ML112990125: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 10/26/2011
| issue date = 10/26/2011
| title = Email, Request for Additional Information, Amendment Request to Adopt TSTF-425-A, Rev. 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force (RITSTF) Initiative 5b.
| title = Email, Request for Additional Information, Amendment Request to Adopt TSTF-425-A, Rev. 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force (RITSTF) Initiative 5b.
| author name = Singal B K
| author name = Singal B
| author affiliation = NRC/NRR/DORL/LPLIV
| author affiliation = NRC/NRR/DORL/LPLIV
| addressee name = Hope T
| addressee name = Hope T
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:From: Singal, Balwant Sent: Wednesday, October 26, 2011 8:43 AM To: 'Hope, Timothy' Cc: 'Slough, Rob'  
{{#Wiki_filter:From:                     Singal, Balwant Sent:                     Wednesday, October 26, 2011 8:43 AM To:                       'Hope, Timothy' Cc:                       'Slough, Rob'


==Subject:==
==Subject:==
Request for Additional Information - Risk Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program - TACs ME6789 and ME6790 Attachments: ME6789-RAI.docx Tim: By application dated August 1, 2011, Luminant Generation Company LLC (Luminant) requested changes to the Comanche Peak Nuclear Power Plant Technical Specifications (TSs) for adoption of the Nuclear Regulatory Commission (NRC) approved Technical Specification Task Force(TSTF) - 425, Revision 3, "Relocate Surveillance Frequencies to Licensee Control - RITSTF [Risk-Informed TSTF] Initiative 5b.The NRC staff will need additional information identified in the attached document to complete its review of the application.  
Request for Additional Information - Risk Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program - TACs ME6789 and ME6790 Attachments:               ME6789-RAI.docx Tim:
 
By application dated August 1, 2011, Luminant Generation Company LLC (Luminant) requested changes to the Comanche Peak Nuclear Power Plant Technical Specifications (TSs) for adoption of the Nuclear Regulatory Commission (NRC) approved Technical Specification Task Force(TSTF) - 425, Revision 3, Relocate Surveillance Frequencies to Licensee Control -
Draft request for additional information (RAI) was transmitted to you via e-mail on October 17, 2011 and was discussed during a conference call on October 25, 2011 for clarification purposes. Luminant agreed to provide their response within 30 days from the date of receipt of formal RAIs.  
RITSTF [Risk-Informed TSTF] Initiative 5b. The NRC staff will need additional information identified in the attached document to complete its review of the application.
 
Draft request for additional information (RAI) was transmitted to you via e-mail on October 17, 2011 and was discussed during a conference call on October 25, 2011 for clarification purposes. Luminant agreed to provide their response within 30 days from the date of receipt of formal RAIs.
Thanks. Balwant K. Singal Senior Project Manager (Comanche Peak and STP) Nuclear Regulatory Commission Division of Operating Reactor Licensing Balwant.Singal@nrc.gov Tel: (301) 415-3016 Fax: (301) 415-1222}}
Thanks.
Balwant K. Singal Senior Project Manager (Comanche Peak and STP)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Balwant.Singal@nrc.gov Tel: (301) 415-3016 Fax: (301) 415-1222}}

Latest revision as of 14:00, 12 November 2019

Email, Request for Additional Information, Amendment Request to Adopt TSTF-425-A, Rev. 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force (RITSTF) Initiative 5b.
ML112990125
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/26/2011
From: Balwant Singal
Plant Licensing Branch IV
To: Hope T
Luminant Generation Co
Singal, Balwant, 415-3016, NRR/DORL/LPL4
References
TAC ME6789, TAC ME6790
Download: ML112990125 (1)


Text

From: Singal, Balwant Sent: Wednesday, October 26, 2011 8:43 AM To: 'Hope, Timothy' Cc: 'Slough, Rob'

Subject:

Request for Additional Information - Risk Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program - TACs ME6789 and ME6790 Attachments: ME6789-RAI.docx Tim:

By application dated August 1, 2011, Luminant Generation Company LLC (Luminant) requested changes to the Comanche Peak Nuclear Power Plant Technical Specifications (TSs) for adoption of the Nuclear Regulatory Commission (NRC) approved Technical Specification Task Force(TSTF) - 425, Revision 3, Relocate Surveillance Frequencies to Licensee Control -

RITSTF [Risk-Informed TSTF] Initiative 5b. The NRC staff will need additional information identified in the attached document to complete its review of the application.

Draft request for additional information (RAI) was transmitted to you via e-mail on October 17, 2011 and was discussed during a conference call on October 25, 2011 for clarification purposes. Luminant agreed to provide their response within 30 days from the date of receipt of formal RAIs.

Thanks.

Balwant K. Singal Senior Project Manager (Comanche Peak and STP)

Nuclear Regulatory Commission Division of Operating Reactor Licensing Balwant.Singal@nrc.gov Tel: (301) 415-3016 Fax: (301) 415-1222