ML18152B785: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:.October 1 2, 2018   Mr. Michael Yox Regulatory Affairs Director Southern Nuclear Operating Company 7835 River Road, Bldg. 140, Vogtle 3&4 Waynesboro, GA 30830
{{#Wiki_filter:.October 12, 2018 Mr. Michael Yox Regulatory Affairs Director Southern Nuclear Operating Company 7835 River Road, Bldg. 140, Vogtle 3&4 Waynesboro, GA 30830


==SUBJECT:==
==SUBJECT:==
Line 24: Line 24:
==Dear Mr. Yox:==
==Dear Mr. Yox:==


This letter is to inform Southern Nuclear Operating Company (SNC) of U.S. Nuclear Regulatory Commission (NRC) vendor inspection findings that are material to the acceptance criteria in the inspections, tests, analyses, and acceptance criteria (ITAAC) for Vogtle Units 3 and 4 (thereafter abbreviated as "material to ITAAC").
This letter is to inform Southern Nuclear Operating Company (SNC) of U.S. Nuclear Regulatory Commission (NRC) vendor inspection findings that are material to the acceptance criteria in the inspections, tests, analyses, and acceptance criteria (ITAAC) for Vogtle Units 3 and 4 (thereafter abbreviated as material to ITAAC). The NRC performed an audit to account for potential ITAAC issues. Attached are the results of the audit and a summary of all vendor inspection findings material to ITAAC.
The NRC performed an audit to account for potential ITAAC issues. Attached are the result s of the audit and a summary of all vendor inspection findings material to ITAAC.
As a result of the audit, the NRC identified additional eighteen vendor inspection findings that are material to ITAAC (see Enclosure 2). The NRCs Enforcement Manual Agencywide Document Access and Management System (ADAMS) Accession No. ML18018B134 provides guidance on closing findings that are material to the acceptance criteria of an ITAAC. The staff conducted reviews of these findings to ensure that adequate corrective actions have been developed and implemented such that the deficiency will not prevent the ITAAC from being successfully completed. Four findings remain open pending further NRC inspection (see ). Although the NRC is planning to review the resolution of these items, you do not need to delay your ITAAC closure activities due to NRC inspection schedules.
As a result of the audit, the NRC identified additional eighteen vendor inspection findings that are material to ITAAC (see Enclosure 2). The NRC's Enforcement Manual Agencywide Document Access and Management System (ADAMS) Accession No. ML18018B134 provides guidance on closing findings that are material to the acceptance criteria of an ITAAC. The staff conducted reviews of these findings to ensure that adequate corrective actions have been developed and implemented such that the deficiency will not prevent the ITAAC from being successfully completed
The NRC expects that SNC will discuss the additional findings in ITAAC closure notifications (ICNs), with the following exception: SNC has already submitted ICNs for Vogtle Units 3 and 4 for an ITAAC associated with one of the ITAAC-related findings identified during the audit (ADAMS Accession Nos. ML17143A239 and ML17143A244). These ICNs do not include a reference to the finding that was identified during the audit. However, the NRC staff analyzed this finding and determined that SNC does not need to update the ICNs for that finding because corrective actions for the finding have been implemented and the NRC has closed the finding.
. F our findings remain open pending further NRC inspection (see Enclosure 1).
This finding is designated NON 99901404/2011-201-03 and was, prior to being closed, material to Vogtle Units 3 and 4 ITAAC 2.5.02.14.
Although the NRC is planning to review the resolution of these items, you do not need to delay your ITAAC closure activities due to NRC inspection schedules.
The NRCs Vendor Inspection Program verifies effective licensee oversight of the supply chain through inspections of a sample of vendors. Licensees are responsible for vendor oversight and vendor performance. It is the agencys expectation that licensees consider NRC vendor inspection findings as potential weaknesses in their procurement programs. Consistent with the
The NRC expects that SNC will discuss the additional findings in ITAAC closure notifications (ICNs), with the following exception: SNC has already submitted ICN s for Vogtle Units 3 and 4 for an ITAAC associated with one of the ITAAC
-related findings identified during the audit (ADAMS Accession Nos. ML17143A239 and ML17143A244
). These ICNs do not include a reference to the finding that was identified during the audit. However, the NRC staff analyzed this finding and determined that SNC does not need to update the ICN s for that finding because corrective actions for the finding have been implemented and the NRC has closed the finding. This finding is designated NON 99901404/2011
-201-03 and was, prior to being closed, material to Vogtle Units 3 and 4 ITAAC 2.5.02.14. The NRC's Vendor Inspection Program verifies effective licensee oversight of the supply chain through inspections of a sample of vendors. Licensees are responsible for vendor oversight and vendor performance. It is the agency's expectation that licensees consider NRC vendor inspection findings as potential weaknesses in their procurement programs.
Consistent with the M.Yox guidance in the NRC
-endorsed Nuclear Energy Institution (NEI) 08
-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, licensees should adequately discuss associated ITAAC findings (including those identified through vendor inspections) in their ITAAC notifications under 10 CFR 52.99(c)(1), (c)(2), and (c)(3)
. Enclosure 1 is a summary of all findings that, as of the issuance date of this letter, are material to the acceptance criteria of ITAAC. Some vendor findings listed in Enclosure 1 were not identified as having errors, but are included in Enclosure 1 so that SNC has a complete list of vendor findings affecting ITAAC. Enclosure 2 lists the vendor inspection findings that were not previously identified as findings material to the acceptance criteria of ITAAC. Please contact Philip O'Bryan at Phil.OBryan@nrc.gov, or (910) 617
-2469, if you have any questions or need assistance regarding these matters.
Sincerely,  /RA/  William B. Jones , Actin g Director Division of Construction Inspection and Operational Programs Office of New Reactors Docket Nos.:
05200025 05200026  Enclosure s: 1. Vendor Findings Material to the Acceptance Criteria of ITAAC
: 2. Vendor Inspection Finding s Not Previously Identified as Material to the Acceptance Criteria of ITAAC


ML18152B785
M.Yox                                            guidance in the NRC-endorsed Nuclear Energy Institution (NEI) 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, licensees should adequately discuss associated ITAAC findings (including those identified through vendor inspections) in their ITAAC notifications under 10 CFR 52.99(c)(1), (c)(2), and (c)(3). is a summary of all findings that, as of the issuance date of this letter, are material to the acceptance criteria of ITAAC. Some vendor findings listed in Enclosure 1 were not identified as having errors, but are included in Enclosure 1 so that SNC has a complete list of vendor findings affecting ITAAC. Enclosure 2 lists the vendor inspection findings that were not previously identified as findings material to the acceptance criteria of ITAAC. Please contact Philip OBryan at Phil.OBryan@nrc.gov, or (910) 617-2469, if you have any questions or need assistance regarding these matters.
  *via e-mail  NRO-002 OFC NRO/DCIP NRO/DCIP NRO/DCIP NAME PKrohn POBryan KKavanagh DATE 9/26/18* 9/26/18* 9/27/18* OFC NRO/DCIP NRO/DCIP RII/DCO NAME ARivera-Varona (BGreen for)
Sincerely,
OAyegbusi SWalke r (VHall for) DATE 9/28/18* 9/27/18* 10/5/18* OFC OGC NRO/DC I P  NAME M ASpencer W Jones  DATE 9/27/18* 10/12/18 Enclosure 1 Enclosure 1: Vendor Findings Material to the Acceptance Criteria of ITAAC Vendor / Docket Inspection Report  (IR) Number and  ADAMS Accession Number Finding Number(s) Affected ITAAC  Issues Identified in NRC Audit of Vendor Inspection Findings Status SPX Copes-Vulcan 99900080 2012-201 ML12158A154 01 2.1.02.12a.iv 2.1.02.12a.v 2.2.03.12a.i 2.2.03.12a.ii IR 2012-201 does not clearly link the finding to the applicable ITAAC. The ITAAC are correctly identified in the 2015 NRC summary of vendor ITAAC findings (ML15219A276).
                                                /RA/
Closed in IR 2015-201 (ML15210A806
William B. Jones, Acting Director Division of Construction Inspection and Operational Programs Office of New Reactors Docket Nos.: 05200025 05200026
) 2013-201 ML13302B397 01 2.1.02.12a.iv 2.2.03.12a.i 2.1.02.12a.iv is incorrectly listed as 2.2.02.a.iv in the body of the inspection report. The ITAAC are listed correctly in the ITAAC table in the back of the report. The ITAAC are also listed correctly in the 2014 NRC summary of vendor ITAAC findings (ML14111A071).
Closed in IR 2015-202 (ML16027A153) 02 2.1.02.12a.v 2.2.03.12a.ii 2.1.02.12a.v is incorrectly listed as 2.2.02.12a.v in the 2014 NRC summary of vendor ITAAC findings (ML14111A071). The finding was closed in IR 2015-202 but was not listed as closed in the 2015 NRC summary of vendor ITAAC findings.
Closed in IR 2015-202 (ML16027A153)


2 Vendor / Docket Inspection Report  (IR) Number and  ADAMS Accession Number Finding Number(s) Affected ITAAC  Issues Identified in NRC Audit of Vendor Inspection Findings Status Westinghouse , Cranberry 99900404  2011-201 ML112440588 02 2.2.03.02a 2.2.03.02b IR 2011-201 does not clearly link this finding to the applicable ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) incorrectly lists the finding number as "99900404/2012
==Enclosures:==
-202-02."  The 2016 NRC summary of ITAAC findings (ML16280A303) correctly lists the finding number and the applicable ITAAC.
: 1. Vendor Findings Material to the Acceptance Criteria of ITAAC
Closed in NRC memo dated December 18, 2017 (ML17346A937) 05 2.2.03.08c.i.03 IR 2011-201 does not clearly link this finding to the applicable ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) correctly lists ITAAC 2.2.03.08c.i.03 as applicable. The 2016 NRC summary of vendor ITAAC findings (ML16280A303) incorrectly lists ITAAC 2.2.03.08c.i.04 as applicable.
: 2. Vendor Inspection Findings Not Previously Identified as Material to the Acceptance Criteria of ITAAC
Open 2012-201 ML12128A072 01 2.1.02.07a.i 2.2.03.07a.i IR 2012-201 does not clearly identify the applicable ITAAC. The finding is closed in the 2013 NRC summary of vendor ITAAC findings (ML13156A136) but lists the incorrect ITAAC. IR 2016
-204 also includes a closure discussion of this finding.
Closed in IR 2016-204 (ML16307A159) 02 and 03 2.1.02.07a.i 2.2.03.07a.i IR 2012-201 does not clearly identify the applicable ITAAC. IR 2012-202 closes the findings but lists the incorrect ITAAC.
Closed in IR 2012-202 (ML12313A461) 2014-201 ML14058A995 01 and 02 2.5.02.14 None Closed in IR 2016-201 (ML15363A360
) 2015-204 ML15113B277 01 2.5.02.07a 2.5.02.07e None Closed in IR 2016-209 (ML17123A085
) 02 and 03 2.5.02.03 None Closed in IR 2016-202 (ML16237A320
)
3 Vendor / Docket Inspection Report  (IR) Number and  ADAMS Accession Number Finding Number(s) Affected ITAAC  Issues Identified in NRC Audit of Vendor Inspection Findings Status Valcor 99900728 2017-201 ML17311A267 01 2.1.02.05a.i None Open Wyle Labs 99900905 2012-201 ML12242A459 01 and 04 2.1.02.12a.i 2.2.01.11a.i 2.2.03.12a.i 2.3.02.11a.i 2.3.06.12a.i IR 2012-201 lists incorrect ITAAC numbers. The 20 13 NRC summary of vendor ITAAC findings (ML13156A136) lists 4 of the ITAAC numbers correctly but does not list ITAAC 2.2.03.12a.i as being affected. Closed in IR 2013-201 (ML14016A447
) Nationa l Technical Systems, Huntsville 99900905 2015-201 ML15078A379 01 2.1.02.07a.i 2.2.03.07a.i IR 2015-201 does not clearly state that finding 01 is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
Closed in NRC memorandum dated April 27, 2018 (ML18102B171) 2015-2 02 ML15152A080 01 2.2.03.12a.i IR 2015-202 does not clearly state that finding 01 is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
Westinghouse,  New Stanton 99901 0 43 2012-201 ML12131A263 03, 04, and 05 2.5.01.03d IR 2012-201 does not clearly state that the findings are material to the ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) correctly lists the applicable ITAAC.
Closed in IR 2013-201 (ML13318A689
)
4 Vendor / Docket Inspection Report  (IR) Number and  ADAMS Accession Number Finding Number(s) Affected ITAAC  Issues Identified in NRC Audit of Vendor Inspection Findings Status Enertech 99901377 201 2-201 ML12306A385 02  None IR 2012-201 does not identify this finding as material to ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) incorrectly lists this finding as material to ITAAC 2.2.03.05a.ii and 2.2.03.02a. In an NRC memorandum dated January 5, 2017 (ML16357A724), this finding was listed as material to an additional ITAAC (2.2.03.03a). This finding is not material to ITAAC.
Closed in NRC memorandum dated January 5, 2017  (ML16357A724) 03 None IR 2012-201 does not identify this finding as material to ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) incorrectly lists this finding as material to ITAAC 2.2.03.04a. This finding is not material to ITAAC.
Closed in NRC memorandum dated January 5, 2017  (ML16357A724)
CS Innovations 99901404 2011-201 ML111890005 03 and 04 2.5.02.14 IR 2011-201 does not clearly state that the findings are material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
Closed in IR 9990404/2014
-203 (ML14262A351)
Obayashi Corporation 99901409 2011-201 ML11286A106 03 3.3.00.02a.i.a 3.3.00.02a.i.b 3.3.00.02a.i.c 3.3.00.02a.i.d IR 2011-201 does not clearly state that the finding is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
Closed in NRC memorandum dated July 6, 2018 (ML18186A573)
Clark Dynamics 99901412 2012-201 ML12108A097 02 2.2.01.05.ii 2.2.02.05a.ii 2.2.05.05a.ii 2.3.02.05.ii 2.3.07.05.ii 2.7.01.05.ii IR 2012-201 does not clearly link the finding to the applicable ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) correctly identifies the applicable ITAAC.
Closed in NRC memorandum dated January 5, 2017 (ML16357A725)


5 Vendor / Docket Inspection Report  (IR) Number and  ADAMS Accession Number Finding Number(s) Affected ITAAC  Issues Identified in NRC Audit of Vendor Inspection Findings Status Kinectrics 99901415 2012-201 ML12179A413 01 and 02 2.2.01.05.ii 2.2.01.06a.i IR 2012-201 does not clearly state that the findings are material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
M.Yox                                   
Closed in IR 2015-201 (ML15148A419)
Cives Steel Company 99901419 2012-201 ML13042A397 03 3.3.00.02a.i.a 3.3.00.02a.i.b 3.3.00.02a.i.c 3.3.00.02a.i.d IR 2012-201 does not clearly state that the finding is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
Closed in NRC memorandum dated May 11, 2018 (ML18131A260)
CB & I Lake Charles 99901425 2014-201 ML14072A315 01  3.3.00.02a.i.a 3.3.00.02a.i.d IR 2014-201 does not clearly state that the finding is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
Closed in NRC memorandum dated April 12, 2018 (ML18101A168)
Pentair 99901431 2013-201 ML13212A265 01 2.1.02.02a 2.1.02.05a.ii 2.2.03.02a 2.2.03.05a.ii IR 2013-201 and the 2014 NRC summary of vendor ITAAC findings (ML14111A071) list the four applicable ITAAC, but also incorrectly include ITAAC 2.1.02.08a.ii. This finding is not material to ITAAC 2.1.02.08a.ii.
Closed in IR 2014-201 (ML14073A652)


6 Vendor / Docket Report Number and  ADAMS Accession Number Finding Number(s) Affected ITAAC  Issues Identified in NRC Audit of Vendor Inspection Findings Status SMCI 99901439 2014-201 ML14121A433 01 3.3.00.02a.i.a IR 2014-201 does not clearly state that the finding is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
==SUBJECT:==
Closed in IR 2015-201 (ML15175A446) 2015-201 ML15175A446 01 and 02 3.3.00.02a.i.a IR 2015-201 does not clearly state that the findings are material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
 
Closed in NRC memorandum dated April 11, 2018 (ML18100A857)
==SUMMARY==
Curt is Wright Qualtech 99901441 2014-201 ML14231B268 03 2.1.02.07a.i 2.2.03.07a.i None Open Oregon Iron Works 99901448 99901449 2014-201 ML14308A463 02 3.3.00.02a.i.d IR 2014-201 does not clearly state that the finding is material to the ITAAC, nor does any subsequent NRC correspondence to SNC.
OF NUCLEAR REGULATORY COMMISSION VENDOR INSPECTIONS AFFECTING INSPECTIONS, TESTS, ANALYSES, AND ACCEPTANCE CRITERIA Dated: October 12, 2018 DISTRIBUTION:
Closed in Vigor IR 2017-201 (ML17226A340)
Public CPatel JJimenez ASakadales NCoovert JBurke VHall NRO_DCIP_QVIB-1 Distribution NRO_DCIP_QVIB-2 Distribution DCIP Branch Chiefs AP1000 CONTACTS ADAMS  Accession No.: ML18152B785            *via e-mail          NRO-002 OFC    NRO/DCIP                    NRO/DCIP            NRO/DCIP NAME    PKrohn                      POBryan              KKavanagh DATE    9/26/18*                    9/26/18*            9/27/18*
WECTEC 99901467 2016-201 ML17013A658 01 2.6.03.08 None Open Enclosure 2 Enclosure 2: Vendor Inspection Findings Not Previously Identified as Material to the Acceptance Criteria of ITAAC
OFC    NRO/DCIP                    NRO/DCIP            RII/DCO NAME    ARivera-Varona (BGreen for)  OAyegbusi            SWalker (VHall for)
DATE    9/28/18*                    9/27/18*            10/5/18*
OFC    OGC                          NRO/DCIP NAME    MASpencer                    WJones DATE    9/27/18*                    10/12/18 OFFICIAL RECORD COPY
 
Enclosure 1: Vendor Findings Material to the Acceptance Criteria of ITAAC Vendor /   Inspection  Finding      Affected        Issues Identified in NRC Audit of Vendor                  Status Docket     Report (IR)  Number(s)    ITAAC          Inspection Findings Number and ADAMS Accession Number SPX Copes- 2012-201    01          2.1.02.12a.iv  IR 2012-201 does not clearly link the finding to the      Closed in Vulcan    ML12158A154              2.1.02.12a.v    applicable ITAAC. The ITAAC are correctly                IR 2015-201 99900080                            2.2.03.12a.i    identified in the 2015 NRC summary of vendor              (ML15210A806) 2.2.03.12a.ii  ITAAC findings (ML15219A276).
2013-201    01          2.1.02.12a.iv  2.1.02.12a.iv is incorrectly listed as 2.2.02.a.iv in the Closed in ML13302B397              2.2.03.12a.i    body of the inspection report. The ITAAC are listed      IR 2015-202 correctly in the ITAAC table in the back of the          (ML16027A153) report. The ITAAC are also listed correctly in the 2014 NRC summary of vendor ITAAC findings (ML14111A071).
02          2.1.02.12a.v    2.1.02.12a.v is incorrectly listed as 2.2.02.12a.v in    Closed in 2.2.03.12a.ii  the 2014 NRC summary of vendor ITAAC findings            IR 2015-202 (ML14111A071). The finding was closed in IR              (ML16027A153) 2015-202 but was not listed as closed in the 2015 NRC summary of vendor ITAAC findings.
Enclosure 1
 
Vendor /      Inspection Finding  Affected        Issues Identified in NRC Audit of Vendor              Status Docket        Report (IR) Number(s) ITAAC          Inspection Findings Number and ADAMS Accession Number Westinghouse, 2011-201    02        2.2.03.02a      IR 2011-201 does not clearly link this finding to the  Closed in NRC Cranberry    ML112440588          2.2.03.02b      applicable ITAAC. The 2013 NRC summary of              memo dated 99900404                                            vendor ITAAC findings (ML13156A136) incorrectly        December 18, lists the finding number as 99900404/2012-202-02. 2017 The 2016 NRC summary of ITAAC findings                (ML17346A937)
(ML16280A303) correctly lists the finding number and the applicable ITAAC.
05        2.2.03.08c.i.03 IR 2011-201 does not clearly link this finding to the  Open applicable ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) correctly lists ITAAC 2.2.03.08c.i.03 as applicable. The 2016 NRC summary of vendor ITAAC findings (ML16280A303) incorrectly lists ITAAC 2.2.03.08c.i.04 as applicable.
2012-201    01        2.1.02.07a.i    IR 2012-201 does not clearly identify the applicable  Closed in IR ML12128A072          2.2.03.07a.i    ITAAC. The finding is closed in the 2013 NRC          2016-204 summary of vendor ITAAC findings (ML13156A136)        (ML16307A159) but lists the incorrect ITAAC. IR 2016-204 also includes a closure discussion of this finding.
02 and 03 2.1.02.07a.i    IR 2012-201 does not clearly identify the applicable  Closed in IR 2.2.03.07a.i    ITAAC. IR 2012-202 closes the findings but lists the  2012-202 incorrect ITAAC.                                      (ML12313A461) 2014-201    01 and 02 2.5.02.14      None                                                  Closed in IR ML14058A995                                                                                  2016-201 (ML15363A360) 2015-204    01        2.5.02.07a      None                                                  Closed in IR ML15113B277          2.5.02.07e                                                            2016-209 (ML17123A085) 02 and 03 2.5.02.03      None                                                  Closed in IR 2016-202 (ML16237A320) 2
 
Vendor /      Inspection  Finding     Affected    Issues Identified in NRC Audit of Vendor                Status Docket        Report (IR) Number(s)   ITAAC        Inspection Findings Number and ADAMS Accession Number Valcor        2017-201    01          2.1.02.05a.i None                                                    Open 99900728      ML17311A267 Wyle Labs    2012-201    01 and 04  2.1.02.12a.i IR 2012-201 lists incorrect ITAAC numbers. The          Closed in IR 99900905      ML12242A459            2.2.01.11a.i 2013 NRC summary of vendor ITAAC findings              2013-201 2.2.03.12a.i (ML13156A136) lists 4 of the ITAAC numbers              (ML14016A447) 2.3.02.11a.i correctly but does not list ITAAC 2.2.03.12a.i as being 2.3.06.12a.i affected.
National      2015-201    01          2.1.02.07a.i IR 2015-201 does not clearly state that finding 01 is  Closed in NRC Technical    ML15078A379            2.2.03.07a.i material to the ITAAC, nor does any subsequent NRC      memorandum Systems,                                          correspondence to SNC.                                  dated April 27, Huntsville    2015-202    01          2.2.03.12a.i IR 2015-202 does not clearly state that finding 01 is  2018 99900905      ML15152A080                          material to the ITAAC, nor does any subsequent NRC      (ML18102B171) correspondence to SNC.
Westinghouse, 2012-201    03, 04, and 2.5.01.03d  IR 2012-201 does not clearly state that the findings    Closed in IR New Stanton  ML12131A263 05                      are material to the ITAAC. The 2013 NRC summary        2013-201 99901043                                          of vendor ITAAC findings (ML13156A136) correctly        (ML13318A689) lists the applicable ITAAC.
3
 
Vendor /      Inspection  Finding  Affected       Issues Identified in NRC Audit of Vendor              Status Docket        Report (IR) Number(s) ITAAC          Inspection Findings Number and ADAMS Accession Number Enertech      2012-201    02        None          IR 2012-201 does not identify this finding as material Closed in NRC 99901377      ML12306A385                          to ITAAC. The 2013 NRC summary of vendor ITAAC        memorandum findings (ML13156A136) incorrectly lists this finding dated January as material to ITAAC 2.2.03.05a.ii and 2.2.03.02a. In  5, 2017 an NRC memorandum dated January 5, 2017                (ML16357A724)
(ML16357A724), this finding was listed as material to an additional ITAAC (2.2.03.03a). This finding is not material to ITAAC.
03        None          IR 2012-201 does not identify this finding as material Closed in NRC to ITAAC. The 2013 NRC summary of vendor ITAAC        memorandum findings (ML13156A136) incorrectly lists this finding  dated January as material to ITAAC 2.2.03.04a. This finding is not  5, 2017 material to ITAAC.                                    (ML16357A724)
CS Innovations 2011-201    03 and 04 2.5.02.14      IR 2011-201 does not clearly state that the findings  Closed in IR 99901404      ML111890005                          are material to the ITAAC, nor does any subsequent    9990404/2014-NRC correspondence to SNC.                            203 (ML14262A351)
Obayashi      2011-201    03        3.3.00.02a.i.a IR 2011-201 does not clearly state that the finding is Closed in NRC Corporation    ML11286A106          3.3.00.02a.i.b material to the ITAAC, nor does any subsequent NRC    memorandum 99901409                            3.3.00.02a.i.c correspondence to SNC.                                dated July 6, 3.3.00.02a.i.d                                                        2018 (ML18186A573)
Clark          2012-201    02        2.2.01.05.ii  IR 2012-201 does not clearly link the finding to the  Closed in NRC Dynamics      ML12108A097          2.2.02.05a.ii  applicable ITAAC. The 2013 NRC summary of              memorandum 99901412                            2.2.05.05a.ii  vendor ITAAC findings (ML13156A136) correctly          dated January 2.3.02.05.ii  identifies the applicable ITAAC.                      5, 2017 2.3.07.05.ii                                                          (ML16357A725) 2.7.01.05.ii 4
 
Vendor /    Inspection  Finding  Affected      Issues Identified in NRC Audit of Vendor               Status Docket      Report (IR) Number(s) ITAAC          Inspection Findings Number and ADAMS Accession Number Kinectrics  2012-201    01 and 02 2.2.01.05.ii  IR 2012-201 does not clearly state that the findings  Closed in IR 99901415    ML12179A413          2.2.01.06a.i  are material to the ITAAC, nor does any subsequent    2015-201 NRC correspondence to SNC.                            (ML15148A419)
Cives Steel  2012-201    03        3.3.00.02a.i.a IR 2012-201 does not clearly state that the finding is Closed in NRC Company      ML13042A397          3.3.00.02a.i.b material to the ITAAC, nor does any subsequent NRC    memorandum 99901419                          3.3.00.02a.i.c correspondence to SNC.                                dated May 11, 3.3.00.02a.i.d                                                        2018 (ML18131A260)
CB & I      2014-201   01       3.3.00.02a.i.a IR 2014-201 does not clearly state that the finding is Closed in NRC Lake Charles ML14072A315          3.3.00.02a.i.d material to the ITAAC, nor does any subsequent NRC     memorandum 99901425                                          correspondence to SNC.                                 dated April 12, 2018 (ML18101A168)
Pentair      2013-201    01        2.1.02.02a    IR 2013-201 and the 2014 NRC summary of vendor        Closed in IR 99901431    ML13212A265          2.1.02.05a.ii  ITAAC findings (ML14111A071) list the four            2014-201 2.2.03.02a    applicable ITAAC, but also incorrectly include ITAAC  (ML14073A652) 2.2.03.05a.ii  2.1.02.08a.ii. This finding is not material to ITAAC 2.1.02.08a.ii.
5
 
Vendor /      Report      Finding  Affected      Issues Identified in NRC Audit of Vendor              Status Docket        Number and  Number(s) ITAAC          Inspection Findings ADAMS Accession Number SMCI          2014-201    01        3.3.00.02a.i.a IR 2014-201 does not clearly state that the finding is Closed in IR 99901439      ML14121A433                          material to the ITAAC, nor does any subsequent NRC    2015-201 correspondence to SNC.                                (ML15175A446) 2015-201   01 and 02 3.3.00.02a.i.a IR 2015-201 does not clearly state that the findings   Closed in NRC ML15175A446                          are material to the ITAAC, nor does any subsequent     memorandum NRC correspondence to SNC.                             dated April 11, 2018 (ML18100A857)
Curtis Wright 2014-201   03       2.1.02.07a.i   None                                                  Open Qualtech      ML14231B268          2.2.03.07a.i 99901441 Oregon Iron   2014-201   02       3.3.00.02a.i.d IR 2014-201 does not clearly state that the finding is Closed in Vigor Works        ML14308A463                          material to the ITAAC, nor does any subsequent NRC     IR 2017-201 99901448                                          correspondence to SNC.                                 (ML17226A340) 99901449 WECTEC       2016-201   01       2.6.03.08     None                                                   Open 99901467      ML17013A658 6
 
Enclosure 2: Vendor Inspection Findings Not Previously Identified as Material to the Acceptance Criteria of ITAAC
: 1. Westinghouse, Cranberry/ Docket 99900404
: 1. Westinghouse, Cranberry/ Docket 99900404
: a. Inspection Scope During the period of March 26 to 30, 2012, the U.S. Nuclear Regulatory Commission (NRC) conducted an inspection at the Westinghouse Electric Company (WEC) facility in Cranberry Township, PA.
: a. Inspection Scope During the period of March 26 to 30, 2012, the U.S. Nuclear Regulatory Commission (NRC) conducted an inspection at the Westinghouse Electric Company (WEC) facility in Cranberry Township, PA. The purpose of the technically-focused inspection was to review implementation of WECs quality assurance program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, and 10 CFR Part 21, Reporting of Defects and Noncompliance. This inspection specifically evaluated the quality assurance program as it pertains to WECs development of test requirements and specifications for the performance of qualification and functional testing for components to be supplied as part of the AP1000 design. The vendor inspection activities were documented in Inspection Report (IR) 99900404/2012-201 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12128A072).
The purpose of the technically
The lead for the abovementioned inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov.
-focused inspection was to review implementation of WEC's quality assurance program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, "Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants," and 10 CFR Part 21, "Reporting of Defects and Noncompliance."
: b. Findings and Observations Inspection Report 99900404/2012-201 contains three findings associated with the following inspections, tests, analyses, and acceptance criteria (ITAAC):
This inspection specifically evaluated the quality assurance program as it pertains to WEC's development of test requirements and specifications for the performance of qualification and functional testing for components to be supplied as part of the AP1000 design.
Design           Inspections, Tests,   Acceptance Criteria ITAAC Commitment                Analysis 2.1.02.07a.i       The Class 1E           Type tests,            A report exists and equipment identified   analyses, or a          concludes that the in Table 2.1.2-1 as     combination of type    Class 1E equipment being qualified for a   tests and analyses     identified in Table harsh environment      will be performed on   2.1.2-1 as being can withstand the      Class 1E equipment      qualified for a harsh environmental          located in a harsh      environment can conditions that would  environment.            withstand the exist before, during,                          environmental and following a                                conditions that would design basis                                    exist before, during, accident without loss                          and following a of safety function for                          design basis the time required to                            accident without loss perform the safety                              of safety function for function.                                      the time required to perform the safety function.
The vendor inspection activities were documented in Inspection Report (IR) 99900404/2012
Enclosure 2
-201 (Agencywide Documents Access and Management System (ADAMS) Accession No.
 
ML12128A072).
Design             Inspections, Tests,   Acceptance Criteria ITAAC Commitment                  Analysis 2.2.03.07a.i       The Class 1E             Type tests,            A report exists and equipment identified     analyses, or a        concludes that the in Table 2.2.3-1 as     combination of type    Class 1E equipment being qualified for a   tests and analyses     identified in Table harsh environment        will be performed on   2.2.3-1 as being can withstand the        Class 1E equipment    qualified for a harsh environmental            located in a harsh    environment can conditions that would    environment.          withstand the exist before, during,                          environmental and following a                                conditions that would design basis                                    exist before, during, accident without loss                          and following a of safety function for                          design basis the time required to                            accident without loss perform the safety                              of safety function for function.                                      the time required to perform the safety function.
The lead for the abovementioned inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301
Inspection Report Finding 99900404/2012-201-01 states, in part, that:
-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov
WEC failed to verify the adequacy of certain design features and include the most adverse design conditions in the test program for performing functional testing of the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012-201-01.
. b. Findings and Observations Inspection Report 99900404/20 12-201 contains three findings associated with the following inspections, tests, analyses, and acceptance criteria (ITAAC)
This finding that the most adverse conditions were not tested during environmental qualification affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
:  ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.1.02.07a.i The Class 1E equipment identified in Table 2.1.2
Inspection Report Finding 99900404/2012-201-02 states:
-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. Type tests, analyses, or a combination of type tests and analyses will be performed on Class 1E equipment located in a harsh environment.
WEC did not identify design interfaces sufficient to allow for the translation of the design basis into specifications. Specifically, APP-GW-J4-072 Interface Specification for Squib Valve Controller, Revision 1, did not include the full range of temperatures that need to be considered when sizing the field run cable/connector systems located between the Plant Monitoring and Protection System, the Diverse Actuation System, and the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012-201-02.
A report exists and concludes that the Class 1E equipment identified in Table 2.1.2-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function.
This finding affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist 2
2 ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.2.03.07a.i The Class 1E equipment identified in Table 2.2.3
 
-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. Type tests, analyses, or a combination of type tests and analyses will be performed on Class 1E equipment located in a harsh environment.
before, during and following a design basis accident for the time required to perform the safety function.
A report exists and concludes that the Class 1E equipment identified in Table 2.2.3-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. Inspection Report Finding 99900404/2012
Inspection Report Finding 99900404/2012-201-03 states:
-201-01 states, in part, that
WEC did not establish measures necessary to ensure that the design basis for the Diverse Actuation System was correctly translated into specifications, drawings, and instructions. Specifically, WEC did not perform a documented calculation or analysis to justify the selection of resistance values contained in APP-GW-J4-072, Interface Specification for Squib Valve Controller, Revision 1, for the field run cabling located between the Diverse Actuation System and the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012-201-03.
WEC failed to verify the adequacy of certain design features and include the most adverse design conditions in the test program for performing functional testing of the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012
This finding affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
-201-01. This finding that the most adverse conditions were not tested during environmental qualification affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
Inspection Report Finding 99900404/2012
-201-02 states:
WEC did not identify design interfaces sufficient to allow for the translation of the design basis into specifications. Specifically, APP
-GW-J4-072 "Interface Specification for Squib Valve Controller," Revision 1, did not include the full range of temperatures that need to be considered when sizing the field run cable/connector systems located between the Plant Monitoring and Protection System, the Diverse Actuation System, and the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012
-201-02. This finding affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental condition s that would exist 3 before, during and following a design basis accident for the time required to perform the safety function.
Inspection Report Finding 99900404/2012
-201-03 states:
WEC did not establish measures necessary to ensure that the design basis for the Diverse Actuation System was correctly translated into specifications, drawings, and instructions.
Specifically, WEC did not perform a documented calculation or analysis to justify the selection of resistance values contained in APP-GW-J4-072, "Interface Specification for Squib Valve Controller," Revision 1, for the field run cabling located between the Diverse Actuation System and the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012
-201-03. This finding affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
: 2. Valcor Engineering Corporation/Docket No. 99900728
: 2. Valcor Engineering Corporation/Docket No. 99900728
: a. Inspection Scope During the period of October 9
: a. Inspection Scope During the period of October 9-12, 2017, the U.S. NRC staff conducted an inspection at the Valcor Engineering Corporations facility (hereafter referred to as Valcor) facility in Springfield, NJ. The purpose of this limited-scope routine inspection was to assess Valcors compliance with provisions of Title 10 of the Code of Federal Regulations (10 CFR) Part 21, Reporting of Defects and Noncompliance, and selected portions of Appendix B, Quality Assurance Program Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to 10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities. This inspection specifically evaluated Valcors implementation of the quality activities associated with the design, fabrication, and testing of the solenoid valves and replacement valve parts for the Westinghouse Electric Company AP1000 reactor design and for the domestic operating reactors. The vendor inspection activities were documented in Inspection Report (IR) 99900728/I-2017-201 (ADAMS Accession No. ML17311A267).
-12, 2017, the U.S. NRC staff conducted an inspection at the Valcor Engineering Corporation's facility (hereafter referred to as Valcor) facility in Springfield, NJ.
The lead for this inspection is Mr. Yamir Diaz-Castillo, who can be reached by phone at 301-415-2228 or via electronic mail at Yamir.Diaz-Castillo@nrc.gov.
The purpose of this limited
3
-scope routine inspection was to assess Valcor's compliance with provisions of Title 10 of the Code of Federal Regulations (10 CFR) Part 21, "Reporting of Defects and Noncompliance," and selected portions of Appendix B, "Quality Assurance Program Criteria for Nuclear Power Plants and Fue l Reprocessing Plants," to 10 CFR Part 50, "Domestic Licensing of Production and Utilization Facilities."
: b. Findings and Observations IR 999007728/I-2017-201 contains one finding associated with the following ITAAC:
This inspection specifically evaluated Valcor's implementation of the quality activities associated with the design, fabrication, and testing of the solenoid valves and replacement valve parts for the Westinghouse Electric Company AP1000 reactor design and for the domestic operating reactors. The vendor inspection activities were documented in Inspection Report (IR) 99900728/
Inspections, Design ITAAC                                    Tests,              Acceptance Criteria Commitment Analysis 2.1.02.05a.i      The Class 1E          Type tests,        A report exists and concludes equipment            analyses, or a    that the Class 1E equipment identified in Table  combination of    identified in Table 2.1.2-1 as 2.1.2-1 as being      type tests and    being qualified for a harsh qualified for a harsh analyses will      environment can withstand the environment can      be performed      environmental conditions that withstand the        on Class 1E        would exist before, during, and environmental        equipment          following a design basis conditions that      located in a      accident without loss of safety would exist before, harsh                function for the time required to during, and          environment.      perform the safety function.
I-2017-201 (ADAMS Accessio n No. ML17311A267
following a design basis accident without loss of safety function for the time required to perform the safety function.
). The lead for this inspection is Mr. Yamir Diaz
IR 99900728/I-2017-201 states:
-Castillo, who can be reached by phone at 301-415-2228 or via electronic mail at Yamir.Diaz
IEEE 323-1974 requires testing or analysis of the valve to be performed at the full range of its performance characteristics. While it appeared that the valves may have sufficient margin to compensate for the lower coil pull-in voltage, this margin had not been specifically quantified as it is unknown what the controller output voltage would be when the input to the controller is at the minimal 180 VDC. A change in applied voltage or temperature could impact the capability of the valve to perform its intended safety function. This issue impacts the domestic AP1000 solenoid valves fabricated by Valcor that are identified in the WEC data sheets APP-PV13-Z0D-101and -111.
-Castillo@nrc.gov.
This issue has been identified as Nonconformance 99900728/I-2017-201-01.
The NRC staff determined that the above vendor finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 2.1.02.05a.i, in that, if left uncorrected, the licensee may not be able to successfully complete the ITAAC. The referenced valves are identified in Table 2.1.2-1 of Appendix C of the Combined License, as being located in a harsh environment.
However, the EQ testing performed on these valves was not performed using the voltage controller which is an integral part of the solenoid valve system and which will be used to supply power to the valves in the plant. As of the completion of the inspection, Valcor had not performed testing or analysis sufficient to verify that the voltage controller output would be adequate to ensure the subject valves would be capable of performing their intended safety functions under all design basis environmental conditions.
4
: 3. National Technical Systems (NTS)/ Docket 99900905
: a. Inspection Scope During the period of December 15-17, 2014, and February 11, 2015, the U.S. NRC staff conducted an inspection at the National Testing Systems (NTS) facility in Huntsville, AL.
The purpose of the inspection was to review NTSs implementation of an adequate quality assurance program as related to the irradiation and submergence testing of the explosive actuators, which are a subcomponent of the 8-inch squib valves being supplied as a part of the Westinghouse Electric Corporation AP1000 reactor design.
The vendor inspection activities were documented in Inspection Report (IR) 99900905/2015-201 (ADAMS Accession No. ML15078A379).
The lead for the above mentioned inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov.
During the week of May 11-15, 2015, the NRC staff conducted an inspection at the NTS facility in Huntsville, AL. The purpose of the inspection was to review NTSs quality assurance activities as it pertains to the qualification testing of the 8-inch high pressure (HP) and the low pressure (LP) squib valves in the Passive Core Cooling System (PXS) of the AP1000 reactor design. The vendor inspection activities were documented in Inspection Report (IR) 99900905/2015-202 (ADAMS Accession No. ML15152A080).
The lead for the above mentioned inspection is Mr. Raju Patel, who can be reached by phone at 301-415-3511 or via electronic mail at Raju.Patel@nrc.gov.
: b. Findings and Observations IR 99900905/2015-201 and IR 99900905/2015-202 each contain one inspection finding.
Design          Inspections, Tests,            Acceptance ITAAC Commitment                Analysis                  Criteria 2.2.03.12a.i        The squib valves and    Tests or type tests of    A test report exists check valves            squib valves will be      and concludes that identified in Table    performed that            each squib valve 2.2.3-1 perform an      demonstrate the          changes position as active                  capability of the        indicated in Table safety-related          valve to operate          2.2.3-1 under design function to change      under its design          conditions.
position as indicated  condition.
in the table.
5


4 b. Findings and Observations IR 999007728/I
2.1.02.07a.i       The Class 1E             Type tests, analyses, A report exists and equipment identified     or a combination of  concludes that the in Table 2.1.2-1 as     type tests and        Class 1E equipment being qualified for a   analyses will be      identified in Table harsh environment       performed on Class    2.1.2-1 as being can withstand the       1E equipment          qualified for a harsh environmental           located in a harsh    environment can conditions that would   environment.          withstand the exist before, during,                         environmental and following a                               conditions that design basis                                   would exist before, accident without loss                         during, and following of safety function for                         a design basis the time required to                           accident without loss perform the safety                            of safety function for function.                                     the time required to perform the safety function.
-2017-201 contains one finding associated with the following ITAAC:
2.2.03.07a.i        The Class 1E            Type tests, analyses, A report exists and equipment identified    or a combination of   concludes that the in Table 2.2.3-1 as      type tests and       Class 1E equipment being qualified for a    analyses will be     identified in Table harsh environment       performed on Class   2.2.3-1 as being can withstand the        1E equipment          qualified for a harsh environmental            located in a harsh    environment can conditions that would    environment.          withstand the exist before, during,                          environmental and following a                                conditions that design basis                                  would exist before, accident without loss                          during, and following of safety function for                        a design basis the time required to                          accident without loss perform the safety                            of safety function for function.                                      the time required to perform the safety function.
ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.1.02.05a.i The Class 1E equipment identified in Table 2.1.2-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. Type tests, analyses, or a combination of type tests and analyses will be performed on Class 1E equipment located in a harsh environment.
IR 99900905/2015-201 states:
A report exists and concludes that the Class 1E equipment identified in Table 2.1.2
NRC inspectors reviewed the irradiation of the squib valve cartridges. The inspectors concluded that the previously stated accuracy of the irradiation system was found to be non-conservative as it did not include several factors that could impact the accuracy of the radiation measurements. As a consequence, nuclear safety related components (squib valve actuators for the Westinghouse AP1000 reactor) currently undergoing environmental qualification at NTS did not receive the full radiation dose when subtracting out the actual uncertainty of the measurement system. This item was identified as Nonconformance 99900905/2015-201-01.
-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function.
6
IR 99900728/I
-2017-201 states:
IEEE 323-1974 requires testing or analysis of the valve to be performed at the full range of its performance characteristics.
While it appeared that the valves may have sufficient margin to compensate for the lower coil pull
-in voltage, this margin had not been specifically quantified as it is unknown what the controller output voltage would be when the input to the controller is at the minimal 180 VDC. A change in applied voltage or temperature could impact the capability of the valve to perform its intended safety function.
This issue impacts the domestic AP1000 solenoid valves fabricated by Valcor that are identified in the WEC data sheets APP
-PV13-Z0D-101and -111. This issue has been identified as Nonconformance 99900728/I
-2017-201-01. The NRC staff determined that the above vendor finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 2.1.02.05a.i, in that, if left uncorrected, the licensee may not be able to successfully complete the ITA AC. The referenced valves are identified in Table 2.1.2
-1 of Appendix C of the Combined License, as being located in a harsh environment.
However, the EQ testing performed on these valves was not performed using the voltage controller which is an integral part of the solenoid valve system and which will be used to supply power to the valves in the plant.
As of the completion of the inspection, Valcor had not performed testing or analysis sufficient to verify that the voltage controller output would be adequate to ensure the subject valves would be capable of performing their intended safety functions under all design basis environmental conditions.
5 3. National Technical Systems (NTS)/ Docket 99900905
: a. Inspection Scope During the period of December 15
-17, 2014, and February 11, 2015, the U.S.
NRC staff conducted an inspection at the National Testing Systems (NTS) facility in Huntsville, AL. The purpose of the inspection was to review NTS's implementation of an adequate quality assurance program as related to the irradiation and submergence testing of the explosive actuators, which are a subcomponent of the 8
-inch squib valves being supplied as a part of the Westinghouse Electric Corporation AP1000 reactor design.
The vendor inspection activities were documented in Inspection Report (IR) 99900905/2015
-201 (ADAMS Accession No.
ML15078A379).
The lead for the above mentioned inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301
-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov
. During the week of May 11
-15, 2015, the NRC staff conducted an inspection at the NTS facility in Huntsville, AL.
The purpose of the inspection was to review NTS's quality assurance activities as it pertains to the qualification testing of the 8
-inch high pressure (HP) and the low pressure (LP) squib valves in the Passive Core Cooling System (PXS) of the AP1000 reactor design.
The vendor inspection activities were documented in Inspection Report (IR) 99900905/2015
-202 (ADAMS Accession No. ML15152A080).
The lead for the above mentioned inspection is Mr. Raju Patel, who can be reached by phone at 301
-415-3511 or via electronic mail at Raju.Patel@nrc.gov. b. Findings and Observations IR 99900905/2015
-201 and IR 99900905/20 1 5-202 each contain one inspection finding.
ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.2.03.12a.i The squib valves and check valves identified in Table 2.2.3-1 perform an active  safety-related function to change position as indicated in the table.
Tests or type tests of squib valves will be performed that demonstrate the capability of the valve to operate under its design condition.
A test report exists and concludes that each squib valve changes position as indicated in Table 2.2.3-1 under design conditions.


6 2.1.02.07a.i The Class 1E equipment identified in Table 2.1.2-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. Type tests, analyses, or a combination of type tests and analyses will be performed on Class 1E equipment located in a harsh environment.
This finding is material to ITAAC 2.1.02.07a.i and 2.2.03.07a.i because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
A report exists and concludes that the Class 1E equipment identified in Table 2.1.2-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. 2.2.03.07a.i The Class 1E equipment identified in Table 2.2.3
IR 99900905/2015-202 states:
-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. Type tests, analyses, or a combination of type tests and analyses will be performed on Class 1E equipment located in a harsh environment.
The NRC inspection team determined that NTS failed to establish a procedure in its test program for verifying that the data acquisition system (DAS) functioned as designed. NTS performed both pre-and post-test verification and validation of the DAS to verify that the DAS software was accurately calculating and reporting those temperature and pressure values that would be used to determine the qualification of the safety-related AP1000 8-inch low pressure squib valves.
A report exists and concludes that the Class 1E equipment identified in Table 2.2.3-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. IR 99900905/2015
However, NTS activities to validate the proper function of the DAS, a testing activity affecting quality, were not performed in accordance with written procedures containing the requirements and acceptance limits of the design documents to assure that all prerequisites for the given test have been met. This issue has been identified as Nonconformance 99900905/2015-202-01 Proper functioning of the DAS system is required to verify design conditions when testing squib valves. Therefore, this finding is material to ITAAC 2.2.03.12a.i because if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
-201 states:
NRC inspectors reviewed the irradiation of the squib valve cartridges. The inspectors concluded that the previously stated accuracy of the irradiation system was found to be non
-conservative as it did not include several factors that could impact the accuracy of the radiation measurements.
As a consequence, nuclear safety related components (squib valve actuators for the Westinghouse AP1000 reactor) currently undergoing environmental qualification at NTS did not receive the full radiation dose when subtracting out the actual uncertainty of the measurement system. This item was identified as Nonconformance 99900905/2015
-201-01.
7 This finding is material to ITAAC 2.1.02.07a.i and 2.2.03.07a.i because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
IR 99900905/2015
-202 states:
The NRC inspection team determined that NTS failed to establish a procedure in its test program for verifying that the data acquisition system (DAS) functioned as designed. NTS performed both pre
-and post-test verification and validation of the DAS to verify that the DAS software was accurately calculating and reporting those temperature and pressure values that would be used to determine the qualification of the safety
-related AP1000 8
-inch low pressure squib valves. However, NTS activities to validate the proper function of the DAS, a testing activity affecting quality, were not performed in accordance with written procedures containing the requirements and acceptance limits of the design documents to assure that all prerequisites for the given test have been met.
This issue has been identified as Nonconformance 99900905/2015
-202-01 Proper functioning of the DAS system is required to verify design conditions when testing squib valves. Therefore, this finding is material to ITAAC 2.2.03.12a.i because if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.
These inspection findings are material to the acceptance criteria of the ITAAC listed above because the findings concern the adequacy of the testing and/or analyses used to support the conclusion that the squib valves meet the acceptance criteria of the ITAAC.
These inspection findings are material to the acceptance criteria of the ITAAC listed above because the findings concern the adequacy of the testing and/or analyses used to support the conclusion that the squib valves meet the acceptance criteria of the ITAAC.
: 4. CS Innovations / Docket No. 99901404
: 4. CS Innovations / Docket No. 99901404
: a. Inspection Scope During the period of April 25
: a. Inspection Scope During the period of April 25-29, 2011, the U.S. NRC staff conducted an inspection at the CS Innovations, Inc. (CSI), facility in Scottsdale, AZ. The purpose of the inspection was to review the quality assurance activities associated with the development of digital instrumentation and control systems and components for the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901404/2011-201 (ADAMS Accession No. ML111890005).
-29, 2011, the U.S.
NRC staff conducted an inspection at the CS Innovations, Inc. (CSI), facility in Scottsdale, AZ.
The purpose of the inspection was to review the quality assurance activities associated with the development of digital instrumentation and control systems and components for the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901404/2011
-201 (ADAMS Accession No. ML111890005).
The lead for this inspection is Mr. Greg Galletti, who can be reached by phone at 301-415-1831 or via electronic mail at Greg.Galletti@nrc.gov.
The lead for this inspection is Mr. Greg Galletti, who can be reached by phone at 301-415-1831 or via electronic mail at Greg.Galletti@nrc.gov.
7
: b. Findings and Observations IR 99901404/2011-201 contains two findings associated with the following ITAAC:
Design        Inspections, Tests, ITAAC                                                          Acceptance Criteria Commitment                Analysis 2.5.02.14        The Component        An inspection and      A report exists and Interface Module      or an audit will be    concludes that CIM (CIM) is developed    performed of the        meets the below listed using a planned      processes used to      life cycle stages. Life design process        design the              cycle stages:
which provides for    hardware,                  a. Design requirements specific design      development                  phase, may be documentation and    software,                    referred to as reviews.              qualification and            conceptual or project testing.                      definition phase
: b. System definition phase
: c. Hardware and software development phase, consisting of hardware and software design and implementation
: d. System integration and test phase
: e. Installation phase IR 99901404/2011-201 states:
The NRC inspector determined that CSI failed to establish and implement provisions to collect information on error reports related to discrete components used in safety-related applications. Specifically, the NRC inspection team determined that CSI procedure QCP 9000-01500, Control of Nonconformance, Revision 6, dated December 12, 2010, did not have provisions for the collection, evaluation, disposition, and notification to affected organizations of nonconforming conditions related to discrete components, such as field programmable gate arrays used in safety-related applications. As a result CSI did not formally collect and evaluate error reports for such safety-related components to determine if nonconforming conditions could exist. This item was identified as Nonconformance 99901404/2011-201-03.
The NRC inspectors determined that CSI failed to establish measures to assure that applicable requirements associated with specific independent verification and validation (IV&V) activities were implemented. Specifically, CSIs IV&V process failed to provide for the development of an independent testing tool during the component or module-based level of development for the CIM-SRNC 8


8 b. Findings and Observations IR 99901404/2011
subsystem, and CSIs IV&V process did not include specific independent test plans for implementation by the IV&V team as required by CSI Report No. 6105-00013. This item was identified as Nonconformance 99901404/2011-201-04.
-201 contains two findings associated with the following ITAAC:
The NRC staff determined that the vendor findings represented ITAAC findings because they were material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 2.5.02.14, in that, if left uncorrected, the licensee may not have been able to demonstrate that the acceptance criterion of this ITAAC was met. The acceptance criteria of this ITAAC require a report exists and concludes that CIM meets the following life cycle stages:
ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.5.02.14 The Component Interface Module (CIM) is developed using a planned design process which provides for specific design documentation and reviews. An inspection and or an audit will be performed of th e processes used to design the hardware, development software, qualification and testing. A report exists and concludes that CIM meets the below listed life cycle stages. Life cycle stages:
: 1. Design requirements phase, may be referred to as conceptual or project definition phase
: a. Design requirements phase, may be referred to as conceptual or project definition phase
: 2. System definition phase
: b. System definition phase  c. Hardware and software development phase, consisting of hardware and software design and implementation
: d. System integration and test phase
: e. Installation phase IR 99901404/2011
-201 states:
The NRC inspector determined that CSI failed to establish and implement provisions to collect information on error reports related to discrete components used in safety
-related applications.
Specifically, the NRC inspection team determined that CSI procedure QCP 9000
-01500, "Control of Nonconformance," Revision 6, dated December 12, 2010, did not have provisions for the collection, evaluation, disposition, and notification to affected organizations of nonconforming conditions related to discrete components, such as field programmable gate arrays used in safety
-related applications.
As a result CSI did not formally collect and evaluate error reports for such safety
-related components to determine if nonconforming conditions could exist.
This item was identified as Nonconformance 99901404/2011
-201-03. The NRC inspectors determined that CSI failed to establish measures to assure that applicable requirements associated with specific independent verification and validation (IV&V) activities were implemented.
Specifically, CSI's IV&V process failed to provide for the development of an independent testing tool during the component or module
-based level of development for the CIM
-SRNC 9 subsystem, and CSI's IV&V process did not include specific independent test plans for implementation by the IV&V team as required by CSI Report No. 6105-00013. This item was identified as Nonconformance 99901404/2011
-201-04. The NRC staff determined that the vendor findings represented ITAAC findings because they were material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 2.5.02.14, in that, if left uncorrected, the licensee may not have been able to demonstrate that the acceptance criterion of this ITAAC was met. The acceptance criteria of this ITAAC require a report exists and concludes that CIM meets the following life cycle stages:
: 1. Design requirements phase, may be referred to as conceptual or project definition phase 2. System definition phase
: 3. Hardware and software development phase, consisting of hardware and software design and implementation
: 3. Hardware and software development phase, consisting of hardware and software design and implementation
: 4. System integration and test phase
: 4. System integration and test phase
: 5. Installation phase The inspectors determined that the quality assurance failures found would have prevented the development of an acceptable report for the CIM and therefore, the ITAAC acceptance criteria would not be met by the licensee.
: 5. Installation phase The inspectors determined that the quality assurance failures found would have prevented the development of an acceptable report for the CIM and therefore, the ITAAC acceptance criteria would not be met by the licensee.
: 5. Obayashi Corporation / Docket No. 99901409
: 5. Obayashi Corporation / Docket No. 99901409
: a. Inspection Scope During the period of September 12
: a. Inspection Scope During the period of September 12-16, 2011, the U.S. NRC staff conducted an inspection at the Obayashi Corporation (hereafter referred to as Obayashi) facility in Tokyo, Japan. The purpose of this inspection was to evaluate the quality assurance activities associated with the design services being provided the Westinghouse Electric Company in support of the AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901409/2011-201 (ADAMS Accession No. ML11286A106).
-16, 2011, the U.S. NRC staff conducted an inspection at the Obayashi Corporation (hereafter referred to as Obayashi) facility in Tokyo, Japan. The purpose of this inspection was to evaluate the quality assurance activities associated with the design services being provided the Westinghouse Electric Company in support of the AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901409/2011
The lead for this inspection is Ms. Kerri Kavanagh, who can be reached by phone at 301-415-3743 or via electronic mail at Kerri.Kavanagh@nrc.gov.
-201 (ADAMS Accession No. ML11286A106).
9
The lead for this inspection is Ms. Kerri Kavanagh, who can be reached by phone at 301-415-3743 or via electronic mail at Kerri.Kavanagh@nrc.gov
: b. Findings and Observations IR 99901409/2012-201 contains one finding associated with the following ITAAC:
.
Design             Inspections, ITAAC                                                        Acceptance Criteria Commitment            Tests, Analysis 3.3.00.02a.i.a The nuclear island       An inspection of the  A report exists which structures, including   nuclear island        reconciles deviations the critical sections   structures will be    during construction and listed in Table 3.3-7,   performed.            concludes that the are seismic Category     Deviations from the  as-built containment I and are designed       design due to as-    internal structures, and constructed to       built conditions will including the critical withstand design         be analyzed for the  sections, conform to the basis loads as           design basis loads. approved design and will specified in the                               withstand the design Design Description,                           basis loads specified in without loss of                               the Design Description structural integrity                           without loss of structural and the                                       integrity or the safety-related                                safety-related functions.
10 b. Findings and Observations IR 99901409/2012
functions.
-201 contains one finding associated with the following ITAAC:
3.3.00.02a.i.b The nuclear island      An inspection of the A report exists which structures, including    nuclear island       reconciles deviations the critical sections    structures will be   during construction and listed in Table 3.3-7,  performed.           concludes that the are seismic Category    Deviations from the   as-built shield building I and are designed      design due to as-     structures, including the and constructed to      built conditions will critical sections, conform withstand design        be analyzed for the  to the approved design basis loads as          design basis loads. and will withstand the specified in the                              design basis loads Design Description,                            specified in the Design without loss of                                Description without loss structural integrity                          of structural integrity or and the                                        the safety-related safety-related                                functions.
ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.a The nuclear island structures, including the critical sections listed in Table 3.3
functions.
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the safety-related functions.
10
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
 
-built conditions will be analyzed for the design basis loads.
Design              Inspections, ITAAC                                                            Acceptance Criteria Commitment            Tests, Analysis 3.3.00.02a.i.c      The nuclear island       An inspection of the  A report exists which structures, including   nuclear island        reconciles deviations the critical sections   structures will be    during construction and listed in Table 3.3-7,   performed.            concludes that the are seismic Category     Deviations from the  as-built structures in the I and are designed       design due to as-    non-radiologically and constructed to       built conditions will controlled area of the withstand design         be analyzed for the  auxiliary building, basis loads as           design basis loads. including the critical specified in the                              sections, conform to the Design Description,                           approved design and will without loss of                               withstand the design structural integrity                           basis loads specified in and the                                       the Design Description safety-related                                without loss of structural functions.                                    integrity or the safety-related functions.
A report exists which reconciles deviations during construction and concludes that the as-built containment internal structures, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety-related functions.
3.3.00.02a.i.d      The nuclear island      An inspection of the A report exists which structures, including    nuclear island       reconciles deviations the critical sections    structures will be   during construction and listed in Table 3.3-7,  performed.           concludes that the are seismic Category    Deviations from the   as-built structures in the I and are designed      design due to as-     radiologically controlled and constructed to      built conditions will area of the auxiliary withstand design        be analyzed for the   building, including the basis loads as          design basis loads. critical sections, conform specified in the                              to the approved design Design Description,                            and will withstand the without loss of                                design basis loads structural integrity                          specified in the Design and the                                        Description without loss safety-related                                of structural integrity or functions.                                    the safety-related functions.
3.3.00.02a.i.b The nuclear island structures, including the critical sections listed in Table 3.3
IR 99901409/2011-201 states:
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the safety-related functions.
The NRC inspectors determined that Obayashi failed to: 1) assure that applicable design basis are correctly translated into calculations; 2) establish procedures for the identification and control of design control interfaces and for coordination among the participating design organizations; and 3) subject design changes to the commensurate design control measures applied to the original design. This item was identified as Nonconformance 99901409/2011-201-03.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
The NRC staff determined that the vendor finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to demonstrate that the acceptance criteria of these ITAACs were met. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built 11
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as-built shield building structures, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
-related functions.


11 ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.c The nuclear island structures, including the critical sections listed in Table 3.3
structures conform to the approved design and will withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and reconcile nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the  safety-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as-built structures in the non-radiologically controlled area of the auxiliary building, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Descripti on without loss of structural integrity or the safety-related functions.
3.3.00.02a.i.d The nuclear island structures, including the critical sections listed in Table 3.3
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the  safety-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as-built structures in the radiologically controlled area of the auxiliary building, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
-related functions.
IR 99901409/2011
-201 states:
The NRC inspectors determined that Obayashi failed to: 1) assure that applicable design basis are correctly translated into calculations; 2) establish procedures for the identification and control of design control interfaces and for coordination among the participating design organizations; and 3) subject design changes to the commensurate design control measures applied to the original design.
This item was identified as Nonconformance 99901409/2011
-201-03. The NRC staff determined that the vendor finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to demonstrate that the acceptance criteria of these ITAACs were met. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as
-built 12 structures conform to the approved design and will withstand the design basis loads without a loss of structural integrity or other safety
-related functions. The inspectors determined that the failure to adequately review and reconcile nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
: 6. Kinectrics / Docket No. 99901415
: 6. Kinectrics / Docket No. 99901415
: a. Inspection Scope During the period of May 14
: a. Inspection Scope During the period of May 14-18, 2012, the U.S. NRC staff conducted an inspection at the Kinectrics Inc. (hereafter referred to as Kinectrics) facility in Toronto, Ontario. The purpose of the inspection was to evaluate the quality assurance activities associated with the supply of testing services by Kinectrics in support of environmental qualification of components being used in the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901415/2012-201 (ADAMS Accession No. ML12179A413).
-18, 2012, the U.S. NRC staff conducted an inspection at the Kinectrics Inc. (hereafter referred to as Kinectrics) facility in Toronto, Ontario. The purpose of the inspection was to evaluate the quality assurance activities associated with the supply of testing services by Kinectrics in support of environmental qualification of components being used in the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction.
The lead for this inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov.
The vendor inspection activities were documented in Inspection Report (IR) 99901415/2012
: b. Findings and Observations IR 99901415/2012-201 contains two findings associated with the following ITAAC:
-201 (ADAMS Accession No. ML12179A413).
Inspections, Tests, ITAAC        Design Commitment                                  Acceptance Criteria Analysis 2.2.01.05.ii       The seismic Category       Type tests,              A report exists and I equipment identified     analyses, or a          concludes that the in Table 2.2.1-1 can       combination of type     seismic Category I withstand seismic          tests and analyses       equipment can design basis loads        of seismic Category     withstand seismic without loss of            I equipment will be     design basis structural integrity      performed.               dynamic loads and safety function.                                without loss of structural integrity and safety function.
The lead for this inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov
12
. b. Findings and Observations IR 99901415/201 2-201 contains two finding s associated with the following ITAAC: ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.2.01.05.ii The seismic Category I equipment identified in Table 2.2.1
-1 can withstand seismic design basis loads without loss of structural integrity and safety function.
Type tests, analyses, or a combination of type tests and analyses of seismic Category I equipment will be performed.
A report exists and concludes that the seismic Category I equipment can withstand seismic design basis dynamic loads without loss of structural integrity and safety function.


13 ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.2.01.06a.i The Class 1E equipment identified in Table 2.2.1
Inspections, Tests, ITAAC          Design Commitment                                Acceptance Criteria Analysis 2.2.01.06a.i       The Class 1E             Type tests,            A report exists and equipment identified     analyses, or a          concludes that the in Table 2.2.1-1 as       combination of type    Class 1E equipment being qualified for a     tests and analyses     identified in Table harsh environment        will be performed on   2.2.1-1 as being can withstand the        Class 1E equipment      qualified for a harsh environmental            located in a harsh      environment can conditions that would    environment.            withstand the exist before, during,                            environmental and following a                                  conditions that would design basis accident                            exist before, during, without loss of safety                            and following a function for the time                            design basis required to perform                              accident without loss the safety function.                              of safety function for the time required to perform the safety function.
-1 as being qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function.
IR 99901415/2012-201 states:
Type tests, analyses, or a combination of type tests and analyses will be performed on Class 1E equipment located in a harsh environment.
The NRC inspectors determined that Kinectrics failed to implement measures to ensure that testing performed by subcontractors was in conformance with procurement documents. Specifically: (1) Kinectrics did not properly dedicate the testing services provided by Global EMC, Inc., for the performance of electromagnetic compatibility testing, as necessary to ensure that the testing was performed in accordance with the stated requirements; and (2) Kinectrics did not ensure that the test report produced by its subcontractor, Clark Testing Laboratories, for seismic testing of electrical penetration assemblies performed in accordance with stated requirements. This item was identified as Nonconformance 99901415/2012-201-01.
A report exists and concludes that the Class 1E equipment identified in Table 2.2.1-1 as bein g qualified for a harsh environment can withstand the environmental conditions that would exist before, during, and following a design basis accident without loss of safety function for the time required to perform the safety function. IR 99901415/2012
The NRC inspectors determined that Kinectrics did not explicitly state the proper technical standard and revision to be used for electromagnetic compatibility testing of electrical penetration assemblies. Consequently, the incorrect revision of the MIL-STD-461 was used to perform the testing. This item was identified as Nonconformance 99901415/2012-201-02.
-201 states:
These items are material to the ITAAC acceptance criteria because if left uncorrected, these issues challenge the validity of the qualification testing performed on the subject equipment as required by the ITAAC.
The NRC inspectors determined that Kinectrics failed to implement measures to ensure that testing performed by subcontractors was in conformance with procurement documents.
13
Specifically: (1) Kinectrics did not properly dedicate the testing services provided by Global EMC, Inc., for the performance of electromagnetic compatibility testing, as necessary to ensure that the testing was performed in accordance with the stated requirements; and (2) Kinectrics did not ensure that the test report produced by its subcontractor, Clark Testing Laboratories, for seismic testing of electrical penetration assemblies performed in accordance with stated requirements.
: 7. Cives Steel Company / Docket No. 99901419
This item was identified as Nonconformance 99901415/2012
: a. Inspection Scope During the period of December 10-14, 2012, the U.S. NRC staff conducted an inspection at the Cives Steel Company (hereafter referred to as Cives) facility in Thomasville, GA.
-201-01. The NRC inspectors determined that Kinectrics did not explicitly state the proper technical standard and revision to be used for electromagnetic compatibility testing of electrical penetration assemblies.
This inspection evaluated the quality assurance activities associated with the fabrication of concrete embedments for the AP1000 reactor plants for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901419/2012-201 (ADAMS Accession No. ML13042A397).
Consequently, the incorrect revision of the MIL
The lead for this inspection is Mr. Jonathan Ortega-Luciano, who can be reached by phone at 301-415-1159 or via electronic mail at Jonathan.Ortega-Luciano@nrc.gov.
-STD-461 was used to perform the testing.
: b. Findings and Observations IR 99901419/2012-201 contains one finding associated with the following ITAAC:
This item was identified as Nonconformance 99901415/2012
Inspections, ITAAC           Design Commitment                               Acceptance Criteria Tests, Analysis 3.3.00.02a.i.a   The nuclear island         An inspection of the  A report exists which structures, including     nuclear island        reconciles deviations the critical sections     structures will be    during construction and listed in Table 3.3-7,     performed.            concludes that the as-are seismic Category I     Deviations from the  built containment and are designed and       design due to as-     internal structures, constructed to             built conditions will including the critical withstand design basis    be analyzed for the   sections, conform to loads as specified in      design basis loads. the approved design the Design Description,                         and will withstand the without loss of                                  design basis loads structural integrity and                        specified in the Design the                                              Description without safety-related                                  loss of structural functions.                                      integrity or the safety-related functions.
-201-02. These items are material to the ITAAC acceptance criteria because if left uncorrected, these issues challenge the validity of the qualification testing performed on the subject equipment as required by the ITAAC.
14
14 7. Cives Steel Company / Docket No. 99901419
: a. Inspection Scope During the period of December 10
-14, 2012, the U.S. NRC staff conducted an inspection at the Cives Steel Company (hereafter referred to as Cives) facility in Thomasville, GA. This inspection evaluated the quality assurance activities associated with the fabrication of concrete embedments for the AP1000 reactor plants for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901419/2012
-201 (ADAMS Accession No. ML13042A397).
The lead for this inspection is Mr. Jonathan Ortega
-Luciano, who can be reached by phone at 301
-415-1159 or via electronic mail at Jonathan.Ortega
-Luciano@nrc.gov
. b. Findings and Observations IR 99901419/2012
-201 contains one finding associated with the following ITAAC: ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.a The nuclear island structures, including the critical sections listed in Table 3.3
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and t he  safety-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as
-built containment internal structures, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety-related functions.


15 ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.b The nuclear island structures, including the critical sections listed in Table 3.3
Inspections, ITAAC       Design Commitment                               Acceptance Criteria Tests, Analysis 3.3.00.02a.i.b The nuclear island         An inspection of the  A report exists which structures, including     nuclear island        reconciles deviations the critical sections     structures will be    during construction and listed in Table 3.3-7,     performed.            concludes that the as-are seismic Category I     Deviations from the  built shield building and are designed and       design due to as-     structures, including constructed to             built conditions will the critical sections, withstand design basis    be analyzed for the   conform to the loads as specified in      design basis loads. approved design and the Design Description,                         will withstand the without loss of                                  design basis loads structural integrity and                        specified in the Design the                                              Description without safety-related                                  loss of structural functions.                                      integrity or the safety-related functions.
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and t he  safety-related functions.
3.3.00.02a.i.c The nuclear island         An inspection of the  A report exists which structures, including     nuclear island        reconciles deviations the critical sections     structures will be    during construction and listed in Table 3.3-7,     performed.            concludes that the as-are seismic Category I     Deviations from the  built structures in the and are designed and       design due to as-     non-radiologically constructed to            built conditions will controlled area of the withstand design basis    be analyzed for the   auxiliary building, loads as specified in      design basis loads. including the critical the Design Description,                         sections, conform to without loss of                                  the approved design structural integrity and                        and will withstand the the                                              design basis loads safety-related                                  specified in the Design functions.                                      Description without loss of structural integrity or the safety-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
15
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as
-built shield building structures, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety-related functions.
3.3.00.02a.i.c The nuclear island structures, including the critical sections listed in Table 3.3
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the  safety-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as
-built structures in the non-radiologically controlled area of the auxiliary building, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
-related functions.


16 ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.d The nuclear island structures, including the critical sections listed in Table 3.3
Inspections, ITAAC           Design Commitment                                 Acceptance Criteria Tests, Analysis 3.3.00.02a.i.d   The nuclear island         An inspection of the    A report exists which structures, including     nuclear island          reconciles deviations the critical sections     structures will be      during construction and listed in Table 3.3-7,     performed.              concludes that the as-are seismic Category I     Deviations from the    built structures in the and are designed and       design due to as-       radiologically controlled constructed to            built conditions will   area of the auxiliary withstand design basis    be analyzed for the     building, including the loads as specified in      design basis loads. critical sections, the Design Description,                           conform to the without loss of                                    approved design and structural integrity and                          will withstand the the                                                design basis loads safety-related                                    specified in the Design functions.                                        Description without loss of structural integrity or the safety-related functions.
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and t he  safety-related functions.
IR 99901419/2012-201 states:
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
The inspectors determined that Cives failed to establish and implement a program for inspection of activities affecting quality to verify conformance with the documented instructions, procedures, and drawings. Specifically, (1) Cives failed to adequately implement its inspection program to inspect stud welds on embedment APP-12S02-CE-PW908 for Vogtle Electric Generating Plant, Unit 3, which connects to stairs in Auxiliary Building Area 1, Wall P, west face, at an elevation of 66 feet 6 inches; and (2) Cives failed to test at least 1 out of every 100 studs welded by each operator as required by Westinghouse Specification APP-SS01-Z0-003, Revision 3, dated March 3, 2011, and the inspection plan entitled, Inspection Fabrication Plan No. 5200-01 for Embeds, Items, and Anchor Bolts, Revision 1, dated December 14, 2011. These issues were identified as Nonconformance (NON) 99901419-2012-201-03.
-built conditions will be analyzed for the design basis loads.
The NRC staff determined that the finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
A report exists which reconciles deviations during construction and concludes that the as
16
-built structures in the radiologically controlled area of the auxiliary building, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
: 8. Chicago Bridge & Iron (CB & I) Lake Charles / Docket No. 99901425
-related functions.
: a. Inspection Scope During the week from February 3-7, 2014, the U.S. NRC staff conducted an inspection at the Chicago Bridge & Iron Lake Charles (hereafter referred to as CB&I LC) facility in Lake Charles, LA. The purpose of the inspection was to evaluate CB&I LCs implementation of quality assurance activities associated with the fabrication and inspection of the Westinghouse Electric Company AP1000 reactor design of structural sub-modules for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901425/2014-201 (ADAMS Accession No. ML14072A315).
IR 99901419/2012
The lead for this inspection is Mr. Paul Prescott, who can be reached by phone at 301-415-3026 or via electronic mail at Paul.Prescott@nrc.gov.
-201 states:
: b. Findings and Observations IR 99901425/2014-201 contains one finding associated with the following ITAAC:
The inspectors determined that Cives failed to establish and implement a program for inspection of activities affecting quality to verify conformance with the documented instructions, procedures, and drawings.
ITAAC                 Design           Inspections, Tests,       Acceptance Commitment                Analysis               Criteria 3.3.00.02.a.i.a     The nuclear island       An inspection of the  A report exists which structures, including   nuclear island        reconciles deviations the critical sections   structures will be    during construction listed in Table 3.3-7,   performed.            and concludes that are seismic Category     Deviations from the  the as-built I and are designed       design due to as-     containment internal and constructed to      built conditions will structures, including withstand design        be analyzed for the   the critical sections, basis loads as          design basis loads. conform to the specified in the                              approved design and Design Description,                            will withstand the without loss of                                design basis loads structural integrity                          specified in the and the safety-                                Design Description related functions.                            without loss of structural integrity or the safety-related functions.
Specifically, (1) Cives failed to adequately implement its inspection program to inspect stud welds on embedment APP
17
-12S02-CE-PW908 for Vogtle Electric Generating Plant, Unit 3, which connects to stairs in Auxiliary Building Area 1, Wall P, west face, at an elevation of 66 feet 6 inches; and (2) Cives failed to test at least 1 out of every 100 studs welded by each operator as required by Westinghouse Specification APP-SS01-Z0-003, Revision 3, dated March 3, 2011, and the inspection plan entitled, "Inspection Fabrication Plan No. 5200
-01 for Embeds, Items, and Anchor Bolts," Revision 1, dated December 14, 2011.
These issues were identified as Nonconformance (NON) 99901419
-2012-201-03. The NRC staff determined that the finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as
-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety
-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
17 8. Chicago Bridge & Iron (CB & I) Lake Charles /
Docket No. 99901425
: a. Inspection Scope During the week from February 3
-7, 2014, the U.S. NRC staff conducted an inspection at the Chicago Bridge & Iron Lake Charles (hereafter referred to as CB&I LC) facility in Lake Charles, LA. The purpose of the inspection was to evaluate CB&I LC's implementation of quality assurance activities associated with the fabrication and inspection of the Westinghouse Electric Company AP1000 reactor design of structural sub-modules for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901425/2014
-201 (ADAMS Accession No.
ML14072A315).
The lead for this inspection is Mr. Paul Prescott, who can be reached by phone at 301-415-3026 or via electronic mail at Paul.Prescott@nrc.gov
. b. Findings and Observations IR 99901425/2014
-201 contains one finding associated with the following ITAAC: ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02.a.i.a The nuclear island structures, including the critical sections listed in Table 3.3
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the safety-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as
-built conditions will be analyzed for the design basis loads.
A report exists which reconciles deviations during construction and concludes that the as-built containment internal structures, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
-related functions.


18 ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.d The nuclear island structures, including the critical sections listed in Table 3.3
ITAAC                   Design           Inspections, Tests,       Acceptance Commitment                Analysis               Criteria 3.3.00.02a.i.d       The nuclear island       Inspection will be    A report exists which structures, including   conducted of the as-  reconciles deviations the critical sections   built piping as        during construction listed in Table 3.3-7,   documented in the      and concludes that are seismic Category     ASME design           the as-built I and are designed      reports.               structures in the and constructed to                              radiologically withstand design                                controlled area of basis loads as                                  the auxiliary building, specified in the                                including the critical Design Description,                            sections, conform to without loss of                                the approved design structural integrity                            and will withstand and the safety-                                the design basis related functions.                              loads specified in the Design Description without loss of structural integrity or the safety-related functions.
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the safety
IR 99901425/2014-201 states:
-related functions.
The NRC inspectors determined that CB&I LC failed to adequately implement measures to control materials, parts, or components which do not conform to requirements in order to prevent their inadvertent use or installation. Specifically, CB&I LC failed to correctly identify unresolved nonconformances on a safety-related sub-module being prepared to ship: one stud that had an incomplete weld was incorrectly located in the documentation; one stud that was identified on the documentation as being added and having incomplete weld did not appear to exist on the module; and one stud was documented as having an incomplete weld, but was actually missing. This item was identified as Nonconformance 99901425/2014-201-01.
Inspection will be conducted of the as
The NRC staff determined that the finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
-built piping as documented in the ASME design reports. A report exists which reconciles deviations during construction and concludes that the as-built structures in the radiologically controlled area of the auxiliary building, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
18
-related functions.
: 9. SMCI / Docket No. 99901439
IR 99901425/2014
: a. Inspection Scope During the period April 7-11, 2014, the U.S. NRC staff conducted an inspection at the Specialty Maintenance and Construction, Inc. (hereafter referred to as SMCI) facility in Lakeland, FL. The purpose of this inspection was evaluate SMCIs implementation of quality assurance activities associated with the fabrication of the remain-in-place steel formwork modules for concrete, in-containment refueling water storage tank wall and reactor vessel cavity modules for the Westinghouse Electric Company (WEC) AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901439/2014-201 (ADAMS Accession No. ML14121A433).
-201 states:
During the period June 8-12, 2015, the NRC staff conducted an inspection at the SMCI facility in Lakeland, FL. The purpose of this inspection was to evaluate SMCIs implementation of quality assurance activities associated with the fabrication of the embed plates for the CA-01 module (steam generator and refueling canal module) and CA-02 module (independent wall structure connecting the CA-01 and CA-03 module, where the CA-03 module is the in-containment refueling water storage tank module).
The NRC inspectors determined that CB&I LC failed to adequately implement measures to control materials, parts, or components which do not conform to requirements in order to prevent their inadvertent use or installation.
These are modules for the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901439/2015-201 (ADAMS Accession No. ML15175A446).
Specifically, CB&I LC failed to correctly identify unresolved nonconformances on a safety-related sub
The lead for the above inspections is Mr. Yamir Diaz-Castillo, who can be reached by phone at 301-415-2228 or via electronic mail at Yamir.Diaz-Castillo@nrc.gov.
-module being prepared to ship: one stud that had an incomplete weld was incorrectly located in the documentation; one stud that was identified on the documentation as being added and having incomplete weld did not appear to exist on the module; and one stud was documented as having an incomplete weld, but was actually missing.
: b. Findings and Observations IR 99901439/2014-201 contains one finding, and IR 99901439-2015-201 contains two findings associated with the following ITAAC:
This item was identified as Nonconformance 99901425/2014
Design            Inspections, ITAAC                                                          Acceptance Criteria Commitment          Tests, Analysis 3.3.00.02a.i.a    The nuclear island      An inspection of  A report exists which reconciles structures, including    the nuclear        deviations during construction the critical sections    island structures  and concludes that the as-built listed in Table 3.3-7,  will be            containment internal structures, are seismic Category    performed.        including the critical sections, I and are designed      Deviations from    conform to the approved design and constructed to      the design due    and will withstand the design withstand design        to as-built        basis loads specified in the basis loads as          conditions will be Design Description without loss specified in the        analyzed for the  of structural integrity or the Design Description,      design basis      safety-related functions.
-201-01. The NRC staff determined that the finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as
without loss of          loads.
-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety
structural integrity and the safety-related functions.
-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
19


19 9. SMCI / Docket No. 99901439
IR 99901439/2014-201 states:
: a. Inspection Scope During the period April 7-11, 2014, the U.S. NRC staff conducted an inspection at the Specialty Maintenance and Construction, Inc. (hereafter referred to as SMCI) facility in Lakeland, FL. The purpose of this inspection was evaluate SMCI's implementation of quality assurance activities associated with the fabrication of the remain
The NRC inspectors determined that SMCI failed to qualify a welding procedure in accordance with WEC specification APP-VW20-ZO-023. Specifically, SMCI welding procedure qualification record (PQR) 1015-Partial Joint Penetration (PJP), lists the results of the ferrite testing of the test weld root as 73 percent, which is outside of the 35-65 percent ferrite range acceptance criteria specified by WEC in APP-VW20-ZO-023. PQR 1015-PJP is a supporting PQR for welding procedure specification (WPS) number 1015. WPS 1015 is being used to perform welding on the in-containment refueling water storage tank modules for the AP1000 reactor design. This item was identified as Nonconformance 99901439/2014-201-01.
-in-place steel formwork modules for concrete, in
IR 99901439/2015-201 states:
-containment refueling water storage tank wall and reactor vessel cavity modules for the Westinghouse Electric Company (WEC) AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901439/2014
The NRC inspectors determined that SMCI failed to transfer all the pertinent design requirements into the applicable instructions and failed to inspect welds in accordance with the applicable travelers and design specification drawings.
-201 (ADAMS Accession No. ML14121A433).
Specifically, (1) SMCI did not adequately incorporate several general notes on NDE requirements from WEC design specifications drawings into all the applicable travelers. These general notes would require visual examination (VT),
During the period June 8
and magnetic particle examination (MT) or liquid penetrant (PT) examination of both the reinforcing fillet weld and the partial joint penetration (PJP). By not correctly transferring nondestructive examination requirements to the SMCI travelers, partial penetration welds did not receive the required surface examinations required by the WEC design drawings; and (2) SMCI only performed VT and MT examination of the reinforcing fillet weld that is applied over the PJP, and did not perform a VT and MT examination of the PJP as required by several general notes from design specification drawing APP-GW-S9-105. Not inspecting the PJP welds leaves the quality of welds to be indeterminate, and therefore affects how these welds would meet their design stress requirements and would perform their intended safety function. This item was identified as Nonconformance 99901439/2015-201-01.
-12, 2015, the NRC staff conducted an inspection at the SMCI facility in Lakeland, FL.
The NRC inspectors determined SMCI failed to control welding consumable filler metal in accordance with applicable procedures and criteria. Specifically, (1)
The purpose of this inspection was to evaluate SMCI's implementation of quality assurance activities associated with the fabrication of the embed plates for the CA
SMCI did not record on form WCIL-001 the weld filler metal that was issued for the time period of June 28, 2014, through July 11, 2014, as required by the applicable procedure; and (2) During a review of traveler 926-CA01-00774, the NRC inspection team noted that a welder used weld filler metal to weld the beam seat that was not the weld filler metal he was issued and required to use. The use of the correct weld filler metal for welding the beam seat was not adequately controlled as required by the applicable procedure. This item was identified as Nonconformance 99901439/2015-201-02.
-01 module (steam generator and refueling canal module) and CA-02 module (independent wall structure connecting the CA
The NRC staff determined that the above findings represent ITAAC findings because they are material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 3.3.00.02a.i.a in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other 20
-01 and CA-03 module, where the CA
-03 module is the in
-containment refueling water storage tank module). These are modules for the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901439/2015
-201 (ADAMS Accession No. ML15175A446).
The lead for the above inspections is Mr. Yamir Diaz
-Castillo, who can be reached by phone at 301
-415-2228 or via electronic mail at Yamir.Diaz
-Castillo@nrc.gov
. b. Findings and Observations IR 99901439/201 4-201 contains one finding, and IR 99901439-2015-201 contains two findings associated with the following ITAAC:
ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.a The nuclear island structures, including the critical sections listed in Table 3.3
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the safety
-related functions.
An inspection of the nuclear island structures will be performed. Deviations from the design due to as-built conditions will be analyzed for the design basis loads. A report exists which reconciles deviations during construction and concludes that the as
-built containment internal structures, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety-related functions.


20 IR 99901439/2014
safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
-201 states:
: 10. Oregon Iron Works / Docket Nos. 99901448/1449
The NRC inspectors determined that SMCI failed to qualify a welding procedure in accordance with WEC specification APP
: a. Inspection Scope During the period of September 22-26, 2014, the U.S. Nuclear Regulatory Commission (NRC) staff conducted an inspection at the Oregon Iron Works, Inc. (hereafter referred to as OIW) facilities in Clackamas, OR and Vancouver, WA. The purpose of the inspection was to evaluate OIWs implementation of quality assurance activities associated with the fabrication and inspection of the CA20 Auxiliary Building Modules for the Westinghouse Electric Company (WEC) AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901448/2014-201 / 999901449/2014-201 (ADAMS Accession No. ML14308A463).
-VW20-ZO-023. Specifically, SMCI welding procedure qualification record (PQR) 1015
The lead for this inspection is Mr. Jonathan Ortega-Luciano, who can be reached by phone at 301-415-1159 or via electronic mail at Jonathan.Ortega-Luciano@nrc.gov.
-Partial Joint Penetration (PJP), lists the results of the ferrite testing of the test weld root as 73 percent, which is outside of the 35
: b. Findings and Observations IR 99901448/2017-201 / 999901449/2014-201 contains one finding associated with the following ITAAC:
-65 percent ferrite range acceptance criteria specified by WEC in APP
Inspections, ITAAC         Design Commitment                             Acceptance Criteria Tests, Analysis 3.3.00.02a.i.d The nuclear island         Inspection will be A report exists which structures, including     conducted of the  reconciles deviations the critical sections     as-built piping as during construction listed in Table 3.3-7,   documented in the and concludes that are seismic Category      ASME design        the as-built structures I and are designed        reports.          in the radiologically and constructed to                          controlled area of the withstand design                            auxiliary building, basis loads as                              including the critical specified in the                            sections, conform to Design Description,                          the approved design without loss of                              and will withstand the structural integrity and                    design basis loads the safety-related                          specified in the functions.                                  Design Description without loss of structural integrity or the safety-related functions.
-VW20-ZO-023. PQR 1015-PJP is a supporting PQR for welding procedure specification (WPS) number 1015.
21
WPS 1015 is being used to perform welding on the in
-containment refueling water storage tank modules for the AP1000 reactor design.
This item was identified as Nonconformance 99901439/2014
-201-01. IR 99901439/2015
-201 states:
The NRC inspectors determined that SMCI failed to transfer all the pertinent design requirements into the applicable instructions and failed to inspect welds in accordance with the applicable travelers and design specification drawings.
Specifically, (1) SMCI did not adequately incorporate several general notes on NDE requirements from WEC design specifications drawings into all the applicable travelers.
These general notes would require visual examination (VT), and magnetic particle examination (MT) or liquid penetrant (PT) examination of both the reinforcing fillet weld and the partial joint penetration (PJP).
By not correctly transferring nondestructive examination requirements to the SMCI travelers, partial penetration welds did not receive the required surface examinations required by the WEC design drawings; and (2) SMCI only performed VT and MT examination of the reinforcing fillet weld that is applied over the PJP, and did not perform a VT and MT examination of the PJP as required by several general notes from design specification drawing APP
-GW-S9-105. Not inspecting the PJP welds leaves the quality of welds to be indeterminate, and therefore affects how these welds would meet their design stress requirements and would perform their intended safety function.
This item was identified as Nonconformance 99901439/2015
-201-01. The NRC inspectors determined SMCI failed to control welding consumable filler metal in accordance with applicable procedures and criteria.
Specifically, (1) SMCI did not record on form WCIL
-001 the weld filler metal that was issued for the time period of June 28, 2014, through July 11, 2014, as required by the applicable procedure; and (2) During a review of traveler 926
-CA01-00774, the NRC inspection team noted that a welder used weld filler metal to weld the beam seat that was not the weld filler metal he was issued and required to use.
The use of the correct weld filler metal for welding the beam seat was not adequately controlled as required by the applicable procedure.
This item was identified as Nonconformance 99901439/2015
-201-02. The NRC staff determined that the above findings represent ITAAC findings because they are material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 3.3.00.02a.i.a in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as
-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other 21 safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee. 10. Oregon Iron Works / Docket Nos. 99901448/1449
: a. Inspection Scope During the period of September 22
-26, 2014, the U.S. Nuclear Regulatory Commission (NRC) staff conducted an inspection at the Oregon Iron Works, Inc. (hereafter referred to as OIW) facilities in Clackamas, OR and Vancouver, WA. The purpose of the inspection was to evaluate OIW's implementation of quality assurance activities associated with the fabrication and inspection of the CA20 Auxiliary Building Modules for the Westinghouse Electric Company (WEC) AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901448/2014-201 / 999901449/2014
-201 (ADAMS Accession No. ML14308A463).
The lead for this inspection is Mr. Jonathan Ortega
-Luciano, who can be reached by phone at 301
-415-1159 or via electronic mail at Jonathan.Ortega
-Luciano@nrc.gov
. b. Findings and Observations IR 99901448/2017
-201 / 999901449/2014
-201 contains one finding associated with the following ITAAC: ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 3.3.00.02a.i.d The nuclear island structures, including the critical sections listed in Table 3.3
-7, are seismic Category I and are designed and constructed to withstand design basis loads as specified in the Design Description, without loss of structural integrity and the safety
-related functions.
Inspection will be conducted of the as-built piping as documented in the ASME design reports. A report exists which reconciles deviations during construction and concludes that the as-built structures in the radiologically controlled area of the auxiliary building, including the critical sections, conform to the approved design and will withstand the design basis loads specified in the Design Description without loss of structural integrity or the safety
-related functions.


22 IR 99901448/2014
IR 99901448/2014-201 / 999901449/2014-201 states:
-201 / 999901449/2014
The NRC inspectors determined that OIW failed to ensure the selection and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components. Additionally, OIW failed to establish appropriate measures that included provisions for source evaluation of subcontractors. This item was identified as Nonconformances 99901448/2014-201-02 and 99901449/2014-201-02.
-201 states:
The NRC staff determined that the above finding is an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 3.3.00.02a.i.d, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of this ITAAC requires that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
The NRC inspectors determined that OIW failed to ensure the selection and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety
: 11. WECTEC/ Docket No. 99901467
-related functions of the structures, systems, and components.
: a. Inspection Scope During the period from November 14-18, 2016, the U.S. NRC conducted an inspection at the Westinghouse/WECTEC facility in Charlotte, North Carolina. The purpose of the inspection was to review implementation of Westinghouses processes for transferring the design requirements contained in the AP1000 Design Control Document into detailed engineering, procurement, and construction documents, consistent with NRC requirements. The vendor inspection activities were documented in Inspection Report (IR) 99901467/2016-201 (ADAMS Accession No. ML17013A658).
Additionally, OIW failed to establish appropriate measures that included provisions for source evaluation of subcontractors.
The lead for this inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.jacobson@nrc.gov.
This item was identified as Nonconformances 99901448/2014
22
-201-02 and 99901449/2014
: b. Findings and Observations IR 99901467/2016-201 contains one finding associated with the following ITAAC:
-201-02. The NRC staff determined that the above finding is an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 3.3.00.02a.i.d, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of th is ITAAC require s that all construction deviations be reconciled to verify that the as
ITAAC                                   Inspections, Design Tests,           Acceptance Criteria Commitment Analysis 2.6.03.08       Circuit breakers       Analyses for      Analyses for the as-built IDS and fuses              the as-built IDS dc electrical distribution installed in IDS      dc electrical    system exist and conclude battery, battery      distribution      that the analyzed fault charger, dc            system to        currents do not exceed the distribution panel,    determine fault  interrupt capacity of circuit and MCC circuits      currents will be  breakers and fuses in the are rated to          performed.        battery, battery charger, dc interrupt fault                          distribution panel, and MCC currents.                                circuits, as determined by their nameplate ratings.
-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety
IR 99901467/2016-201 states, in part, that:
-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.
The inspectors identified that Document CDI 3398 does not list the circuit breakers interrupting current rating as a critical characteristic. Consequently, no specific actions were taken as part of the dedication process (or as part of any other Westinghouse process) to identify and verify the validity of the breakers interrupting current ratings.
: 11. WECTEC/ Docket No. 99901 467  a. Inspection Scope During the period from November 14
The inspectors noted the interrupting current capacity of these components is a critical element of the IDS design and is also specifically called out in ITAAC 2.6.03.08. While Westinghouse performed commercial grade surveys of the commercial manufacturer, as described in Document CDI 3398, these surveys did not specifically evaluate the adequacy of the methods used by the commercial manufacturer to establish the interrupting current ratings, or whether sufficient quality controls were implemented at facilities utilized to test the interrupting current capacity of the breakers. While not specifically reviewed during this inspection, Westinghouse indicated the concern raised by the inspectors would also apply to fuses, as their interrupting capacity was also not captured via the dedication process.
-18, 2016, the U.S. NRC conducted an inspection at the Westinghouse/WECTEC facility in Charlotte, North Carolina.
ITAAC 2.6.03.08 states, Circuit breakers and fuses installed in IDS battery, battery charger, dc distribution panel, and MCC circuits are rated to interrupt fault currents.
The purpose of the inspection was to review implementation of Westinghouse's processes for transferring the design requirements contained in the AP1000 Design Control Document into detailed engineering, procurement, and construction documents, consistent with NRC requirements. The vendor inspection activities were documented in Inspection Report (IR) 99901467/2016
The acceptance criteria for this ITAAC states, Analyses for the as-built IDS dc electrical distribution system exist and conclude that the analyzed fault currents do not exceed the interrupt capacity of circuit breakers and fuses in the battery, battery charger, dc distribution panel, and MCC circuits, as determined by their nameplate ratings.
-201 (ADAMS Accession No. ML17013A658).
Contrary to the above, prior to November 18, 2016, Westinghouse failed to identify and verify the adequacy of circuit breaker and fuse interrupting current ratings as a critical characteristic, as part of its commercial grade dedication process. This issue is identified as Nonconformance 99901467/2016-201-01.
The lead for this inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.jacobson@nrc.gov
The issue is material to ITAAC 2.6.03.08 because if the interrupting ratings for the circuit breakers and fuses cannot be verified, the analyses which compares the available fault currents to those ratings would be invalid, and if left uncorrected, the licensee may not be able to successfully complete the ITAAC.
.
23}}
23 b. Findings and Observations IR 99901467/2016
-201 contains one finding associated with the following ITAAC:
ITAAC Design Commitment Inspections, Tests, Analysis Acceptance Criteria 2.6.03.08 Circuit breakers and fuses installed in IDS battery, battery charger, dc distribution panel, and MCC circuits are rated to interrupt fault currents. Analyses for the as-built IDS dc electrical distribution system to determine fault currents will be performed.
Analyses for the as
-built IDS dc electrical distribution system exist and conclude that the analyzed fault currents do not exceed the interrupt capacity of circuit breakers and fuses in the battery, battery charger, dc distribution panel, and MCC circuits, as determined by their nameplate ratings.
IR 99901467/2016-201 states, in part, that
The inspectors identified that Document CDI 3398 does not list the circuit breakers' interrupting current rating as a critical characteristic.
Consequently, no specific actions were taken as part of the dedication process (or as part of any other Westinghouse process) to identify and verify the validity of the breakers' interrupting current ratings. The inspectors noted the interrupting current capacity of these components is a critical element of the IDS design and is also specifically called out in ITAAC 2.6.03.08.
While Westinghouse performed commercial grade surveys of the commercial manufacturer, as described in Document CDI 3398, these surveys did not specifically evaluate the adequacy of the methods used by the commercial manufacturer to establish the interrupting current ratings, or whether sufficient quality controls were implemented at facilities utilized to test the interrupting current capacity of the breakers.
While not specifically reviewed during this inspection, Westinghouse indicated the concern raised by the inspectors would also apply to fuses, as their interrupting capacity was also not captured via the dedication process.
ITAAC 2.6.03.08 states, "Circuit breakers and fuses installed in IDS battery, battery charger, dc distribution panel, and MCC circuits are rated to interrupt fault currents."
The acceptance criteria for this ITAAC states, "Analyses for the as
-built IDS dc electrical distribution system exist and conclude that the analyzed fault currents do not exceed the interrupt capacity of circuit breakers and fuses in the battery, battery charger, dc distribution panel, and MCC circuits, as determined by their nameplate ratings."
Contrary to the above, prior to November 18, 2016, Westinghouse failed to identify and verify the adequacy of circuit breaker and fuse interrupting current ratings as a critical characteristic, as part of its commercial grade dedication process.
This issue is identified as Nonconformance 99901467/2016
-201-01. The issue is material to ITAAC 2.6.03.08 because if the interrupting ratings for the circuit breakers and fuses cannot be verified, the analyses which compares the available fault currents to those ratings would be invalid, and if left uncorrected, the licensee may not be able to successfully complete the ITAAC
.}}

Latest revision as of 00:55, 21 October 2019

Summary of Nuclear Regulatory Commission Vendor Inspections Affecting Inspections, Tests, Analyses, and Acceptance Criteria
ML18152B785
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/12/2018
From: William Jones
Division of Construction Inspection and Operational Programs
To: Yox M
Southern Nuclear Operating Co
O'Bryan P, NRO/DCIP
References
Download: ML18152B785 (32)


Text

.October 12, 2018 Mr. Michael Yox Regulatory Affairs Director Southern Nuclear Operating Company 7835 River Road, Bldg. 140, Vogtle 3&4 Waynesboro, GA 30830

SUBJECT:

SUMMARY

OF NUCLEAR REGULATORY COMMISSION VENDOR INSPECTIONS AFFECTING INSPECTIONS, TESTS, ANALYSES, AND ACCEPTANCE CRITERIA

Dear Mr. Yox:

This letter is to inform Southern Nuclear Operating Company (SNC) of U.S. Nuclear Regulatory Commission (NRC) vendor inspection findings that are material to the acceptance criteria in the inspections, tests, analyses, and acceptance criteria (ITAAC) for Vogtle Units 3 and 4 (thereafter abbreviated as material to ITAAC). The NRC performed an audit to account for potential ITAAC issues. Attached are the results of the audit and a summary of all vendor inspection findings material to ITAAC.

As a result of the audit, the NRC identified additional eighteen vendor inspection findings that are material to ITAAC (see Enclosure 2). The NRCs Enforcement Manual Agencywide Document Access and Management System (ADAMS) Accession No. ML18018B134 provides guidance on closing findings that are material to the acceptance criteria of an ITAAC. The staff conducted reviews of these findings to ensure that adequate corrective actions have been developed and implemented such that the deficiency will not prevent the ITAAC from being successfully completed. Four findings remain open pending further NRC inspection (see ). Although the NRC is planning to review the resolution of these items, you do not need to delay your ITAAC closure activities due to NRC inspection schedules.

The NRC expects that SNC will discuss the additional findings in ITAAC closure notifications (ICNs), with the following exception: SNC has already submitted ICNs for Vogtle Units 3 and 4 for an ITAAC associated with one of the ITAAC-related findings identified during the audit (ADAMS Accession Nos. ML17143A239 and ML17143A244). These ICNs do not include a reference to the finding that was identified during the audit. However, the NRC staff analyzed this finding and determined that SNC does not need to update the ICNs for that finding because corrective actions for the finding have been implemented and the NRC has closed the finding.

This finding is designated NON 99901404/2011-201-03 and was, prior to being closed, material to Vogtle Units 3 and 4 ITAAC 2.5.02.14.

The NRCs Vendor Inspection Program verifies effective licensee oversight of the supply chain through inspections of a sample of vendors. Licensees are responsible for vendor oversight and vendor performance. It is the agencys expectation that licensees consider NRC vendor inspection findings as potential weaknesses in their procurement programs. Consistent with the

M.Yox guidance in the NRC-endorsed Nuclear Energy Institution (NEI) 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, licensees should adequately discuss associated ITAAC findings (including those identified through vendor inspections) in their ITAAC notifications under 10 CFR 52.99(c)(1), (c)(2), and (c)(3). is a summary of all findings that, as of the issuance date of this letter, are material to the acceptance criteria of ITAAC. Some vendor findings listed in Enclosure 1 were not identified as having errors, but are included in Enclosure 1 so that SNC has a complete list of vendor findings affecting ITAAC. Enclosure 2 lists the vendor inspection findings that were not previously identified as findings material to the acceptance criteria of ITAAC. Please contact Philip OBryan at Phil.OBryan@nrc.gov, or (910) 617-2469, if you have any questions or need assistance regarding these matters.

Sincerely,

/RA/

William B. Jones, Acting Director Division of Construction Inspection and Operational Programs Office of New Reactors Docket Nos.: 05200025 05200026

Enclosures:

1. Vendor Findings Material to the Acceptance Criteria of ITAAC
2. Vendor Inspection Findings Not Previously Identified as Material to the Acceptance Criteria of ITAAC

M.Yox

SUBJECT:

SUMMARY

OF NUCLEAR REGULATORY COMMISSION VENDOR INSPECTIONS AFFECTING INSPECTIONS, TESTS, ANALYSES, AND ACCEPTANCE CRITERIA Dated: October 12, 2018 DISTRIBUTION:

Public CPatel JJimenez ASakadales NCoovert JBurke VHall NRO_DCIP_QVIB-1 Distribution NRO_DCIP_QVIB-2 Distribution DCIP Branch Chiefs AP1000 CONTACTS ADAMS Accession No.: ML18152B785 *via e-mail NRO-002 OFC NRO/DCIP NRO/DCIP NRO/DCIP NAME PKrohn POBryan KKavanagh DATE 9/26/18* 9/26/18* 9/27/18*

OFC NRO/DCIP NRO/DCIP RII/DCO NAME ARivera-Varona (BGreen for) OAyegbusi SWalker (VHall for)

DATE 9/28/18* 9/27/18* 10/5/18*

OFC OGC NRO/DCIP NAME MASpencer WJones DATE 9/27/18* 10/12/18 OFFICIAL RECORD COPY

Enclosure 1: Vendor Findings Material to the Acceptance Criteria of ITAAC Vendor / Inspection Finding Affected Issues Identified in NRC Audit of Vendor Status Docket Report (IR) Number(s) ITAAC Inspection Findings Number and ADAMS Accession Number SPX Copes- 2012-201 01 2.1.02.12a.iv IR 2012-201 does not clearly link the finding to the Closed in Vulcan ML12158A154 2.1.02.12a.v applicable ITAAC. The ITAAC are correctly IR 2015-201 99900080 2.2.03.12a.i identified in the 2015 NRC summary of vendor (ML15210A806) 2.2.03.12a.ii ITAAC findings (ML15219A276).

2013-201 01 2.1.02.12a.iv 2.1.02.12a.iv is incorrectly listed as 2.2.02.a.iv in the Closed in ML13302B397 2.2.03.12a.i body of the inspection report. The ITAAC are listed IR 2015-202 correctly in the ITAAC table in the back of the (ML16027A153) report. The ITAAC are also listed correctly in the 2014 NRC summary of vendor ITAAC findings (ML14111A071).

02 2.1.02.12a.v 2.1.02.12a.v is incorrectly listed as 2.2.02.12a.v in Closed in 2.2.03.12a.ii the 2014 NRC summary of vendor ITAAC findings IR 2015-202 (ML14111A071). The finding was closed in IR (ML16027A153) 2015-202 but was not listed as closed in the 2015 NRC summary of vendor ITAAC findings.

Enclosure 1

Vendor / Inspection Finding Affected Issues Identified in NRC Audit of Vendor Status Docket Report (IR) Number(s) ITAAC Inspection Findings Number and ADAMS Accession Number Westinghouse, 2011-201 02 2.2.03.02a IR 2011-201 does not clearly link this finding to the Closed in NRC Cranberry ML112440588 2.2.03.02b applicable ITAAC. The 2013 NRC summary of memo dated 99900404 vendor ITAAC findings (ML13156A136) incorrectly December 18, lists the finding number as 99900404/2012-202-02. 2017 The 2016 NRC summary of ITAAC findings (ML17346A937)

(ML16280A303) correctly lists the finding number and the applicable ITAAC.

05 2.2.03.08c.i.03 IR 2011-201 does not clearly link this finding to the Open applicable ITAAC. The 2013 NRC summary of vendor ITAAC findings (ML13156A136) correctly lists ITAAC 2.2.03.08c.i.03 as applicable. The 2016 NRC summary of vendor ITAAC findings (ML16280A303) incorrectly lists ITAAC 2.2.03.08c.i.04 as applicable.

2012-201 01 2.1.02.07a.i IR 2012-201 does not clearly identify the applicable Closed in IR ML12128A072 2.2.03.07a.i ITAAC. The finding is closed in the 2013 NRC 2016-204 summary of vendor ITAAC findings (ML13156A136) (ML16307A159) but lists the incorrect ITAAC. IR 2016-204 also includes a closure discussion of this finding.

02 and 03 2.1.02.07a.i IR 2012-201 does not clearly identify the applicable Closed in IR 2.2.03.07a.i ITAAC. IR 2012-202 closes the findings but lists the 2012-202 incorrect ITAAC. (ML12313A461) 2014-201 01 and 02 2.5.02.14 None Closed in IR ML14058A995 2016-201 (ML15363A360) 2015-204 01 2.5.02.07a None Closed in IR ML15113B277 2.5.02.07e 2016-209 (ML17123A085) 02 and 03 2.5.02.03 None Closed in IR 2016-202 (ML16237A320) 2

Vendor / Inspection Finding Affected Issues Identified in NRC Audit of Vendor Status Docket Report (IR) Number(s) ITAAC Inspection Findings Number and ADAMS Accession Number Valcor 2017-201 01 2.1.02.05a.i None Open 99900728 ML17311A267 Wyle Labs 2012-201 01 and 04 2.1.02.12a.i IR 2012-201 lists incorrect ITAAC numbers. The Closed in IR 99900905 ML12242A459 2.2.01.11a.i 2013 NRC summary of vendor ITAAC findings 2013-201 2.2.03.12a.i (ML13156A136) lists 4 of the ITAAC numbers (ML14016A447) 2.3.02.11a.i correctly but does not list ITAAC 2.2.03.12a.i as being 2.3.06.12a.i affected.

National 2015-201 01 2.1.02.07a.i IR 2015-201 does not clearly state that finding 01 is Closed in NRC Technical ML15078A379 2.2.03.07a.i material to the ITAAC, nor does any subsequent NRC memorandum Systems, correspondence to SNC. dated April 27, Huntsville 2015-202 01 2.2.03.12a.i IR 2015-202 does not clearly state that finding 01 is 2018 99900905 ML15152A080 material to the ITAAC, nor does any subsequent NRC (ML18102B171) correspondence to SNC.

Westinghouse, 2012-201 03, 04, and 2.5.01.03d IR 2012-201 does not clearly state that the findings Closed in IR New Stanton ML12131A263 05 are material to the ITAAC. The 2013 NRC summary 2013-201 99901043 of vendor ITAAC findings (ML13156A136) correctly (ML13318A689) lists the applicable ITAAC.

3

Vendor / Inspection Finding Affected Issues Identified in NRC Audit of Vendor Status Docket Report (IR) Number(s) ITAAC Inspection Findings Number and ADAMS Accession Number Enertech 2012-201 02 None IR 2012-201 does not identify this finding as material Closed in NRC 99901377 ML12306A385 to ITAAC. The 2013 NRC summary of vendor ITAAC memorandum findings (ML13156A136) incorrectly lists this finding dated January as material to ITAAC 2.2.03.05a.ii and 2.2.03.02a. In 5, 2017 an NRC memorandum dated January 5, 2017 (ML16357A724)

(ML16357A724), this finding was listed as material to an additional ITAAC (2.2.03.03a). This finding is not material to ITAAC.

03 None IR 2012-201 does not identify this finding as material Closed in NRC to ITAAC. The 2013 NRC summary of vendor ITAAC memorandum findings (ML13156A136) incorrectly lists this finding dated January as material to ITAAC 2.2.03.04a. This finding is not 5, 2017 material to ITAAC. (ML16357A724)

CS Innovations 2011-201 03 and 04 2.5.02.14 IR 2011-201 does not clearly state that the findings Closed in IR 99901404 ML111890005 are material to the ITAAC, nor does any subsequent 9990404/2014-NRC correspondence to SNC. 203 (ML14262A351)

Obayashi 2011-201 03 3.3.00.02a.i.a IR 2011-201 does not clearly state that the finding is Closed in NRC Corporation ML11286A106 3.3.00.02a.i.b material to the ITAAC, nor does any subsequent NRC memorandum 99901409 3.3.00.02a.i.c correspondence to SNC. dated July 6, 3.3.00.02a.i.d 2018 (ML18186A573)

Clark 2012-201 02 2.2.01.05.ii IR 2012-201 does not clearly link the finding to the Closed in NRC Dynamics ML12108A097 2.2.02.05a.ii applicable ITAAC. The 2013 NRC summary of memorandum 99901412 2.2.05.05a.ii vendor ITAAC findings (ML13156A136) correctly dated January 2.3.02.05.ii identifies the applicable ITAAC. 5, 2017 2.3.07.05.ii (ML16357A725) 2.7.01.05.ii 4

Vendor / Inspection Finding Affected Issues Identified in NRC Audit of Vendor Status Docket Report (IR) Number(s) ITAAC Inspection Findings Number and ADAMS Accession Number Kinectrics 2012-201 01 and 02 2.2.01.05.ii IR 2012-201 does not clearly state that the findings Closed in IR 99901415 ML12179A413 2.2.01.06a.i are material to the ITAAC, nor does any subsequent 2015-201 NRC correspondence to SNC. (ML15148A419)

Cives Steel 2012-201 03 3.3.00.02a.i.a IR 2012-201 does not clearly state that the finding is Closed in NRC Company ML13042A397 3.3.00.02a.i.b material to the ITAAC, nor does any subsequent NRC memorandum 99901419 3.3.00.02a.i.c correspondence to SNC. dated May 11, 3.3.00.02a.i.d 2018 (ML18131A260)

CB & I 2014-201 01 3.3.00.02a.i.a IR 2014-201 does not clearly state that the finding is Closed in NRC Lake Charles ML14072A315 3.3.00.02a.i.d material to the ITAAC, nor does any subsequent NRC memorandum 99901425 correspondence to SNC. dated April 12, 2018 (ML18101A168)

Pentair 2013-201 01 2.1.02.02a IR 2013-201 and the 2014 NRC summary of vendor Closed in IR 99901431 ML13212A265 2.1.02.05a.ii ITAAC findings (ML14111A071) list the four 2014-201 2.2.03.02a applicable ITAAC, but also incorrectly include ITAAC (ML14073A652) 2.2.03.05a.ii 2.1.02.08a.ii. This finding is not material to ITAAC 2.1.02.08a.ii.

5

Vendor / Report Finding Affected Issues Identified in NRC Audit of Vendor Status Docket Number and Number(s) ITAAC Inspection Findings ADAMS Accession Number SMCI 2014-201 01 3.3.00.02a.i.a IR 2014-201 does not clearly state that the finding is Closed in IR 99901439 ML14121A433 material to the ITAAC, nor does any subsequent NRC 2015-201 correspondence to SNC. (ML15175A446) 2015-201 01 and 02 3.3.00.02a.i.a IR 2015-201 does not clearly state that the findings Closed in NRC ML15175A446 are material to the ITAAC, nor does any subsequent memorandum NRC correspondence to SNC. dated April 11, 2018 (ML18100A857)

Curtis Wright 2014-201 03 2.1.02.07a.i None Open Qualtech ML14231B268 2.2.03.07a.i 99901441 Oregon Iron 2014-201 02 3.3.00.02a.i.d IR 2014-201 does not clearly state that the finding is Closed in Vigor Works ML14308A463 material to the ITAAC, nor does any subsequent NRC IR 2017-201 99901448 correspondence to SNC. (ML17226A340) 99901449 WECTEC 2016-201 01 2.6.03.08 None Open 99901467 ML17013A658 6

Enclosure 2: Vendor Inspection Findings Not Previously Identified as Material to the Acceptance Criteria of ITAAC

1. Westinghouse, Cranberry/ Docket 99900404
a. Inspection Scope During the period of March 26 to 30, 2012, the U.S. Nuclear Regulatory Commission (NRC) conducted an inspection at the Westinghouse Electric Company (WEC) facility in Cranberry Township, PA. The purpose of the technically-focused inspection was to review implementation of WECs quality assurance program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, and 10 CFR Part 21, Reporting of Defects and Noncompliance. This inspection specifically evaluated the quality assurance program as it pertains to WECs development of test requirements and specifications for the performance of qualification and functional testing for components to be supplied as part of the AP1000 design. The vendor inspection activities were documented in Inspection Report (IR) 99900404/2012-201 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12128A072).

The lead for the abovementioned inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov.

b. Findings and Observations Inspection Report 99900404/2012-201 contains three findings associated with the following inspections, tests, analyses, and acceptance criteria (ITAAC):

Design Inspections, Tests, Acceptance Criteria ITAAC Commitment Analysis 2.1.02.07a.i The Class 1E Type tests, A report exists and equipment identified analyses, or a concludes that the in Table 2.1.2-1 as combination of type Class 1E equipment being qualified for a tests and analyses identified in Table harsh environment will be performed on 2.1.2-1 as being can withstand the Class 1E equipment qualified for a harsh environmental located in a harsh environment can conditions that would environment. withstand the exist before, during, environmental and following a conditions that would design basis exist before, during, accident without loss and following a of safety function for design basis the time required to accident without loss perform the safety of safety function for function. the time required to perform the safety function.

Enclosure 2

Design Inspections, Tests, Acceptance Criteria ITAAC Commitment Analysis 2.2.03.07a.i The Class 1E Type tests, A report exists and equipment identified analyses, or a concludes that the in Table 2.2.3-1 as combination of type Class 1E equipment being qualified for a tests and analyses identified in Table harsh environment will be performed on 2.2.3-1 as being can withstand the Class 1E equipment qualified for a harsh environmental located in a harsh environment can conditions that would environment. withstand the exist before, during, environmental and following a conditions that would design basis exist before, during, accident without loss and following a of safety function for design basis the time required to accident without loss perform the safety of safety function for function. the time required to perform the safety function.

Inspection Report Finding 99900404/2012-201-01 states, in part, that:

WEC failed to verify the adequacy of certain design features and include the most adverse design conditions in the test program for performing functional testing of the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012-201-01.

This finding that the most adverse conditions were not tested during environmental qualification affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.

Inspection Report Finding 99900404/2012-201-02 states:

WEC did not identify design interfaces sufficient to allow for the translation of the design basis into specifications. Specifically, APP-GW-J4-072 Interface Specification for Squib Valve Controller, Revision 1, did not include the full range of temperatures that need to be considered when sizing the field run cable/connector systems located between the Plant Monitoring and Protection System, the Diverse Actuation System, and the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012-201-02.

This finding affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist 2

before, during and following a design basis accident for the time required to perform the safety function.

Inspection Report Finding 99900404/2012-201-03 states:

WEC did not establish measures necessary to ensure that the design basis for the Diverse Actuation System was correctly translated into specifications, drawings, and instructions. Specifically, WEC did not perform a documented calculation or analysis to justify the selection of resistance values contained in APP-GW-J4-072, Interface Specification for Squib Valve Controller, Revision 1, for the field run cabling located between the Diverse Actuation System and the squib valve actuators. This issue has been identified as Nonconformance 99900404/2012-201-03.

This finding affects the ITAAC listed in the table above because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.

2. Valcor Engineering Corporation/Docket No. 99900728
a. Inspection Scope During the period of October 9-12, 2017, the U.S. NRC staff conducted an inspection at the Valcor Engineering Corporations facility (hereafter referred to as Valcor) facility in Springfield, NJ. The purpose of this limited-scope routine inspection was to assess Valcors compliance with provisions of Title 10 of the Code of Federal Regulations (10 CFR) Part 21, Reporting of Defects and Noncompliance, and selected portions of Appendix B, Quality Assurance Program Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to 10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities. This inspection specifically evaluated Valcors implementation of the quality activities associated with the design, fabrication, and testing of the solenoid valves and replacement valve parts for the Westinghouse Electric Company AP1000 reactor design and for the domestic operating reactors. The vendor inspection activities were documented in Inspection Report (IR) 99900728/I-2017-201 (ADAMS Accession No. ML17311A267).

The lead for this inspection is Mr. Yamir Diaz-Castillo, who can be reached by phone at 301-415-2228 or via electronic mail at Yamir.Diaz-Castillo@nrc.gov.

3

b. Findings and Observations IR 999007728/I-2017-201 contains one finding associated with the following ITAAC:

Inspections, Design ITAAC Tests, Acceptance Criteria Commitment Analysis 2.1.02.05a.i The Class 1E Type tests, A report exists and concludes equipment analyses, or a that the Class 1E equipment identified in Table combination of identified in Table 2.1.2-1 as 2.1.2-1 as being type tests and being qualified for a harsh qualified for a harsh analyses will environment can withstand the environment can be performed environmental conditions that withstand the on Class 1E would exist before, during, and environmental equipment following a design basis conditions that located in a accident without loss of safety would exist before, harsh function for the time required to during, and environment. perform the safety function.

following a design basis accident without loss of safety function for the time required to perform the safety function.

IR 99900728/I-2017-201 states:

IEEE 323-1974 requires testing or analysis of the valve to be performed at the full range of its performance characteristics. While it appeared that the valves may have sufficient margin to compensate for the lower coil pull-in voltage, this margin had not been specifically quantified as it is unknown what the controller output voltage would be when the input to the controller is at the minimal 180 VDC. A change in applied voltage or temperature could impact the capability of the valve to perform its intended safety function. This issue impacts the domestic AP1000 solenoid valves fabricated by Valcor that are identified in the WEC data sheets APP-PV13-Z0D-101and -111.

This issue has been identified as Nonconformance 99900728/I-2017-201-01.

The NRC staff determined that the above vendor finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 2.1.02.05a.i, in that, if left uncorrected, the licensee may not be able to successfully complete the ITAAC. The referenced valves are identified in Table 2.1.2-1 of Appendix C of the Combined License, as being located in a harsh environment.

However, the EQ testing performed on these valves was not performed using the voltage controller which is an integral part of the solenoid valve system and which will be used to supply power to the valves in the plant. As of the completion of the inspection, Valcor had not performed testing or analysis sufficient to verify that the voltage controller output would be adequate to ensure the subject valves would be capable of performing their intended safety functions under all design basis environmental conditions.

4

3. National Technical Systems (NTS)/ Docket 99900905
a. Inspection Scope During the period of December 15-17, 2014, and February 11, 2015, the U.S. NRC staff conducted an inspection at the National Testing Systems (NTS) facility in Huntsville, AL.

The purpose of the inspection was to review NTSs implementation of an adequate quality assurance program as related to the irradiation and submergence testing of the explosive actuators, which are a subcomponent of the 8-inch squib valves being supplied as a part of the Westinghouse Electric Corporation AP1000 reactor design.

The vendor inspection activities were documented in Inspection Report (IR) 99900905/2015-201 (ADAMS Accession No. ML15078A379).

The lead for the above mentioned inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov.

During the week of May 11-15, 2015, the NRC staff conducted an inspection at the NTS facility in Huntsville, AL. The purpose of the inspection was to review NTSs quality assurance activities as it pertains to the qualification testing of the 8-inch high pressure (HP) and the low pressure (LP) squib valves in the Passive Core Cooling System (PXS) of the AP1000 reactor design. The vendor inspection activities were documented in Inspection Report (IR) 99900905/2015-202 (ADAMS Accession No. ML15152A080).

The lead for the above mentioned inspection is Mr. Raju Patel, who can be reached by phone at 301-415-3511 or via electronic mail at Raju.Patel@nrc.gov.

b. Findings and Observations IR 99900905/2015-201 and IR 99900905/2015-202 each contain one inspection finding.

Design Inspections, Tests, Acceptance ITAAC Commitment Analysis Criteria 2.2.03.12a.i The squib valves and Tests or type tests of A test report exists check valves squib valves will be and concludes that identified in Table performed that each squib valve 2.2.3-1 perform an demonstrate the changes position as active capability of the indicated in Table safety-related valve to operate 2.2.3-1 under design function to change under its design conditions.

position as indicated condition.

in the table.

5

2.1.02.07a.i The Class 1E Type tests, analyses, A report exists and equipment identified or a combination of concludes that the in Table 2.1.2-1 as type tests and Class 1E equipment being qualified for a analyses will be identified in Table harsh environment performed on Class 2.1.2-1 as being can withstand the 1E equipment qualified for a harsh environmental located in a harsh environment can conditions that would environment. withstand the exist before, during, environmental and following a conditions that design basis would exist before, accident without loss during, and following of safety function for a design basis the time required to accident without loss perform the safety of safety function for function. the time required to perform the safety function.

2.2.03.07a.i The Class 1E Type tests, analyses, A report exists and equipment identified or a combination of concludes that the in Table 2.2.3-1 as type tests and Class 1E equipment being qualified for a analyses will be identified in Table harsh environment performed on Class 2.2.3-1 as being can withstand the 1E equipment qualified for a harsh environmental located in a harsh environment can conditions that would environment. withstand the exist before, during, environmental and following a conditions that design basis would exist before, accident without loss during, and following of safety function for a design basis the time required to accident without loss perform the safety of safety function for function. the time required to perform the safety function.

IR 99900905/2015-201 states:

NRC inspectors reviewed the irradiation of the squib valve cartridges. The inspectors concluded that the previously stated accuracy of the irradiation system was found to be non-conservative as it did not include several factors that could impact the accuracy of the radiation measurements. As a consequence, nuclear safety related components (squib valve actuators for the Westinghouse AP1000 reactor) currently undergoing environmental qualification at NTS did not receive the full radiation dose when subtracting out the actual uncertainty of the measurement system. This item was identified as Nonconformance 99900905/2015-201-01.

6

This finding is material to ITAAC 2.1.02.07a.i and 2.2.03.07a.i because, if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.

IR 99900905/2015-202 states:

The NRC inspection team determined that NTS failed to establish a procedure in its test program for verifying that the data acquisition system (DAS) functioned as designed. NTS performed both pre-and post-test verification and validation of the DAS to verify that the DAS software was accurately calculating and reporting those temperature and pressure values that would be used to determine the qualification of the safety-related AP1000 8-inch low pressure squib valves.

However, NTS activities to validate the proper function of the DAS, a testing activity affecting quality, were not performed in accordance with written procedures containing the requirements and acceptance limits of the design documents to assure that all prerequisites for the given test have been met. This issue has been identified as Nonconformance 99900905/2015-202-01 Proper functioning of the DAS system is required to verify design conditions when testing squib valves. Therefore, this finding is material to ITAAC 2.2.03.12a.i because if the deficiencies are left uncorrected, the testing program would fail to provide the requisite assurance that the squib valves would perform as required in design basis conditions, including harsh environmental conditions that would exist before, during and following a design basis accident for the time required to perform the safety function.

These inspection findings are material to the acceptance criteria of the ITAAC listed above because the findings concern the adequacy of the testing and/or analyses used to support the conclusion that the squib valves meet the acceptance criteria of the ITAAC.

4. CS Innovations / Docket No. 99901404
a. Inspection Scope During the period of April 25-29, 2011, the U.S. NRC staff conducted an inspection at the CS Innovations, Inc. (CSI), facility in Scottsdale, AZ. The purpose of the inspection was to review the quality assurance activities associated with the development of digital instrumentation and control systems and components for the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901404/2011-201 (ADAMS Accession No. ML111890005).

The lead for this inspection is Mr. Greg Galletti, who can be reached by phone at 301-415-1831 or via electronic mail at Greg.Galletti@nrc.gov.

7

b. Findings and Observations IR 99901404/2011-201 contains two findings associated with the following ITAAC:

Design Inspections, Tests, ITAAC Acceptance Criteria Commitment Analysis 2.5.02.14 The Component An inspection and A report exists and Interface Module or an audit will be concludes that CIM (CIM) is developed performed of the meets the below listed using a planned processes used to life cycle stages. Life design process design the cycle stages:

which provides for hardware, a. Design requirements specific design development phase, may be documentation and software, referred to as reviews. qualification and conceptual or project testing. definition phase

b. System definition phase
c. Hardware and software development phase, consisting of hardware and software design and implementation
d. System integration and test phase
e. Installation phase IR 99901404/2011-201 states:

The NRC inspector determined that CSI failed to establish and implement provisions to collect information on error reports related to discrete components used in safety-related applications. Specifically, the NRC inspection team determined that CSI procedure QCP 9000-01500, Control of Nonconformance, Revision 6, dated December 12, 2010, did not have provisions for the collection, evaluation, disposition, and notification to affected organizations of nonconforming conditions related to discrete components, such as field programmable gate arrays used in safety-related applications. As a result CSI did not formally collect and evaluate error reports for such safety-related components to determine if nonconforming conditions could exist. This item was identified as Nonconformance 99901404/2011-201-03.

The NRC inspectors determined that CSI failed to establish measures to assure that applicable requirements associated with specific independent verification and validation (IV&V) activities were implemented. Specifically, CSIs IV&V process failed to provide for the development of an independent testing tool during the component or module-based level of development for the CIM-SRNC 8

subsystem, and CSIs IV&V process did not include specific independent test plans for implementation by the IV&V team as required by CSI Report No. 6105-00013. This item was identified as Nonconformance 99901404/2011-201-04.

The NRC staff determined that the vendor findings represented ITAAC findings because they were material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 2.5.02.14, in that, if left uncorrected, the licensee may not have been able to demonstrate that the acceptance criterion of this ITAAC was met. The acceptance criteria of this ITAAC require a report exists and concludes that CIM meets the following life cycle stages:

1. Design requirements phase, may be referred to as conceptual or project definition phase
2. System definition phase
3. Hardware and software development phase, consisting of hardware and software design and implementation
4. System integration and test phase
5. Installation phase The inspectors determined that the quality assurance failures found would have prevented the development of an acceptable report for the CIM and therefore, the ITAAC acceptance criteria would not be met by the licensee.
5. Obayashi Corporation / Docket No. 99901409
a. Inspection Scope During the period of September 12-16, 2011, the U.S. NRC staff conducted an inspection at the Obayashi Corporation (hereafter referred to as Obayashi) facility in Tokyo, Japan. The purpose of this inspection was to evaluate the quality assurance activities associated with the design services being provided the Westinghouse Electric Company in support of the AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901409/2011-201 (ADAMS Accession No. ML11286A106).

The lead for this inspection is Ms. Kerri Kavanagh, who can be reached by phone at 301-415-3743 or via electronic mail at Kerri.Kavanagh@nrc.gov.

9

b. Findings and Observations IR 99901409/2012-201 contains one finding associated with the following ITAAC:

Design Inspections, ITAAC Acceptance Criteria Commitment Tests, Analysis 3.3.00.02a.i.a The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the are seismic Category Deviations from the as-built containment I and are designed design due to as- internal structures, and constructed to built conditions will including the critical withstand design be analyzed for the sections, conform to the basis loads as design basis loads. approved design and will specified in the withstand the design Design Description, basis loads specified in without loss of the Design Description structural integrity without loss of structural and the integrity or the safety-related safety-related functions.

functions.

3.3.00.02a.i.b The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the are seismic Category Deviations from the as-built shield building I and are designed design due to as- structures, including the and constructed to built conditions will critical sections, conform withstand design be analyzed for the to the approved design basis loads as design basis loads. and will withstand the specified in the design basis loads Design Description, specified in the Design without loss of Description without loss structural integrity of structural integrity or and the the safety-related safety-related functions.

functions.

10

Design Inspections, ITAAC Acceptance Criteria Commitment Tests, Analysis 3.3.00.02a.i.c The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the are seismic Category Deviations from the as-built structures in the I and are designed design due to as- non-radiologically and constructed to built conditions will controlled area of the withstand design be analyzed for the auxiliary building, basis loads as design basis loads. including the critical specified in the sections, conform to the Design Description, approved design and will without loss of withstand the design structural integrity basis loads specified in and the the Design Description safety-related without loss of structural functions. integrity or the safety-related functions.

3.3.00.02a.i.d The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the are seismic Category Deviations from the as-built structures in the I and are designed design due to as- radiologically controlled and constructed to built conditions will area of the auxiliary withstand design be analyzed for the building, including the basis loads as design basis loads. critical sections, conform specified in the to the approved design Design Description, and will withstand the without loss of design basis loads structural integrity specified in the Design and the Description without loss safety-related of structural integrity or functions. the safety-related functions.

IR 99901409/2011-201 states:

The NRC inspectors determined that Obayashi failed to: 1) assure that applicable design basis are correctly translated into calculations; 2) establish procedures for the identification and control of design control interfaces and for coordination among the participating design organizations; and 3) subject design changes to the commensurate design control measures applied to the original design. This item was identified as Nonconformance 99901409/2011-201-03.

The NRC staff determined that the vendor finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to demonstrate that the acceptance criteria of these ITAACs were met. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built 11

structures conform to the approved design and will withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and reconcile nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.

6. Kinectrics / Docket No. 99901415
a. Inspection Scope During the period of May 14-18, 2012, the U.S. NRC staff conducted an inspection at the Kinectrics Inc. (hereafter referred to as Kinectrics) facility in Toronto, Ontario. The purpose of the inspection was to evaluate the quality assurance activities associated with the supply of testing services by Kinectrics in support of environmental qualification of components being used in the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901415/2012-201 (ADAMS Accession No. ML12179A413).

The lead for this inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.Jacobson@nrc.gov.

b. Findings and Observations IR 99901415/2012-201 contains two findings associated with the following ITAAC:

Inspections, Tests, ITAAC Design Commitment Acceptance Criteria Analysis 2.2.01.05.ii The seismic Category Type tests, A report exists and I equipment identified analyses, or a concludes that the in Table 2.2.1-1 can combination of type seismic Category I withstand seismic tests and analyses equipment can design basis loads of seismic Category withstand seismic without loss of I equipment will be design basis structural integrity performed. dynamic loads and safety function. without loss of structural integrity and safety function.

12

Inspections, Tests, ITAAC Design Commitment Acceptance Criteria Analysis 2.2.01.06a.i The Class 1E Type tests, A report exists and equipment identified analyses, or a concludes that the in Table 2.2.1-1 as combination of type Class 1E equipment being qualified for a tests and analyses identified in Table harsh environment will be performed on 2.2.1-1 as being can withstand the Class 1E equipment qualified for a harsh environmental located in a harsh environment can conditions that would environment. withstand the exist before, during, environmental and following a conditions that would design basis accident exist before, during, without loss of safety and following a function for the time design basis required to perform accident without loss the safety function. of safety function for the time required to perform the safety function.

IR 99901415/2012-201 states:

The NRC inspectors determined that Kinectrics failed to implement measures to ensure that testing performed by subcontractors was in conformance with procurement documents. Specifically: (1) Kinectrics did not properly dedicate the testing services provided by Global EMC, Inc., for the performance of electromagnetic compatibility testing, as necessary to ensure that the testing was performed in accordance with the stated requirements; and (2) Kinectrics did not ensure that the test report produced by its subcontractor, Clark Testing Laboratories, for seismic testing of electrical penetration assemblies performed in accordance with stated requirements. This item was identified as Nonconformance 99901415/2012-201-01.

The NRC inspectors determined that Kinectrics did not explicitly state the proper technical standard and revision to be used for electromagnetic compatibility testing of electrical penetration assemblies. Consequently, the incorrect revision of the MIL-STD-461 was used to perform the testing. This item was identified as Nonconformance 99901415/2012-201-02.

These items are material to the ITAAC acceptance criteria because if left uncorrected, these issues challenge the validity of the qualification testing performed on the subject equipment as required by the ITAAC.

13

7. Cives Steel Company / Docket No. 99901419
a. Inspection Scope During the period of December 10-14, 2012, the U.S. NRC staff conducted an inspection at the Cives Steel Company (hereafter referred to as Cives) facility in Thomasville, GA.

This inspection evaluated the quality assurance activities associated with the fabrication of concrete embedments for the AP1000 reactor plants for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901419/2012-201 (ADAMS Accession No. ML13042A397).

The lead for this inspection is Mr. Jonathan Ortega-Luciano, who can be reached by phone at 301-415-1159 or via electronic mail at Jonathan.Ortega-Luciano@nrc.gov.

b. Findings and Observations IR 99901419/2012-201 contains one finding associated with the following ITAAC:

Inspections, ITAAC Design Commitment Acceptance Criteria Tests, Analysis 3.3.00.02a.i.a The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the as-are seismic Category I Deviations from the built containment and are designed and design due to as- internal structures, constructed to built conditions will including the critical withstand design basis be analyzed for the sections, conform to loads as specified in design basis loads. the approved design the Design Description, and will withstand the without loss of design basis loads structural integrity and specified in the Design the Description without safety-related loss of structural functions. integrity or the safety-related functions.

14

Inspections, ITAAC Design Commitment Acceptance Criteria Tests, Analysis 3.3.00.02a.i.b The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the as-are seismic Category I Deviations from the built shield building and are designed and design due to as- structures, including constructed to built conditions will the critical sections, withstand design basis be analyzed for the conform to the loads as specified in design basis loads. approved design and the Design Description, will withstand the without loss of design basis loads structural integrity and specified in the Design the Description without safety-related loss of structural functions. integrity or the safety-related functions.

3.3.00.02a.i.c The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the as-are seismic Category I Deviations from the built structures in the and are designed and design due to as- non-radiologically constructed to built conditions will controlled area of the withstand design basis be analyzed for the auxiliary building, loads as specified in design basis loads. including the critical the Design Description, sections, conform to without loss of the approved design structural integrity and and will withstand the the design basis loads safety-related specified in the Design functions. Description without loss of structural integrity or the safety-related functions.

15

Inspections, ITAAC Design Commitment Acceptance Criteria Tests, Analysis 3.3.00.02a.i.d The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction and listed in Table 3.3-7, performed. concludes that the as-are seismic Category I Deviations from the built structures in the and are designed and design due to as- radiologically controlled constructed to built conditions will area of the auxiliary withstand design basis be analyzed for the building, including the loads as specified in design basis loads. critical sections, the Design Description, conform to the without loss of approved design and structural integrity and will withstand the the design basis loads safety-related specified in the Design functions. Description without loss of structural integrity or the safety-related functions.

IR 99901419/2012-201 states:

The inspectors determined that Cives failed to establish and implement a program for inspection of activities affecting quality to verify conformance with the documented instructions, procedures, and drawings. Specifically, (1) Cives failed to adequately implement its inspection program to inspect stud welds on embedment APP-12S02-CE-PW908 for Vogtle Electric Generating Plant, Unit 3, which connects to stairs in Auxiliary Building Area 1, Wall P, west face, at an elevation of 66 feet 6 inches; and (2) Cives failed to test at least 1 out of every 100 studs welded by each operator as required by Westinghouse Specification APP-SS01-Z0-003, Revision 3, dated March 3, 2011, and the inspection plan entitled, Inspection Fabrication Plan No. 5200-01 for Embeds, Items, and Anchor Bolts, Revision 1, dated December 14, 2011. These issues were identified as Nonconformance (NON) 99901419-2012-201-03.

The NRC staff determined that the finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.

16

8. Chicago Bridge & Iron (CB & I) Lake Charles / Docket No. 99901425
a. Inspection Scope During the week from February 3-7, 2014, the U.S. NRC staff conducted an inspection at the Chicago Bridge & Iron Lake Charles (hereafter referred to as CB&I LC) facility in Lake Charles, LA. The purpose of the inspection was to evaluate CB&I LCs implementation of quality assurance activities associated with the fabrication and inspection of the Westinghouse Electric Company AP1000 reactor design of structural sub-modules for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901425/2014-201 (ADAMS Accession No. ML14072A315).

The lead for this inspection is Mr. Paul Prescott, who can be reached by phone at 301-415-3026 or via electronic mail at Paul.Prescott@nrc.gov.

b. Findings and Observations IR 99901425/2014-201 contains one finding associated with the following ITAAC:

ITAAC Design Inspections, Tests, Acceptance Commitment Analysis Criteria 3.3.00.02.a.i.a The nuclear island An inspection of the A report exists which structures, including nuclear island reconciles deviations the critical sections structures will be during construction listed in Table 3.3-7, performed. and concludes that are seismic Category Deviations from the the as-built I and are designed design due to as- containment internal and constructed to built conditions will structures, including withstand design be analyzed for the the critical sections, basis loads as design basis loads. conform to the specified in the approved design and Design Description, will withstand the without loss of design basis loads structural integrity specified in the and the safety- Design Description related functions. without loss of structural integrity or the safety-related functions.

17

ITAAC Design Inspections, Tests, Acceptance Commitment Analysis Criteria 3.3.00.02a.i.d The nuclear island Inspection will be A report exists which structures, including conducted of the as- reconciles deviations the critical sections built piping as during construction listed in Table 3.3-7, documented in the and concludes that are seismic Category ASME design the as-built I and are designed reports. structures in the and constructed to radiologically withstand design controlled area of basis loads as the auxiliary building, specified in the including the critical Design Description, sections, conform to without loss of the approved design structural integrity and will withstand and the safety- the design basis related functions. loads specified in the Design Description without loss of structural integrity or the safety-related functions.

IR 99901425/2014-201 states:

The NRC inspectors determined that CB&I LC failed to adequately implement measures to control materials, parts, or components which do not conform to requirements in order to prevent their inadvertent use or installation. Specifically, CB&I LC failed to correctly identify unresolved nonconformances on a safety-related sub-module being prepared to ship: one stud that had an incomplete weld was incorrectly located in the documentation; one stud that was identified on the documentation as being added and having incomplete weld did not appear to exist on the module; and one stud was documented as having an incomplete weld, but was actually missing. This item was identified as Nonconformance 99901425/2014-201-01.

The NRC staff determined that the finding represented an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC listed above, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.

18

9. SMCI / Docket No. 99901439
a. Inspection Scope During the period April 7-11, 2014, the U.S. NRC staff conducted an inspection at the Specialty Maintenance and Construction, Inc. (hereafter referred to as SMCI) facility in Lakeland, FL. The purpose of this inspection was evaluate SMCIs implementation of quality assurance activities associated with the fabrication of the remain-in-place steel formwork modules for concrete, in-containment refueling water storage tank wall and reactor vessel cavity modules for the Westinghouse Electric Company (WEC) AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901439/2014-201 (ADAMS Accession No. ML14121A433).

During the period June 8-12, 2015, the NRC staff conducted an inspection at the SMCI facility in Lakeland, FL. The purpose of this inspection was to evaluate SMCIs implementation of quality assurance activities associated with the fabrication of the embed plates for the CA-01 module (steam generator and refueling canal module) and CA-02 module (independent wall structure connecting the CA-01 and CA-03 module, where the CA-03 module is the in-containment refueling water storage tank module).

These are modules for the Westinghouse AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in IR 99901439/2015-201 (ADAMS Accession No. ML15175A446).

The lead for the above inspections is Mr. Yamir Diaz-Castillo, who can be reached by phone at 301-415-2228 or via electronic mail at Yamir.Diaz-Castillo@nrc.gov.

b. Findings and Observations IR 99901439/2014-201 contains one finding, and IR 99901439-2015-201 contains two findings associated with the following ITAAC:

Design Inspections, ITAAC Acceptance Criteria Commitment Tests, Analysis 3.3.00.02a.i.a The nuclear island An inspection of A report exists which reconciles structures, including the nuclear deviations during construction the critical sections island structures and concludes that the as-built listed in Table 3.3-7, will be containment internal structures, are seismic Category performed. including the critical sections, I and are designed Deviations from conform to the approved design and constructed to the design due and will withstand the design withstand design to as-built basis loads specified in the basis loads as conditions will be Design Description without loss specified in the analyzed for the of structural integrity or the Design Description, design basis safety-related functions.

without loss of loads.

structural integrity and the safety-related functions.

19

IR 99901439/2014-201 states:

The NRC inspectors determined that SMCI failed to qualify a welding procedure in accordance with WEC specification APP-VW20-ZO-023. Specifically, SMCI welding procedure qualification record (PQR) 1015-Partial Joint Penetration (PJP), lists the results of the ferrite testing of the test weld root as 73 percent, which is outside of the 35-65 percent ferrite range acceptance criteria specified by WEC in APP-VW20-ZO-023. PQR 1015-PJP is a supporting PQR for welding procedure specification (WPS) number 1015. WPS 1015 is being used to perform welding on the in-containment refueling water storage tank modules for the AP1000 reactor design. This item was identified as Nonconformance 99901439/2014-201-01.

IR 99901439/2015-201 states:

The NRC inspectors determined that SMCI failed to transfer all the pertinent design requirements into the applicable instructions and failed to inspect welds in accordance with the applicable travelers and design specification drawings.

Specifically, (1) SMCI did not adequately incorporate several general notes on NDE requirements from WEC design specifications drawings into all the applicable travelers. These general notes would require visual examination (VT),

and magnetic particle examination (MT) or liquid penetrant (PT) examination of both the reinforcing fillet weld and the partial joint penetration (PJP). By not correctly transferring nondestructive examination requirements to the SMCI travelers, partial penetration welds did not receive the required surface examinations required by the WEC design drawings; and (2) SMCI only performed VT and MT examination of the reinforcing fillet weld that is applied over the PJP, and did not perform a VT and MT examination of the PJP as required by several general notes from design specification drawing APP-GW-S9-105. Not inspecting the PJP welds leaves the quality of welds to be indeterminate, and therefore affects how these welds would meet their design stress requirements and would perform their intended safety function. This item was identified as Nonconformance 99901439/2015-201-01.

The NRC inspectors determined SMCI failed to control welding consumable filler metal in accordance with applicable procedures and criteria. Specifically, (1)

SMCI did not record on form WCIL-001 the weld filler metal that was issued for the time period of June 28, 2014, through July 11, 2014, as required by the applicable procedure; and (2) During a review of traveler 926-CA01-00774, the NRC inspection team noted that a welder used weld filler metal to weld the beam seat that was not the weld filler metal he was issued and required to use. The use of the correct weld filler metal for welding the beam seat was not adequately controlled as required by the applicable procedure. This item was identified as Nonconformance 99901439/2015-201-02.

The NRC staff determined that the above findings represent ITAAC findings because they are material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 3.3.00.02a.i.a in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of these ITAACs require that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other 20

safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with adequate documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.

10. Oregon Iron Works / Docket Nos. 99901448/1449
a. Inspection Scope During the period of September 22-26, 2014, the U.S. Nuclear Regulatory Commission (NRC) staff conducted an inspection at the Oregon Iron Works, Inc. (hereafter referred to as OIW) facilities in Clackamas, OR and Vancouver, WA. The purpose of the inspection was to evaluate OIWs implementation of quality assurance activities associated with the fabrication and inspection of the CA20 Auxiliary Building Modules for the Westinghouse Electric Company (WEC) AP1000 reactor design for the Vogtle Units 3 and 4 currently under construction. The vendor inspection activities were documented in Inspection Report (IR) 99901448/2014-201 / 999901449/2014-201 (ADAMS Accession No. ML14308A463).

The lead for this inspection is Mr. Jonathan Ortega-Luciano, who can be reached by phone at 301-415-1159 or via electronic mail at Jonathan.Ortega-Luciano@nrc.gov.

b. Findings and Observations IR 99901448/2017-201 / 999901449/2014-201 contains one finding associated with the following ITAAC:

Inspections, ITAAC Design Commitment Acceptance Criteria Tests, Analysis 3.3.00.02a.i.d The nuclear island Inspection will be A report exists which structures, including conducted of the reconciles deviations the critical sections as-built piping as during construction listed in Table 3.3-7, documented in the and concludes that are seismic Category ASME design the as-built structures I and are designed reports. in the radiologically and constructed to controlled area of the withstand design auxiliary building, basis loads as including the critical specified in the sections, conform to Design Description, the approved design without loss of and will withstand the structural integrity and design basis loads the safety-related specified in the functions. Design Description without loss of structural integrity or the safety-related functions.

21

IR 99901448/2014-201 / 999901449/2014-201 states:

The NRC inspectors determined that OIW failed to ensure the selection and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components. Additionally, OIW failed to establish appropriate measures that included provisions for source evaluation of subcontractors. This item was identified as Nonconformances 99901448/2014-201-02 and 99901449/2014-201-02.

The NRC staff determined that the above finding is an ITAAC finding because it was material to the acceptance criteria of VEGP Units 3 and 4 ITAAC 3.3.00.02a.i.d, in that, if left uncorrected, the licensee may not have been able to successfully complete the ITAAC. The acceptance criteria of this ITAAC requires that all construction deviations be reconciled to verify that the as-built structures will conform to the approved design and withstand the design basis loads without a loss of structural integrity or other safety-related functions. The inspectors determined that the failure to adequately review and accept nonconforming items in accordance with documented procedures may have resulted in a construction deviation that may not be properly reconciled by the licensee.

11. WECTEC/ Docket No. 99901467
a. Inspection Scope During the period from November 14-18, 2016, the U.S. NRC conducted an inspection at the Westinghouse/WECTEC facility in Charlotte, North Carolina. The purpose of the inspection was to review implementation of Westinghouses processes for transferring the design requirements contained in the AP1000 Design Control Document into detailed engineering, procurement, and construction documents, consistent with NRC requirements. The vendor inspection activities were documented in Inspection Report (IR) 99901467/2016-201 (ADAMS Accession No. ML17013A658).

The lead for this inspection is Mr. Jeffrey Jacobson, who can be reached by phone at 301-415-2977 or via electronic mail at Jeffrey.jacobson@nrc.gov.

22

b. Findings and Observations IR 99901467/2016-201 contains one finding associated with the following ITAAC:

ITAAC Inspections, Design Tests, Acceptance Criteria Commitment Analysis 2.6.03.08 Circuit breakers Analyses for Analyses for the as-built IDS and fuses the as-built IDS dc electrical distribution installed in IDS dc electrical system exist and conclude battery, battery distribution that the analyzed fault charger, dc system to currents do not exceed the distribution panel, determine fault interrupt capacity of circuit and MCC circuits currents will be breakers and fuses in the are rated to performed. battery, battery charger, dc interrupt fault distribution panel, and MCC currents. circuits, as determined by their nameplate ratings.

IR 99901467/2016-201 states, in part, that:

The inspectors identified that Document CDI 3398 does not list the circuit breakers interrupting current rating as a critical characteristic. Consequently, no specific actions were taken as part of the dedication process (or as part of any other Westinghouse process) to identify and verify the validity of the breakers interrupting current ratings.

The inspectors noted the interrupting current capacity of these components is a critical element of the IDS design and is also specifically called out in ITAAC 2.6.03.08. While Westinghouse performed commercial grade surveys of the commercial manufacturer, as described in Document CDI 3398, these surveys did not specifically evaluate the adequacy of the methods used by the commercial manufacturer to establish the interrupting current ratings, or whether sufficient quality controls were implemented at facilities utilized to test the interrupting current capacity of the breakers. While not specifically reviewed during this inspection, Westinghouse indicated the concern raised by the inspectors would also apply to fuses, as their interrupting capacity was also not captured via the dedication process.

ITAAC 2.6.03.08 states, Circuit breakers and fuses installed in IDS battery, battery charger, dc distribution panel, and MCC circuits are rated to interrupt fault currents.

The acceptance criteria for this ITAAC states, Analyses for the as-built IDS dc electrical distribution system exist and conclude that the analyzed fault currents do not exceed the interrupt capacity of circuit breakers and fuses in the battery, battery charger, dc distribution panel, and MCC circuits, as determined by their nameplate ratings.

Contrary to the above, prior to November 18, 2016, Westinghouse failed to identify and verify the adequacy of circuit breaker and fuse interrupting current ratings as a critical characteristic, as part of its commercial grade dedication process. This issue is identified as Nonconformance 99901467/2016-201-01.

The issue is material to ITAAC 2.6.03.08 because if the interrupting ratings for the circuit breakers and fuses cannot be verified, the analyses which compares the available fault currents to those ratings would be invalid, and if left uncorrected, the licensee may not be able to successfully complete the ITAAC.

23