|
|
Line 3: |
Line 3: |
| | issue date = 10/06/2008 | | | issue date = 10/06/2008 |
| | title = NRC Security Inspection Report 05000397/2008402 | | | title = NRC Security Inspection Report 05000397/2008402 |
| | author name = Shannon M P | | | author name = Shannon M |
| | author affiliation = NRC/RGN-IV/DRS/PSB | | | author affiliation = NRC/RGN-IV/DRS/PSB |
| | addressee name = Parrish J V | | | addressee name = Parrish J |
| | addressee affiliation = Energy Northwest | | | addressee affiliation = Energy Northwest |
| | docket = 05000397 | | | docket = 05000397 |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:Energy Northwest - 1 - October 6, 2008 | | {{#Wiki_filter:ber 6, 2008 |
|
| |
|
| J. (Mail Drop 1023) Chief Executive Officer Energy Northwest P.O. Box 968 Richland, WA 99352-0968
| | ==SUBJECT:== |
| | | COLUMBIA GENERATING STATION - NRC SECURITY INSPECTION REPORT 05000397/2008402 |
| SUBJECT: COLUMBIA GENERATING STATION - NRC SECURITY INSPECTION REPORT 05000397/2008402 | |
|
| |
|
| ==Dear Mr. Parrish:== | | ==Dear Mr. Parrish:== |
Line 31: |
Line 30: |
| No findings of significance were identified. | | No findings of significance were identified. |
|
| |
|
| In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. Energy Northwest - 2 - In accordance with 10 CFR 2.390(b)(1)(ii) the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1). | | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV611 RYAN PLAZA DRIVE, SUITE 400ARLINGTON, TEXAS 76011-4005 Energy Northwest - 2 - In accordance with 10 CFR 2.390(b)(1)(ii) the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1). |
| | |
| Sincerely,/RA/ Michael P. Shannon Plant Support Branch Division of Reactor Safety Docket: 50-397 License: NPF-21
| |
|
| |
|
| ===Enclosure:===
| | Sincerely, |
| Inspection Report 05000397/2008402 w/Attachment Supplemental Information | | /RA/ Michael P. Shannon Plant Support Branch Division of Reactor Safety Docket: 50-397 License: NPF-21 Enclosure: Inspection Report 05000397/2008402 w/Attachment Supplemental Information |
|
| |
|
| cc w/o enclosure: Gregory V. Cullen Manager, Regulatory Programs Energy Northwest P.O. Box 968, Mail Drop PE20 Richland, WA 99352-0968 | | cc w/o enclosure: Gregory V. Cullen Manager, Regulatory Programs Energy Northwest P.O. Box 968, Mail Drop PE20 Richland, WA 99352-0968 |
| }} | | }} |
|
---|
Category:Letter
MONTHYEARGO2-24-110, Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification GO2-24-109, Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations ML24290A1142024-10-17017 October 2024 CGS FPTI 2024011 GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24247A1572024-09-12012 September 2024 Withholding Determination Letter for Presentation Materials for Energy Northwest Pre-application Meeting 8-9-2024 ML24255A1012024-09-12012 September 2024 Request for Withholding Information from Public Disclosure Energy Northwest Regulatory Engagement Plan, Revision 0 GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan IR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 07200035/20244012024-08-19019 August 2024 Security Baseline Inspection Report 07200035/2024401 IR 05000397/20244022024-08-13013 August 2024 Security Baseline Inspection Report 05000397/2024402 IR 05000397/20240022024-08-0909 August 2024 Integrated Inspection Report 05000397/2024002 GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan IR 05000397/20240122024-07-10010 July 2024 – Safety Conscious Work Environment Issue of Concern Follow-up Inspection 05000397/2024012 ML24180A1482024-06-28028 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000397/2024011) and Request for Information IR 05000397/20244202024-06-27027 June 2024 – Security Baseline Inspection Report 05000397 2024420 Cover Letter GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection ML24099A2232024-06-12012 June 2024 Issuance of Amendment No. 275 to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing ML24128A2242024-05-31031 May 2024 Issuance of Amendment No. 274 to Revise Technical Specifications to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report IR 05000397/20240012024-04-24024 April 2024 Integrated Inspection Report 05000397/2024001 GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report ML24089A2282024-04-15015 April 2024 – Acceptance of Requested Licensing Action License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 ML24074A4532024-04-11011 April 2024 Request for Withholding Information from Public Disclosure IR 05000397/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000397/2024401 (Cover Letter Only) IR 05000397/20244032024-03-28028 March 2024 Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000397/2024403 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24058A0692024-03-14014 March 2024 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Emergency Plan ML24044A0492024-03-12012 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0064 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 ML24047A0422024-03-0707 March 2024 Issuance of Amendment No. 273 Renewed Facility Operating License and Technical Specification Clean Up IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) IR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 05000397/LER-2024-001, Failure to Track Operability of Requirements of Transversing In-Core Probe Valves2024-01-22022 January 2024 Failure to Track Operability of Requirements of Transversing In-Core Probe Valves GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection 2024-09-24
[Table view] |
Text
ber 6, 2008
SUBJECT:
COLUMBIA GENERATING STATION - NRC SECURITY INSPECTION REPORT 05000397/2008402
Dear Mr. Parrish:
On September 25, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Columbia Generating Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on September 25, 2008, with Mr. Dale Atkinson, Vice President, Nuclear Generation and CNO, and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV611 RYAN PLAZA DRIVE, SUITE 400ARLINGTON, TEXAS 76011-4005 Energy Northwest - 2 - In accordance with 10 CFR 2.390(b)(1)(ii) the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/ Michael P. Shannon Plant Support Branch Division of Reactor Safety Docket: 50-397 License: NPF-21 Enclosure: Inspection Report 05000397/2008402 w/Attachment Supplemental Information
cc w/o enclosure: Gregory V. Cullen Manager, Regulatory Programs Energy Northwest P.O. Box 968, Mail Drop PE20 Richland, WA 99352-0968