Line 3: Line 3:
| issue date = 08/28/2015
| issue date = 08/28/2015
| title = IR 05000461/2015407; on 08/18/2015 - 08/20/2015; Clinton Power Station; Routine Security Baseline Inspection. (Cover Letter Only)
| title = IR 05000461/2015407; on 08/18/2015 - 08/20/2015; Clinton Power Station; Routine Security Baseline Inspection. (Cover Letter Only)
| author name = Kemker B J
| author name = Kemker B
| author affiliation = NRC/RGN-III/DRS/PSB
| author affiliation = NRC/RGN-III/DRS/PSB
| addressee name = Hanson B C
| addressee name = Hanson B
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| docket = 05000461
| docket = 05000461
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION ust 28, 2015
[[Issue date::August 28, 2015]]


Mr. Bryan Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
==SUBJECT:==
CLINTON POWER STATION NRC SECURITY BASELINE INSPECTION REPORT 05000461/2015407


SUBJECT: CLINTON POWER STATION NRC SECURITY BASELINE INSPECTION REPORT 05000461/2015407
==Dear Mr. Hanson:==
On August 20, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection, at your Clinton Power Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process.
 
The enclosed inspection report documents the inspection results, which were discussed on August 20, 2015, with Mr. T. Stoner and other members of your staff.
 
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
 
The NRC inspectors did not identify any findings or violations.


==Dear Mr. Hanson:==
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
On August 20, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection, at your Clinton Power Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on August 20, 2015, with Mr. T. Stoner and other members of your staff. The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. The NRC inspectors did not identify any findings or violations. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. provide an acceptable response, please mark your entire response "Security-Related Information-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
 
However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. provide an acceptable response, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1).


Sincerely,/RA/
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Brian J. Kemker, Acting Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 Nonpublic


===Enclosure:===
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
IR 05000461/2015407


===w/Attachment:===
Sincerely,
Supplemental Information cc w/encl: N. Simonian, NSIR/DSO/DDSO/ST E. Wharton, NSIR T. Dimitriadis, RI B. Desai, RII C. Pederson, RIII D. Roberts, RIII M. Haire, RIV B. Brooks, Clinton Station Security Manager J. Klinger, State Liaison Officer Illinois Emergency Management Agency cc w/o encl: Distribution via LISTSERV
/RA/
Brian J. Kemker, Acting Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 Nonpublic Enclosure: IR 05000461/2015407 w/Attachment: Supplemental Information cc w/encl: N. Simonian, NSIR/DSO/DDSO/ST E. Wharton, NSIR T. Dimitriadis, RI B. Desai, RII C. Pederson, RIII D. Roberts, RIII M. Haire, RIV B. Brooks, Clinton Station Security Manager J. Klinger, State Liaison Officer Illinois Emergency Management Agency cc w/o encl: Distribution via LISTSERV
}}
}}

Latest revision as of 07:12, 31 October 2019

IR 05000461/2015407; on 08/18/2015 - 08/20/2015; Clinton Power Station; Routine Security Baseline Inspection. (Cover Letter Only)
ML15243A047
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/28/2015
From: Brian Kemker
Plant Support Branch II
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2015407
Download: ML15243A047 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ust 28, 2015

SUBJECT:

CLINTON POWER STATION NRC SECURITY BASELINE INSPECTION REPORT 05000461/2015407

Dear Mr. Hanson:

On August 20, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection, at your Clinton Power Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process.

The enclosed inspection report documents the inspection results, which were discussed on August 20, 2015, with Mr. T. Stoner and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

The NRC inspectors did not identify any findings or violations.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. provide an acceptable response, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1).

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Brian J. Kemker, Acting Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 Nonpublic Enclosure: IR 05000461/2015407 w/Attachment: Supplemental Information cc w/encl: N. Simonian, NSIR/DSO/DDSO/ST E. Wharton, NSIR T. Dimitriadis, RI B. Desai, RII C. Pederson, RIII D. Roberts, RIII M. Haire, RIV B. Brooks, Clinton Station Security Manager J. Klinger, State Liaison Officer Illinois Emergency Management Agency cc w/o encl: Distribution via LISTSERV