| On January 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Comanche Peak Nuclear Power Plant, Independent Spent Fuel Storage Installation. The NRC inspector disc ussed the results of this ins pection with Mr. J. Dreyfuss, Plant Manager, and other members of your staff. The inspector documented the results of this inspection in the enclosed inspection report. | | On January 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Comanche Peak Nuclear Power Plant, Independent Spent Fuel Storage Installation. The NRC inspector discussed the results of this inspection with Mr. J. Dreyfuss, Plant Manager, and other members of your staff. The inspector documented the results of this inspection in the enclosed inspection report. |
|
| |
|
| The NRC inspectors did not identify any finding or violation of more than minor significance. | | The NRC inspectors did not identify any finding or violation of more than minor significance. |
|
| |
|
| In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | | In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of ADAMS. |
|
| |
|
| However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response "Security-Related Information - Withhold from Public Disclosure Under 10 CFR 2.390" (d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii). | | ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| | |
| | However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information - Withhold from Public Disclosure Under 10 CFR 2.390 (d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii). |
|
| |
|
| Sincerely, | | Sincerely, |
| /RA/ | | /RA/ |
| Jeremy R. Groom, Chief Plant Support Branch 1 Division Reactor Safety | | Jeremy R. Groom, Chief Plant Support Branch 1 Division Reactor Safety Docket Nos. 50-445, 50-446, and 72-074 License Nos. NPF-87 and NPF-89 Nonpublic Enclosures: |
| | | 1. NRC Inspection Report 05000445/2018402, 05000446/2018402, and 07200074/2018402 2. Supplemental Information cc w/o encls: Electronic Distribution ML18065A425 Entire Report: ADAMS: Non-Publicly Available Non-Sensitive Keyword: |
| Docket Nos. 50-445, 50-446, and 72-074 License Nos. NPF-87 and NPF-89 | | SUNSI Review By: Yes No Publicly Available Sensitive _______MD 3.4 A.3 ADAMS ACCESSION NUMBER: ML18065A430 Cover Letter Only: ADAMS: Non-Publicly Available Non-Sensitive Keyword: |
| | | SUNSI Review By: Yes No Publicly Available Sensitive NRC-002 OFFICE DRS/PSB1 DRS/PSB1 DRP/RBBA DRS/PSB1 DNMS NAME CJewett JGroom MHaire JGroom RKellar SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ |
| Nonpublic Enclosures: 1. NRC Inspection Report 05000445/2018402, 05000446/2018402, and 07200074/2018402 2. Supplemental Information | | DATE 2/21/18 2/22/18 2/28/18 3/6/18 3/6/18 |
| | |
| cc w/o encls: Electronic Distribution | |
| | |
| ML18065A425 Entire Report: ADAMS: Non-Publicly Available Non-Sensitive Keyword: SUNSI Review By: Yes No Publicly Available Sensitive _______MD 3.4 A.3 ADAMS ACCESSION NUMBER: ML18065A430 Cover Letter Only: ADAMS: Non-Publicly Available Non-Sensitive Keyword: SUNSI Review By: Yes No Publicly Available Sensitive NRC-002 OFFICE DRS/PSB1 DRS/PSB1 DRP/RBBA DRS/PSB1 DNMS NAME CJewett JGroom MHaire JGroom RKellar SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ DATE 2/21/18 2/22/18 2/28/18 3/6/18 3/6/18 | |
| }} | | }} |
|
---|
Category:Letter
MONTHYEARIR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 CP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV 2024-02-02
[Table view] |
Text
rch 6, 2018
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2, NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY INSPECTION REPORT 05000445/2018402, 05000446/2018402, AND 07200074/2018402
Dear Mr. Peters:
On January 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Comanche Peak Nuclear Power Plant, Independent Spent Fuel Storage Installation. The NRC inspector discussed the results of this inspection with Mr. J. Dreyfuss, Plant Manager, and other members of your staff. The inspector documented the results of this inspection in the enclosed inspection report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of ADAMS.
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information - Withhold from Public Disclosure Under 10 CFR 2.390 (d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Jeremy R. Groom, Chief Plant Support Branch 1 Division Reactor Safety Docket Nos. 50-445, 50-446, and 72-074 License Nos. NPF-87 and NPF-89 Nonpublic Enclosures:
1. NRC Inspection Report 05000445/2018402, 05000446/2018402, and 07200074/2018402 2. Supplemental Information cc w/o encls: Electronic Distribution ML18065A425 Entire Report: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By: Yes No Publicly Available Sensitive _______MD 3.4 A.3 ADAMS ACCESSION NUMBER: ML18065A430 Cover Letter Only: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By: Yes No Publicly Available Sensitive NRC-002 OFFICE DRS/PSB1 DRS/PSB1 DRP/RBBA DRS/PSB1 DNMS NAME CJewett JGroom MHaire JGroom RKellar SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/
DATE 2/21/18 2/22/18 2/28/18 3/6/18 3/6/18