ML19109A036: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 9: Line 9:
| docket = 05000277, 05000278
| docket = 05000277, 05000278
| license number = DPR-044, DPR-056
| license number = DPR-044, DPR-056
| contact person = Tobin J C
| contact person = Tobin J
| document type = Meeting Notice
| document type = Meeting Notice
| page count = 2
| page count = 2
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:Page 1 of 2 Talking Points NRC Pre-Submittal Call April 23, 2019 Subject Peach Bottom Atomic Power Station, Units 2 and 3  
{{#Wiki_filter:Page 1 of 2 Talking Points NRC Pre-Submittal Call April 23, 2019 Subject Peach Bottom Atomic Power Station, Units 2 and 3 License Amendment Request to Revise Technical Specifications for a Temporary One-Time Extension of Completion Time Discussion This licensing action will be a temporary one-time request to extend the Completion Time for Technical Specifications 3.8.1, Required Action A.3, from 7 days to 21 days for both units.
 
License Amendment Request to Revise Technical Specifications for a Temporary One-Time Extension of Completion Time  
 
Discussion This licensing action will be a tempor ary one-time request to extend the Completion Time for Technical Specific ations 3.8.1, Required Action A.3, from 7 days to 21 days for both units.
Sufficient time is needed to replace 27 electrical cables which are reaching the end of their dependable service life.
Sufficient time is needed to replace 27 electrical cables which are reaching the end of their dependable service life.
The cables are located in an undergr ound duct bank between the Unit 3 Emergency Auxiliary Transformer and a junction box serving the 3SU-E 4.16 kV feed switchgear that norma lly supplies the E22 and E42 4.16 kV buses for Unit 2 and the E13 and E 33 4.16 kV buses for Unit 3.
The cables are located in an underground duct bank between the Unit 3 Emergency Auxiliary Transformer and a junction box serving the 3SU-E 4.16 kV feed switchgear that normally supplies the E22 and E42 4.16 kV buses for Unit 2 and the E13 and E33 4.16 kV buses for Unit 3.
The work is currently planned for later in November 2019 to accommodate a suitable work window.
The work is currently planned for later in November 2019 to accommodate a suitable work window.
The work is being estimated to take approximately 384 hours (16 days).
The work is being estimated to take approximately 384 hours (16 days).
The schedule includes time for as-found testing, cutting and removing existing cables, duct bank inspection
The schedule includes time for as-found testing, cutting and removing existing cables, duct bank inspection/cleaning, pulling of new cables, new cable termination work, testing, etc.
/cleaning, pulling of new cables, new cable termination work, testing, etc.  
 
The schedule also includes additional time for contingencies (approximately 4 days) for possible inclement weather condition delays, duct bank repair work, additional testing, etc.
The schedule also includes additional time for contingencies (approximately 4 days) for possible inclement weather condition delays, duct bank repair work, additional testing, etc.
During the extended Completion Time period, the 33 kV Conowingo line (SBO line), the Unit 2 Emergency Auxiliary Transformer (2SU-E 4.16 kV feed), and all four (4) Emergency Diesel Generators (EDGs) are planned to be protected, available, an d operable to provide power.
During the extended Completion Time period, the 33 kV Conowingo line (SBO line), the Unit 2 Emergency Auxiliary Transformer (2SU-E 4.16 kV feed), and all four (4) Emergency Diesel Generators (EDGs) are planned to be protected, available, and operable to provide power.
FLEX equipment will also be available.  
FLEX equipment will also be available.


Page 2 of 2}}
Page 2 of 2 SBO Line Tie 2 SU-B Area of Work}}

Latest revision as of 21:20, 19 October 2019

License Amendment Request to Revise Technical Specifications for a Temporary One-Time Extension of Completion Time
ML19109A036
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/23/2019
From: Jennifer Tobin
Plant Licensing Branch 1
To: Bryan Hanson
Exelon Nuclear
Tobin J
References
Download: ML19109A036 (2)


Text

Page 1 of 2 Talking Points NRC Pre-Submittal Call April 23, 2019 Subject Peach Bottom Atomic Power Station, Units 2 and 3 License Amendment Request to Revise Technical Specifications for a Temporary One-Time Extension of Completion Time Discussion This licensing action will be a temporary one-time request to extend the Completion Time for Technical Specifications 3.8.1, Required Action A.3, from 7 days to 21 days for both units.

Sufficient time is needed to replace 27 electrical cables which are reaching the end of their dependable service life.

The cables are located in an underground duct bank between the Unit 3 Emergency Auxiliary Transformer and a junction box serving the 3SU-E 4.16 kV feed switchgear that normally supplies the E22 and E42 4.16 kV buses for Unit 2 and the E13 and E33 4.16 kV buses for Unit 3.

The work is currently planned for later in November 2019 to accommodate a suitable work window.

The work is being estimated to take approximately 384 hours0.00444 days <br />0.107 hours <br />6.349206e-4 weeks <br />1.46112e-4 months <br /> (16 days).

The schedule includes time for as-found testing, cutting and removing existing cables, duct bank inspection/cleaning, pulling of new cables, new cable termination work, testing, etc.

The schedule also includes additional time for contingencies (approximately 4 days) for possible inclement weather condition delays, duct bank repair work, additional testing, etc.

During the extended Completion Time period, the 33 kV Conowingo line (SBO line), the Unit 2 Emergency Auxiliary Transformer (2SU-E 4.16 kV feed), and all four (4) Emergency Diesel Generators (EDGs) are planned to be protected, available, and operable to provide power.

FLEX equipment will also be available.

Page 2 of 2 SBO Line Tie 2 SU-B Area of Work