ML14155A049: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 05/24/2014
| issue date = 05/24/2014
| title = E-Mail Dated May 24, 2014, from William Barley, Humboldt Bay Power Plant, to Alan Bjornsen, NRC, Providing Answers for License Termination Plan Review
| title = E-Mail Dated May 24, 2014, from William Barley, Humboldt Bay Power Plant, to Alan Bjornsen, NRC, Providing Answers for License Termination Plan Review
| author name = Barley W H
| author name = Barley W
| author affiliation = Pacific Gas & Electric Co
| author affiliation = Pacific Gas & Electric Co
| addressee name = Bjornsen A B
| addressee name = Bjornsen A
| addressee affiliation = NRC/FSME/DWMEP
| addressee affiliation = NRC/FSME/DWMEP
| docket = 05000133
| docket = 05000133
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:Bjornsen, Alan From: Barley, William H <WHB6@pge.com>
{{#Wiki_filter:Bjornsen, Alan From:                               Barley, William H <WHB6@pge.com>
Sent: Saturday, May 24, 2014 10:54 AM To: Bjornsen, Alan Cc: Sharp, Loren; Sokolsky, David; Albers, John P; Smith, Mark G (HBPP); Strehlow, Michael;Salmon, James; Kristofzski, John G; Rod, Kerry; Barron, Tricia A.
Sent:                               Saturday, May 24, 2014 10:54 AM To:                                 Bjornsen, Alan Cc:                                 Sharp, Loren; Sokolsky, David; Albers, John P; Smith, Mark G (HBPP); Strehlow, Michael; Salmon, James; Kristofzski, John G; Rod, Kerry; Barron, Tricia A.


==Subject:==
==Subject:==
Questions Attachments:
Questions Attachments:                         NRC Questions answers for review.docx Alan, sorry it has taken this long to get these answers back to you. There was a diverse group of personnel providing input to the questions and the coordination took longer than expected. Please let me know if you have any further questions once you have reviewed the responses.
NRC Questions answers for review.docx Alan, sorry it has taken this long to get these answers back to you. There was a diverse group of personnel providing input to the questions and the coordination took longer than expected.
Thanks, Bill Bill Barley HBPP Site Closure Manager Office: 707-444-0856 Work Cell: 707-267-0071 Alternate Cell: 602-684-0993 Alt email: whbarlev@cox.net PG&E is committed to protecting our customers' privacy.
Please let me know if you have any further questions once you have reviewed the responses.
To learn more, please visit http://www.pge.com/about/company/privacy/customer/
Thanks, Bill Bill Barley HBPP Site Closure Manager Office: 707-444-0856 Work Cell: 707-267-0071 Alternate Cell: 602-684-0993 Alt email: whbarlev@cox.net PG&E is committed to protecting our customers' privacy.To learn more, please visit http://www.pge.com/about/company/privacy/customer/
: 1. HBPP is eligible for the National Register of Historic Places: a) What are SHPO's comments?; b) Did SHPO allow for it dismantlement?
: 1. HBPP is eligible for the National Register of Historic Places: a) What are SHPO's comments?;
In 2010, PG&E prepared a mitigation plan that fulfills the Condition of Certification CUL-1O for demolition of Units 1, 2, and 3 for the Humboldt Bay Generating Station California Energy Commission (CEC) license. This plan mitigates for the demolition of Units 1, 2, and 3. The plant site, composed of two gas-oil fired steam turbine units with one of the nation's first commercial nuclear powered generators, served the Humboldt load pocket, a region of electrical demand that is somewhat isolated from the remainder of the California grid. In 2003, PAR Environmental Services evaluated Unit 3 and recommended that it appeared to meet the criteria for listing in the National Register of Historic Places at a national level of significance. The State of California's Office of Historic Preservation concurred in this assessment. This evaluation did not include Units 1 and 2. Later it was determined that the three units should be considered as a complex, and that mitigation measures should be developed for the complex as a whole. CEC Condition CUL-1O required that a Mitigation Plan be prepared for the demolition work to assure that the adverse effects / negative impacts caused by the demolition would be mitigated. The mitigation plan ended up including Historic American Engineering records (HAER); an illustrated history book; interpretive panels; and donation of archives and artifacts to the Clark Museum in Eureka.
b) Did SHPO allow for it dismantlement?
: 2. What are PG&E's records for review of cultural sites before the construction of Unit 3?
In 2010, PG&E prepared a mitigation plan that fulfills the Condition of Certification CUL-1O for demolition of Units 1, 2, and 3 for the Humboldt Bay Generating Station California Energy Commission (CEC) license. This plan mitigates for the demolition of Units 1, 2, and 3. The plant site, composed of two gas-oil fired steam turbine units with one of the nation's first commercial nuclear powered generators, served the Humboldt load pocket, a region of electrical demand that is somewhat isolated from the remainder of the California grid. In 2003, PAR Environmental Services evaluated Unit 3 and recommended that it appeared to meet the criteria for listing in the National Register of Historic Places at a national level of significance.
* Although there were no records for cultural site review prior to construction of units 1, 2 or 3 due to their construction before requirements, significant cultural review and oversight for cultural artifacts were implemented for ISFSI and HBGS construction. Further, excavation work plans for decommissioning include cessation of work should cultural artifacts be encountered to allow for investigation and documentation.
The State of California's Office of Historic Preservation concurred in this assessment.
: 3. Were any radioactive gases, liquids, or solid wastes released during the operation of Unit 3?
This evaluation did not include Units 1 and 2. Later it was determined that the three units should be considered as a complex, and that mitigation measures should be developed for the complex as a whole. CEC Condition CUL-1O required that a Mitigation Plan be prepared for the demolition work to assure that the adverse effects / negative impacts caused by the demolition would be mitigated.
* There were routine effluent releases during both operation and since cessation of operation in accordance with NRC effluent regulations for both gaseous and liquid effluents. Solid radioactive waste was sent to permitted radioactive burial sites. The HBPP LTP Chapter 3 provides the effluent release data as well as the waste volumes and activity content by year. The historical site assessment as part of the license termination plan contains documentation for past leaks and spills on site as well as site radiological characterization data used for planning remediation and MARSSIM surveys.
The mitigation plan ended up including Historic American Engineering records (HAER); an illustrated history book; interpretive panels; and donation of archives and artifacts to the Clark Museum in Eureka.2. What are PG&E's records for review of cultural sites before the construction of Unit 3?* Although there were no records for cultural site review prior to construction of units 1, 2 or 3 due to their construction before requirements, significant cultural review and oversight for cultural artifacts were implemented for ISFSI and HBGS construction.
: 4. What has PG&E done to insure that direct radiation from Unit 3 is well below applicable limits?
Further, excavation work plans for decommissioning include cessation of work should cultural artifacts be encountered to allow for investigation and documentation.
* Refueling building shielding and restrictions to personnel in the area outside the building are considered for high radioactivity work. Dose rates on radioactive material stored in outside areas is minimized. To the extent possible, waste is shipped in an expeditious manner to maintain site doses ALARA. The restricted area fence lines are routinely surveyed and continuously monitored by environmental TLDs.
: 3. Were any radioactive gases, liquids, or solid wastes released during the operation of Unit 3?* There were routine effluent releases during both operation and since cessation of operation in accordance with NRC effluent regulations for both gaseous and liquid effluents.
This data is used to demonstrate that all members of the public in the controlled area receive less than 100 mrem in the calendar year. Additional TLDs are used to monitor for potential doses to the unrestricted area to demonstrate compliance with 40CFR190.
Solid radioactive waste was sent to permitted radioactive burial sites. The HBPP LTP Chapter 3 provides the effluent release data as well as the waste volumes and activity content by year. The historical site assessment as part of the license termination plan contains documentation for past leaks and spills on site as well as site radiological characterization data used for planning remediation and MARSSIM surveys.4. What has PG&E done to insure that direct radiation from Unit 3 is well below applicable limits?* Refueling building shielding and restrictions to personnel in the area outside the building are considered for high radioactivity work. Dose rates on radioactive material stored in outside areas is minimized.
1
To the extent possible, waste is shipped in an expeditious manner to maintain site doses ALARA. The restricted area fence lines are routinely surveyed and continuously monitored by environmental TLDs.This data is used to demonstrate that all members of the public in the controlled area receive less than 100 mrem in the calendar year. Additional TLDs are used to monitor for potential doses to the unrestricted area to demonstrate compliance with 40CFR190.1
: 5. What actions are being taken by PG&E to give the expectation that radiological impacts will remain within Regulatory limits?
: 5. What actions are being taken by PG&E to give the expectation that radiological impacts will remain within Regulatory limits?* Dose rates in outside areas are monitored as radioactive material is moved around site. Work on significantly contaminated equipment is performed with HEPA filtered ventilation spaces with particulate effluent monitoring.
* Dose rates in outside areas are monitored as radioactive material is moved around site. Work on significantly contaminated equipment is performed with HEPA filtered ventilation spaces with particulate effluent monitoring. Once radiological conditions are sufficiently reduced, structures are released for open air demolition. During the demolition process, dust and silica control measures are used that further reduce the potential for any radiological concerns. Temporary and continuous particulate environmental air monitors are used to verify adequacy of controls employed. In the evaluation contained within the LTP License Amendment Request, dated May 3, 2013, Section 6.0(3)(iii)
Once radiological conditions are sufficiently reduced, structures are released for open air demolition.
PG&E committed to maintain annual exposures to onsite and offsite personnel ALARA.
During the demolition process, dust and silica control measures are used that further reduce the potential for any radiological concerns.
: 6. Has PG&E identified a landfill site where the LLRW and demolition debris will be taken?
Temporary and continuous particulate environmental air monitors are used to verify adequacy of controls employed.
* Waste for the Unit 3 "footprint" will be sent to either the Energy Solutions Part 61 burial site in Utah or through the HBPP 10CFR20.2002 exemption to the U. S. Ecology burial site in Idaho. Some amount of B and C level wastes has been sent to the WCS burial site in Texas. Waste from outside the Unit 3 "footprint" may be radiologically cleared and sent for disposal in class 2 landfill sites within the state of California. Waste from outside of the Unit 3 footprint that contains licensed radionuclides would be designated to be sent to either the Utah or Idaho burial sites.
In the evaluation contained within the LTP License Amendment Request, dated May 3, 2013, Section 6.0(3)(iii)
: 7. Has PG&E implemented any enhanced security measures (in the case of terrorism), and emergency planning that could mitigate a potential terrorist attack?
PG&E committed to maintain annual exposures to onsite and offsite personnel ALARA.6. Has PG&E identified a landfill site where the LLRW and demolition debris will be taken?* Waste for the Unit 3 "footprint" will be sent to either the Energy Solutions Part 61 burial site in Utah or through the HBPP 10CFR20.2002 exemption to the U. S. Ecology burial site in Idaho. Some amount of B and C level wastes has been sent to the WCS burial site in Texas. Waste from outside the Unit 3"footprint" may be radiologically cleared and sent for disposal in class 2 landfill sites within the state of California.
* PG&E has implemented orders for protection of the spent fuel and greater than class C material stored in the ISFSI. Additionally for Unit 3, PG&E is in compliance with 10CFR37 requirements for protection of radioactive materials.
Waste from outside of the Unit 3 footprint that contains licensed radionuclides would be designated to be sent to either the Utah or Idaho burial sites.7. Has PG&E implemented any enhanced security measures (in the case of terrorism), and emergency planning that could mitigate a potential terrorist attack?* PG&E has implemented orders for protection of the spent fuel and greater than class C material stored in the ISFSI. Additionally for Unit 3, PG&E is in compliance with 10CFR37 requirements for protection of radioactive materials.
: 8. Are there any potential conflicts that could arise with the HBGS?
: 8. Are there any potential conflicts that could arise with the HBGS?* Work on site is coordinated with HBGS to control impacts to the generation equipment and electrical switchyard.
* Work on site is coordinated with HBGS to control impacts to the generation equipment and electrical switchyard. Potential impacts are factored into the HBPP work plans to minimize the impacts to HBGS.
Potential impacts are factored into the HBPP work plans to minimize the impacts to HBGS.HBPP Unit 3 License Condition C.4 requires a Cross Contamination Prevention and Monitoring Plan to maintain validity of the final status surveys performed beneath the HBGS.9. Does the CA DTSC require anything different than the NRC in overseeing site investigations?
HBPP Unit 3 License Condition C.4 requires a Cross Contamination Prevention and Monitoring Plan to maintain validity of the final status surveys performed beneath the HBGS.
* The CA DTSC has remained focused on the non-radiological remediation of the HBPP site. From the non-radiological contamination standpoint, the site remediation is to that of an industrial site since PG&E will continue to use the site for electric operations.
: 9. Does the CA DTSC require anything different than the NRC in overseeing site investigations?
CA DTSC has agreed to allow for NRC lead in the radiological remediation of the site as delineated in the submitted license termination plan.2
* The CA DTSC has remained focused on the non-radiological remediation of the HBPP site. From the non-radiological contamination standpoint, the site remediation is to that of an industrial site since PG&E will continue to use the site for electric operations. CA DTSC has agreed to allow for NRC lead in the radiological remediation of the site as delineated in the submitted license termination plan.
: 10. When was the Humboldt County grading permit received?0 We have received several permits from Humboldt County for the site. As work progresses onsite in each particular area, grading permits are obtained for all grading/excavation activities that will move more than 50 cubic yards of material (gross). Grading permits, demolition permits and building permits all fall under the jurisdiction of Humboldt County Building Department thus all of these permits are considered"building" permits. As demolition work continues, we expect more grading and demolition permits to be obtained.
2
Here is a table of the approved Humboldt County Building, Demolition and Grading permits from 2012 to now.Humboldt Bay Power Plant APN: 305-131-035 Humboldt County Building, Demolition and Grading Permits 2012 to Present 3-Bulding, [-Demolition.  
: 10. When was the Humboldt County grading permit received?
--Electrical, PH-Preassembled Housing, X-Grading and Excavation Permit ;; Issued Description Responsible 12-227-X-4 3/16/2012 Unit 3Circulation Pipe Removal PG&E 12-296-X-4 4/5/2012 Count Room Parking Lot Grading PG&E 12-600-X-4 6/26/2012 Demolish Existing -oundations and Regrade Site PG&c 12-812-B-4 8/23/2012 New vv'v1YS Bldg and Associated Grading PG&E 8/31/2012 60kV Switchyard Grading Permit ABB 12-905-3-4 9/17/2012 Install GIS Building (60kV Switchyard)
0 We have received several permits from Humboldt County for the site. As work progresses onsite in each particular area, grading permits are obtained for all grading/excavation activities that will move more than 50 cubic yards of material (gross). Grading permits, demolition permits and building permits all fall under the jurisdiction of Humboldt County Building Department thus all of these permits are considered "building" permits. As demolition work continues, we expect more grading and demolition permits to be obtained. Here is a table of the approved Humboldt County Building, Demolition and Grading permits from 2012 to now.
A3B 22-908-P.H-4 9/17/2012 Install 60kV MPAC Building ABB 12-907-5-4 9/17/2012 Construct Battery Building (60kV Switchyard)
Humboldt Bay Power Plant APN: 305-131-035 Humboldt County Building, Demolition and Grading Permits 2012 to Present 3-Bulding, [-Demolition. --Electrical, PH-Preassembled Housing, X-Grading and Excavation Permit ;;       Issued   Description                                                             Responsible 12-227-X-4     3/16/2012 Unit 3Circulation Pipe Removal                                           PG&E 12-296-X-4     4/5/2012 Count Room Parking Lot Grading                                           PG&E 12-600-X-4     6/26/2012 Demolish Existing -oundations and Regrade Site                           PG&c 12-812-B-4     8/23/2012 New vv'v1YS Bldg and Associated Grading                                 PG&E 12-S*S-X-4    8/31/2012 60kV Switchyard Grading Permit                                           ABB 12-905-3-4     9/17/2012 Install GIS Building (60kV Switchyard)                                   A3B 22-908-P.H-4   9/17/2012 Install 60kV MPAC Building                                               ABB 12-907-5-4     9/17/2012 Construct Battery Building (60kV Switchyard)                             ABS 12-813-X-4     8,/23/2012 60kV Switchyard Utility Removal                                         A3B 12-960-X-4     9/27/2012 GWTS Grading                                                             PG&E 13-111-0-4     7/29/2013 Turbine Building Demolition                                             Kiewit 13-607-H-4     6/14/2013 Install fire monitoring station GIS Building                             ABB 13-975-PH-4   9/10/2013 New Office Trailer(Count Room Parking Lot)                               PG&E 13-1196-B-4   10/30/2013 New Warehouse/office trailer                                             PG&E 11-398-0-4     4/11/201-a WP-01!41 Hot machine Shop Building Demolition and 3elow Grade Excavation CB&l 14-399-X-4     4/11/2014 WP-26Unit 2 0emolition                                                   CB&I 14-400-0-4     4/1L/2014 Oily Water Separator Demolition                                           CB&I
ABS 12-813-X-4 8,/23/2012 60kV Switchyard Utility Removal A3B 12-960-X-4 9/27/2012 GWTS Grading PG&E 13-111-0-4 7/29/2013 Turbine Building Demolition Kiewit 13-607-H-4 6/14/2013 Install fire monitoring station GIS Building ABB 13-975-PH-4 9/10/2013 New Office Trailer(Count Room Parking Lot) PG&E 13-1196-B-4 10/30/2013 New Warehouse/office trailer PG&E 11-398-0-4 4/11/201-a WP-01!41 Hot machine Shop Building Demolition and 3elow Grade Excavation CB&l 14-399-X-4 4/11/2014 WP-26Unit 2 0emolition CB&I 14-400-0-4 4/1L/2014 Oily Water Separator Demolition CB&I 11. When was the City of Eureka Pretreatment Permit issued for the discharge into Elk River WWTP?* HBPP has an existing Special Sewer Discharge Permit with Humboldt Community Services District (HCSD), issued 5/4/10, and effective for 5 years. It was confirmed that all HCSD wastewater (including any from HBPP) is delivered to the Elk River WWTP. There is an interagency agreement governing this arrangement between HCSD and Elk River. Additionally, PG&E had a permit issued by City of Eureka Public Works on April 17, 2012 that expired on April 17, 2014 to transport holding tank wastewater directly to the Elk River WWTP.3
: 11. When was the City of Eureka Pretreatment Permit issued for the discharge into Elk River WWTP?
: 12. The ACOE Permit Application for the Intake and Discharge Canal Remediation Project lists a number of permits in Section 5 that may be required.
* HBPP has an existing Special Sewer Discharge Permit with Humboldt Community Services District (HCSD), issued 5/4/10, and effective for 5 years. It was confirmed that all HCSD wastewater (including any from HBPP) is delivered to the Elk River WWTP. There is an interagency agreement governing this arrangement between HCSD and Elk River. Additionally, PG&E had a permit issued by City of Eureka Public Works on April 17, 2012 that expired on April 17, 2014 to transport holding tank wastewater directly to the Elk River WWTP.
Have they been applied for?* In Section 5 of the section 404 permit application, supplement indicates that the permit for the ACOE has been sent and is expecting the permit as soon as NMFS consultation is complete.
3
See question number 10 concerning the grading permit.Agency Permit Status US Army Corps of Engineers Clean Water Act Section 404 Applied for -Expecting Individual Permit permit as soon as NMFS consultation complete National Marine Fisheries Federal Endangered Species USFWS consultation Service and U.S. Fish and Act Section 7 Consultations complete -NMFS pending Wildlife Service Advisory Council on Historic National Historic Completed Preservation/State Historic Preservation Act Section 106 Preservation Office Consultation California Coastal Coastal Development Permit Permit received Commission for construction in the coastal zone North Coast Regional Water Clean Water Act Section 401 Permit received Quality Control Board Water Quality Certification Humboldt Bay Harbor, Harbor District Permit for Permit received Recreation, and Conservation construction on the shore of District Humboldt Bay Humboldt County Grading Permit Unknown (contractor scope)4}}
: 12. The ACOE Permit Application for the Intake and Discharge Canal Remediation Project lists a number of permits in Section 5 that may be required. Have they been applied for?
* In Section 5 of the section 404 permit application, supplement indicates that the permit for the ACOE has been sent and is expecting the permit as soon as NMFS consultation is complete. See question number 10 concerning the grading permit.
Agency                         Permit                       Status US Army Corps of Engineers     Clean Water Act Section 404   Applied for - Expecting Individual Permit             permit as soon as NMFS consultation complete National Marine Fisheries       Federal Endangered Species   USFWS consultation Service and U.S. Fish and       Act Section 7 Consultations   complete - NMFS pending Wildlife Service Advisory Council on Historic   National Historic             Completed Preservation/State Historic     Preservation Act Section 106 Preservation Office             Consultation California Coastal             Coastal Development Permit   Permit received Commission                     for construction in the coastal zone North Coast Regional Water     Clean Water Act Section 401   Permit received Quality Control Board           Water Quality Certification Humboldt Bay Harbor,           Harbor District Permit for   Permit received Recreation, and Conservation   construction on the shore of District                       Humboldt Bay Humboldt County                 Grading Permit               Unknown (contractor scope) 4}}

Latest revision as of 03:45, 4 November 2019

E-Mail Dated May 24, 2014, from William Barley, Humboldt Bay Power Plant, to Alan Bjornsen, NRC, Providing Answers for License Termination Plan Review
ML14155A049
Person / Time
Site: Humboldt Bay
Issue date: 05/24/2014
From: Barley W
Pacific Gas & Electric Co
To: Bjornsen A
NRC/FSME/DWMEP
References
Download: ML14155A049 (5)


Text

Bjornsen, Alan From: Barley, William H <WHB6@pge.com>

Sent: Saturday, May 24, 2014 10:54 AM To: Bjornsen, Alan Cc: Sharp, Loren; Sokolsky, David; Albers, John P; Smith, Mark G (HBPP); Strehlow, Michael; Salmon, James; Kristofzski, John G; Rod, Kerry; Barron, Tricia A.

Subject:

Questions Attachments: NRC Questions answers for review.docx Alan, sorry it has taken this long to get these answers back to you. There was a diverse group of personnel providing input to the questions and the coordination took longer than expected. Please let me know if you have any further questions once you have reviewed the responses.

Thanks, Bill Bill Barley HBPP Site Closure Manager Office: 707-444-0856 Work Cell: 707-267-0071 Alternate Cell: 602-684-0993 Alt email: whbarlev@cox.net PG&E is committed to protecting our customers' privacy.

To learn more, please visit http://www.pge.com/about/company/privacy/customer/

1. HBPP is eligible for the National Register of Historic Places: a) What are SHPO's comments?; b) Did SHPO allow for it dismantlement?

In 2010, PG&E prepared a mitigation plan that fulfills the Condition of Certification CUL-1O for demolition of Units 1, 2, and 3 for the Humboldt Bay Generating Station California Energy Commission (CEC) license. This plan mitigates for the demolition of Units 1, 2, and 3. The plant site, composed of two gas-oil fired steam turbine units with one of the nation's first commercial nuclear powered generators, served the Humboldt load pocket, a region of electrical demand that is somewhat isolated from the remainder of the California grid. In 2003, PAR Environmental Services evaluated Unit 3 and recommended that it appeared to meet the criteria for listing in the National Register of Historic Places at a national level of significance. The State of California's Office of Historic Preservation concurred in this assessment. This evaluation did not include Units 1 and 2. Later it was determined that the three units should be considered as a complex, and that mitigation measures should be developed for the complex as a whole. CEC Condition CUL-1O required that a Mitigation Plan be prepared for the demolition work to assure that the adverse effects / negative impacts caused by the demolition would be mitigated. The mitigation plan ended up including Historic American Engineering records (HAER); an illustrated history book; interpretive panels; and donation of archives and artifacts to the Clark Museum in Eureka.

2. What are PG&E's records for review of cultural sites before the construction of Unit 3?
  • Although there were no records for cultural site review prior to construction of units 1, 2 or 3 due to their construction before requirements, significant cultural review and oversight for cultural artifacts were implemented for ISFSI and HBGS construction. Further, excavation work plans for decommissioning include cessation of work should cultural artifacts be encountered to allow for investigation and documentation.
3. Were any radioactive gases, liquids, or solid wastes released during the operation of Unit 3?
  • There were routine effluent releases during both operation and since cessation of operation in accordance with NRC effluent regulations for both gaseous and liquid effluents. Solid radioactive waste was sent to permitted radioactive burial sites. The HBPP LTP Chapter 3 provides the effluent release data as well as the waste volumes and activity content by year. The historical site assessment as part of the license termination plan contains documentation for past leaks and spills on site as well as site radiological characterization data used for planning remediation and MARSSIM surveys.
4. What has PG&E done to insure that direct radiation from Unit 3 is well below applicable limits?
  • Refueling building shielding and restrictions to personnel in the area outside the building are considered for high radioactivity work. Dose rates on radioactive material stored in outside areas is minimized. To the extent possible, waste is shipped in an expeditious manner to maintain site doses ALARA. The restricted area fence lines are routinely surveyed and continuously monitored by environmental TLDs.

This data is used to demonstrate that all members of the public in the controlled area receive less than 100 mrem in the calendar year. Additional TLDs are used to monitor for potential doses to the unrestricted area to demonstrate compliance with 40CFR190.

1

5. What actions are being taken by PG&E to give the expectation that radiological impacts will remain within Regulatory limits?
  • Dose rates in outside areas are monitored as radioactive material is moved around site. Work on significantly contaminated equipment is performed with HEPA filtered ventilation spaces with particulate effluent monitoring. Once radiological conditions are sufficiently reduced, structures are released for open air demolition. During the demolition process, dust and silica control measures are used that further reduce the potential for any radiological concerns. Temporary and continuous particulate environmental air monitors are used to verify adequacy of controls employed. In the evaluation contained within the LTP License Amendment Request, dated May 3, 2013, Section 6.0(3)(iii)

PG&E committed to maintain annual exposures to onsite and offsite personnel ALARA.

6. Has PG&E identified a landfill site where the LLRW and demolition debris will be taken?
  • Waste for the Unit 3 "footprint" will be sent to either the Energy Solutions Part 61 burial site in Utah or through the HBPP 10CFR20.2002 exemption to the U. S. Ecology burial site in Idaho. Some amount of B and C level wastes has been sent to the WCS burial site in Texas. Waste from outside the Unit 3 "footprint" may be radiologically cleared and sent for disposal in class 2 landfill sites within the state of California. Waste from outside of the Unit 3 footprint that contains licensed radionuclides would be designated to be sent to either the Utah or Idaho burial sites.
7. Has PG&E implemented any enhanced security measures (in the case of terrorism), and emergency planning that could mitigate a potential terrorist attack?
  • PG&E has implemented orders for protection of the spent fuel and greater than class C material stored in the ISFSI. Additionally for Unit 3, PG&E is in compliance with 10CFR37 requirements for protection of radioactive materials.
8. Are there any potential conflicts that could arise with the HBGS?
  • Work on site is coordinated with HBGS to control impacts to the generation equipment and electrical switchyard. Potential impacts are factored into the HBPP work plans to minimize the impacts to HBGS.

HBPP Unit 3 License Condition C.4 requires a Cross Contamination Prevention and Monitoring Plan to maintain validity of the final status surveys performed beneath the HBGS.

9. Does the CA DTSC require anything different than the NRC in overseeing site investigations?
  • The CA DTSC has remained focused on the non-radiological remediation of the HBPP site. From the non-radiological contamination standpoint, the site remediation is to that of an industrial site since PG&E will continue to use the site for electric operations. CA DTSC has agreed to allow for NRC lead in the radiological remediation of the site as delineated in the submitted license termination plan.

2

10. When was the Humboldt County grading permit received?

0 We have received several permits from Humboldt County for the site. As work progresses onsite in each particular area, grading permits are obtained for all grading/excavation activities that will move more than 50 cubic yards of material (gross). Grading permits, demolition permits and building permits all fall under the jurisdiction of Humboldt County Building Department thus all of these permits are considered "building" permits. As demolition work continues, we expect more grading and demolition permits to be obtained. Here is a table of the approved Humboldt County Building, Demolition and Grading permits from 2012 to now.

Humboldt Bay Power Plant APN: 305-131-035 Humboldt County Building, Demolition and Grading Permits 2012 to Present 3-Bulding, [-Demolition. --Electrical, PH-Preassembled Housing, X-Grading and Excavation Permit ;; Issued Description Responsible 12-227-X-4 3/16/2012 Unit 3Circulation Pipe Removal PG&E 12-296-X-4 4/5/2012 Count Room Parking Lot Grading PG&E 12-600-X-4 6/26/2012 Demolish Existing -oundations and Regrade Site PG&c 12-812-B-4 8/23/2012 New vv'v1YS Bldg and Associated Grading PG&E 12-S*S-X-4 8/31/2012 60kV Switchyard Grading Permit ABB 12-905-3-4 9/17/2012 Install GIS Building (60kV Switchyard) A3B 22-908-P.H-4 9/17/2012 Install 60kV MPAC Building ABB 12-907-5-4 9/17/2012 Construct Battery Building (60kV Switchyard) ABS 12-813-X-4 8,/23/2012 60kV Switchyard Utility Removal A3B 12-960-X-4 9/27/2012 GWTS Grading PG&E 13-111-0-4 7/29/2013 Turbine Building Demolition Kiewit 13-607-H-4 6/14/2013 Install fire monitoring station GIS Building ABB 13-975-PH-4 9/10/2013 New Office Trailer(Count Room Parking Lot) PG&E 13-1196-B-4 10/30/2013 New Warehouse/office trailer PG&E 11-398-0-4 4/11/201-a WP-01!41 Hot machine Shop Building Demolition and 3elow Grade Excavation CB&l 14-399-X-4 4/11/2014 WP-26Unit 2 0emolition CB&I 14-400-0-4 4/1L/2014 Oily Water Separator Demolition CB&I

11. When was the City of Eureka Pretreatment Permit issued for the discharge into Elk River WWTP?
  • HBPP has an existing Special Sewer Discharge Permit with Humboldt Community Services District (HCSD), issued 5/4/10, and effective for 5 years. It was confirmed that all HCSD wastewater (including any from HBPP) is delivered to the Elk River WWTP. There is an interagency agreement governing this arrangement between HCSD and Elk River. Additionally, PG&E had a permit issued by City of Eureka Public Works on April 17, 2012 that expired on April 17, 2014 to transport holding tank wastewater directly to the Elk River WWTP.

3

12. The ACOE Permit Application for the Intake and Discharge Canal Remediation Project lists a number of permits in Section 5 that may be required. Have they been applied for?
  • In Section 5 of the section 404 permit application, supplement indicates that the permit for the ACOE has been sent and is expecting the permit as soon as NMFS consultation is complete. See question number 10 concerning the grading permit.

Agency Permit Status US Army Corps of Engineers Clean Water Act Section 404 Applied for - Expecting Individual Permit permit as soon as NMFS consultation complete National Marine Fisheries Federal Endangered Species USFWS consultation Service and U.S. Fish and Act Section 7 Consultations complete - NMFS pending Wildlife Service Advisory Council on Historic National Historic Completed Preservation/State Historic Preservation Act Section 106 Preservation Office Consultation California Coastal Coastal Development Permit Permit received Commission for construction in the coastal zone North Coast Regional Water Clean Water Act Section 401 Permit received Quality Control Board Water Quality Certification Humboldt Bay Harbor, Harbor District Permit for Permit received Recreation, and Conservation construction on the shore of District Humboldt Bay Humboldt County Grading Permit Unknown (contractor scope) 4