately 250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> of staff time to do so. As stated in the e-mail, these estimates were based on the NRC staffs initial review of the application and were subject to change due to factors such as requests for additional information and unanticipated addition of scope to the review.
The NRC staffs review of the licensees request has resulted in two rounds of requests for additional information, and TVA has twice modified its original request. Both modifications have added additional complexity to the staffs review. As a result, the NRC staff has expended approximately 280 hours0.00324 days <br />0.0778 hours <br />4.62963e-4 weeks <br />1.0654e-4 months <br /> on its review of the request. The staff estimates that it will require an additional 70 hours8.101852e-4 days <br />0.0194 hours <br />1.157407e-4 weeks <br />2.6635e-5 months <br /> to complete review of the licensees request, for a total of 350 hours0.00405 days <br />0.0972 hours <br />5.787037e-4 weeks <br />1.33175e-4 months <br />.
Regarding the schedule, TVAs September 4, 2019, supplement to the request to adopt TSTF-500 included a new proposed change that the NRC staff determined expands the scope of the request beyond what was provided to the public in the notice published in the Federal Register on June 18, 2019 (84 FR 28348). The NRC staff prepared a new notice that was published in the Federal Register on September 12, 2019 (84 FR 48180). To account for the limited time available for the staff to complete its review following the expiration of the hearing period, the NRC staff is revising the estimated completion date of its review of the licensees request to adopt TSTF-500 to December 2019. Similarly, the NRC staff is revising its estimated completion date for its review of TVAs request to adopt TSTF-425 to February 2020 to account for the timing of TVAs planned supplement to address changes being made by TSTF-500 and the time needed for the staff to complete its review, once received. As practicable, the NRC staff will attempt to meet the licensees requested issuance dates.
The NRC staffs revised estimates assume that all remaining information will be provided in a timely fashion and that there will not be any additional changes made to either of TVAs requests that add to the scope of review. Should either change, the NRC staff will provide a revised estimate, as necessary.
If you have any questions, please contact Michael Wentzel at 301-415-6459 or by e-mail to Michael.Wentzel@nrc.gov.
Sincerely,
/RA/
Undine Shoop, Chief Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-390 and 50-391 cc: Listserv
ML19249C667 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DORL/LPL2-2/BC NAME MWentzel LRonewicz UShoop DATE 9/09/2019 9/09/2019 10/08/2019