| | issue date = 04/09/2014 | | | issue date = 04/09/2014 |
| | title = Request for Withholding Information from Public Disclosure | | | title = Request for Withholding Information from Public Disclosure |
| | author name = Purnell B A | | | author name = Purnell B |
| | author affiliation = NRC/NRR/DORL/LPLIII-2 | | | author affiliation = NRC/NRR/DORL/LPLIII-2 |
| | addressee name = Pacilio M J | | | addressee name = Pacilio M |
| | addressee affiliation = Exelon Generation Co, LLC | | | addressee affiliation = Exelon Generation Co, LLC |
| | docket = 05000461 | | | docket = 05000461 |
Line 15: |
Line 15: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Michael J. Pacilio Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 April 9, 2014 | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 9, 2014 Mr. Michael J. Pacilio Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| CLINTON POWER STATION, UNIT 1 -REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE | | CLINTON POWER STATION, UNIT 1 -REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE |
|
| |
|
| ==Dear Mr. Pacilio:== | | ==Dear Mr. Pacilio:== |
| By letter 1 to the U.S. Nuclear Regulatory Commission (NRC) dated March 27, 2014, Exelon Generation Company, LLC submitted results of a post-irradiation examination of a GE14i isotope test assembly performed by Global Nuclear Fuel-Americas, LLC (GNF-A). This submittal included an affidavit dated January 9, 2014, executed by Russel E. Stachowski of GNF-A, requesting that information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) Part 2, Section 2.390: | | |
| * GNF-A report, NEDC-33845P, "Clinton EOC14 GE14i (ITA) Fuel Examination October 2013," Revision 0, January 2014. The letter and the nonproprietary version of this document have been made publicly available. | | 1 By letter to the U.S. Nuclear Regulatory Commission (NRC) dated March 27, 2014, Exelon Generation Company, LLC submitted results of a post-irradiation examination of a GE14i isotope test assembly performed by Global Nuclear Fuel- Americas, LLC (GNF-A). This submittal included an affidavit dated January 9, 2014, executed by Russel E. Stachowski of GNF-A, requesting that information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) Part 2, Section 2.390: |
| The affidavit stated that the information identified in the document listed above should be considered exempt from mandatory public disclosure for the following reasons: a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic advantage over other companies; | | * GNF-A report, NEDC-33845P, "Clinton EOC14 GE14i (ITA) Fuel Examination October 2013," Revision 0, January 2014. |
| : b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product. We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. | | The letter and the nonproprietary version of this document have been made publicly available. |
| Therefore, the information marked as proprietary will 1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML 14086A550. | | The affidavit stated that the information identified in the document listed above should be considered exempt from mandatory public disclosure for the following reasons: |
| M. Pacilio be withheld from public disclosure pursuant to 10 CFR 2.390 and Section 1 03(b), of the Atomic Energy Act of 1954, as amended. Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. | | : a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic advantage over other companies; |
| If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information. | | : b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product. |
| If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. | | We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the information marked as proprietary will 1 |
| In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure. | | Agencywide Documents Access and Management System (ADAMS) Accession No. ML14086A550. |
| | |
| | M. Pacilio be withheld from public disclosure pursuant to 10 CFR 2.390 and Section 103(b), of the Atomic Energy Act of 1954, as amended. |
| | Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information. |
| | If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure. |
| If you have any questions regarding this matter, I may be reached at 301-415-1380. | | If you have any questions regarding this matter, I may be reached at 301-415-1380. |
| Docket No. 50-461 cc: Mr. Jim Clark Senior Project Manager Sincerely, Blake Purnell, Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Global Nuclear Fuel -Americas, LLC Castle Hayne Road, Wilmington, NC 28402 Distribution via ListServ M. Pacilio be withheld from public disclosure pursuant to 10 CFR 2.390 and Section 1 03(b), of the Atomic Energy Act of 1954, as amended. Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents.
| | Sincerely, Blake Purnell, Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461 cc: Mr. Jim Clark Senior Project Manager Global Nuclear Fuel -Americas, LLC Castle Hayne Road, Wilmington, NC 28402 Distribution via ListServ |
| If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
| | |
| If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information.
| | ..*ML14094A578 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC LPL3-2/PM NAME BPurnell SRohrer TTate BPurnell DATE 4/7/14 4/7/14 4/8/14 4/9/14}} |
| In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
| |
| If you have any questions regarding this matter, I may be reached at 301-415-1380.
| |
| Docket No. 50-461 cc: Mr. Jim Clark Senior Project Manager Sincerely, IRA/ Blake Purnell, Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Global Nuclear Fuel -Americas, LLC Castle Hayne Road, Wilmington, NC 28402 Distribution via ListServ DISTRIBUTION: | |
| PUBLIC LPL3-2 R/F RidsAcrsAcnw_MaiiCTR Resource RidsNrrPMCiinton Resource ADAMS Accession No *ML 14094A578
| |
| .. OFFICE LPL3-2/PM LPL3-2/LA NAME BPurnell SRohrer DATE 4/7/14 4/7/14 RidsNrrLASRohrer Resource RidsNrrDssSrxb RidsNrrDorllpl3-2 Resource RidsRgn3MaiiCenter Resource LPL3-2/BC LPL3-2/PM TTate BPurnell 4/8/14 4/9/14 OFFICIAL RECORD COPY}} | |
|
---|
Category:Letter
MONTHYEARIR 05000461/20240032024-11-0505 November 2024 Integrated Inspection Report 05000461/2024003 ML24285A1452024-10-24024 October 2024 Ltr. to Gail Cheatham, Kickapoo Tribe of Indians of the Kickapoo Reservation in Ks Re CPS Sect 106 Consult ML24285A1462024-10-24024 October 2024 Ltr. to Gena Kakkak, Chairwoman, Menominee Indian Tribe of Wisconsin Re CPS Section 106 Consultation IR 05000461/20244032024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024403 ML24285A1482024-10-24024 October 2024 Ltr. to Joseph Rupnick, Chairman, Prairie Band Potawatomi Nation Re CPS Section 106 Consultation ML24285A1442024-10-24024 October 2024 Ltr. to Estavio Elizondo, Sr., Chairman, Kickapoo Traditional Tribe of Texas Re CPS Section 106 Consultation IR 05000461/20244022024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024402 ML24285A1472024-10-24024 October 2024 Ltr. to Geoffrey M. Standing Bear, Principal Chief, Osage Nation Re CPS Section 106 Consultation ML24285A1422024-10-24024 October 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Re CPS Section 106 Consultation ML24283A1642024-10-23023 October 2024 Summary of the 2024 Environmental Audit Related to the Review of the License Renewal Application Environmental Report (EPID Number L-2024-LNE-0000)(Docket Number:50-461) ML24285A1412024-10-21021 October 2024 Ltr. to Craig Harper, Chief, Peoria Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1432024-10-21021 October 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma Re CPS Section 106 Consultation RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24215A2932024-09-27027 September 2024 Scoping Summary Letter 05000461/LER-2023-002-01, Reactor Core Isolation Cooling Inoperable Prior to Mode Change2024-09-24024 September 2024 Reactor Core Isolation Cooling Inoperable Prior to Mode Change ML24211A2302024-09-11011 September 2024 – Request for Partial Site Release for Facility Operating License No. NPF-62 IR 05000461/20240112024-09-0909 September 2024 Commercial Grade Dedication Inspection Report 05000461/2024011 RS-24-087, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2024-09-0909 September 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station IR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing IR 05000461/20240022024-08-0909 August 2024 Integrated Inspection Report 05000461/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24212A2212024-08-0202 August 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-LNE-0000) (Docket Number: 50-461) ML24157A3242024-07-11011 July 2024 Issuance of Amendment No. 254 Revision of Reactor Water Cleanup Isolation Valve Timing ML24158A0772024-07-0303 July 2024 Notice of Consideration of Approval of Partial Site Release, Public Meeting, and Request for Comments (EPID L-2023-LLA-0088) - Letter ML24163A3252024-06-28028 June 2024 Aging Management Regulatory Audit Plan ML24163A3242024-06-28028 June 2024 LRA - Portal Letter ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24290A0942024-05-21021 May 2024 Letter from Rachael Mangum (Achp) to Stephen Koenick (NRC) License Renewal Application for the Clinton Power Station Unit 1 Dewitt County, Il, Achp Project Number: 020924 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes IR 05000461/20240122024-05-20020 May 2024 Biennial Problem Identification and Resolution Inspection Report Report 05000461/2024012 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-050, Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2024-05-0909 May 2024 Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20240012024-05-0707 May 2024 Integrated Inspection Report 05000461/2024001 ML24103A1032024-05-0101 May 2024 SHPO Consultation Letter for Clinton License Renewal ML24120A3442024-04-30030 April 2024 Ltr. to Gena Kakkak, Chairman, Menominee Indian Tribe of Wisconsin; Re., CPS Section 106 Consultation ML24120A3432024-04-30030 April 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma; Re., CPS Section 106 Consultation RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24103A0992024-04-30030 April 2024 Achp Scoping Letter for Clinton License Renewal ML24120A3462024-04-30030 April 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24120A3452024-04-30030 April 2024 Ltr. to Lester Randell, Chairman, Kickapoo Tribe of Indians of the Kickapoo Reservation in Kansas; Re., CPS Section 106 Consultation ML24103A1152024-04-30030 April 2024 Ltr. to Geoffrey Standing Bear, Principal Chief, the Osage Nation; Re., CPS Section 106 Consultation ML24107B0312024-04-29029 April 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24089A2222024-04-11011 April 2024 LRA - Acceptance and Opportunity for Hearing - Letter 2024-09-09
[Table view] Category:Proprietary Information Review
MONTHYEARML21279A0062021-10-13013 October 2021 Request for Withholding Information from Public Disclosure ML21201A3852021-07-23023 July 2021 Request for Withholding Information Regarding Proposed Alternative to Use ASME Code Case N-893 (EPIDs L-2020-LLR-0147 and -0148) ML21084A1352021-04-0505 April 2021 Request for Withholding Information from Public Disclosure ML21028A7122021-02-0303 February 2021 Request for Withholding Information Regarding Proposed Alternative to Use ASME Code Case N-893 (Epids L-2020-LLR-0147 and -0148) ML20317A1342020-11-12012 November 2020 Request for Withholding Information from Public Disclosure; Guarantees of Payment of Deferred Premiums ML19336A0192019-12-0303 December 2019 Request for Withholding Information Regarding Guarantees of Payment of Deferred Premiums ML17320A1452017-11-20020 November 2017 Request for Withholding Information Regarding Guarantees of Payment of Deferred Premiums ML16337A2762016-12-0909 December 2016 Calvert; Clinton; Dresden; LaSalle; Limerick; Nine Mile Point; Oyster Creek; Peach Bottom; Quad Cities; R.E. Ginna; Three Mile Island - Request for Withholding Information Regarding; Guarantees of Payment of Deferred Premiums ML16098A3222016-04-27027 April 2016 Request to Withhold Emergency Preparedness Documents from Public Disclosure (CAC Nos. MF7504-MF7525) ML14199A5772014-07-28028 July 2014 Request for Withholding Information from Public Disclosure ML14094A5782014-04-0909 April 2014 Request for Withholding Information from Public Disclosure ML13326A7732014-01-24024 January 2014 Request for Withholding Information from Public Disclosure ML13016A5002013-01-30030 January 2013 Request for Withholding Information from Public Disclosure for Braidwood Station, Units 1 & 2; Byron Station, Units 1 & 2; Clinton Power Station, Unit 1; Dresden Nuclear Power Station, Units 2 & 3; LaSalle County Station, Units 1 & 2 ML0934800502009-12-17017 December 2009 Request for Withholding Information from Public Disclosure ML0931706632009-11-23023 November 2009 Withholding Information from Public Disclosure, ME1643 ML0931706902009-11-23023 November 2009 Request for Withholding Information from Public Disclosure - Ltr. Dated 11/12/2009 ML0907103302009-04-30030 April 2009 Corp., Request for Withholding Information from Public Disclosure ML0822807952008-08-22022 August 2008 Amergen Energy Company, LLC - Request for Withholding Information from Public Disclosure for Clinton Power Station, Unit No. 1, Oyster Creek Nuclear Generating Station, and Three Mile Island Nuclear Station, Unit 1 ML0822002442008-08-11011 August 2008 Request for Withholding Information from Public Disclosure for Local Power Range Monitor Calibration Frequency Increase for Clinton Power Station, Unit 1 ML0534203322005-12-13013 December 2005 Withholding from Public Disclosure, BWRVIP-04A, MC6448 ML0530704152005-10-26026 October 2005 Withholding from Public Disclosure, Holtec International Report No. HI-2033124 and Report No. HI-2043215, MC4202 ML0307607802003-03-28028 March 2003 Request for Witholding Information from Public Disclosure ML0203704022002-03-11011 March 2002 Reply to December 21, 2001 Ltr. - Request for Withholding Information from Public Disclosure ML0205206032002-03-0505 March 2002 Request for Withholding Information from Public Disclosure ML0204304762002-03-0505 March 2002 Request for Withholding Information - by Letter Dated June 18, 2001, Requested Approval of Uprated Power Operations at Clinton ML0205200812002-02-28028 February 2002 Request for Withholding Information from Public Disclosure - by Letter Dated November 21, 2001 (RS-01-272) from K. R. Jury of Amergen (Exelon) 2021-07-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 9, 2014 Mr. Michael J. Pacilio Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
CLINTON POWER STATION, UNIT 1 -REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE
Dear Mr. Pacilio:
1 By letter to the U.S. Nuclear Regulatory Commission (NRC) dated March 27, 2014, Exelon Generation Company, LLC submitted results of a post-irradiation examination of a GE14i isotope test assembly performed by Global Nuclear Fuel- Americas, LLC (GNF-A). This submittal included an affidavit dated January 9, 2014, executed by Russel E. Stachowski of GNF-A, requesting that information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) Part 2, Section 2.390:
- GNF-A report, NEDC-33845P, "Clinton EOC14 GE14i (ITA) Fuel Examination October 2013," Revision 0, January 2014.
The letter and the nonproprietary version of this document have been made publicly available.
The affidavit stated that the information identified in the document listed above should be considered exempt from mandatory public disclosure for the following reasons:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic advantage over other companies;
- b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the information marked as proprietary will 1
Agencywide Documents Access and Management System (ADAMS) Accession No. ML14086A550.
M. Pacilio be withheld from public disclosure pursuant to 10 CFR 2.390 and Section 103(b), of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-1380.
Sincerely, Blake Purnell, Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461 cc: Mr. Jim Clark Senior Project Manager Global Nuclear Fuel -Americas, LLC Castle Hayne Road, Wilmington, NC 28402 Distribution via ListServ
..*ML14094A578 OFFICE LPL3-2/PM LPL3-2/LA LPL3-2/BC LPL3-2/PM NAME BPurnell SRohrer TTate BPurnell DATE 4/7/14 4/7/14 4/8/14 4/9/14