|
|
Line 3: |
Line 3: |
| | issue date = 09/28/2006 | | | issue date = 09/28/2006 |
| | title = Memo 09/28/06 Request for Technical Assistance - Appendix R Disputed Violations Regarding Quad Cities Nuclear Power Station (TIA 2006-005) | | | title = Memo 09/28/06 Request for Technical Assistance - Appendix R Disputed Violations Regarding Quad Cities Nuclear Power Station (TIA 2006-005) |
| | author name = Pederson C D | | | author name = Pederson C |
| | author affiliation = NRC/RGN-III/DRS | | | author affiliation = NRC/RGN-III/DRS |
| | addressee name = Nieh H K | | | addressee name = Nieh H |
| | addressee affiliation = NRC/NRR/ADRA/DPR | | | addressee affiliation = NRC/NRR/ADRA/DPR |
| | docket = 05000254, 05000265 | | | docket = 05000254, 05000265 |
Revision as of 11:19, 13 July 2019
|
---|
Category:License-Technical Assistance Request (TAR)
MONTHYEARML0627105392006-09-28028 September 2006 Memo 09/28/06 Request for Technical Assistance - Appendix R Disputed Violations Regarding Quad Cities Nuclear Power Station (TIA 2006-005) 2006-09-28
[Table view] Category:Memoranda
MONTHYEARML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21277A2472021-11-0505 November 2021 Notification of Significant Licensing Action - Proposed Issuance of Order Approving the Transfer of Licenses for Which a Hearing Has Been Requested - Exelon Generation Company, LLC; Et. Al ML20150B3182020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Exelon Generation Co., LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Quad Cities ISFSI ML20234A4472020-08-21021 August 2020 Summary of the July 29, 2020 Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 ML20098G3132020-04-0707 April 2020 Actions Related to the Requirements for Work Hour Controls During the Coronavirus Disease 2019 Public Health Emergency ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML14324A1392014-11-20020 November 2014 Notice of Closed Meeting with Exelon Nuclear to Discuss Exelon Nuclear'S 12/19/2013, Application for Amendment of the Dresden and Quad Cities Nuclear Power Station'S Technical Specifications to Add Reference to Topical Report WCAP-16865-P-A ML14241A6332014-09-11011 September 2014 Summary of August 23, 2014, Meeting with Exelon Generation Company, LLC Regarding Areva Xm Fuel Transition Request for Dresden and Quad Cities Nuclear Station ML14219A2822014-08-0707 August 2014 Notice of Forthcoming Meeting with Exelon Generation Company, LLC (EGC) Regarding Areva Xm Fuel Transition Request for Dresden and Quad Cities Nuclear Stations ML14104A9372014-04-23023 April 2014 U.S. Nuclear Regulatory Commission Staff'S Spot-Check Review of Mid-American Energy Company'S 25 Percent Ownership Interest in Quad Cities Nuclear Power Station Units 1 and 2 on April 9, 2014 ML13309A0802013-12-11011 December 2013 Memorandum to File: Transcript for 10 CFR 2.206 Petition from Beyond Nuclear (Et Al) Regarding General Electric Mark I and Mark II Boiling-Water Reactors ML13193A0482013-08-14014 August 2013 Notice of Forthcoming Meeting with Exelon Generation Company, LLC (EGC) Regarding Areva Xm Fuel Transition Request for Dresden and Quad Cities Nuclear Stations ML13190A3522013-07-10010 July 2013 Notice of Forthcoming Teleconference with Exelon Generation Company, LLC ML12348A6962012-12-17017 December 2012 1/3/2013 - Notice of Forthcoming Meeting with Exelon Generation Company, LLC, to Discuss Requests for Additional Information Regarding Exelon Physical Security Plans ML1208602902012-03-26026 March 2012 Notice of Forthcoming Public Meeting with Exelon Generation to Discuss Future Fleet Submittal Regarding Licensed Operator Eligibility Requirements ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML0926801972009-09-29029 September 2009 Notice of Pre-application Meeting to Discuss Egc'S Plants to Submit Power Uprate Requests for Various Units in Its Reactor Fleet ML0914901422009-06-0909 June 2009 Notice of Meeting with Exelon Generation Company on Licensing Practices and Processes ML0822614782008-08-13013 August 2008 Staff Position Regarding the Use of Methods Described in Abb/Westinghouse Topical Report CENPD-300-P-A, Reference Safety Report for Boiling Water Reactor Reload Fuel, for Safety Limit Minimum Critical Power Ratio Determinations ML0810600322008-04-15015 April 2008 Notice of Revised Meeting with Exelon Generation Company, LLC to Discuss Licensing Activities for Braidwood, Byron, Clinton, Dresden, LaSalle, Limerick, Oyster Creek, Peach Bottom, Quad Cities, and Three Mile Island ML0808605822008-04-0808 April 2008 Notice of Meeting with Exelon Generation Company, LLC (Exelon), to Discuss Licensing Activities ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0706404152007-03-27027 March 2007 Final Response to Quad Cities Nuclear Power Station - Task Interface Agreement (TIA) 2006-005 Appendix R Disputed Violations ML0636204862007-01-23023 January 2007 Final Response to Quad Cities Nuclear Power Station - Task Interface Agreement 2006-002 Replacement of Reactor Relief Valves with Valves Not Qualified in Accordance with Section 50.49 of Title 10 of Code of Federal Regulations (10 CFR) ML0627105392006-09-28028 September 2006 Memo 09/28/06 Request for Technical Assistance - Appendix R Disputed Violations Regarding Quad Cities Nuclear Power Station (TIA 2006-005) ML0610406142006-04-20020 April 2006 Dryer Inspection Results Decision ML0529700402005-10-24024 October 2005 11/08-09/2005 Notice of Technical Meeting with Exelon Generation Company, LLC Regarding for Quad Cities New Steam Dryers ML0525202372005-09-0909 September 2005 Forthcoming Meeting with Exelon Generation Company, LLC - Quad Cities Nuclear Power Station to Discuss Results and Evaluations of the Performance of the Steam Dryer ML0522301052005-08-11011 August 2005 Forthcoming Meeting with Exelon Generation Company, LLC - Dresden Nuclear Power Station; Quad Cities Nuclear Power Station ML0519303142005-07-18018 July 2005 Summary of Closed Meeting with Exelon Generation Company and Westinghouse Electric Company to Discuss Proprietary Information Related to Request for License Amd Supporting Transition to Westinghouse Fuel ML0519200502005-07-11011 July 2005 Notice of Meeting with Exelon Generation Company, LLC, to Discuss Results & Conclusions of Operation of Quad Cities, Unit 2 During Startup, Power Assention, & at Extended Power Uprate Levels Using New Steam Dryer ML0517200622005-06-21021 June 2005 Forthcoming Closed Meeting with Exelon Generation Company and Westinghouse Electric Company to Discuss Proprietary Information Related to Request for License Amendment Supporting Transition to Westinghouse Fuel ML0524902042005-06-16016 June 2005 Enclosure 2, Attachment 9 - GE Report GE-NE-0000-0041-9435, Quad Cities 1 & 2 Steam Dryer Replacement - 4% Structural Damping for Steam Dryer Skirt Fiv Analysis, Dated 06/16/2005 ML0514300552005-06-0202 June 2005 6/2/05, Quad Cities - Summary of May 5, 2005, Closed Meeting with Westinghouse to Discuss Information Related to Application of OPTIMA2 Topical Reports ML0514302632005-05-25025 May 2005 Quad Cities - Proprietary Determination for Handouts for April 14, 2005, Meeting with Westinghouse on Application of Optima2 Topical Reports ML0510800012005-05-0202 May 2005 Proprietary Determination of Attachments One Through Five of GE-ENG-DRY-044, for April 11, 12, and 13, 2005, Meeting with Exelon Generation Company on Design and Analysis of New Dryers for the Quad Cities Station ML0511604182005-04-21021 April 2005 4/21/05, Braidwood and Byron Stations, Units 1 and 2 - Summary of April 12, 2005, Telephone Conference Regarding the Emergency Plan for the Above Facilities (TAC Nos. MC6669 Thru MC6684) ML0511105932005-04-21021 April 2005 Meeting Notice, Meeting with Exelon Generation Company, LLC - Quad Cities Nuclear Power Station ML0509004442005-03-31031 March 2005 Program Plan for Power Uprate Operating Experience Review ML0504504552005-02-22022 February 2005 February 22, 2005 - Proprietary Determination for Handouts for January 25 and 26, 2005, Meeting with Exelon Generation Company on Steam Dryer Analyses for the Quad Cities and Dresden Nuclear Power Stations ML0432900732004-12-0303 December 2004 Summary of Meeting with Exelon Generation Company, LLC Regarding Exelon'S Extended Power Uprate Vibrations Assessment and Vulnerability Review and Steam Dryer Replacement Project for Dresden & Quad Cities ML0430703132004-11-12012 November 2004 Renewal of Full-Power Operating License for Dresden Nuclear Power Station, Units Nos. 2 and 3, and the Quad Cities Nuclear Power Station, Units Nos. 1 and 2 - Memo to Comm. from L. Reyes ML0232903632004-09-29029 September 2004 RAI Data for Incorporation Into Power Uprate Review Standard ML0417400862004-06-21021 June 2004 All Region III Facility Training Managers Revised NRC Form 398 - Personal Qualification Statement Licensee ML0412400532004-04-30030 April 2004 Transmittal of Preliminary Quad Cities Unit 2 ASP Analysis for Internal and External Peer Review 2023-02-15
[Table view] |
Text
September 28, 2006MEMORANDUM TO:Ho K. Nieh, Acting Division DirectorDivision of Policy and Rulemaking Office of Nuclear Reactor RegulationFROM:Cynthia D. Pederson, Director /RA/Division of Reactor Safety
SUBJECT:
REQUEST FOR TECHNICAL ASSISTANCE - APPENDIX RDISPUTED VIOLATIONS REGARDING QUAD CITIES NUCLEAR POWER STATION (TIA 2006-005) Region III requests NRR assistance in the review of the Quad Cities Nuclear Power Station's(QCNPS) response to two NRC Non-Cited Violations (NCV) regarding compliance with10 CFR Part 50 Appendix R requirements. NRR review of the licensee's response will supportthe Region III evaluation and formal response to the licensee's contestment of the findings. Furthermore, Region III believes that these two non-cited violations raise several questions thatare of generic nature and have implications on future resolution of issues.Specifically, the Region III office requests NRR review and evaluation of the licensee'sresponse relating to:*reliance upon the safe shutdown makeup pump (SSMP), for the purpose ofmeeting 10 CFR Part 50 Appendix R, III.G.2 requirements, without prior NRCreview and approval; and*reliance upon the residual heat removal service water (RHRSW) systemmulti-unit cross-tie capability, for the purpose of meeting 10 CFR Part50 Appendix R, III.G.2 requirements, without prior NRC review and approval.NRR review is requested due to the complexities involving 10 CFR Part 50 Appendix Rrequirements and potential wide-ranging implications resulting from the conclusions of the review of the licensee's response. CONTACT:J. Lara, DRS(630) 829-9731 BackgroundQCNPS has contested two NCVs identified during the 2006 triennial fire protection inspection. Please refer to the associated NRC inspection report and licensee's response for detailedbackground and analysis regarding these two NCVs. The two NCVs were documented in inspection report 05000254(265)/2006002 (ML062140118). The licensee's basis for contesting the Non-Cited Violations are documented in a letter dated August 31, 2006 (ML062560198). With respect to the SSMP finding, the SSMP system was originally installed as a dedicatedshutdown system, and therefore, the system was required to meet the regulations in Appendix R,Section III.G.3. The licensee subsequently maintained compliance with10 CFR Part 50 Appendix R,Section III.G.2 based on the SSMP and reactor core isolationcooling (RCIC) being redundant. The licensee maintains that the systems m eet therequirements to be considered redundant si nce the systems perform the same designfunctions. We note, however, that t he system redundancy is limited to the inventory makeupfunction for a fire event. Since the SSMP system would only be used for inventory makeup,plant safe shutdown would also require the use of other systems to perform the overall samesystem function as RCIC. With respect to the RHRSW finding, the licensee maintains that for multiple unit plants, systemsshared between units may be credited as redundant for each unit. Accordingly, the licensee relies upon the opposite unit RHRSW system, through a locally-operated system cross-tievalve, for the purposes of meeting 10 CFR Part 50 Appendix R, Section III.G.2 requirement toensure that at least one redundant train of a system is available to support safe shutdown.Requested ActionReview the licensee's response to the issued NRC inspection report findings and provideanswers to the following specific questions:With respect to NCV 05000254(265)/2006002-01:1.Can licensees perform a 10 CFR 50.59 evaluation (or other equivalent adverseeffects evaluation) for fire protection program changes which result in changing a previously approved "alternate/dedicated" Safe Shutdown system to a"redundant" system? If not, please identify what regulatory tool precludes thelicensee from making such a change and how we have communicated this expectation to licensees2.If such evaluation processes can be utilized, what is the system design criteriawhich licensee's must meet to rely upon these systems as "redundant" for thepurposes of meeting 10 CFR 50, Appendix R, III.G.2 requirements? 3.For Boiling Water Reactors, what systems can licensees appropriately classifyas "preferred" for the purposes of meeting 10 CFR 50, Appendix R, III.G.2requirements? For those systems, has the NRC defined the design or functionalrequirements for systems to be classified as "preferred"? 4.With respect to the Quad Cities NCV and licensee response, can the licenseeclassify the safe shutdown makeup pum p system (SSMP), as redundant to thereactor core isolation cooling system (RCIC) for the purposes of meeting 10 CFR Part 50 Appendix R, III.G.2?
5.With respect to the Quad Cities NCV and licensee response, does the licensee'sposition asserting compliance with 10 CFR 50 Appendix R, III.G.2 have meritand thereby warrant withdrawal of the NCV? With respect to NCV 05000254(265)/2006002-02:6.Can licensees perform a 10 CFR 50.59 evaluation (or other equivalent adverseeffects evaluation) for fire protection program changes which result in reliance on a multi-unit cross tie capability for the purpose of meeting10 CFR Part 50 Appendix R, III.G.2? If not, please identify what regulatory toolprecludes the licensee from making such a change and how we have communicated this expectation to licensees7.With respect to the Quad Cities NCV and licensee response, for the residualheat removal service water (RHRSW) system configuration, can the licensee relyupon the multi-unit cross-tie capability (previously relied upon for meeting10 CFR Part 50 Appendix R, III.G.3), for the purpose of meeting10 CFR Part 50 Appendix R, III.G.2? 8.With respect to the Quad Cities NCV and licensee response, does the licensee'sposition asserting compliance with 10 CFR 50 Appendix R, III.G.2, throughreliance upon the multi-unit cross-tie capability, have merit and thereby warrantwithdrawal of the NCV? CoordinationThis request was discussed between Julio Lara of Region III and Sunil Weerakkody of NRRduring a telephone conference on September 27, 2006. It was agreed that NRR would acceptthis issue as a Task Interface Agreement and respond to this request by November 3, 2006.Docket No. 50-254; 50-265 cc:J. Honcharik, NRRC. Pederson, DRS J. F. Lara, DRS K. O'Brien, EICS CoordinationThis request was discussed between Julio Lara of Region III and Sunil Weerakkody of NRRduring a telephone conference on September 27, 2006. It was agreed that NRR would acceptthis issue as a Task Interface Agreement and respond to this request by November 3, 2006. Docket No. 50-254; 50-265 cc:J. Honcharik, NRRC. Pederson, DRS J. F. Lara, DRS K. O'Brien, EICSDOCUMENT NAME:E:\Filenet\ML062710539.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIRIIIRIIIRIIINAMEJLara:jbCPederson DATE9/28/069/28/06OFFICIAL RECORD COPY