Text

Tom Tynan Southern Nuclear Vice President - Vogtle Operating Company, Inc.

7821 River Road Waynesboro, Georgia 30830 Tel 706.8263151 Fax 7068263321 September 24, 2009 SOUTHERN COMPANY A

SM Energy to Serve lOur World Docket Nos.: 50-424 NL-09-1449 50-425 U. S. Nuclear Regulatory Commission AnN: Document Control Desk Washington, D. C. 20555-0001 Vogtle Electric Generating Plant Emergency Response Data System (EROS)

Data Point Library Modification Ladies and Gentlemen:

In accordance with the requirements of 10CFR50, Appendix E, Section VI, Item 3a, Southern Nuclear Operating Company (SNC) is submitting changes to the Vogtle Electric Generating Plant Unit 1 and Unit 2 Emergency Response Data System (EROS) data point library. Data point UV6130 (Borated Water Storage Tank Level), was revised on both Unit 1 and Unit 2 as a result of changes to the scaling and setpoints for the Refueling Water Storage Tank level instrumentation.

The changes were implemented on July 21,2008. However, it was not recognized until September 4, 2009 that the Nuclear Regulatory Commission (NRC) had not been notified of the changes to the EROS data point library within 30 days of implementing the change as required by 10CFR50, Appendix E, Section VI, Item 3a. This deficient condition was identified during a broadness review, for a condition report, that had been generated when it was discovered, that other EROS data points had been modified and the NRC had not been notified of the changes within 30 days of making the changes as disclJssed in letter NL-09-1 088 from SNC to the NRC, dated July 10, 2009.

This letter contains no NRC commitments. If you have any questions, please advise.

Sincerely,

/.)/~

T. E. Tynan Vice President - Vogtle

U. S. Nuclear Regulatory Commission Log:

Page 2 TETfTMH/<>

Enclosures:

1. Marked-up changes to the VEGP Unit 1 EROS Data Point Library
2. Marked-up changes to the VEGP Unit 2 EROS Data Point Library cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. T. E. Tynan, Vice President - Vogtle Ms. P. M. Marino, Vice President - Engineering RType: CVC7000 U. S. Nuclear Regulatorv Commission Mr. L. A. Reyes, Regional Administrator Ms. D. N. Wright, NRR Project Manager - Vogtle Mr. M. Cain, Senior Resident Inspector - Vogtle

Vogtle Electric Generating Plant Emergency Response Data System (EROS)

Data Point Library Modifications Enclosure 1 Mark-up Changes to the VEGP Unit 1 EROS Data Point Library

Chapter 13 - Emergency Response Data System (EROS)

Date  :[§IE}

Reactor Unit VOl Data Feeder N/A NRC EROS Parameter BWST LEVEL Point ID UV6l30 Plant Spec. Point VALIDATED RWST LEVEL Generic/Cond. BORATED WATER STORAGE TANK LEVEL AnaloglDigital A Engr. UnitslDig  %

Engr. Units 0.0 to 100.0 %

Minimum Instr. 0.0 Maximum Instr. 100.0 Zero Point TNKBOT Reference Point GALLONS REMAIN AT ZERO POINT Proc or Sens. P Number of Sensors 4 How Processed VALIDATED AVERAGE Sensor Locations RWST Alarmtrrip Setpoints

~

NI Power Cut Off N/A NI Power Turn On N/A Instrument Failure N/A Temp.Comp. N Level Reference DRY Unique System Indicates the level in the RWST. The average of the four valid signals is used. Invalid inputs are discarded prior to calculating the average. The point is marked invalid ifall of the inputs are invalid.

Appendix C Page 58 T:IConfigISpecsIX5AB05\1PCDOCSIAX5AB05-00031 (Vol 2) IChapter_13. doc

Vogtle Electric Generating Plant Emergency Response Data System (EROS)

Data Point Library Modifications Enclosure 2 Mark-up Changes to the VEGP Unit 2 EROS Data Point Library

Chapter 13 - Emergency Response Data System (EROS)

Date  :~

Reactor Unit V02 Data Feeder N/A NRC EROS Parameter BWST LEVEL Point ID UV6130 Plant Spec. Point VALIDATED RWST LEVEL Generic/Cond. BORATED WATER STORAGE TANK LEVEL Analog/Digital A Engr. Units/Dig  %

Engr. Units 0.0 to 100.0 %

Minimum lnstr. 0.0 Maximum lnstr. 100.0 Zero Point TNKBOT Reference Point GALLONS REMAIN AT ZERO POINT Proc or Sens. P Number of Sensors 4 How Processed VALIDATED AVERAGE Sensor Locations RWST Alarmffrip Setpoints  :~

NI Power Cut Off N/A NI Power Turn On N/A Instrument Failure N/A Temp. Compo N Level Reference DRY Unique System Indicates the level in the RWST. The average of the four valid signals is used. Invalid inputs are discarded prior to calculating the average. The point is marked invalid ifall of the inputs are invalid.

Appendix C Page 119 T:IConfigISpecsIXSABOSIIPCDOCSIAXSABOS-00031 (Vol 2) IChapter_13. doc