ML11285A478: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov] | ||
Sent: Monday, September 12, 2011 2:35 PM To: Poole, Justin; Milano, Patrick; Campbell, Stephen; Epperson, Dan Cc: Arent, Gordon; Smith, James D; Bryan, | Sent: Monday, September 12, 2011 2:35 PM To: Poole, Justin; Milano, Patrick; Campbell, Stephen; Epperson, Dan Cc: Arent, Gordon; Smith, James D; Bryan, Robert H Jr; Smith, James D; Crouch, William D | ||
==Subject:== | ==Subject:== | ||
NRC PM Open Items List 9-13-11 R1.docx Attachments: | NRC PM Open Items List 9-13-11 R1.docx Attachments: NRC PM Open Items List 9-13-11 R1.docx Updated - Rev 1. For next phone call. | ||
NRC PM Open Items List 9-13-11 R1. | Thank you, | ||
~*~*~*~*~*~*~*~*~*~*~*~ | |||
Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services dlboyd@tva.gov 423-365-8764 1 | |||
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 523 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF22EC0EB8) | |||
Hearing Identifier: | |||
==Subject:== | ==Subject:== | ||
NRC PM Open Items List 9-13-11 R1.docx | NRC PM Open Items List 9-13-11 R1.docx Sent Date: 9/12/2011 2:35:16 PM Received Date: 9/12/2011 2:35:20 PM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients: | ||
Tracking Status: None | "Arent, Gordon" <garent@tva.gov> | ||
Tracking Status: None | Tracking Status: None "Smith, James D" <jdsmith@tva.gov> | ||
Tracking Status: None | Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov> | ||
Tracking Status: None "Smith, James D" <smith1jd@westinghouse.com> | |||
Tracking Status: None "Crouch, William D" <wdcrouch@tva.gov> | |||
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov> | |||
Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov> | |||
Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov> | |||
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov> | |||
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 272 9/12/2011 2:35:20 PM NRC PM Open Items List 9-13-11 R1.docx 31614 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: | |||
Recipients Received: | |||
Page 1 of 4 NRC PM Open Items List 9/13/11 (423) 751-7777 ID 4233652004# | |||
Page 1 of 4 | No. Description Status Additional Comments Resp Org/Person | ||
No. Description Status Additional Comments Resp Org/Person 1. Cyber Security Plan/Controls and | : 1. Cyber Security Plan/Controls and NRC TI issued NRC Inspection in 2011 Heinrich/Snyder Implementation TBD (Bryan) | ||
To be discussed at the next ACRS meeting (October NRC Table 5th - closed portion). | |||
Top/Pilot Oct 2011 Set up follow-up meeting 9/20 or 9/21 Procedures complete 9/30/11 Pre-inspection TBD Inspection Dec 2011 | |||
: 2. Instrumentation RAI List (Knuettel) 1. 9/23/11 RAI Responses Eng/Hilmes | |||
: 1. Item 3 for GA-ESI RM-1000 RAD 2. Various - | |||
* Item 1 GA/ESI is preparing a report to document (Smith) | |||
Monitors. see status the conformance of their CGD program to NRC | |||
: 2. GA proprietary, non-proprietary and 3. 9/26/11 requirements based on NRC telecom on 8/30/11. | |||
affidavits for withholding submittals 4. 10/1/11 | |||
* Item 2 - 04038903-1SP - Prop due 9/30/11 | |||
(~12 documents.) 5. 11/30/11 04038903-2SP - Prop due 10/6/11 | |||
: 3. NRC comments on procedures to 04038903-4SP - Prop due 10/21/11 GA-ESI 04038903-QSR - Prop due 9/30/11 | |||
: 4. RM1000 EMI/RFI questions | |||
* Item 3 OP-7.3-240 - Prop due 9/26/11 | |||
: 5. Submit non-prop/affidavits | |||
* Item 4 Create new bridge document 04038800-1SP - Prop due 10/1/11 | |||
: 3. Verify MACCs values for SAMA Cost 1. 9/8/11A 1. Non-conservatisms in some values identified. ENG/Koontz Benefit Evaluation 2. 9/13/11 Discuss updated results with NRC | |||
: 3. 9/20/11 2. Submitted revised tables | |||
: 3. Submit revised RAI responses | |||
Page 2 of 4 No. Description Status Additional Comments Resp Org/Person | |||
: 4. Exemption to 10CFR50.49 for some 9/23/11 Hilmes Category II cables (Stockton) | |||
: 5. Complete Implementation (Hemmer) Pump Additional clarification to Phase I actions will be Hemmer Relocation needed. Fleet wide issue. (Smith) 5/30/12 Substantial building to complete and equipment in May. | |||
Bldg Plan Provide document of mitigating equipment and 9/23/11 location for unit 2. | |||
Inspection - | |||
June 2012 Phase I commitments 10/1/11 | |||
: 6. Chapter 15.5 RAIs 9/21/11 Includes FHA calc. X/Q discussion for each accident, Wastrack corrections to previously submitted dose calcs, and a (Bryan) complete 15.5 markup. Potential meeting following submittal. Look at splitting submittal up. | |||
: 7. Fire Protection Report Questions 1. 10/24-28/11 1. Audit ENG/Hilmes regarding OMA 2.9/30/11 2. Group 7 RAI response (Crouch) 3.10/1/11 3. Receive Group 8 RAIs | |||
: 4. 11/4/11 4. Response to Group 8 | |||
: 5. 11/30/11 5. Submit As-designed U1/U2 FPR | |||
: 6. TBD 6. Fire Protection Program Audit Frequency | |||
: 8. Tech Spec Revisions from latest T/S 1. Oct, 2011 1. CSST A & B - discretionary Licensing/Elton markup and NRC Review comments 2. Sept, 2011 2. I-131 DEI (Bryan) | |||
: 3. Oct, 2011 3. Diesel Generator Frequency | |||
: 4. TBD 4. Unit 1 AST FHA | |||
: 9. ACRS Topics 10/5/11 Cyber, Chapter 15 except dose, Chapter 4 (Fuels), Gordon WINCISE, Hydrology, process for FSAR drawing documentation update, | |||
: 10. SSER 22/23/24 Open Items Response 9/16/11 9/16 is the target date for the next SSER update. The Licensing expanded HH list and status is covered periodically. | |||
Page 3 of 4 No. Description Status Additional Comments Resp Org/Person | |||
: 11. Transient Analysis issues 9/16/11 Question on RG revision and modes 3, 4, & 5. TVA to ENG/Koontz provide write up explaining NRC acceptance (CLB) of WEC/Morgan Boron dilution RAI response unit1 for modes 3, 4, & 5. | |||
: 12. FSAR A106 9/16/11 Target date. Lic/Stockton Correction - change note 17 of Table 7.1.1 to Reg Guide 1.152 R 3 instead of R 2 How will note on FSAR figure 9.2-23 change for two unit operation when the CCS C-S and 2B pumps are realigned | |||
: 13. Develop list of planned License 1. 11/1/11 1. Review Unit 1 SER for exemptions. Sand NRR/TVA Conditions, Exemptions and Relief 2. TBD baskets, cyber security, physical security, PAD (Bryan) | |||
Requests (Crouch) 4.0 | |||
: 2. NRR to review current exemptions | |||
: 14. Verify Tech Spec Setpoints match calcs 1. 10/4/11 1. 6 SSDs remaining to be issued. Possible submittal Eng/Hilmes if any number changes. (Bryan) | |||
TS certification 2. TBD 2. TS certification | |||
: 15. Issue two Unit Offsite Dose Calculation 3/1/12 Determine actual need date Chemistry/ | |||
Manual (Beach) Review TS Chapter 5 Woods programs also (Bryan) | |||
: 16. Issue Unit 2 Completion Letter (Crouch) 8/1/12 Licensing | |||
: 17. Submit final as-constructed FSAR 7/1/12 Licensing/ | |||
figures Stockton | |||
: 18. TMI action items 7/1/12 TVA to provide letter when TMI actions are field Licensing complete. (Gordon) | |||
: 19. ASME N-801 & N-802 code cases March 2012` NRC response to relief request submitted 9/1/11. NRR | |||
: 0. Discretionary Actions | |||
: 1. Letter to terminate Part 30/40 License 4/1/12 Licensing after receipt of Part 50 License (Crouch) | |||
: 2. Combined U1/U2 FSAR (Stockton) 3/1/13 Licensing | |||
: 3. Status of GSI 199 Eastern Seismicity Fall 2011 No action pending upcoming Generic Letter TVA/NRR (Crouch) Related information on GSI 194 may need input | |||
: 4. Letter to notify NRC when Vital Area 12/1/11 Security Plan Update - Boundary to be restored by Lic/Crouch Boundary returned to original location 9/30/11 | |||
Page 4 of 4 No. Description Status Additional Comments Resp Org/Person | |||
: 5. IEB 88-02 SG Tube Cracking TBD Tubes are assumed locked in the WEC analysis. Corp SG/ | |||
Waiting for NRC concurrence. Webber ISI/Tinley}} | |||
: | |||
Revision as of 14:31, 12 November 2019
ML11285A478 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 09/12/2011 |
From: | - No Known Affiliation |
To: | Division of Operating Reactor Licensing |
References | |
Download: ML11285A478 (6) | |
Text
WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]
Sent: Monday, September 12, 2011 2:35 PM To: Poole, Justin; Milano, Patrick; Campbell, Stephen; Epperson, Dan Cc: Arent, Gordon; Smith, James D; Bryan, Robert H Jr; Smith, James D; Crouch, William D
Subject:
NRC PM Open Items List 9-13-11 R1.docx Attachments: NRC PM Open Items List 9-13-11 R1.docx Updated - Rev 1. For next phone call.
Thank you,
~*~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services dlboyd@tva.gov 423-365-8764 1
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 523 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF22EC0EB8)
Subject:
NRC PM Open Items List 9-13-11 R1.docx Sent Date: 9/12/2011 2:35:16 PM Received Date: 9/12/2011 2:35:20 PM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:
"Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Smith, James D" <jdsmith@tva.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None "Smith, James D" <smith1jd@westinghouse.com>
Tracking Status: None "Crouch, William D" <wdcrouch@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>
Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 272 9/12/2011 2:35:20 PM NRC PM Open Items List 9-13-11 R1.docx 31614 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Page 1 of 4 NRC PM Open Items List 9/13/11 (423) 751-7777 ID 4233652004#
No. Description Status Additional Comments Resp Org/Person
- 1. Cyber Security Plan/Controls and NRC TI issued NRC Inspection in 2011 Heinrich/Snyder Implementation TBD (Bryan)
To be discussed at the next ACRS meeting (October NRC Table 5th - closed portion).
Top/Pilot Oct 2011 Set up follow-up meeting 9/20 or 9/21 Procedures complete 9/30/11 Pre-inspection TBD Inspection Dec 2011
- 1. Item 3 for GA-ESI RM-1000 RAD 2. Various -
- Item 1 GA/ESI is preparing a report to document (Smith)
Monitors. see status the conformance of their CGD program to NRC
- 2. GA proprietary, non-proprietary and 3. 9/26/11 requirements based on NRC telecom on 8/30/11.
affidavits for withholding submittals 4. 10/1/11
- Item 2 - 04038903-1SP - Prop due 9/30/11
(~12 documents.) 5. 11/30/11 04038903-2SP - Prop due 10/6/11
- 3. NRC comments on procedures to 04038903-4SP - Prop due 10/21/11 GA-ESI 04038903-QSR - Prop due 9/30/11
- 4. RM1000 EMI/RFI questions
- Item 3 OP-7.3-240 - Prop due 9/26/11
- 5. Submit non-prop/affidavits
- Item 4 Create new bridge document 04038800-1SP - Prop due 10/1/11
- 3. Verify MACCs values for SAMA Cost 1. 9/8/11A 1. Non-conservatisms in some values identified. ENG/Koontz Benefit Evaluation 2. 9/13/11 Discuss updated results with NRC
- 3. 9/20/11 2. Submitted revised tables
- 3. Submit revised RAI responses
Page 2 of 4 No. Description Status Additional Comments Resp Org/Person
- 4. Exemption to 10CFR50.49 for some 9/23/11 Hilmes Category II cables (Stockton)
- 5. Complete Implementation (Hemmer) Pump Additional clarification to Phase I actions will be Hemmer Relocation needed. Fleet wide issue. (Smith) 5/30/12 Substantial building to complete and equipment in May.
Bldg Plan Provide document of mitigating equipment and 9/23/11 location for unit 2.
Inspection -
June 2012 Phase I commitments 10/1/11
- 6. Chapter 15.5 RAIs 9/21/11 Includes FHA calc. X/Q discussion for each accident, Wastrack corrections to previously submitted dose calcs, and a (Bryan) complete 15.5 markup. Potential meeting following submittal. Look at splitting submittal up.
- 7. Fire Protection Report Questions 1. 10/24-28/11 1. Audit ENG/Hilmes regarding OMA 2.9/30/11 2. Group 7 RAI response (Crouch) 3.10/1/11 3. Receive Group 8 RAIs
- 4. 11/4/11 4. Response to Group 8
- 5. 11/30/11 5. Submit As-designed U1/U2 FPR
- 6. TBD 6. Fire Protection Program Audit Frequency
- 8. Tech Spec Revisions from latest T/S 1. Oct, 2011 1. CSST A & B - discretionary Licensing/Elton markup and NRC Review comments 2. Sept, 2011 2. I-131 DEI (Bryan)
- 3. Oct, 2011 3. Diesel Generator Frequency
- 9. ACRS Topics 10/5/11 Cyber, Chapter 15 except dose, Chapter 4 (Fuels), Gordon WINCISE, Hydrology, process for FSAR drawing documentation update,
- 10. SSER 22/23/24 Open Items Response 9/16/11 9/16 is the target date for the next SSER update. The Licensing expanded HH list and status is covered periodically.
Page 3 of 4 No. Description Status Additional Comments Resp Org/Person
- 11. Transient Analysis issues 9/16/11 Question on RG revision and modes 3, 4, & 5. TVA to ENG/Koontz provide write up explaining NRC acceptance (CLB) of WEC/Morgan Boron dilution RAI response unit1 for modes 3, 4, & 5.
- 12. FSAR A106 9/16/11 Target date. Lic/Stockton Correction - change note 17 of Table 7.1.1 to Reg Guide 1.152 R 3 instead of R 2 How will note on FSAR figure 9.2-23 change for two unit operation when the CCS C-S and 2B pumps are realigned
- 13. Develop list of planned License 1. 11/1/11 1. Review Unit 1 SER for exemptions. Sand NRR/TVA Conditions, Exemptions and Relief 2. TBD baskets, cyber security, physical security, PAD (Bryan)
Requests (Crouch) 4.0
- 2. NRR to review current exemptions
- 14. Verify Tech Spec Setpoints match calcs 1. 10/4/11 1. 6 SSDs remaining to be issued. Possible submittal Eng/Hilmes if any number changes. (Bryan)
TS certification 2. TBD 2. TS certification
- 15. Issue two Unit Offsite Dose Calculation 3/1/12 Determine actual need date Chemistry/
Manual (Beach) Review TS Chapter 5 Woods programs also (Bryan)
- 16. Issue Unit 2 Completion Letter (Crouch) 8/1/12 Licensing
- 17. Submit final as-constructed FSAR 7/1/12 Licensing/
figures Stockton
- 18. TMI action items 7/1/12 TVA to provide letter when TMI actions are field Licensing complete. (Gordon)
- 19. ASME N-801 & N-802 code cases March 2012` NRC response to relief request submitted 9/1/11. NRR
- 0. Discretionary Actions
- 1. Letter to terminate Part 30/40 License 4/1/12 Licensing after receipt of Part 50 License (Crouch)
- 2. Combined U1/U2 FSAR (Stockton) 3/1/13 Licensing
- 3. Status of GSI 199 Eastern Seismicity Fall 2011 No action pending upcoming Generic Letter TVA/NRR (Crouch) Related information on GSI 194 may need input
- 4. Letter to notify NRC when Vital Area 12/1/11 Security Plan Update - Boundary to be restored by Lic/Crouch Boundary returned to original location 9/30/11
Page 4 of 4 No. Description Status Additional Comments Resp Org/Person
Waiting for NRC concurrence. Webber ISI/Tinley