{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:ENT000290
NUCLEAR REGULATORY COMMISSION
                                                                                Submitted: March 29, 2012
OFFICE OF NUCLEAR REACTOR REGULATION
                                          UNITED STATES
WASHINGTON, D.C. 20555-0001
                            NUCLEAR REGULATORY COMMISSION
August 2, 2004
                        OFFICE OF NUCLEAR REACTOR REGULATION
NRC REGULATORY ISSUE SUMMARY 2004-13
                                WASHINGTON, D.C. 20555-0001
CONSIDERATION OF SHELTERING IN LICENSEES RANGE OF
                                          August 2, 2004
PROTECTIVE ACTION RECOMMENDATIONS
                  NRC REGULATORY ISSUE SUMMARY 2004-13
      CONSIDERATION OF SHELTERING IN LICENSEES RANGE OF
                    PROTECTIVE ACTION RECOMMENDATIONS
ADDRESSEES
ADDRESSEES
All holders of operating licenses for nuclear power reactors, except those who have
All holders of operating licenses for nuclear power reactors, except those who have
permanently ceased operations and have certified that fuel has been permanently removed
permanently ceased operations and have certified that fuel has been permanently removed
from the reactor vessel.
from the reactor vessel.
INTENT The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary (RIS)
INTENT
The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary (RIS)
to clarify the regulatory requirement that licensees develop a range of protective actions that
to clarify the regulatory requirement that licensees develop a range of protective actions that
includes sheltering for the public in the plume exposure pathway emergency planning zone
includes sheltering for the public in the plume exposure pathway emergency planning zone
(EPZ). This RIS requires no action or written response on the part of addressees.
(EPZ). This RIS requires no action or written response on the part of addressees.
BACKGROUND INFORMATION
BACKGROUND INFORMATION
Section 50.47(b)(10) of Title 10 of the Code of Federal Regulations (CFR) states in part that
Section 50.47(b)(10) of Title 10 of the Code of Federal Regulations (CFR) states in part that
licensees are to develop a range of protective actions for the public in the plume exposure
licensees are to develop a range of protective actions for the public in the plume exposure
 
pathway EPZ. In addition, 10 CFR 50.47(b)(10) states that in developing this range of
pathway EPZ. In addition, 10 CFR 50.47(b)(10) states that in developing this range of
 
protective actions, consideration is to be given to sheltering, and that the guidelines for the
protective actions, consideration is to be given to sheltering, and that the guidelines for the
 
choice of protective actions be consistent with Federal guidance.
choice of protective actions be consistent with Federal guidance.  
Following an inspection at Point Beach in August 2003 (ML040360104), the NRC staff
Following an inspection at Point Beach in August 2003 (ML040360104), the NRC staff
performed a review of licensee emergency plans, implementing procedures, and notification
performed a review of licensee emergency plans, implementing procedures, and notification
forms to evaluate the extent licensees considered sheltering when recommending protective
forms to evaluate the extent licensees considered sheltering when recommending protective
 
actions to offsite organizations. During the review, the NRC staff has noticed that licensee
actions to offsite organizations. During the review, the NRC staff has noticed that licensee
 
emergency plans, implementing procedures and notification forms consider sheltering in one of
emergency plans, implementing procedures and notification forms consider sheltering in one of
three ways: (1) sheltering as an alternative to evacuation (shelter rather than evacuate),
three ways: (1) sheltering as an alternative to evacuation (shelter rather than evacuate),
(2) sheltering as a supplement to evacuation (evacuate downwind sectors and shelter the
(2) sheltering as a supplement to evacuation (evacuate downwind sectors and shelter the
 
remaining sectors until further instructions are provided), and (3) sheltering is not considered by
remaining sectors until further instructions are provided), and (3) sheltering is not considered by
 
the licensee. The NRC staff has also noticed that some licensees have addressed sheltering
the licensee. The NRC staff has also noticed that some licensees have addressed sheltering
inconsistently in their emergency plan, implementing procedures, and notification forms. For
inconsistently in their emergency plan, implementing procedures, and notification forms. For
 
example, sheltering is considered as an alternative to evacuation in the emergency plan, but it
example, sheltering is considered as an alternative to evacuation in the emergency plan, but it
is not included as an option in the implementing procedures or on the notification form.
is not included as an option in the implementing procedures or on the notification form.
ML041210046
ML041210046
ENT000290
 
Submitted:  March 29, 2012
                                                                                      RIS 2004-13
RIS 2004-13
                                                                                      Page 2 of 4
Page 2 of 4
DISCUSSION
DISCUSSION
The decision to recommend a protective action involves a judgment in which the radiation dose
The decision to recommend a protective action involves a judgment in which the radiation dose
avoidance provided by the protective action is weighed in the context of the risks involved in
avoidance provided by the protective action is weighed in the context of the risks involved in
 
taking the action. Since the decision will most likely be made under emergency conditions,
taking the action. Since the decision will most likely be made under emergency conditions,
considerable planning is necessary to reduce the complexity of decisions required to effectively
considerable planning is necessary to reduce the complexity of decisions required to effectively
 
protect the public at the time of an emergency.
protect the public at the time of an emergency.
Plant conditions are the major determining factors in developing early protective action
Plant conditions are the major determining factors in developing early protective action
recommendations. To be most effective, protective actions (evacuation or shelter) need to be
recommendations. To be most effective, protective actions (evacuation or shelter) need to be
 
taken before or shortly after the start of a major radioactive release to the atmosphere.
taken before or shortly after the start of a major radioactive release to the atmosphere.  
 
According to the original version of Appendix 1, Emergency Action Level Guidelines for Nuclear
According to the original version of Appendix 1, Emergency Action Level Guidelines for Nuclear
Power Plants, in NUREG-0654/FEMA-REP-1, Criteria for Preparation and Evaluation of
Power Plants, in NUREG-0654/FEMA-REP-1, Criteria for Preparation and Evaluation of
Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power
Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power
Plants, the initial protective action for a General Emergency is to shelter the population close to
Plants, the initial protective action for a General Emergency is to shelter the population close to
 
the plant while considering the advisability of evacuation. The guidance in the original version
the plant while considering the advisability of evacuation. The guidance in the original version
 
of Appendix 1 further states that if core damage is in progress and containment failure is judged
of Appendix 1 further states that if core damage is in progress and containment failure is judged
to be imminent, shelter should be recommended for people in those areas that cannot be
to be imminent, shelter should be recommended for people in those areas that cannot be
 
evacuated before the plume arrives. Although the original guidance was never intended to
evacuated before the plume arrives. Although the original guidance was never intended to
 
imply that the appropriate initial protective action for severe accidents was to only shelter the
imply that the appropriate initial protective action for severe accidents was to only shelter the
population that is near the plant, it was not explicit on this point.
population that is near the plant, it was not explicit on this point.
Subsequently, portions of Appendix 1 were revised in Supplement 3 Criteria for Protective
Subsequently, portions of Appendix 1 were revised in Supplement 3 Criteria for Protective
Action Recommendations for Severe Accidents, to NUREG-0654/FEMA-REP-1, Criteria for
Action Recommendations for Severe Accidents, to NUREG-0654/FEMA-REP-1, Criteria for
Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in
Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in
 
Support of Nuclear Power Plants. Revised Appendix 1 states that for a General Emergency,
Support of Nuclear Power Plants. Revised Appendix 1 states that for a General Emergency,
the preferred initial protective action is to evacuate immediately about two miles in all directions
the preferred initial protective action is to evacuate immediately about two miles in all directions
 
from the plant and about five miles downwind, unless other conditions make evacuation
from the plant and about five miles downwind, unless other conditions make evacuation
 
dangerous. Note 5 to Figure 1, Severe Damage or Loss of Control of Facility Public Protective
dangerous. Note 5 to Figure 1, Severe Damage or Loss of Control of Facility Public Protective
 
Actions, in Supplement 3, states that sheltering may be the appropriate action for controlled
Actions, in Supplement 3, states that sheltering may be the appropriate action for controlled
releases of radioactive material from the containment, if there is assurance that the release is
releases of radioactive material from the containment, if there is assurance that the release is
short term (puff release) and the area near the plant cannot be evacuated before the plume
short term (puff release) and the area near the plant cannot be evacuated before the plume
 
arrives.
arrives.10 CFR 50.47(b)(10) requires that the consideration of sheltering be included in the range of
10 CFR 50.47(b)(10) requires that the consideration of sheltering be included in the range of
protective action recommendations consistent with Federal guidance. In addition to the Federal
protective action recommendations consistent with Federal guidance. In addition to the Federal
 
guidance discussed above, EPA 400-R-92-001, Manual of Protective Action Guides and
guidance discussed above, EPA 400-R-92-001, Manual of Protective Action Guides and
Protective Actions for Nuclear Accidents (EPA 400), dated May 1992, also contains information
Protective Actions for Nuclear Accidents (EPA 400), dated May 1992, also contains information
 
on evacuation and sheltering. Section 5.5.3, General Guidance for Evacuation and Sheltering,
on evacuation and sheltering. Section 5.5.3, General Guidance for Evacuation and Sheltering,
states that the process of evaluating, recommending, and implementing evacuation or shelter
states that the process of evaluating, recommending, and implementing evacuation or shelter
 
for the public is far from an exact science, particularly in view of time constraints that prevent
for the public is far from an exact science, particularly in view of time constraints that prevent
 
thorough analysis at the time of an emergency. The effectiveness of evacuation and shelter can
thorough analysis at the time of an emergency. The effectiveness of evacuation and shelter can
be improved considerably by planning and testing. Also, EPA 400 states that sheltering may be
 
appropriate (when available) for areas not designated for immediate evacuation because: 1) it
be improved considerably by planning and testing. Also, EPA 400 states that sheltering may be
 
appropriate (when available) for areas not designated for immediate evacuation because: 1) it
 
positions the public to receive additional instructions; and 2) it may provide protection equal to
positions the public to receive additional instructions; and 2) it may provide protection equal to
or greater than evacuation.


or greater than evacuation. 
                                                                                    RIS 2004-13
RIS 2004-13
                                                                                    Page 3 of 4
Page 3 of 4
SUMMARY OF ISSUE
SUMMARY OF ISSUE
The NRC staff has identified a generic misinterpretation of the regulatory requirement to include
The NRC staff has identified a generic misinterpretation of the regulatory requirement to include
sheltering in a licensee's range of protective action recommendations (PARs) consistent with
sheltering in a licensee's range of protective action recommendations (PARs) consistent with
 
Federal guidance. The NRC staff has found that some emergency plans specifically state that
Federal guidance. The NRC staff has found that some emergency plans specifically state that
the licensee will provide only evacuation as a PAR. In those cases, the appropriate protective
 
the licensee will provide only evacuation as a PAR. In those cases, the appropriate protective
 
action recommendation consistent with Federal guidance may not be made to State and/or local
action recommendation consistent with Federal guidance may not be made to State and/or local
 
authorities. Even if the licensee has established an understanding with State and local
authorities. Even if the licensee has established an understanding with State and local
 
authorities not to recommend a sheltering protective action, 10 CFR 50.47(b)(10) still requires
authorities not to recommend a sheltering protective action, 10 CFR 50.47(b)(10) still requires
that sheltering be considered in developing the range of protective action recommendations in
that sheltering be considered in developing the range of protective action recommendations in
the licensee's emergency plan.
the licensee's emergency plan.
Federal guidance states that sheltering may be the appropriate action for controlled releases of
Federal guidance states that sheltering may be the appropriate action for controlled releases of
radioactive material from the containment, if there is assurance that the release is short term
radioactive material from the containment, if there is assurance that the release is short term
(puff release) and the area near the plant cannot be evacuated before the plume arrives.  
(puff release) and the area near the plant cannot be evacuated before the plume arrives.
 
Federal guidance also states that sheltering may be appropriate (when available) for areas not
Federal guidance also states that sheltering may be appropriate (when available) for areas not
 
designated for immediate evacuation because: 1) it positions the public to receive additional
designated for immediate evacuation because: 1) it positions the public to receive additional
instructions; and 2) it may provide protection equal to or greater than evacuation. Additionally, a
 
instructions; and 2) it may provide protection equal to or greater than evacuation. Additionally, a
 
licensee's emergency plan, implementing procedures, and notification forms need to include the
licensee's emergency plan, implementing procedures, and notification forms need to include the
consideration of sheltering consistent with Federal guidance.
consideration of sheltering consistent with Federal guidance.
BACKFIT DISCUSSION
BACKFIT DISCUSSION
This RIS clarifies the regulatory requirements in 10 CFR 50.47(b)(10) related to the need for
This RIS clarifies the regulatory requirements in 10 CFR 50.47(b)(10) related to the need for
licensees to develop a range of protective actions (including sheltering) for the public in the
licensees to develop a range of protective actions (including sheltering) for the public in the
 
plume exposure pathway EPZ. This RIS does not impose new or modified staff requirements or
plume exposure pathway EPZ. This RIS does not impose new or modified staff requirements or
 
uniquely prescribe a way to comply with the regulations, or require any action or written
uniquely prescribe a way to comply with the regulations, or require any action or written
 
response. Therefore, this RIS does not constitute a backfit under 10 CFR 50.109 and the staff
response. Therefore, this RIS does not constitute a backfit under 10 CFR 50.109 and the staff
 
did not perform a backfit analysis.
did not perform a backfit analysis.
FEDERAL REGISTER
FEDERAL REGISTER NOTIFICATION
NOTIFICATION
A notice of opportunity for public comment on this RIS was not published in the Federal Register
A notice of opportunity for public comment on this RIS was not published in the  
Federal Register
because this RIS is informational and pertains to a staff position that does not represent a
because this RIS is informational and pertains to a staff position that does not represent a
departure from current regulatory practice.


departure from current regulatory practice.
                                                                                  RIS 2004-13
RIS 2004-13
                                                                                  Page 4 of 4
Page 4 of 4
PAPERWORK REDUCTION ACT STATEMENT
PAPERWORK REDUCTION ACT STATEMENT
This RIS does not request any information collections and, therefore, is not subject to the
This RIS does not request any information collections and, therefore, is not subject to the
Line 199: Line 142:
If you have any questions about this matter, please contact Robert Kahler by telephone or by
If you have any questions about this matter, please contact Robert Kahler by telephone or by
e-mail at the numbers listed below.
e-mail at the numbers listed below.
/RA/Terrence Reis, Acting Chief
                                            /RA/
Reactor Operations Branch
                                            Terrence Reis, Acting Chief
                                            Reactor Operations Branch
                                            Division of Inspection Program Management
                                            Office of Nuclear Reactor Regulation
Technical Contact:  Robert Kahler, NSIR
                    (301) 415-2992
                    Email: rek@nrc.gov
Attachment: List of Recently Issued Regulatory Issue Summaries


Division of Inspection Program Management
                                                                                          Attachment
 
                                                                                          RIS 2004-13
Office of Nuclear Reactor RegulationTechnical Contact:Robert Kahler, NSIR
                                                                                          Page 1 of 1
(301) 415-2992
                                        LIST OF RECENTLY ISSUED
 
                                  NRC REGULATORY ISSUE SUMMARIES
Email: rek@nrc.gov
____________________________________________________________________________________
Attachment: List of Recently Issued Regulatory Issue Summaries
Regulatory Issue                                            Date of
Summary No.                  Subject                    Issuance        Issued to
____________________________________________________________________________________
2004-12          Clarification on Use of Later              07/28/2004 All holders of operating licenses
                Editions and Addenda to the                          for nuclear power reactors except
                ASME OM Code and Section XI                          those who have permanently
                                                                      ceased operations and have
                                                                      certified that fuel has been
                                                                      permanently removed from the
                                                                      reactor vessel.
2003-18,        Use of Nuclear Energy INSTITUTE            07/13/2004 All holders of operating licenses
Supplement 1    (NEI) 99-01, Methodology for                        for nuclear power reactors and
                Development of Emergency Action                      licensees that have permanently
                Levels, Revision 4, Dated January                    ceased operations and have
                2003                                                  certified that fuel has been
                                                                      permanently removed from the
                                                                      reactor vessel.
2004-11          Supporting Information Associated          06/29/2004 All submitters of proprietary
                with Requests For Withholding                        information to the Nuclear
                Proprietary Information                              Regulatory Commission.
2004-10          Preparation And Scheduling of              06/14/2004 All holders of operating licenses
                Operator Licensing Examinations                      for nuclear power reactors, except
                                                                      those who have permanently
                                                                      ceased operations and have
                                                                      certified that fuel has been
                                                                      permanently removed from the
                                                                      reactor vessel.
2004-09          Status on Deferral of Active              06/07/2004 All holders of materials licenses for
                Regulation of Ground-water                            uranium and thorium recovery
                Protection At In Situ Leach                          facilities.
                Uranium Extraction Facilities
2004-08          Results of the License Termination        05/28/2004 All holders of operating licenses
                Rule Analysis                                        for nuclear power reactors,
                                                                      research and test reactors, as well
                                                                      as decommissioning sites.
Note:            NRC generic communications may be received in electronic format shortly after they are
                  issued by subscribing to the NRC listserver as follows:
                  To subscribe send an e-mail to <listproc@nrc.gov >, no subject, and the following
                  command in the message portion:
                                    subscribe gc-nrr firstname lastname
______________________________________________________________________________________
______________________________________________________________________________________
OL = Operating License
OL = Operating License
CP = Construction Permit
CP = Construction Permit
Attachment
RIS 2004-13
Page 1 of 1
LIST OF RECENTLY ISSUED
NRC REGULATORY ISSUE SUMMARIES
____________________________________________________________________________________Regulatory Issue  Date of
  Summary No.      Subject  IssuanceIssued to
____________________________________________________________________________________2004-12Clarification on Use of Later
Editions and Addenda to the
ASME OM Code and Section XI07/28/2004All holders of operating licenses
for nuclear power reactors except
those who have permanently
ceased operations and have
certified that fuel has been
permanently removed from the
reactor vessel.
2003-18, Supplement 1
Use of Nuclear Energy INSTITUTE (NEI) 99-01, Methodology for
Development of Emergency Action
Levels, Revision 4, Dated January
200307/13/2004All holders of operating licenses
for nuclear power reactors and
licensees that have permanently
ceased operations and have
certified that fuel has been
permanently removed from the
reactor vessel.2004-11Supporting Information Associated
with Requests For Withholding
Proprietary Information06/29/2004All submitters of proprietary
information to the Nuclear
Regulatory Commission.2004-10Preparation And Scheduling of
Operator Licensing Examinations06/14/2004All holders of operating licenses
for nuclear power reactors, except
those who have permanently
ceased operations and have
certified that fuel has been
permanently removed from the
reactor vessel. 2004-09Status on Deferral of Active
Regulation of Ground-water
Protection At In Situ Leach
Uranium Extraction Facilities06/07/2004All holders of materials licenses for
uranium and thorium recovery
facilities.2004-08Results of the License Termination
Rule Analysis05/28/2004All holders of operating licenses
for nuclear power reactors,
research and test reactors, as well
as decommissioning sites.
Note:NRC generic communications may be received in electronic format shortly after they are
issued by subscribing to the NRC listserver as follows:
To subscribe send an e-mail to <
listproc@nrc.gov
>, no subject, and the following
command in the message portion:
subscribe gc-nrr firstname lastname
}}
}}

Latest revision as of 06:00, 12 November 2019

Entergy Pre-Filed Evidentiary Hearing Exhibit ENT000290, NRC Regulatory Issue Summary 2004-13 Consideration of Sheltering in Licensee'S Range of Protective Action Recommendations
ML12089A549
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/02/2004
From: Reis T
Office of Nuclear Reactor Regulation
To:
Atomic Safety and Licensing Board Panel
SECY RAS
Shared Package
ML12089A543 List:
References
RAS 22120, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01 RIS-04-013
Download: ML12089A549 (5)


See also: RIS 2004-13

Text

ENT000290

Submitted: March 29, 2012

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555-0001

August 2, 2004

NRC REGULATORY ISSUE SUMMARY 2004-13

CONSIDERATION OF SHELTERING IN LICENSEES RANGE OF

PROTECTIVE ACTION RECOMMENDATIONS

ADDRESSEES

All holders of operating licenses for nuclear power reactors, except those who have

permanently ceased operations and have certified that fuel has been permanently removed

from the reactor vessel.

INTENT

The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary (RIS)

to clarify the regulatory requirement that licensees develop a range of protective actions that

includes sheltering for the public in the plume exposure pathway emergency planning zone

(EPZ). This RIS requires no action or written response on the part of addressees.

BACKGROUND INFORMATION

Section 50.47(b)(10) of Title 10 of the Code of Federal Regulations (CFR) states in part that

licensees are to develop a range of protective actions for the public in the plume exposure

pathway EPZ. In addition, 10 CFR 50.47(b)(10) states that in developing this range of

protective actions, consideration is to be given to sheltering, and that the guidelines for the

choice of protective actions be consistent with Federal guidance.

Following an inspection at Point Beach in August 2003 (ML040360104), the NRC staff

performed a review of licensee emergency plans, implementing procedures, and notification

forms to evaluate the extent licensees considered sheltering when recommending protective

actions to offsite organizations. During the review, the NRC staff has noticed that licensee

emergency plans, implementing procedures and notification forms consider sheltering in one of

three ways: (1) sheltering as an alternative to evacuation (shelter rather than evacuate),

(2) sheltering as a supplement to evacuation (evacuate downwind sectors and shelter the

remaining sectors until further instructions are provided), and (3) sheltering is not considered by

the licensee. The NRC staff has also noticed that some licensees have addressed sheltering

inconsistently in their emergency plan, implementing procedures, and notification forms. For

example, sheltering is considered as an alternative to evacuation in the emergency plan, but it

is not included as an option in the implementing procedures or on the notification form.

ML041210046

RIS 2004-13

Page 2 of 4

DISCUSSION

The decision to recommend a protective action involves a judgment in which the radiation dose

avoidance provided by the protective action is weighed in the context of the risks involved in

taking the action. Since the decision will most likely be made under emergency conditions,

considerable planning is necessary to reduce the complexity of decisions required to effectively

protect the public at the time of an emergency.

Plant conditions are the major determining factors in developing early protective action

recommendations. To be most effective, protective actions (evacuation or shelter) need to be

taken before or shortly after the start of a major radioactive release to the atmosphere.

According to the original version of Appendix 1, Emergency Action Level Guidelines for Nuclear

Power Plants, in NUREG-0654/FEMA-REP-1, Criteria for Preparation and Evaluation of

Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power

Plants, the initial protective action for a General Emergency is to shelter the population close to

the plant while considering the advisability of evacuation. The guidance in the original version

of Appendix 1 further states that if core damage is in progress and containment failure is judged

to be imminent, shelter should be recommended for people in those areas that cannot be

evacuated before the plume arrives. Although the original guidance was never intended to

imply that the appropriate initial protective action for severe accidents was to only shelter the

population that is near the plant, it was not explicit on this point.

Subsequently, portions of Appendix 1 were revised in Supplement 3 Criteria for Protective

Action Recommendations for Severe Accidents, to NUREG-0654/FEMA-REP-1, Criteria for

Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in

Support of Nuclear Power Plants. Revised Appendix 1 states that for a General Emergency,

the preferred initial protective action is to evacuate immediately about two miles in all directions

from the plant and about five miles downwind, unless other conditions make evacuation

dangerous. Note 5 to Figure 1, Severe Damage or Loss of Control of Facility Public Protective

Actions, in Supplement 3, states that sheltering may be the appropriate action for controlled

releases of radioactive material from the containment, if there is assurance that the release is

short term (puff release) and the area near the plant cannot be evacuated before the plume

arrives.

10 CFR 50.47(b)(10) requires that the consideration of sheltering be included in the range of

protective action recommendations consistent with Federal guidance. In addition to the Federal

guidance discussed above, EPA 400-R-92-001, Manual of Protective Action Guides and

Protective Actions for Nuclear Accidents (EPA 400), dated May 1992, also contains information

on evacuation and sheltering. Section 5.5.3, General Guidance for Evacuation and Sheltering,

states that the process of evaluating, recommending, and implementing evacuation or shelter

for the public is far from an exact science, particularly in view of time constraints that prevent

thorough analysis at the time of an emergency. The effectiveness of evacuation and shelter can

be improved considerably by planning and testing. Also, EPA 400 states that sheltering may be

appropriate (when available) for areas not designated for immediate evacuation because: 1) it

positions the public to receive additional instructions; and 2) it may provide protection equal to

or greater than evacuation.

RIS 2004-13

Page 3 of 4

SUMMARY OF ISSUE

The NRC staff has identified a generic misinterpretation of the regulatory requirement to include

sheltering in a licensee's range of protective action recommendations (PARs) consistent with

Federal guidance. The NRC staff has found that some emergency plans specifically state that

the licensee will provide only evacuation as a PAR. In those cases, the appropriate protective

action recommendation consistent with Federal guidance may not be made to State and/or local

authorities. Even if the licensee has established an understanding with State and local

authorities not to recommend a sheltering protective action, 10 CFR 50.47(b)(10) still requires

that sheltering be considered in developing the range of protective action recommendations in

the licensee's emergency plan.

Federal guidance states that sheltering may be the appropriate action for controlled releases of

radioactive material from the containment, if there is assurance that the release is short term

(puff release) and the area near the plant cannot be evacuated before the plume arrives.

Federal guidance also states that sheltering may be appropriate (when available) for areas not

designated for immediate evacuation because: 1) it positions the public to receive additional

instructions; and 2) it may provide protection equal to or greater than evacuation. Additionally, a

licensee's emergency plan, implementing procedures, and notification forms need to include the

consideration of sheltering consistent with Federal guidance.

BACKFIT DISCUSSION

This RIS clarifies the regulatory requirements in 10 CFR 50.47(b)(10) related to the need for

licensees to develop a range of protective actions (including sheltering) for the public in the

plume exposure pathway EPZ. This RIS does not impose new or modified staff requirements or

uniquely prescribe a way to comply with the regulations, or require any action or written

response. Therefore, this RIS does not constitute a backfit under 10 CFR 50.109 and the staff

did not perform a backfit analysis.

FEDERAL REGISTER NOTIFICATION

A notice of opportunity for public comment on this RIS was not published in the Federal Register

because this RIS is informational and pertains to a staff position that does not represent a

departure from current regulatory practice.

RIS 2004-13

Page 4 of 4

PAPERWORK REDUCTION ACT STATEMENT

This RIS does not request any information collections and, therefore, is not subject to the

requirements of the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).

If you have any questions about this matter, please contact Robert Kahler by telephone or by

e-mail at the numbers listed below.

/RA/

Terrence Reis, Acting Chief

Reactor Operations Branch

Division of Inspection Program Management

Office of Nuclear Reactor Regulation

Technical Contact: Robert Kahler, NSIR

(301) 415-2992

Email: rek@nrc.gov

Attachment: List of Recently Issued Regulatory Issue Summaries

Attachment

RIS 2004-13

Page 1 of 1

LIST OF RECENTLY ISSUED

NRC REGULATORY ISSUE SUMMARIES

____________________________________________________________________________________

Regulatory Issue Date of

Summary No. Subject Issuance Issued to

____________________________________________________________________________________

2004-12 Clarification on Use of Later 07/28/2004 All holders of operating licenses

Editions and Addenda to the for nuclear power reactors except

ASME OM Code and Section XI those who have permanently

ceased operations and have

certified that fuel has been

permanently removed from the

reactor vessel.

2003-18, Use of Nuclear Energy INSTITUTE 07/13/2004 All holders of operating licenses

Supplement 1 (NEI) 99-01, Methodology for for nuclear power reactors and

Development of Emergency Action licensees that have permanently

Levels, Revision 4, Dated January ceased operations and have

2003 certified that fuel has been

permanently removed from the

reactor vessel.

2004-11 Supporting Information Associated 06/29/2004 All submitters of proprietary

with Requests For Withholding information to the Nuclear

Proprietary Information Regulatory Commission.

2004-10 Preparation And Scheduling of 06/14/2004 All holders of operating licenses

Operator Licensing Examinations for nuclear power reactors, except

those who have permanently

ceased operations and have

certified that fuel has been

permanently removed from the

reactor vessel.

2004-09 Status on Deferral of Active 06/07/2004 All holders of materials licenses for

Regulation of Ground-water uranium and thorium recovery

Protection At In Situ Leach facilities.

Uranium Extraction Facilities

2004-08 Results of the License Termination 05/28/2004 All holders of operating licenses

Rule Analysis for nuclear power reactors,

research and test reactors, as well

as decommissioning sites.

Note: NRC generic communications may be received in electronic format shortly after they are

issued by subscribing to the NRC listserver as follows:

To subscribe send an e-mail to <listproc@nrc.gov >, no subject, and the following

command in the message portion:

subscribe gc-nrr firstname lastname

______________________________________________________________________________________

OL = Operating License

CP = Construction Permit