| From: | John Hickman Division of Decommissioning, Uranium Recovery and Waste Programs |
| To: | Barley W Pacific Gas & Electric Co |
| Hickman J | |
| References | |
| Download: ML19183A013 (2) | |
Text
From: Hickman, John Sent: Friday, June 21, 2019 9:13 AM To: Barley, William <WHB6@pge.com>
Cc: Achten, Sarah <Sarah.Achten@nrc.gov>
Subject:
RE: NRC Submittal HBL-19-011, FSS Report for the Relay Building and MEPPS Island Building Mr. Barley:
By letter dated May 22, 2019 (ML19143A046), Pacific Gas & Electric Co. submitted a Final Status Survey Report for the Relay Building and the MEPPS Island Building at Humboldt Bay Power Plan Unit 3.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this report. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed [amendment
/ exemption / request] in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
The NRC staff expects to complete this review in approximately 6 months, which is November 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
If you have any questions, please contact me.
John B. Hickman, Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards From: Hartwig, Adriana <ADH6@pge.com>
Sent: Wednesday, May 22, 2019 3:55 PM To: Hickman, John <John.Hickman@nrc.gov>; Morris, Scott <Scott.Morris@nrc.gov>
Cc: HBPP Humboldt Distribution <DCPPBASESHD@pge.com>; Lopez, Brandy
<BNSM@pge.com>
Subject:
[External_Sender] NRC Submittal HBL-19-011, FSS Report for the Relay Building and MEPPS Island Building The electronic file of the following letter that was recently sent to the Nuclear Regulatory Commission is attached to this e-mail and is being routed for your information.
NRC Submittal HBL-19-011, Final Status Survey Report for the Relay Building (Survey Units RLY01-01 and RLY01-02) and the MEPPS Island Building (Survey Units MEPPS01-01 and MEPPS01-02)
Signed by: James M. Welsch - Senior Vice President, Generation and Chief Nuclear Officer Adriana Hartwig PG&E l Diablo Canyon l Regulatory Services l 104/5/536B l Phone 805-545-3188