ML110060057: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: Mozafari, Brenda Sent: Wednesday, January 05, 2011 3:35 PM To: Castell, Curt Cc: Boyle, Patrick; Lingam, Siva | {{#Wiki_filter:From: Mozafari, Brenda Sent: Wednesday, January 05, 2011 3:35 PM To: Castell, Curt Cc: Boyle, Patrick; Lingam, Siva | ||
==Subject:== | ==Subject:== | ||
Exemption and TS Change regarding M5 Alloy Fuel Usage (TACs ME4911 and ME4912) | Exemption and TS Change regarding M5 Alloy Fuel Usage (TACs ME4911 and ME4912) | ||
: Curt, As we have touched upon informally, I am sending you more this formal indication that in accordance with LIC-109, the NRC staff completed the acceptance review of the exemption request dated October 19, 2010, regarding M5 Alloy Fuel Usage. The NRC staff finds this exemption request to be acceptable for review in that the submittal reasonably appear to contain sufficient technical information, both in scope and depth, for the staff to begin the detailed technical review consistent with the time frame described in your correspondence. | |||
The ongoing review may result in some questions that will need to be addressed informally or formally prior to the completion of the staff's final assessment of the amendment and exemption (TACs ME4911 and ME4912, respectively). I will contact you regarding any need for clarification or requests for additional information. | Likewise, your amendment request on this subject dated October 20, 2010, has been accepted for full review consistent with LIC-109. | ||
The ongoing review may result in some questions that will need to be addressed informally or formally prior to the completion of the staff's final assessment of the amendment and exemption (TACs ME4911 and ME4912, respectively). I will contact you regarding any need for clarification or requests for additional information. | |||
Thanks, | : Thanks, Brenda L. Mozafari Senior Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2020 email: brenda.mozafari@nrc.gov}} |
Latest revision as of 04:47, 13 November 2019
ML110060057 | |
Person / Time | |
---|---|
Site: | Robinson |
Issue date: | 01/05/2011 |
From: | Mozafari B Plant Licensing Branch II |
To: | Castell C Carolina Power & Light Co |
Mozafari B, NRR/ADRO/DORL, 415-2020 | |
References | |
TAC ME4911, TAC ME4912 | |
Download: ML110060057 (1) | |
Text
From: Mozafari, Brenda Sent: Wednesday, January 05, 2011 3:35 PM To: Castell, Curt Cc: Boyle, Patrick; Lingam, Siva
Subject:
Exemption and TS Change regarding M5 Alloy Fuel Usage (TACs ME4911 and ME4912)
- Curt, As we have touched upon informally, I am sending you more this formal indication that in accordance with LIC-109, the NRC staff completed the acceptance review of the exemption request dated October 19, 2010, regarding M5 Alloy Fuel Usage. The NRC staff finds this exemption request to be acceptable for review in that the submittal reasonably appear to contain sufficient technical information, both in scope and depth, for the staff to begin the detailed technical review consistent with the time frame described in your correspondence.
Likewise, your amendment request on this subject dated October 20, 2010, has been accepted for full review consistent with LIC-109.
The ongoing review may result in some questions that will need to be addressed informally or formally prior to the completion of the staff's final assessment of the amendment and exemption (TACs ME4911 and ME4912, respectively). I will contact you regarding any need for clarification or requests for additional information.
- Thanks, Brenda L. Mozafari Senior Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2020 email: brenda.mozafari@nrc.gov